- CN205857761U CN205857761U CN201620876445.0U CN201620876445U CN205857761U CN 205857761 U CN205857761 U CN 205857761U CN 201620876445 U CN201620876445 U CN 201620876445U CN 205857761 U CN205857761 U CN 205857761U
- Authority
- CN
- China
- Prior art keywords
- adjustment part
- connector
- top board
- level adjuster
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Floor Finish (AREA)
Abstract
This utility model provides a kind of level adjuster, belongs to construction auxiliary equipment field, and including the first adjustment part, connector and the second adjustment part, the first adjustment part is slidably connected with connector;Second adjustment part is slidably connected with connector;The axis of the first adjustment part is through the center of gravity of connector, and the axis of the second adjustment part is through the center of gravity of connector, and the axis of the first adjustment part and the axis collinear of the second adjustment part;The end of the second adjustment part is provided with connecting portion, is connected for fixing with ceiling.This level adjuster is applied on furred ceiling, when carrying out furred ceiling, by changing the height of the vertical direction of level adjuster and then adjusting the height of furred ceiling, operate more flexible during furred ceiling, reducing the difficulty of construction, on-demand be adjusted, the quality of furred ceiling is higher, accuracy is higher, is greatly improved the quality of construction.
Description
Technical field
This utility model relates to construction auxiliary equipment field, in particular to a kind of level adjuster.
Background technology
It is known that aerospace engineering high-quality precision and sophisticated technology require strictly reach ultimate attainment, space flight Factory Building processing installation equipment with
Sample is the most accurate, and this must have the clean room meeting equipment purity requirements in the most just requiring space flight processing Factory Building.In recent years
Coming, it is more extensive that clean board is applied in space flight Factory Building, and in clean room construction technology level directly determines Factory Building, space flight sets
The cleanliness factor of standby environment.In installation process, due to the special environment of space flight Factory Building, need in many rooms of space flight Factory Building
Carry out installation of ceiling.Furred ceiling refers to the top finishing of house living environment.Briefly, it is simply that refer to the finishing of ceiling, it is room
One of pith of interior trim.Furred ceiling has insulation, heat insulation, sound insulation, the effect of sound absorption, be also electrically, air conditioner, communication
Hidden layer with engineerings such as fire prevention, warning line equipment.Furred ceiling finishing material is to discriminate between the Main Basis of furred ceiling title, mainly
Have: light steel keel gypsum board furred ceiling, plaster tablet suspended ceiling, mineral wool board ceiling, clamping plate furred ceiling, abnormity strip aluminum-pinch furred ceiling, square
Plating paint aluminum-pinch furred ceiling, stained glass furred ceiling, aluminum honeycomb perforated sound-absorbing plate furred ceiling, the compound furred ceiling in full room etc., fill in whole room
Decorations occupy considerable status, room top surface is made suitable decoration, indoor environment can not only be beautified, moreover it is possible to build rich
Rich colorful interior space artistic image.When selecting suspended ceiling decoration material and design, to follow and both save material, firm, peace
Entirely, the most attractive in appearance, practical principle.
Inventor finds under study for action, and the furred ceiling of traditional space flight Factory Building at least has a disadvantage in that in work progress
During traditional ceiling construction, the size of furred ceiling the most necessarily determines, the distance of its short transverse
Also being fixing, when carrying out furred ceiling, the requirement to size is high, the technology of workman is required height, easily occurs that error causes hanging
The Quality Down on top, the probability repeating construction increases, and adds cost.
Utility model content
The purpose of this utility model is to provide a kind of level adjuster, to improve the furred ceiling of prior art in installation process
Middle size is fixing cannot adjust the difficulty causing adding installation and the problem adding construction cost.
Embodiment of the present utility model is achieved in that
Based on above-mentioned purpose, this utility model provides a kind of level adjuster, including the first adjustment part, connector and
Second adjustment part, wherein:
Described first adjustment part is slidably connected with described connector, described first adjustment part and the slip side of described connector
To the length direction being parallel to described first adjustment part;Described second adjustment part is slidably connected with described connector, and described second
The glide direction of adjustment part and described connector is parallel to the length direction of described first adjustment part;The axle of described first adjustment part
Line is through the center of gravity of described connector, and the axis of described second adjustment part is through the center of gravity of described connector, and described first adjusts
The axis of one integral piece and the axis collinear of described second adjustment part;The end of described second adjustment part is provided with connecting portion, for
Ceiling is fixing to be connected.
In this utility model preferred embodiment, described connector include top board, base plate, left plate, right plate and
Front side board, the head and the tail connection successively of described top board, described base plate, described left plate and described right plate surrounds the knot with cavity
Structure, described cavity includes two openings being oppositely arranged, and described front side board is positioned at opening part described in, and described front side board is respectively
It is connected with described top board, described base plate, described left plate and described right plate;Described first adjustment part slides with described top board
Connecting, described second adjustment part is slidably connected with described base plate.
In this utility model preferred embodiment, described top board, described base plate, described front side board, described left plate with
And described right plate is disposed as rectangular slab.
In this utility model preferred embodiment, described first adjustment part includes the first bolt and two the first spiral shells
Cap, described first bolt is perpendicular to described top board and arranges, top board described in described first bolt-through, two described nut spiral shells respectively
It is connected to described first bolt, and two described nuts are not positioned at the both sides in plate face of described top board.
In this utility model preferred embodiment, described first adjustment part also includes elastic washer, described elastic washer
Being provided with two, two described elastic washers are set on described first screw rod, and two described elastic washers lay respectively at often
Between individual described first nut and described top board.
In this utility model preferred embodiment, described first adjustment part is provided with the first graduation mark, described first
The measurement direction of graduation mark is parallel with the length direction of described first adjustment part.
In this utility model preferred embodiment, described second adjustment part includes the second screw rod and the second nut, institute
Stating the second screw rod and be perpendicular to described base plate, described second screw rod runs through described base plate, described second screw rod away from described top board
End be provided with limiting section, described limiting section is along outside outwardly described second screw rod of radial direction of described second screw rod
Side face, described second nut is bolted in described second screw rod, and described second nut is positioned at described base plate with described limiting section
The both sides in plate face.
In this utility model preferred embodiment, described second adjustment part also includes locking spring, described locking spring
It is set on described second screw rod, and described locking spring is between the plate face of described limiting section and described base plate.
In this utility model preferred embodiment, described second adjustment part also includes locking spring, described locking spring
It is set on described second screw rod, and described locking spring is between the plate face of described limiting section and described base plate.
In this utility model preferred embodiment, described second adjustment part is provided with the second graduation mark, described second
The measurement direction of graduation mark is parallel with the length direction of described second adjustment part.
This utility model embodiment provides the benefit that:
In sum, this utility model embodiment provides a kind of level adjuster, and it is simple and reasonable, processing and manufacturing
Convenient, install and low cost of manufacture, meanwhile, this level adjuster is applied on furred ceiling, when carrying out furred ceiling, by changing level
The height of the vertical direction of adjustor and then the height of adjustment furred ceiling, operate more flexible, reduce construction during furred ceiling
Difficulty, on-demand is adjusted, and the quality of furred ceiling is higher, and accuracy is higher, is greatly improved the quality of construction.Specific as follows:
The level adjuster that the present embodiment provides, including connector, the first adjustment part and the second adjustment part, first adjusts
Part and the second adjustment part are slidably connected to connector respectively, when carrying out furred ceiling, the first adjustment part are installed on the top of floor,
I.e. achieve the installation of level adjuster, then, ceiling is attached by connecting elements and the second adjustment part, whole dress
Join process simple and reliable, flexible operation.First adjustment part and the second adjustment part are slidably connected with connector, and the first adjustment part is relative
Can be adjusted in the position of connector, meanwhile, the second adjustment part can be adjusted with the position of connector, pacifies in reality
In process of assembling, when the position of furred ceiling needs to adjust in time, by individually operated first adjustment part, the second adjustment part or logical
The first adjustment part and the second adjustment part is operated after simultaneously, flexible during operation.And first adjustment part and the second adjustment part
All passing the center of gravity of connector, the first adjustment part and the axis collinear of the second adjustment part, level adjuster is as connecting ceiling
During with the intermediate member of floor, stress balance, it is hardly damaged, safe and reliable during use.
Accompanying drawing explanation
In order to be illustrated more clearly that the technical scheme of this utility model embodiment, will use required in embodiment below
Accompanying drawing be briefly described, it will be appreciated that the following drawings illustrate only some embodiment of the present utility model, the most should be by
Regard the restriction to scope as, for those of ordinary skill in the art, on the premise of not paying creative work, also may be used
To obtain other relevant accompanying drawings according to these accompanying drawings.
Fig. 1 is the structure chart of the level adjuster of this utility model embodiment;
Fig. 2 is the structure chart of the connector of the level adjuster of this utility model embodiment;
Fig. 3 is first adjustment part connection diagram with connector of this utility model embodiment;
Fig. 4 is second adjustment part connection diagram with connector of this utility model embodiment.
In figure:
Connector 100, top board 110, base plate 120, left plate 130, right plate 140, front side board 150,
First adjustment part 200, the first screw rod 210, the first nut 220, elastic washer 230,
Second adjustment part 300, the second screw rod 310, the second nut 320, locking spring 330, limiting section 340.
Detailed description of the invention
Furred ceiling refers to the top finishing of house living environment.Briefly, it is simply that refer to the finishing of ceiling, it is interior decoration
One of pith.Furred ceiling has insulation, heat insulation, sound insulation, the effect of sound absorption, is also electrically, air conditioner, communicates and prevent
The hidden layer of the engineerings such as fire, warning line equipment.Furred ceiling finishing material is to discriminate between the Main Basis of furred ceiling title, mainly has: light
Steel joist plaster tablet suspended ceiling, plaster tablet suspended ceiling, mineral wool board ceiling, clamping plate furred ceiling, abnormity strip aluminum-pinch furred ceiling, square plating paint aluminum
Cover plate ceiling, stained glass furred ceiling, aluminum honeycomb perforated sound-absorbing plate furred ceiling, the compound furred ceiling in full room etc., account in whole indoor decoration
There is considerable status, room top surface is made suitable decoration, indoor environment can not only be beautified, moreover it is possible to build rich and varied
Interior space artistic image.When selecting suspended ceiling decoration material and design, follow not only save material, firmly, safety, but also beautiful
Sight, practical principle.During traditional ceiling construction, the size of furred ceiling the most necessarily determines, its short transverse
Distance be also fixing, when carrying out furred ceiling, high to the requirement of size, the technology of workman is required height, error easily occurs
Causing the Quality Down of furred ceiling, the probability repeating construction increases, and adds cost.
In consideration of it, this utility model designer devises a kind of level adjuster, by floor and sky during furred ceiling
Card is attached, and is arranged on the top of ceiling as a kind of connecting elements, and when actual installation, level adjuster includes three
Individual parts, the position of three parts can relative variability, and then change the length that level adjuster is overall, and then have adjusted sky
The height of card, easy to use and reliable.
For making the purpose of this utility model embodiment, technical scheme and advantage clearer, new below in conjunction with this practicality
Accompanying drawing in type embodiment, is clearly and completely described the technical scheme in this utility model embodiment, it is clear that retouched
The embodiment stated is a part of embodiment of this utility model rather than whole embodiments.Generally described in the accompanying drawing herein and
The assembly of this utility model embodiment illustrated can be arranged with various different configurations and design.
Therefore, below the detailed description of the embodiment of the present utility model provided in the accompanying drawings is not intended to limit requirement
The scope of the present utility model of protection, but it is merely representative of selected embodiment of the present utility model.Based in this utility model
Embodiment, the every other embodiment that those of ordinary skill in the art are obtained under not making creative work premise, all
Belong to the scope of this utility model protection.
It should also be noted that similar label and letter represent similar terms, therefore, the most a certain Xiang Yi in following accompanying drawing
Individual accompanying drawing is defined, then need not it be defined further and explains in accompanying drawing subsequently.
In description of the present utility model, it should be noted that term " on ", D score, "left", "right", " interior ", " outward " etc.
Orientation or the position relationship of instruction are based on orientation shown in the drawings or position relationship, or when this utility model product uses
The orientation usually put or position relationship, be for only for ease of description this utility model and simplify description rather than instruction or dark
The device or the element that show indication must have specific orientation, with specific azimuth configuration and operation, therefore it is not intended that right
Restriction of the present utility model.Describe additionally, term " first ", " second " etc. are only used for distinguishing, and it is not intended that indicate or dark
Show relative importance.
In description of the present utility model, in addition it is also necessary to explanation, unless otherwise clearly defined and limited, term " sets
Put ", should be interpreted broadly " installation ", " being connected ", " connection ", connect for example, it may be fixing, it is also possible to be to removably connect,
Or be integrally connected;Can be to be mechanically connected, it is also possible to be electrical connection;Can be to be joined directly together, it is also possible to pass through intermediary
It is indirectly connected to, can be the connection of two element internals.For the ordinary skill in the art, can manage with concrete condition
Solve above-mentioned term concrete meaning in this utility model.
Embodiment
Refer to Fig. 1, present embodiments provide a kind of level adjuster, for floor and ceiling being carried out the company of installation
Connecing, level adjuster is connected, then by the middle dark hanging beam of word aluminum and variola by expansion bolt is fixing with the concrete layer of floor
Plate connects.Concrete, level adjuster includes connector the 100, first adjustment part 200 and the second adjustment part 300.
Referring to Fig. 2, connector 100 is to connect the first adjustment part 200 and parts of the second adjustment part 300, plays connection
Effect with transmission power.The on-demand setting of planform of connector 100, is preferably arranged to regular shape, it is simple to processing, and stress
Balance, more safe and reliable during use.Concrete, connector 100 is set to the cube shape with cavity, and it includes top board
110, base plate 120, left plate 130, right plate 140 and front side board 150, top board 110, base plate 120, left plate 130 and the right side
Side plate 140 head and the tail connection successively surrounds the structure with cavity, and cavity includes two openings being oppositely arranged, front side board 150
In an opening part, and front side board 150 is connected with top board 110, base plate 120, left plate 130 and right plate 140 respectively.Whole company
The gravity of fitting 100 is light, and transport, with easy for installation, save the material of processing simultaneously, provides cost savings.Connector 100 uses
Rustless steel or alloy material are made, and structural strength is high, and during use, stress is good, is hardly damaged.Actual add man-hour, top board
110, base plate 120, front side board 150, left plate 130 and right plate 140 are all processed as rectangular slab, simple in construction, processing and manufacturing
Convenient, meanwhile, the symmetry of rectangular slab is good, more convenient during installation.Top board 110, base plate 120, front side board 150, left side
Plate 130 and right plate 140 can use welding manner processing to obtain connector 100, and overall structure is solid and reliable.The present embodiment
Another alternative in, connector 100 uses one-body molded being processed into, and processes more convenient, saves and be manufactured into
This.
In actual use, top board 110 is above, and base plate 120 is positioned at lower section, left plate 130, right plate 140
With front side board 150 is between top board 110 and base plate 120, top board 110 and base plate 120 are respectively arranged with through hole, for bolt
Pass.The position of the through hole on the position of the through hole on top board 110 and base plate 120 is all arranged near front side board 150, it is ensured that through hole
Axis through the center of gravity of connector 100.
Referring to Fig. 1 and Fig. 3, the first adjustment part 200 is slidably connected with being connected, and the first adjustment part 200 is relative to connector
The glide direction of 100 is parallel to the length direction of the first adjustment part 200.Being preferably arranged to, the first adjustment part 200 includes the first spiral shell
Bolt, elastic washer 230 and two the first nuts 220, the first bolt is inserted in the through hole of top board 110, and the first bolt
One end is stretched between top board 110 and base plate 120, and two the first nuts 220 are screwed onto on the first bolt respectively, two the first nuts
The both sides in the 220 plate faces laying respectively at top board 110.First bolt is perpendicular to top board 110 and arranges, and the first bolt is arranged on top board
After 110, it is more uniformly stressed.Meanwhile, being provided with the first graduation mark on the first bolt, the measurement direction of the first graduation mark is parallel
Length direction in the first bolt, it is simple to calculate the distance adjusted during adjustment, adjusts more rationally reliable.Elastic washer 230 sets
Being equipped with two, each elastic washer 230 is set on the first bolt, and elastic washer 230 is positioned at the first nut 220 and top board 110
Between, the first nut 220 is provided with two, and top board 110 has two plate faces, therefore, each first nut 220 and top board 110
A plate face between be provided with an elastic washer 230, the attachment structure of the first nut 220 and top board 110 more firmly may be used
Lean on, it is simple to tightening of the first nut 220, and the first nut 220 is difficult to loosen.
In actual mechanical process, the first spiral shell can be carried out by the first nut 220 of the lower section that adjustment is positioned at top board 110
The length adjustment of bar 210, meanwhile, the corresponding position being positioned at the first nut 220 above top board 110 that adjusts, above the
The position of one nut 220 adjusts accordingly according to the position of the second nut 320, it is ensured that adjusting two the first screw rods 210
After length relative to top board 110, the first screw rod 210 is difficult to rock together with can being securely attached to top board 110.Cause
This, it is possible to realize, in the scheme of the first adjustment part 200 length adjustment, the first screw rod 210 arranging first nut 220 also
Being possible, first nut 220 is positioned at the lower section of top board 110.The end away from top board 110 of the first screw rod 210 is passed through
Expansion bolt is connected with the concrete layer of floor.
Referring to Fig. 1 and Fig. 4, the second adjustment part 300 is slidably connected with connector 100, the second adjustment part 300 and connector
The glide direction of 100 is parallel with the length direction of the second adjustment part 300, is preferably arranged to, and the second adjustment part 300 includes the second spiral shell
Bar 310, locking spring 330 and the second nut 320, the second screw rod 310 hangs down through the through hole on base plate 120, the second screw rod 310
Directly being provided with the second graduation mark on base plate 120, the second screw rod 310, the measurement of the second graduation mark is oriented parallel to the second screw rod
The length direction of 310, during by operating adjustment that the second adjustment part 300 carries out length, it is simple to by the chi on the second screw rod 310
Little progress row adjusts accurately, adjusts convenient.The end away from top board 110 of the second screw rod 310 is provided with limiting section 340,
Limiting section 340 is along the outer peripheral face of outwardly second screw rod 310 of radial direction of the second screw rod 310, and the second nut 320 is bolted in
Second screw rod 310, and the second nut 320 is positioned at the both sides in plate face of base plate 120 with limiting section 340.When reality adjusts, second
Nut 320 bears the gravity of bottom, is sling by ceiling.In i.e., one end of the dark hanging beam of word aluminum is connected with limiting section 340, middle word aluminum
The other end of dark hanging beam is connected with ceiling, and ceiling is lifted on limiting section 340, and limiting section 340 transmits the force to the second spiral shell
Cap 320.By adjusting the second nut 320, change second screw rod 310 length relative to base plate 120, and then have adjusted whole water
The length of flat adjustor, it is achieved that the adjustment of heights of ceilings.In actual mechanical process, in order to ensure the second screw rod 310 with
Connectivity robustness between base plate 120, a sheathed locking spring 330 on the second screw rod 310, locking spring 330 is positioned at limit
Between the bottom surface of position portion 340 and base plate 120, the elastic force of locking spring 330 self acts on base plate 120 and limiting section 340, real
Existing locking function.Meanwhile, locking spring 330 does not interferes with the adjustment of the second nut 320.In order to ensure that limiting section 340 can be with
The middle dark hanging beam of word aluminum coordinates closely, and stress is more reliable and more stable, and limiting section 340 is set to annular projection, annular projection
Axis direction is parallel with the axis direction of the second screw rod 310, i.e. annular projection around the second screw rod 310 axis in the form of a ring,
Further, annular projection is set to circular, locking spring 330 between limiting section 340 and base plate 120, locking spring
330 coordinate more closely with annular projection, and one end of locking spring 330 is positioned on the end face of limiting section 340, it is simple to locking spring
Its elastic force is applied on limiting section 340 and base plate 120 by 330.At the same time it can also be the end of the close base plate 120 at limiting section 340
Face arranges annular groove, and locking spring 330 is positioned at annular groove, easier for installation.
The level adjuster that the present embodiment provides, is used for being connected between floor and ceiling, can be by adjusting level
The length of adjustor changes the height of ceiling, convenient and reliable during installation.
It should be noted that in the case of not conflicting, the embodiment in this utility model and the feature in embodiment can
To be mutually combined.
The foregoing is only preferred embodiment of the present utility model, be not limited to this utility model, for this
For the technical staff in field, this utility model can have various modifications and variations.All in spirit of the present utility model and principle
Within, any modification, equivalent substitution and improvement etc. made, within should be included in protection domain of the present utility model.
Claims (10)
1. a level adjuster, it is characterised in that include the first adjustment part, connector and the second adjustment part, wherein:
Described first adjustment part is slidably connected with described connector, and described first adjustment part is flat with the glide direction of described connector
Row is in the length direction of described first adjustment part;Described second adjustment part is slidably connected with described connector, and described second adjusts
The glide direction of part and described connector is parallel to the length direction of described first adjustment part;The axis of described first adjustment part is worn
Crossing the center of gravity of described connector, the axis of described second adjustment part is through the center of gravity of described connector, and described first adjustment part
The axis collinear of axis and described second adjustment part;The end of described second adjustment part is provided with connecting portion, is used for and variola
Plate is fixing to be connected.
Level adjuster the most according to claim 1, it is characterised in that described connector includes top board, base plate, left side
Plate, right plate and front side board, the head and the tail connection successively of described top board, described base plate, described left plate and described right plate is enclosed
Becoming to have the structure of cavity, described cavity includes two openings being oppositely arranged, and described front side board is positioned at opening part described in, and
Described front side board is connected with described top board, described base plate, described left plate and described right plate respectively;Described first adjustment part
Being slidably connected with described top board, described second adjustment part is slidably connected with described base plate.
Level adjuster the most according to claim 2, it is characterised in that described top board, described base plate, described front side board,
Described left plate and described right plate are disposed as rectangular slab.
Level adjuster the most according to claim 2, it is characterised in that described first adjustment part include the first bolt and
Two the first nuts, described first bolt is perpendicular to described top board and arranges, and top board described in described first bolt-through, described in two
Nut is bolted in described first bolt respectively, and two described nuts are not positioned at the both sides in plate face of described top board.
Level adjuster the most according to claim 4, it is characterised in that described first adjustment part also includes elastic washer,
Described elastic washer is provided with two, and two described elastic washers are set on described first screw rod, and two described cushions
Circle lays respectively between each described first nut and described top board.
Level adjuster the most according to claim 1, it is characterised in that be provided with the first scale on described first adjustment part
Line, the measurement direction of described first graduation mark is parallel with the length direction of described first adjustment part.
Level adjuster the most according to claim 2, it is characterised in that described second adjustment part include the second screw rod and
Second nut, described second screw rod is perpendicular to described base plate, and described second screw rod runs through described base plate, described second screw rod remote
Be provided with limiting section from the end of described top board, described limiting section is along the radial direction of described second screw rod outwardly described
The outer peripheral face of two screw rods, described second nut is bolted in described second screw rod, and described second nut is positioned at described limiting section
The both sides in the plate face of described base plate.
Level adjuster the most according to claim 7, it is characterised in that described second adjustment part also includes locking spring,
Described locking spring is set on described second screw rod, and described locking spring is positioned at the plate face of described limiting section and described base plate
Between.
Level adjuster the most according to claim 8, it is characterised in that described limiting section is annular projection, described ring-type
Protruding axis direction is parallel with the axis direction of described second screw rod.
Level adjuster the most according to claim 1, it is characterised in that be provided with for the second quarter on described second adjustment part
Degree line, the measurement direction of described second graduation mark is parallel with the length direction of described second adjustment part.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620876445.0U CN205857761U (en) | 2016-08-12 | 2016-08-12 | Level adjuster |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620876445.0U CN205857761U (en) | 2016-08-12 | 2016-08-12 | Level adjuster |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205857761U true CN205857761U (en) | 2017-01-04 |
Family
ID=57593657
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620876445.0U Active CN205857761U (en) | 2016-08-12 | 2016-08-12 | Level adjuster |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205857761U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110761567A (en) * | 2019-10-30 | 2020-02-07 | 芜湖科逸住宅设备有限公司 | Level regulator for assembly type building component |
CN111058621A (en) * | 2019-12-26 | 2020-04-24 | 江苏恒桂创科建筑工程科技有限公司 | Early system of tearing open of floor template free of support |
-
2016
- 2016-08-12 CN CN201620876445.0U patent/CN205857761U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110761567A (en) * | 2019-10-30 | 2020-02-07 | 芜湖科逸住宅设备有限公司 | Level regulator for assembly type building component |
CN111058621A (en) * | 2019-12-26 | 2020-04-24 | 江苏恒桂创科建筑工程科技有限公司 | Early system of tearing open of floor template free of support |
CN111058621B (en) * | 2019-12-26 | 2024-06-04 | 江苏恒桂创科建筑工程科技有限公司 | Early system of tearing open of floor template support-free |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106284815B (en) | Furred ceiling clean board construction technique | |
CN101787761B (en) | Special aluminum square tube ceiling and construction method thereof | |
CN210032297U (en) | Light steel keel suspended ceiling | |
CN205857761U (en) | Level adjuster | |
CN201095838Y (en) | Inner concave combination type suspended ceiling buckle | |
CN103114694A (en) | Decoration insulation board system | |
CN205857509U (en) | Acoustic board mounting structure | |
CN103122697A (en) | Installation method of indoor large-scale suspended ceiling | |
CN204899080U (en) | Inhale roof | |
CN116163461A (en) | Space structure assembled ultra-large color grain metal plate suspended ceiling and construction method | |
CN203308047U (en) | Installing and suspending assembly of finish material | |
CN1873151B (en) | Tie bar installation in use for suspended ceiling of building | |
CN203160500U (en) | Glass ceiling installation structure | |
CN205012539U (en) | Lacing film lamp support | |
CN205990692U (en) | A kind of furred ceiling | |
CN206267403U (en) | A kind of plaster tablet suspended ceiling structure of high-bearing capacity | |
CN204475765U (en) | A kind of platform mould keel | |
CN205242798U (en) | Room furred ceiling | |
CN105569250B (en) | A kind of GRG ceiling suspended ceilings | |
CN206554353U (en) | Sunk panel modeling structure on a kind of ceiling decoration | |
CN205557959U (en) | GRG ceiling furred ceiling | |
CN209114698U (en) | A kind of ceiling structure facilitating lamp installation | |
CN208965851U (en) | A kind of plasterboard keel frame connecting structure | |
CN220451212U (en) | Triangle joint assembled furred ceiling subassembly | |
CN207244975U (en) | A kind of reinforcement type aluminium suspended ceiling buckle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |