CN205829053U - A kind of arc pay off rack laid for high tension cable - Google Patents

A kind of arc pay off rack laid for high tension cable Download PDF

Info

Publication number
CN205829053U
CN205829053U CN201620777496.8U CN201620777496U CN205829053U CN 205829053 U CN205829053 U CN 205829053U CN 201620777496 U CN201620777496 U CN 201620777496U CN 205829053 U CN205829053 U CN 205829053U
Authority
CN
China
Prior art keywords
montant
cross bar
high tension
tension cable
arc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620777496.8U
Other languages
Chinese (zh)
Inventor
王新利
徐海林
李从耀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Mechanical and Electrical Construction Co Ltd
Original Assignee
China Gezhouba Group Mechanical and Electrical Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Mechanical and Electrical Construction Co Ltd filed Critical China Gezhouba Group Mechanical and Electrical Construction Co Ltd
Priority to CN201620777496.8U priority Critical patent/CN205829053U/en
Application granted granted Critical
Publication of CN205829053U publication Critical patent/CN205829053U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Details Of Indoor Wiring (AREA)

Abstract

This utility model provides a kind of arc pay off rack laid for high tension cable, including arcwall face, horizontal stand, vertical support frame and fixed plate, described arcwall face includes the arc gusset laying respectively at left side and right side, described horizontal stand and vertical support frame are welded on outside gusset, described horizontal stand and vertical support frame form right angle inside arcwall face and support, at least one fixed plate is welded in the side supported at right angle between described horizontal stand, described fixed plate has at least one perforate, described perforate is for fixing external environment condition by expansion bolt by arc pay off rack.This utility model compact conformation, economical and practical, when high voltage cable passes through, it is possible to the arcuately smooth advance in face, bending radius and gib are effectively ensured, are conducive to improving cable laying efficiency and safety.

Description

A kind of arc pay off rack laid for high tension cable
Technical field
This utility model relates to a kind of paying-off implement technical field, and a kind of arc laid for high tension cable is put Coil holder.
Background technology
Nowadays, increasing power engineering can use high tension cable as the carrier of power transmission.High tension cable one As external diameter is thick, weight big, when cable through the hole of building, floor or during corner, owing to the gravity vertically transferred is very big, Depending merely on manpower and cannot ensure the bending radius of cable, cable outer layer is easily caused damage by the sharp corners of building, uses lifting Suspender then cannot meet cable and transfer required distance, and operation inconvenience;Meanwhile, cable two ends lay after putting in place shaping fixing before, Cable cannot be fixed on permanent support immediately.
Utility model content
Goal of the invention of the present utility model is: for the problem of above-mentioned existence, it is provided that a kind of high tension cable that is used for lays Arc pay off rack.
The technical solution adopted in the utility model is such that a kind of arc pay off rack laid for high tension cable, tool Body includes that arcwall face, horizontal stand, vertical support frame and fixed plate, described arcwall face include laying respectively at the arc on left side and right side Gusset, described horizontal stand and vertical support frame are welded on outside gusset, and described horizontal stand and vertical support frame are inside arcwall face Formation right angle supports, and at least one fixed plate is welded in the side supported at right angle between described horizontal stand, and described fixed plate has Having at least one perforate, described perforate is for being fixed on external environment condition by expansion bolt by arc pay off rack.
Further, described arcwall face also includes the parallel steel pipe being welded on equably between gusset of N root, outside described steel pipe Set pvc pipe.
Further, described horizontal stand includes and the first cross bar, the second montant, the 3rd montant and the 4th montant.
Further, described first cross bar is the first right-angle side that right angle supports, and described first cross bar welds the successively First end of two montants, the first end of the 3rd montant and the non-end positions of the 4th montant.
Further, described second montant, the 3rd montant and the 4th montant are each perpendicular to the first cross bar.
Further, described second montant, the 3rd montant and the 4th montant exceed 200mm outside arcwall face respectively, described The raised area has wrapped up rubber peel.
Further, described vertical support frame includes the first montant, the second cross bar, the 3rd cross bar and the 4th cross bar.
Further, described first montant is the second right-angle side that right angle supports, and described first montant welds the successively First end of two cross bars, the first end of the 3rd cross bar and the first end of the 4th cross bar, the non-end positions of described second cross bar Weld with the first end of the 4th montant.
Further, described second cross bar, the 3rd cross bar and the 4th cross bar are each perpendicular to the first montant.
Further, described second cross bar, the 3rd cross bar and the 4th cross bar exceed 200mm outside arcwall face respectively, described The raised area has wrapped up rubber peel.
In sum, owing to have employed technique scheme, the beneficial effects of the utility model are: arc pay off rack is not only The gravity of high tension cable can be born, it is ensured that Cable Bending Radius and smooth pass through, it is also possible to avoid cable by hole, building When plate or corner, rub with sharp corners, protection cable outer layer and sheath;When being also used as cable shaping simultaneously Interim fixed support;Avoid when high tension cable is laid by hole, floor or corner and cannot ensure Cable Bending Radius And the problem that cable is fixed temporarily;Arc pay off rack simple in construction, easily making, cost of manufacture is cheap, easy and simple to handle, improves construction Speed.
Accompanying drawing explanation
Fig. 1 is the side structure schematic diagram of the arc pay off rack that this utility model lays for high tension cable.
Fig. 2 is the plan structure schematic diagram of the arc pay off rack that this utility model lays for high tension cable.
Labelling in figure: 1-gusset, 2-the first montant, 3-the first cross bar, 4-fixed plate, 5-perforate, 6-the second montant, 7- Three montants, 8-the 4th montant, 9-the second cross bar, 10-the 3rd cross bar, 11-the 4th cross bar, 12-steel pipe, 13-external environment condition.
Detailed description of the invention
Below in conjunction with the accompanying drawings, this utility model is described in detail.
In order to make the purpose of this utility model, technical scheme and advantage clearer, below in conjunction with accompanying drawing and enforcement Example, is further elaborated to this utility model.Should be appreciated that specific embodiment described herein is only in order to explain This utility model, is not used to limit this utility model.
As shown in Figure 1-2, a kind of arc pay off rack laid for high tension cable, specifically include arcwall face, horizontal stand, Vertical support frame and fixed plate 4, described arcwall face includes laying respectively at the arc gusset 1 on left side and right side, described horizontal stand and Vertical support frame is welded on outside gusset 1, and described horizontal stand and vertical support frame form right angle inside arcwall face and support, described water At least one fixed plate 4 is welded in the side supported at right angle between flat support, and described fixed plate 4 has at least one perforate 5, institute Stating perforate 5 for fixed plate 4 being fixed on external environment condition 13 by expansion bolt, during construction, high tension cable needs to pass through hole Mouthful, the external environment condition 13 such as floor and corner, external environment condition 13 irregular structure and be inconvenient to place high voltage cable, employing expansion Fixed plate 4 is fixed on hole or floor or corner by perforate 5 by bolt, and arc pay off rack is fixed, high voltage cable It is positioned on arcwall face, makes high voltage cable have certain bending radius when laying and be fixed temporarily, it is to avoid sharply to turn High voltage cable is caused damage by angle.
Described arcwall face also includes the parallel steel pipe 12 being welded on equably between gusset of N root, the present embodiment preferably nine Steel pipe 12, described steel pipe 12 overcoat pvc pipe, when high voltage cable needs to drag, the pvc pipe of steel pipe 12 and appearance surface cover is permissible Friction between high voltage cable is changed into rolling friction, it is to avoid when high voltage cable lays, scratch high line cable.
Described horizontal stand includes and the first cross bar the 3, second montant the 6, the 3rd montant 7 and the 4th montant 8;Described first is horizontal Bar 3 is the first right-angle side that right angle supports, and described first cross bar 3 welds the first end of the second montant 6, the 3rd montant 7 successively The first end and the non-end positions of the 4th montant 8;Described second montant the 6, the 3rd montant 7 and the 4th montant 8 are each perpendicular to First cross bar 3;Described second montant the 6, the 3rd montant 7 and the 4th montant 8 exceed 200mm outside arcwall face, described the raised area Wrap up rubber peel;The material that horizontal stand uses is angle steel, stabilized structure, and the part exceeded can play lever effect, anti- Only high voltage cable landing from arcwall face.
Described vertical support frame includes the first montant the 2, second cross bar the 9, the 3rd cross bar 10 and the 4th cross bar 11;Described first erects Bar 2 is the second right-angle side that right angle supports, and described first montant 2 welds the first end of the second cross bar 9, the 3rd cross bar 10 successively The first end and the first end of the 4th cross bar 11, the first end weldering of the non-end positions of described second cross bar 9 and the 4th montant 8 Connect;Described second cross bar the 9, the 3rd cross bar 10 and the 4th cross bar 11 are each perpendicular to the first montant 2;Described second cross bar the 9, the 3rd is horizontal Bar 10 and the 4th cross bar 11 exceed 200mm outside arcwall face, and described the raised area has wrapped up rubber peel;The material that vertical support frame uses Material is angle steel, stabilized structure, and horizontal stand coordinate can be to the strongest holding power of arc pay off rack offer, the part exceeded Lever effect can be played, prevent high voltage cable landing from arcwall face.
The foregoing is only preferred embodiment of the present utility model, not in order to limit this utility model, all at this Any amendment, equivalent and the improvement etc. made within the spirit of utility model and principle, should be included in this utility model Protection domain within.

Claims (10)

1. the arc pay off rack laid for high tension cable, it is characterised in that: include arcwall face, horizontal stand, vertically prop up Frame and fixed plate, described arcwall face includes the arc gusset laying respectively at left side and right side, described horizontal stand and vertical support frame Be welded on outside gusset, described horizontal stand and vertical support frame formed inside arcwall face right angle support, described horizontal stand it Between right angle support side weld at least one fixed plate, described fixed plate has at least one perforate, and described perforate is used for By expansion bolt, arc pay off rack is fixed in external environment condition.
2. the arc pay off rack laid for high tension cable as claimed in claim 1, it is characterised in that: described arcwall face also includes The parallel steel pipe being welded on equably between gusset of N root, described steel pipe overcoat pvc pipe.
3. the arc pay off rack laid for high tension cable as claimed in claim 2, it is characterised in that: described horizontal stand includes First cross bar, the second montant, the 3rd montant and the 4th montant.
4. the arc pay off rack laid for high tension cable as claimed in claim 3, it is characterised in that: described first cross bar is straight Angle support the first right-angle side, described first cross bar welds successively the first end of the second montant, the 3rd montant the first end with And the 4th non-end positions of montant.
5. the arc pay off rack laid for high tension cable as claimed in claim 4, it is characterised in that: described second montant, the Three montants and the 4th montant are each perpendicular to the first cross bar.
6. the arc pay off rack laid for high tension cable as claimed in claim 5, it is characterised in that: described second montant, the Three montants and the 4th montant exceed arcwall face 200mm respectively, and described the raised area has wrapped up rubber peel.
7. the arc pay off rack laid for high tension cable as claimed in claim 6, it is characterised in that: described vertical support frame includes First montant, the second cross bar, the 3rd cross bar and the 4th cross bar.
8. the arc pay off rack laid for high tension cable as claimed in claim 7, it is characterised in that: described first montant is straight Angle support the second right-angle side, described first montant welds successively the first end of the second cross bar, the 3rd cross bar the first end with And the 4th first end of cross bar, the non-end positions of described second cross bar is welded with the first end of the 4th montant.
9. the arc pay off rack laid for high tension cable as claimed in claim 8, it is characterised in that: described second cross bar, the Three cross bars and the 4th cross bar are each perpendicular to the first montant.
10. the arc pay off rack laid for high tension cable as claimed in claim 9, it is characterised in that: described second cross bar, the Three cross bars and the 4th cross bar exceed 200mm outside arcwall face respectively, and described the raised area has wrapped up rubber peel.
CN201620777496.8U 2016-07-22 2016-07-22 A kind of arc pay off rack laid for high tension cable Expired - Fee Related CN205829053U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620777496.8U CN205829053U (en) 2016-07-22 2016-07-22 A kind of arc pay off rack laid for high tension cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620777496.8U CN205829053U (en) 2016-07-22 2016-07-22 A kind of arc pay off rack laid for high tension cable

Publications (1)

Publication Number Publication Date
CN205829053U true CN205829053U (en) 2016-12-21

Family

ID=57560346

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620777496.8U Expired - Fee Related CN205829053U (en) 2016-07-22 2016-07-22 A kind of arc pay off rack laid for high tension cable

Country Status (1)

Country Link
CN (1) CN205829053U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111244831A (en) * 2020-03-20 2020-06-05 广东韶钢松山股份有限公司 Cable arrangement method
CN113883334A (en) * 2021-11-19 2022-01-04 上海船舶研究设计院(中国船舶工业集团公司第六0四研究院) Fan-shaped hose support

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111244831A (en) * 2020-03-20 2020-06-05 广东韶钢松山股份有限公司 Cable arrangement method
CN113883334A (en) * 2021-11-19 2022-01-04 上海船舶研究设计院(中国船舶工业集团公司第六0四研究院) Fan-shaped hose support

Similar Documents

Publication Publication Date Title
CN205829053U (en) A kind of arc pay off rack laid for high tension cable
CN110589192B (en) Low-abrasion building material conveying device
CN202721426U (en) Special pay-off rack for BV and BLV cables
CN204369415U (en) The auxiliary device of thin plate handling
JP3208039U (en) Long tube guide support device
CN206466801U (en) A kind of lift cable unreeling rack
CN206929490U (en) Poling moves protection of pipe device in pipe
CN202612853U (en) Bracket for pipe dragging
CN205149911U (en) Workshop transfer device
CN203423463U (en) Vertical cable pay-off seat
CN202316592U (en) Copper wire feeding device
CN203428586U (en) Film feeding mechanism used for packing machine
CN215160357U (en) Safety protection device for gantry crane
CN202405700U (en) Lifting mobile wire releasing device
CN203567787U (en) Carrying tooling of wall hanging plates
CN205952682U (en) Road roller gyro wheel delivery frock
CN105869878B (en) Novel and multifunctional coiling rack
CN204508414U (en) A kind of cable rack
CN204624982U (en) The vertical overhead hoist of a kind of tubing
CN110565930A (en) Telescopic movable operation platform for top construction of light well and construction method thereof
CN204264194U (en) The wire rod labour-saving go-cart of a kind of carrying dish circle
CN202156826U (en) Semi-automatic unwinding device
CN214866930U (en) Steel strand fixing and penetrating device
CN206681391U (en) A kind of material slipper bracket for building
CN210848043U (en) Automatic feeding device of straightening machine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161221

Termination date: 20190722

CF01 Termination of patent right due to non-payment of annual fee