Summary of the invention
This utility model is applicable to the Novel water source heat pump water intake system of the bigger seasonal height of water and discloses new side
Case, uses and rises the phase and extract the situation that the seasonal height of water of water lines reply is big dry season two, solve existing scheme because of
What water level seasonality drop brought greatly takes the problem less than qualified water source in extreme season under environment.
This utility model is applicable to the Novel water source heat pump water intake system of the bigger seasonal height of water and includes fetching water on the ground
Structures, underground water intake structures and water intaking piping, be provided with water intaking piping in underground water intake structures.Underground water intake structures bag
Including underground hoistway and underground water pump chamber, the upper end of underground hoistway connects with intake strucure on the ground, the lower end of underground hoistway and ground
Lower pump chamber connects, and water intaking piping includes unit section hydraulic pipeline and water intaking section hydraulic pipeline, the upper end of unit section hydraulic pipeline
Connect with water resource heat pump from offshore side, the upper end pass-out of underground hoistway, the lower end of unit section hydraulic pipeline be located in the ground pump chamber
The water side connection of interior water-delivery pump, water intaking section hydraulic pipeline includes water intaking section water delivery house steward, rises phase aqueduct, dry season
Aqueduct, water intaking section water delivery house steward outlet connect with the water inlet end of water-delivery pump, fetch water section water delivery house steward import with rise
The outlet of phase aqueduct, the interruption-forming three way type that goes out of aqueduct in dry season connect, and the intake of the phase aqueduct that rises sets
In water intaking layer below the normal mean water in river, dry season, the intake of aqueduct was located at river mean water in dry season
In the water intaking layer of lower section.Water-delivery pump rises phase aqueduct and/or aqueduct in described dry season pumps into described in being passed through by river
Described unit section hydraulic pipeline, water source is delivered to water source heat pump units by described unit section hydraulic pipeline.
This utility model be applicable to the Novel water source heat pump water intake system of the bigger seasonal height of water use the phase of rising and
Extract the situation that the water lines reply height of water is big dry season two, have the advantages that annual water intaking is stable.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described in further detail.
As it is shown in figure 1, this utility model is applicable to the Novel water source heat pump water intake system bag of the bigger seasonal height of water
Include intake strucure, underground water intake structures and water intaking piping on the ground, in underground water intake structures, be provided with water intaking piping, it is also possible to
The auxiliary equipments such as arranging inspection platform, the problem simultaneously taking account of current seepage, at the bottom pocket that underground water intake is constructed also
Can arrange gutter, gutter can lead to the subdrainage passage of deeper.Underground water intake structures include underground hoistway
And underground water pump chamber, the upper end of underground hoistway connects with intake strucure on the ground, and the lower end of underground hoistway is with underground water pump chamber even
Logical, water intaking piping includes unit section hydraulic pipeline and water intaking section hydraulic pipeline, and the upper end of unit section hydraulic pipeline is from underground hoistway
Offshore side, upper end pass-out connect with water resource heat pump, the lower end of unit section hydraulic pipeline and the water-delivery pump being located in the ground in pump chamber
Water side connection, water intaking section hydraulic pipeline include fetch water section water delivery house steward, the phase aqueduct that rises, aqueduct in dry season,
The outlet of water intaking section water delivery house steward connects with the water inlet end of water-delivery pump, the import of water intaking section water delivery house steward and the phase aqueduct that rises
Outlet, aqueduct in dry season go out interruption-forming three way type connection, it is normal that the intake of the phase aqueduct that rises is located at river
In water intaking layer below mean water, dry season, the intake of aqueduct was located at the water intaking below river mean water in dry season
In layer.Water-delivery pump rises phase aqueduct and/or aqueduct in described dry season pumps into described unit section described in being passed through by river
Hydraulic pipeline, water source is delivered to water source heat pump units by described unit section hydraulic pipeline.Such scheme uses the phase water-supply-pipe that rises
Road, aqueduct in dry season tackle the water intaking demand in the case of normal water intaking and extreme seasonality respectively, and built-in water intaking
Piping avoids the external problem being easily disturbed, destroying brought of pipeline, owing to being arranged in the environment of a relative closure, and pipe
Construction and the maintenance of system are the most relatively easy.
During building underground water intake structures and water intaking piping and later stage repairing, safeguarding, it is frequently encountered by needs
The operation that the parts with constant weight of big part are transported into, are gone out, owing to underground water intake structures include two connected differences
Constructing space, hanging device directly hangs out from well head, entering to seem is inconvenient in use.In order to solve this problem, this programme is adopted
With installing the scheme of lifting transferring equipment in underground water pump chamber, as it is shown in figure 1, specifically underground water pump chamber top is provided with and hangs
Shipping unit, handling apparatus includes that the handling track being fixed on underground water pump chamber top and the handling can slided on handling track are made
Industry platform, one end of handling track extends to the lower port of underground hoistway, the thing that underground hoistway is transported by lifting job platform
Part is transported to the setting position of underground water pump chamber along handling track crane, lifting job platform by the object in underground water pump chamber along handling
Track crane be transported to the porch of hoistway lower end, underground backward on send out missile silo road.In such scheme, internal handling apparatus draws
Enter building and the maintenance work in later stage of great convenience early stage.Further, attendant passes in and out underground water intake structure for convenience
Building thing, this programme connectivity part in hoistway upper end, underground with intake strucure on the ground is provided with maintaining ladder, and attendant is by dimension
Protect cat ladder turnover underground water intake structures.
In order to improve the stability of the pipeline being exposed in river, reduce in river the magazine granules such as silt and enter intake pipe
In system, it is ensured that water intaking quality and efficiency, the water intaking end of phase of the rising aqueduct of this programme is passed through the part of water intaking layer by rising
Water phase water-supply-pipe concrete pedestal is fixed on riverbed, is provided with filtering net part at the intake of the phase aqueduct that rises water intaking end,
River enters the phase aqueduct that rises after sieve pack filters.Meanwhile, this programme dry season aqueduct water intaking end
The part being passed through water intaking layer is fixed on riverbed by water-supply-pipe concrete pedestal in dry season, aqueduct water intaking in dry season end
Being provided with filtering net part at intake, river enters aqueduct in dry season after sieve pack filters.In order to ensure water source heat
Pump can get satisfactory water source in dry season, and aqueduct in dry season is designed to according to circumstances to extend by this programme
Scheme, specifically aqueduct in dry season water intaking end be passed through the part of water intaking layer include sealing successively splicing connection base section,
Extension, intake section, extension includes that pipeline section is propped up in some extensions connected by sealing flange.A pipeline section is extended by increasing
Quantity, or change and extend the size of pipeline section itself and can realize the purpose of change aqueduct length.Further, for
The appropriate section making above-mentioned aqueduct water intaking in dry season end can adapt to the requirement of river bed specific environment, and this programme also may be used
With the scheme being designed to deform by its part, i.e. extend pipeline section be can elastic telescopic, the pipeline body of torsional deflection, water intaking
Mouth section is fixed on by intake section positioner on the riverbed setting water intaking layer.Above scheme makes intake section be possible not only to
Extend from axially, it is also possible to from radial distorted, enhance the motility of water intaking.
On the basis of such scheme, this programme further discloses a kind of intake section motion guiding device, specifically
It is that intake section positioner includes the positioning track being fixed on riverbed and the location base of location of can sliding on positioning track
Seat, intake section fixed mount is located on the pedestal of location, and location pedestal drives intake section to slide along positioning track, location.Water intaking
The concrete scheme of mouth section positioner enhances the stability of intake section.Further, in order to realize the automatization of Underwater Navigation,
Change according to water body parameter changes the position of dry point in good time, and this programme also discloses the side of being automatically positioned of a kind of intake section
Case, i.e. aqueduct in dry season also include intake section positioner control system, intake section positioner control system bag
Include water temperature detection module, location pedestal drives module, control module, and control module transmits, according to water temperature detection module, the water temperature of coming
Value drives module drive location pedestal to drive intake section along positioning rail with the comparison result control location pedestal of set water temperature value
Road slides, location.The scheme of above-mentioned intelligent water intaking greatly improves automatization and the navigability of water intake system.
This programme is fetched water in the river of natural environment, can be brought into by the silt in the river of certain depth unavoidably, in order to
Improve this situation, it is ensured that water source heat pump units normally works, remove the drift in water-supply-pipe in time, it is necessary to aqueduct
Carry out periodic cleaning.In order to realize above-mentioned technical purpose, this programme introduces counter-flushing pipeline, and specifically water intaking piping also includes
Counter-flushing pipeline, counter-flushing pipeline includes backwash total pipeline, rise phase aqueduct Backwash pipeline, aqueduct in dry season
Backwash pipeline, the water inlet of backwash total pipeline connects with unit section hydraulic pipeline upper end, the outlet of backwash total pipeline
Three way type is formed with the water inlet of the water inlet of phase aqueduct Backwash pipeline that rises, aqueduct Backwash pipeline in dry season
Connection, the outlet of phase aqueduct Backwash pipeline of rising connects with the downstream line of the phase aqueduct that rises, and dry season is defeated
The outlet of waterpipe Backwash pipeline connects with the downstream line of aqueduct in dry season.As it is shown in figure 1, carrying out backwash
Time, close water intaking section water delivery house steward and the connectivity points of phase aqueduct of rising, aqueduct Backwash pipeline in dry season and low water
The connectivity points of phase aqueduct, water-delivery pump is rushed through phase aqueduct Backwash pipeline of rising by aqueduct water intaking in dry season
Wash the phase aqueduct that rises.Close water intaking section water delivery house steward and the connectivity points of aqueduct in dry season, the phase aqueduct that rises anti-
The connectivity points of flushing pipe and the phase aqueduct that rises, water-delivery pump is fetched water through water-supply-pipe in dry season by the phase aqueduct that rises
Road Backwash pipeline rinses aqueduct in dry season.The silt in water-supply-pipe downstream progressively moves to along with the minimizing of upstream quantity of sand and mud
Upstream, then be discharged, so circulation is finally reached the purpose of cleaning pipeline.
Circuit that above scheme relates to, module, electronic devices and components all can use scheme generally in the art and type selecting, also
Specially designed scheme can be used according to actual needs.
The Novel water source heat pump water intake system being applicable to the bigger seasonal height of water of this programme uses phase of rising and withered
The water phase two extracts the situation that the water lines seasonal height of water of reply is big, use the convenient early stage of lifting transferring equipment structure and after
The maintenance of phase, uses the water intaking guider that can change water intaking position the most flexibly to improve the quality of water intaking and water supply
Stability, uses the drift in backwash piping cleaning water-supply-pipe, effectively prevent line clogging, reduce Water source heat pump unit
The fault rate of group.Based on above feature, the Novel water source heat pump water intaking being applicable to the bigger seasonal height of water of this programme is
System is compared currently existing scheme and is had substantive distinguishing features and progress.
The Novel water source heat pump water intake system being applicable to the bigger seasonal height of water of this programme is not limited to concrete reality
Executing the content disclosed in mode, the technical scheme occurred in embodiment can be with individualism, it is also possible to mutually comprise, this area skill
Art personnel combine, according to this programme, the simple alternative that common knowledge makes and fall within the scope of this programme.