CN205772865U - Extensive potroom overhaul of the equipments aid system - Google Patents
Extensive potroom overhaul of the equipments aid system Download PDFInfo
- Publication number
- CN205772865U CN205772865U CN201620510025.0U CN201620510025U CN205772865U CN 205772865 U CN205772865 U CN 205772865U CN 201620510025 U CN201620510025 U CN 201620510025U CN 205772865 U CN205772865 U CN 205772865U
- Authority
- CN
- China
- Prior art keywords
- track
- girder
- factory building
- promote
- overhaul
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Extensive potroom overhaul of the equipments aid system relates to a kind of Large aluminum electrolytic plant workshop, with overhaul shop, workshop crane gear is overhauled supplementary structure.This utility model provides a kind of potroom overhaul of the equipments aid system the most extensive to crane facility maintenance.This utility model includes the Factory Building girder with Factory Building track, it is characterised in that: it is provided with by lifting device in the middle part of Factory Building girder and can promote track girder, can promote and on track girder, be provided with the track that the crane gear corresponding with Factory Building track runs.
Description
Technical field
This utility model relates to a kind of Large aluminum electrolytic plant workshop, with overhaul shop, workshop crane gear is overhauled supplementary structure.
Background technology
Development along with aluminum electrolysis technology, the continuous maturation of aluminum electrolysis technology, the scale of electrolytic aluminium is constantly expanding with capacity, the capacity of current electrolysis aluminum has reached 600KAV, and the magnetic field intensity at potroom can reach more than 1000 Gausses, in such strong magnetic field circumstance, maintenance of equipment difficulty can be caused, workshop arranges substantial amounts of crane gear, if crane gear damages, its maintenance exists serious problem.
Summary of the invention
This utility model is aiming at the problems referred to above, it is provided that a kind of potroom overhaul of the equipments aid system the most extensive to crane facility maintenance.
In order to realize above-mentioned purpose of the present utility model, this utility model adopts the following technical scheme that, this utility model includes the Factory Building girder with Factory Building track, it is characterized in that: be provided with by lifting device in the middle part of Factory Building girder and can promote track girder, can promote and on track girder, be provided with the track that the crane gear corresponding with Factory Building track runs.
As a kind of preferred version of the present utility model, it is provided with the delivery track of gantry transferring system corresponding to the lower section that can promote track girder;The carrying track corresponding with Factory Building track it is provided with in gantry transferring system.
As another kind of preferred version of the present utility model, described Factory Building girder is provided with upset car bumper corresponding to the two ends that can promote track girder.
As the third preferred version of the present utility model, it is positioned at and can promote the two ends of track girder and be provided with lifting guide upright post, promote and be provided with upright guide rail on guide upright post, track girder two ends can be promoted and be provided with the directive wheel coordinated with upright guide rail.
Further, described lifting guide upright post top is provided with crossbeam, and described lifting device is the hoisting equipment being arranged on crossbeam, and the steel wire rope of the hoisting equipment fixed pulley through crossbeam two ends is connected with the movable pulley that can promote track girder two ends.
Further, on described crossbeam the fixed pulley of one end and the center of circle of the movable pulley corresponding with this fixed pulley not on same vertical straight line.
As the 4th kind of preferred version of the present utility model, described Factory Building girder and can promote and be provided with the clinch cooperated and locking mechanism between track girder.
As the 5th kind of preferred version of the present utility model, described lifting is provided with lifting power supply guider on track girder, lifting power supply guider touches line with the Factory Building on Factory Building girder for electric slip ring with cable by power supply folding arm and is connected.
The beneficial effects of the utility model: 1, this utility model can promote track girder by setting, when crane gear normally uses, can promote track girder and keep concordant with Factory Building girder, and crane gear is normally walked with promoting on track girder at Factory Building girder;When crane gear breaks down and needs repairing, track girder can be promoted and mention, then gantry transferring system be opened to promoting at track girder, the carrying track on gantry transferring system top and Factory Building track alignment;Reach crane gear carry on track;Then gantry transferring system is had laterally crane gear transport to be keeped in repair to maintenance shop, it is to avoid the harmful effect to maintenance of the strong magnetic in workshop.
2, this utility model is by arranging upset car bumper, when promoting track girder and lift, can be put down by upset car stop, prevents crane gear from dropping at track girder and cause industrial accident from can promote.
3, this utility model is cooperated by setting directive wheel and upright guide rail, can make the lifting that can promote track girder more stable, and can prevent the eccentric upset produced because promoting track girder, safe and reliable.
4, this utility model utilizes hoisting equipment the two ends that can promote track girder to be promoted and put down simultaneously, makes to promote track girder two ends and steadily rises problems such as not havinging inclination, further operation stability of the present utility model.
5, this utility model is by arranging clinch, can ensure that track and the Factory Building track of the crane gear that can promote on track girder operation can well coordinate, it is ensured that crane gear does not haves the problems such as card when running between the track that Factory Building track and crane gear run;Being provided with locking mechanism, can prevent from promoting track girder maloperation or wire cable rupture when, can promote track girder and not fall out or lift, safety is good.
6, of the present utility model lifting is provided with lifting power supply guider on track girder, it is ensured that crane gear still has stable power supply can promote on track girder.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Fig. 2 can promote the top view of track girder.
Fig. 3 is the A portion enlarged drawing of Fig. 1.
Fig. 4 is the B portion enlarged drawing of Fig. 1.
Fig. 5 is the partial enlarged drawing of Fig. 2.
Fig. 6 is the structural representation of upset car bumper.
Fig. 7 is the structural representation that directive wheel coordinates place with guide rail.
Fig. 8 is an up powering guider and can promoting the structural representation that track girder is connected.
In accompanying drawing, 1 is delivery track, 2 is locking mechanism, 3 for can promote track girder, 4 is Factory Building track, 5 is power supply folding arm, 6 is cable, 7 is crossbeam, 8 is lifting device, 9 tracks run for crane gear, 10 is fixed pulley, 11 for promoting guide upright post, 12 is steel wire rope, 13 is movable pulley, 14 is upset car bumper, 15 is Factory Building girder, 16 for promoting power supply guider, 17 is inductive switch, 18 is directive wheel, 19 is connecting portion, 20 is upright guide rail, 21 is vehicle blocking frame, 22 is overturning oil cylinder, 23 is pedestal, 24 on take turns, 25 is lower whorl.
Detailed description of the invention
This utility model includes the Factory Building girder 15 with Factory Building track 4, it is characterised in that: it is provided with by lifting device 8 in the middle part of Factory Building girder 15 and can promote track girder 3, can promote and on track girder 3, be provided with the track 9 that the crane gear corresponding with Factory Building track 4 runs.
As a kind of preferred version of the present utility model, it is provided with the delivery track 1 of gantry transferring system corresponding to the lower section that can promote track girder 3;The carrying track corresponding with Factory Building track 4 it is provided with in gantry transferring system.
As another kind of preferred version of the present utility model, described Factory Building girder 15 is provided with upset car bumper 14 corresponding to the two ends that can promote track girder 3.
Described upset car bumper 14 includes the pedestal 23 being arranged on Factory Building girder 15, hinged on pedestal 23 is provided with the vehicle blocking frame 21 corresponding with Factory Building track 4, is provided with overturning oil cylinder 22 between pedestal 23 and vehicle blocking frame 21.
As the third preferred version of the present utility model, it is positioned at and can promote the two ends of track girder 3 and be provided with lifting guide upright post 11, promote and be provided with upright guide rail 20 on guide upright post 11, track girder 3 two ends can be promoted and be provided with the directive wheel 18 coordinated with upright guide rail 20.
Described track girder 3 two ends that promote are provided with connecting portion 19, and described directive wheel 18 is arranged on connecting portion 19, directive wheel 18 include coordinating with guide rail on take turns 24 and lower whorl 25.For avoiding the connection that can promote track girder 3 and Factory Building girder 15 that track 9 and the interference of Factory Building track 4 running crane gear occurs, by arranging directive wheel 18 at connecting portion 19, thus realize the guiding that can promote track girder 3, and be directed to take turns 18 be set on take turns 24 and lower whorl 25, the wobbler action produced at connecting portion 19 can be eliminated.
Further, described lifting guide upright post 11 top is provided with crossbeam 7, and described lifting device 8 is the hoisting equipment being arranged on crossbeam 7, and the steel wire rope 12 of the hoisting equipment fixed pulley 10 through crossbeam 7 two ends is connected with the movable pulley 13 that can promote track girder 3 two ends.
Further, on described crossbeam 7 fixed pulley 10 of one end and the center of circle of the movable pulley 13 corresponding with this fixed pulley 10 not on same vertical straight line.
As the 4th kind of preferred version of the present utility model, described Factory Building girder 15 and can promote and be provided with the clinch cooperated and locking mechanism 2 between track girder 3.
Described locking mechanism 2 includes by being arranged at the electric pushrod device that can promote track girder about 3 both sides;On described Factory Building girder 15, the electric pushrod device corresponding to downside is provided with lower lockhole, and on the crossbeam 7 of described lifting guide upright post 11, the electric pushrod device corresponding to upside is provided with upper lockhole.
It is provided with inductive switch on described electric pushrod device 17.When inductive switch senses that can promote electric pushrod device 17 on the downside of when track girder 3 moves to lower limit position stretches out, and locked with Factory Building girder 15, making to promote track girder 3 will not promote because of maloperation;When inductive switch senses that can promote track girder 3 moves to upper extreme position, upside electric pushrod device 17 stretches out, locked with crossbeam 7, prevents promoting track girder 3 and drops, and safety is good.
As the 5th kind of preferred version of the present utility model, described lifting is provided with lifting power supply guider 16 on track girder 3, lifting power supply guider 16 touches line with the Factory Building on Factory Building girder 15 for electric slip ring with cable 6 by power supply folding arm 5 and is connected.
Described lifting power supply guider 16 is installed on by cross regulating tank and can promote on track girder 3.It is easy to touch line with Factory Building for electric slip ring be connected and match.
During the actual application of this utility model, maintenance shop can be set up on the potroom side of high magnetic field intensity;Carrying track and gantry transferring system is utilized potroom and maintenance shop to be coupled together;One maintenance shop can coordinate multiple potroom to use;When equipment breaks down and needs repairing, can promote track girder 3 and mention, gantry transferring system moves to can promote at track girder 3, and the crane gear needed repairing moves on the delivery track 1 in gantry transferring system;Then gantry transferring system transverse shifting on carrying track, it would be desirable to the crane gear of maintenance moves to maintenance shop and places under repair, and can avoid the highfield impact on maintenance of equipment, easy to maintenance.
It is understandable that, above with respect to specific descriptions of the present utility model, it is merely to illustrate this utility model and is not limited to the technical scheme described by this utility model embodiment, it will be understood by those within the art that, still this utility model can be modified or equivalent, to reach identical technique effect;Needs are used, all within protection domain of the present utility model as long as meeting.
Claims (10)
1. extensive potroom overhaul of the equipments aid system, including the Factory Building girder (15) with Factory Building track (4), it is characterized in that: Factory Building girder (15) middle part is provided with by lifting device (8) can promote track girder (3), can promote and be provided with the track (9) that the crane gear corresponding with Factory Building track (4) runs on track girder (3).
Extensive potroom overhaul of the equipments aid system the most according to claim 1, it is characterised in that: the delivery track (1) of gantry transferring system it is provided with corresponding to the lower section that can promote track girder (3);The carrying track corresponding with Factory Building track (4) it is provided with in gantry transferring system.
Extensive potroom overhaul of the equipments aid system the most according to claim 1, it is characterised in that: on described Factory Building girder (15), the two ends that can promote track girder (3) are provided with upset car bumper (14).
Extensive potroom overhaul of the equipments aid system the most according to claim 3, it is characterized in that: described upset car bumper (14) includes the pedestal (23) being arranged on Factory Building girder (15), pedestal (23) is the most hinged is provided with the vehicle blocking frame (21) corresponding with Factory Building track (4), is provided with overturning oil cylinder (22) between pedestal (23) and vehicle blocking frame (21).
Extensive potroom overhaul of the equipments aid system the most according to claim 1, it is characterized in that: be positioned at and can promote the two ends of track girder (3) and be provided with lifting guide upright post (11), promote and be provided with upright guide rail (20) on guide upright post (11), track girder (3) two ends can be promoted and be provided with the directive wheel (18) coordinated with upright guide rail (20).
Extensive potroom overhaul of the equipments aid system the most according to claim 5, it is characterized in that: described track girder (3) two ends that promote are provided with connecting portion (19), described directive wheel (18) is arranged on connecting portion (19), directive wheel (18) include coordinating with guide rail on take turns (24) and lower whorl (25).
Extensive potroom overhaul of the equipments aid system the most according to claim 5, it is characterized in that: described lifting guide upright post (11) top is provided with crossbeam (7), described lifting device (8) is for be arranged at the hoisting equipment on crossbeam (7), and the steel wire rope (12) of the hoisting equipment fixed pulley (10) through crossbeam (7) two ends is connected with the movable pulley (13) that can promote track girder (3) two ends.
Extensive potroom overhaul of the equipments aid system the most according to claim 7, it is characterised in that: the fixed pulley (10) of the upper one end of described crossbeam (7) and the center of circle of the movable pulley (13) corresponding with this fixed pulley (10) be not on same vertical straight line.
Extensive potroom overhaul of the equipments aid system the most according to claim 1, it is characterised in that: described Factory Building girder (15) and can promote and be provided with the clinch cooperated and locking mechanism (2) between track girder (3).
Extensive potroom overhaul of the equipments aid system the most according to claim 1, it is characterized in that: described lifting is provided with lifting power supply guider (16) on track girder (3), lifting power supply guider (16) is touched line with the Factory Building on Factory Building girder (15) for electric slip ring with cable (6) by power supply folding arm (5) and is connected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620510025.0U CN205772865U (en) | 2016-05-31 | 2016-05-31 | Extensive potroom overhaul of the equipments aid system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620510025.0U CN205772865U (en) | 2016-05-31 | 2016-05-31 | Extensive potroom overhaul of the equipments aid system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205772865U true CN205772865U (en) | 2016-12-07 |
Family
ID=58138561
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620510025.0U Expired - Fee Related CN205772865U (en) | 2016-05-31 | 2016-05-31 | Extensive potroom overhaul of the equipments aid system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205772865U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105858467A (en) * | 2016-05-31 | 2016-08-17 | 中国有色(沈阳)冶金机械有限公司 | Overhauling auxiliary system for large-scale electrolytic aluminum workshop appliance |
CN109607033A (en) * | 2018-12-19 | 2019-04-12 | 五冶集团上海有限公司 | A kind of overhaul of the equipments track |
-
2016
- 2016-05-31 CN CN201620510025.0U patent/CN205772865U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105858467A (en) * | 2016-05-31 | 2016-08-17 | 中国有色(沈阳)冶金机械有限公司 | Overhauling auxiliary system for large-scale electrolytic aluminum workshop appliance |
CN109607033A (en) * | 2018-12-19 | 2019-04-12 | 五冶集团上海有限公司 | A kind of overhaul of the equipments track |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205501818U (en) | Steel truss arch bridge maintenance car | |
CN208235340U (en) | It is a kind of can automatic lifting steel strand tension Mobile workbench | |
CN206126684U (en) | Electric installation is got in automation of overhead wiping line | |
CN104632088A (en) | Petroleum drilling machine tower-shaped derrick sleeving mounting method | |
CN105752852A (en) | Gantry crane for lifting containers | |
CN205772865U (en) | Extensive potroom overhaul of the equipments aid system | |
CN107512661A (en) | A kind of replacing of vehicle wheel method | |
CN201990395U (en) | Automatic electricity taking device for overhead trolley conductor | |
CN105858467A (en) | Overhauling auxiliary system for large-scale electrolytic aluminum workshop appliance | |
CN108706019B (en) | Intelligent identification's multipurpose tram car lifting system | |
CN205170212U (en) | Semi -portal crane | |
CN204038992U (en) | A kind of erecting stage for subway busbar | |
CN105539205A (en) | Comprehensive operation vehicle for subway overhead line system | |
CN207451439U (en) | A kind of Overhead Crane Bridge | |
CN105565222A (en) | Vehicle-mounted mobile lifting overhaul platform | |
CN202866692U (en) | Petroleum drilling tool ramp transferring device | |
CN202924955U (en) | Oven door service car for coke oven | |
CN205275061U (en) | Semi -portal crane | |
CN205045724U (en) | Hoisting apparatus of lifting hook formula impeller head | |
CN206721693U (en) | A kind of elevating mechanism of dragging suspension basket | |
CN203578756U (en) | Slide water gap sand filling device | |
CN204096949U (en) | The adjustable gauntry crane of a kind of suspension centre | |
CN206394468U (en) | Insertion hoistable platform with automatic telescopic railing | |
CN202089039U (en) | Suspended-type lifting platform | |
CN102839896A (en) | Mine safety door |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161207 Termination date: 20200531 |