Prior art keywords
floor
girder
steel beam
longeron
reinforced steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620425830.3U
Other languages
Chinese (zh)
Inventor
张少彪
宣立军
张振禹
雷学玲
马慧敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Bureau Construction Development Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Bureau Construction Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Bureau Construction Development Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201620425830.3U priority Critical patent/CN205743066U/en
Application granted granted Critical
Publication of CN205743066U publication Critical patent/CN205743066U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of interim reinforcement structure of floor for bearing heavy load, this floor is provided with many crossbeams, it is provided with multiple tracks longeron, if this reinforcement structure includes longitudinally disposed arterial highway reinforced steel beam and girder and Duo Gen brace steel post between two adjacent described crossbeams;Described brace steel post is supported on below described longeron, is welded with one and supports joist between two laterally adjacent described brace steel posts, is vertically connected with one and supports shaped steel on described support joist;Arranging described reinforced steel beam and girder together described in adjacent twice between longeron, described reinforced steel beam and girder is supported on below floor, and reinforced steel beam and girder described in per pass is connected with described crossbeam by anchor slab by many described support type bracing members, the two ends of described reinforced steel beam and girder.Load on floor can be delivered evenly to ground by this utility model effectively, both can guarantee that floor is not subject to crushing, and can improve again the bearing capacity of floor;When floor heavy duty is removed, easily remove, can quickly revert to original state.

Description

For bearing the interim reinforcement structure of floor of heavy load
Technical field
This utility model relates to a kind of floor reinforcement structure, and a kind of floor for bearing heavy load is strengthened temporarily Structure.
Background technology
For the bigger space that utilizes, most domestic new building is all designed with basement.Basement can monolayer or many Layer, can be as underground parking, warehouse, pumping plant, and machine room etc. uses, and it is red that basement region area the most all covers building Area in line region, on it, floor can bear pedestrian and general vehicle load.But, on locality, floor need to be stacked temporarily When lot of materials or installation large-scale component, need heavy-duty machinery (such as truck crane etc.) operation on floor, original floor Design load can not meet the demand of actual loading on floor, now needs to take effective strengthening measure, makes the floor will not It is subject to crushing because of heavy duty, it is to avoid floor produces collapse phenomenon because of overweight.
Summary of the invention
This utility model provides a kind of floor for bearing heavy load for solving technical problem present in known technology Interim reinforcement structure, this structure is not only able to improve the bearing capacity of floor temporarily, additionally it is possible to quickly revert to original state.
This utility model is adopted the technical scheme that by solving technical problem present in known technology: one is used for bearing The interim reinforcement structure of floor of heavy load, this floor is provided with many crossbeams, is provided with between two adjacent described crossbeams Multiple tracks longeron, if this reinforcement structure includes longitudinally disposed arterial highway reinforced steel beam and girder and Duo Gen brace steel post;Described supporting steel Post is supported on below described longeron, is welded with one and supports joist between two laterally adjacent described brace steel posts, Vertically it is connected with one on described support joist and supports shaped steel;Add described in arranging between longeron described in adjacent twice together Strong girder steel, described reinforced steel beam and girder is supported on below floor, reinforced steel beam and girder described in per pass by many described support type bracing members, The two ends of described reinforced steel beam and girder are connected with described crossbeam by anchor slab.
Many described brace steel posts are evenly arranged.
This utility model has the advantage that with good effect: this utility model is that the driving floor under heavy load adds consolidation Structure, employing shaped steel as main reinforcement material, load path is: floor heavy duty-floor-reinforced steel beam and girder-support shaped steel -support joist-brace steel post-ground, effectively the load on floor can be delivered evenly to ground, both can guarantee that floor It is not subject to crushing, the bearing capacity of floor can be improved again;When floor heavy duty is removed, shaped steel can be easy to remove, can be quickly Revert to original state.In sum, this utility model has that principle is simple, processing ease, supporting effect are good and shaped steel The advantages such as recoverable.
Accompanying drawing explanation
Fig. 1 is front elevation view of the present utility model;
Fig. 2 is side elevational view of the present utility model.
In figure: 1, reinforced steel beam and girder;2, joist is supported;3, brace steel post;4, shaped steel is supported;5, crossbeam;6, vertical Beam;7, floor.
Detailed description of the invention
For summary of the invention of the present utility model, feature and effect can be further appreciated that, hereby enumerate following example, and coordinate Accompanying drawing describes in detail as follows:
Referring to Fig. 1 and Fig. 2, a kind of interim reinforcement structure of floor for bearing heavy load, this floor 7 is provided with many Root crossbeam 5, is provided with multiple tracks longeron 6 between two adjacent described crossbeams 5, and this reinforcement structure includes longitudinally disposed If arterial highway reinforced steel beam and girder 1 and Duo Gen brace steel post 3;Described brace steel post 3 is supported on below described longeron 6, in horizontal phase It is welded with one between two adjacent described brace steel posts 3 and supports joist 2, described support joist 2 is vertically connected with one Individual support shaped steel 4;Described reinforced steel beam and girder 1, described reinforced steel beam and girder 1 together are being set between longeron 6 described in adjacent twice Being supported on below floor 7, reinforced steel beam and girder 1 described in per pass is supported by many described support shaped steel 4, described reinforced steel beam and girder 1 Two ends be connected with described crossbeam 5 by anchor slab.
In the present embodiment, in order to be delivered evenly on ground by the load on floor, many described brace steel posts 3 are equal Even layout.
Construction method of the present utility model:
Anchor slab is first installed on floor crossbeam 5, then lifts brace steel post 3 with truck crane, support floor longeron 6 and complete peace Dress;Use truck crane lifting reinforced steel beam and girder 5, and weld with the most mounted anchor slab;Joist 2 will be supported on ground Weld with supporting shaped steel 4, then utilize truck crane to be lifted to elevator, utilize elevator its jacking to be arrived afterwards Precalculated position, and two ends and brace steel post 3 firm welding of joist 2 will be supported;Supporting shaped steel 4 and reinforced steel beam and girder 1 Between jump a queue backing plate, after holding out against reinforced steel beam and girder 1, then spot welding holds out against face surrounding.
Although preferred embodiment of the present utility model being described above in conjunction with accompanying drawing, but this utility model not office Being limited to above-mentioned detailed description of the invention, above-mentioned detailed description of the invention is only schematically, is not restrictive, this The those of ordinary skill in field, under enlightenment of the present utility model, is being protected without departing from this utility model objective and claim In the case of the scope protected, it is also possible to make a lot of form, within these belong to protection domain of the present utility model.

Claims (2)

1., for bearing the interim reinforcement structure of floor of heavy load, this floor is provided with many crossbeams, adjacent two Multiple tracks longeron it is provided with between crossbeam, it is characterised in that if this reinforcement structure includes that longitudinally disposed arterial highway is strengthened described in root Girder steel and Duo Gen brace steel post;
Described brace steel post is supported on below described longeron, is welded with one between two laterally adjacent described brace steel posts Root supports joist, is vertically connected with one and supports shaped steel on described support joist;
Arranging described reinforced steel beam and girder together described in adjacent twice between longeron, described reinforced steel beam and girder is supported on below floor, Reinforced steel beam and girder described in per pass is by many described support type bracing members, and the two ends of described reinforced steel beam and girder are by anchor slab and described crossbeam Connect.
The interim reinforcement structure of floor for bearing heavy load the most according to claim 1, it is characterised in that many Described in root, brace steel post is evenly arranged.
CN201620425830.3U 2016-05-11 2016-05-11 For bearing the interim reinforcement structure of floor of heavy load Expired - Fee Related CN205743066U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620425830.3U CN205743066U (en) 2016-05-11 2016-05-11 For bearing the interim reinforcement structure of floor of heavy load

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620425830.3U CN205743066U (en) 2016-05-11 2016-05-11 For bearing the interim reinforcement structure of floor of heavy load

Publications (1)

Publication Number Publication Date
CN205743066U true CN205743066U (en) 2016-11-30

Family

ID=57369133

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620425830.3U Expired - Fee Related CN205743066U (en) 2016-05-11 2016-05-11 For bearing the interim reinforcement structure of floor of heavy load

Country Status (1)

Country Link
CN (1) CN205743066U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114737790A (en) * 2022-05-07 2022-07-12 中国十九冶集团有限公司 Reverse dismantling method for high-rise frame structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114737790A (en) * 2022-05-07 2022-07-12 中国十九冶集团有限公司 Reverse dismantling method for high-rise frame structure
CN114737790B (en) * 2022-05-07 2023-02-28 中国十九冶集团有限公司 Reverse dismantling method for high-rise frame structure

Similar Documents

Publication Publication Date Title
CN102644358A (en) Steel coupling beam capable of being replaced after strong earthquake
CN102913137B (en) Sinking tubular steel derrick and mounting method of same
CN102518050A (en) Operation platform for replacing support saddle of bridge
CN201386291Y (en) Static load test device of composite foundation
CN104828758A (en) Thermal power generating unit draught fan structure support overall transfer device and transfer method
CN202247713U (en) Combined protective shed frame
CN100362200C (en) Supporting displacement method for lifting component and supporting system thereof
CN103967263B (en) Hydraulic automatic jumping discharging platform
CN102425123B (en) Combined type protection shed frame and construction method thereof
CN205743066U (en) For bearing the interim reinforcement structure of floor of heavy load
CN206581147U (en) The support system constructed for bridge long-cantilever capping beam
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN203947758U (en) Novel hydraulic automatic climbing discharging platform
CN205741942U (en) A kind of great cantilever chooses arm pier cap beam segmental timbering
CN211008659U (en) Tunnel basement reinforcing structure
CN104233961A (en) Triangular supporting bracket of suspended cast bridge block 0
CN106144877A (en) A kind of attachment means for Longspan Bridge lifting and construction method
CN106522563A (en) Building construction member slip mechanism and installation and demounting method thereof
CN103204428A (en) Loading-transporting lifting appliance for steel bar truss floor support plate
CN202260191U (en) Mobile mounting rack for cabinet-type equipment
CN205777531U (en) Floor slab construction beam string shuttering supporting equipment
CN205527291U (en) A frame type frame for hoisting two superimposed sheets
CN208251142U (en) A kind of overhanging type Prefabricated steel construction basis of construction elevator
CN107237515A (en) The support meanss and its application method of circular steel truss structure
CN208617174U (en) A kind of building hoist base support formula bracing means

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161130

Termination date: 20210511

CF01 Termination of patent right due to non-payment of annual fee