CN205742998U - Straight cutting dish pin falsework side bar formwork system - Google Patents

Straight cutting dish pin falsework side bar formwork system Download PDF

Info

Publication number
CN205742998U
CN205742998U CN201620417184.6U CN201620417184U CN205742998U CN 205742998 U CN205742998 U CN 205742998U CN 201620417184 U CN201620417184 U CN 201620417184U CN 205742998 U CN205742998 U CN 205742998U
Authority
CN
China
Prior art keywords
bar
side bar
fixed
vertical rod
formwork system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620417184.6U
Other languages
Chinese (zh)
Inventor
王鲁
罗大永
程菲
谢东峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Tanki Industry & Commerce Group Co Ltd
Original Assignee
Shandong Tanki Industry & Commerce Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Tanki Industry & Commerce Group Co Ltd filed Critical Shandong Tanki Industry & Commerce Group Co Ltd
Priority to CN201620417184.6U priority Critical patent/CN205742998U/en
Application granted granted Critical
Publication of CN205742998U publication Critical patent/CN205742998U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Straight cutting dish pin falsework side bar formwork system, belongs to technical field of building construction.It is characterized in that: be connected by cross bar (1) between vertical rod at the bottom of beam (12) bar edge-on with beam (2), side bar (7) outside is provided with diagonal brace (9), at the bottom of diagonal brace (9) and beam, the distance between vertical rod (12) is gradually increased from the bottom to top, the two ends of master at the bottom of beam stupefied (10) bar edge-on with beam (2) respectively and diagonal brace (9) are fixed and are connected, vertical rod at the bottom of beam (12) upper end is fixed with the beam bar (11) arranged along side bar (7) length direction, and beam bar (11) is supported on the downside of master at the bottom of beam stupefied (10).This straight cutting dish pin falsework side bar formwork system simple in construction, easy to operate, work progress standardization and standardization, the advantage such as have that speed of application is fast, reduction of erection time, reduction cost of labor, consumptive material are few, and ensure that side bar formwork system stress balance and monolithic stability.

Description

Straight cutting dish pin falsework side bar formwork system
Technical field
Straight cutting dish pin falsework side bar formwork system, belongs to technical field of building construction.
Background technology
In recent years, at the realm of building construction, labour cost rises steadily, and the proportion shared in construction costs of cost of labor is increasing, how to accelerate speed of application, contracting duration cost declining, increase the benefit be requirement of engineering in the face of and a major issue of solution.The many advantages such as straight cutting dish pin falsework is easy to operate with it, time and labour saving, remarkable in economical benefits obtain rapid promotion and application in engineering, but straight cutting dish pin falsework is limited by self fixing modulus, it needs fastener type steel pipe to assist when side bar formwork, owing to each engineering actual condition is different, uneven plus operative's level, fastener type steel pipe many and random as auxiliary so that side bar formwork way is chaotic, and consumptive material of wasting time and energy.Therefore engineering construction is had great importance by the standardization of side bar formwork system and standardization.
Summary of the invention
The technical problems to be solved in the utility model is: overcome the deficiencies in the prior art, it is provided that a kind of simple in construction, easy to operate, time and labour saving, constructing operation standardization and normalized straight cutting dish pin falsework side bar formwork system.
This utility model solves its technical problem and be the technical scheme is that this straight cutting dish pin falsework side bar formwork system, stupefied including master at the bottom of the edge-on bar of beam and beam, the edge-on bar of beam is vertically fixed on the inner side of side bar, the stupefied width along side bar of master at the bottom of beam is secured transverse to the lower section of side bar, it is characterized in that: also include vertically being fixed on vertical rod at the bottom of the beam below side bar, it is connected by cross bar between the bar edge-on with beam of vertical rod at the bottom of beam, diagonal brace it is provided with outside side bar, at the bottom of diagonal brace and beam, the distance between vertical rod is gradually increased from the bottom to top, two ends bar edge-on with beam respectively and diagonal brace that master at the bottom of beam is stupefied are fixed and are connected, vertical rod upper end at the bottom of beam is fixed with the beam bar that edgewise beam length direction is arranged, beam bar is supported on the downside that master at the bottom of beam is stupefied.
Preferably, vertical rod at the bottom of described beam is fixed with the bracing piece of the width along side bar by fastener, and bracing piece two ends are separately fixed on the edge-on bar of beam and diagonal brace.
Preferably, vertical rod at the bottom of described beam being additionally provided with the horizon bar of the length direction along side bar, horizon bar is fixed by fastener.
Preferably, the edge-on bar of described beam and the connection dish being respectively fixed with in vertical rod at the bottom of beam for being connected cross bar, cross bar two ends are provided with and are connected the straight inserting head that dish coordinates.
Preferably, the floor master that described beam edge-on bar upper end is fixed with level by adjustable torr support is stupefied.
Preferably, described beam bar is fixed on vertical rod upper end at the bottom of beam by adjustable torr support.
Preferably, the upper end of described adjustable torr support is fixed with the supporting plate in edgewise beam length direction, and the both sides of supporting plate flip up the support slot forming rectangle.
Compared with prior art, this utility model straight cutting dish pin falsework side bar formwork system is had the beneficial effect that
1, at the bottom of beam pole pair beam, the stupefied middle part of master is supported, thus provide effective for template bottom side bar and support, avoid pouring during side bar that at the bottom of template and beam, master is stupefied deforms, pour safe and reliable, by vertical rod at the bottom of beam and beam bar, the application site of the common steel tube of fastener type is concentrated, reduce the usage amount of fastener type common steel tube, make constructing operation standardization, and side bar supporting construction is simple, accelerate speed of application, reduction of erection time, reduce cost of labor, the most chaotic side bar formwork system and mold method is made to be improved, form standardized side bar formwork system and mold method;Side bar support system stress can be balanced by diagonal brace.
2, the edge-on bar of beam near side bar can be balanced by bracing piece by diagonal brace, and horizon bar and bracing piece make side bar formwork system form stability in the large.
3, the various vertical rods such as vertical rod at the bottom of cross bar and the edge-on bar of beam, beam are connected by connection dish, simple in construction, easy to operate, time and labour saving.
4, the stupefied height with beam bar of floor master can quickly be adjusted by adjustable torr support, easy to operate, accelerate speed of application, reduction of erection time.
5, being fixed support by supporting plate to beam bar and floor master are stupefied, easy to operate, the reduction of erection time, beam bar and the stupefied fixation of floor master are reliable.
Accompanying drawing explanation
Fig. 1 is the schematic front view of straight cutting dish pin falsework side bar formwork system.
Fig. 2 is the local drawing of straight cutting dish pin falsework side bar formwork system.
Fig. 3 is the structural representation of adjustable torr support.
In figure: 1, cross bar 2, the edge-on bar of beam 3, connection dish 4, floor master be stupefied 5, floor 6, adjustable torr support 601, supporting plate 602, support slot 603, screw rod 604, leading screw 7, side bar 8, beam side master are stupefied 9, master at the bottom of diagonal brace 10, beam is stupefied 11, vertical rod 13, horizon bar 14, fastener 15, bracing piece at the bottom of beam bar 12, beam.
Detailed description of the invention
Fig. 1 ~ 3 are most preferred embodiments of the present utility model, and 1 ~ 3 pair of this utility model is described further below in conjunction with the accompanying drawings.
Straight cutting dish pin falsework side bar formwork system, including master stupefied 10 at the bottom of the edge-on bar of beam 2 and beam, the edge-on bar of beam 2 is vertically fixed on the inner side of side bar 7, master at the bottom of beam stupefied 10 is secured transverse to the lower section of side bar 7 along the width of side bar 7, also include vertically being fixed on vertical rod 12 at the bottom of the beam below side bar 7, it is connected by cross bar 1 between the bar edge-on with beam of vertical rod 12 at the bottom of beam 2, diagonal brace 9 it is provided with outside side bar 7, at the bottom of diagonal brace 9 and beam, the distance between vertical rod 12 is gradually increased from the bottom to top, the two ends of master at the bottom of beam stupefied 10 bar 2 edge-on with beam respectively and diagonal brace 9 are fixed and are connected, vertical rod 12 upper end at the bottom of beam is fixed with the beam bar 11 arranged along side bar 7 length direction, beam bar 11 is supported on the downside of master at the bottom of beam stupefied 10.It is supported in the middle part of beam bar 11 stupefied to master at the bottom of beam 10, thus provide effective for template bottom side bar 7 and support, avoid deforming pouring master stupefied 10 at the bottom of template and beam during side bar 7, pour safe and reliable, by vertical rod at the bottom of beam 12 and beam bar 11, the application site of the common steel tube of fastener type is concentrated, reduce the usage amount of fastener type common steel tube, make constructing operation standardization, and side bar supporting construction is simple, accelerate speed of application, reduction of erection time, reduce cost of labor, the most chaotic side bar 7 formwork system and mold method is made to be improved, form standardized side bar 7 formwork system and mold method;Side bar formwork system stress can be balanced by diagonal brace 9.
Concrete: as shown in Figure 1 and 2: the edge-on bar of beam 2 and the connection dish 3 being respectively fixed with in vertical rod at the bottom of beam 12 for being connected cross bar 1, four vertical pin-and-holes are uniformly offered on connection dish 3, cross bar 1 two ends are provided with the straight inserting head coordinated with pin-and-hole, the various vertical rods such as vertical rod 12 at the bottom of cross bar 1 and the edge-on bar of beam 2, beam are connected by connection dish 3, simple in construction, easy to operate, time and labour saving.The template of side bar 7 both sides is fixed by vertical beam side master stupefied 8, and the beam side master stupefied 8 of side bar 7 both sides connects by the bolt of level is fixing.
The left end of master at the bottom of beam stupefied 10 is fixed with the edge-on bar of beam 2 near side bar 7 and is connected, and right-hand member is fixing with diagonal brace 9 to be connected.The bottom of diagonal brace 9 arranges near vertical rod at the bottom of beam 12 and fixes, and diagonal brace 9 is fastener type steel pipe, makes vertical rod 12 at the bottom of beam and beam edge-on bar 2 stress the most reasonable, the stability in the large of formwork system at the bottom of strengthened beam.
Vertical rod 12 at the bottom of beam is fixedly connected with the bracing piece 15 of the width along side bar 7 by fastener 14, and bracing piece 15 is the most spaced apart.Bracing piece 15 and cross bar 1 one_to_one corresponding, and bracing piece 15 is arranged on the top of cross bar 1, so it can be avoided that bracing piece 15 clashes with the position being connected dish 3, make side bar form bracing system more be simple and convenient to operate flexibly, accelerate speed of application, reduction of erection time, reduction cost of labor.The left end of bracing piece 15 is fixed with the edge-on bar of beam 2 near side bar 7 and is connected, and right-hand member is fixing with diagonal brace 9 to be connected.Bracing piece 15 can also be arranged on the lower section of connection dish 3, and the quantity of bracing piece 15 can also be as desired to select, when installing bracing piece 15, need to make bracing piece 15 be connected dish 3 position stagger, it is to avoid bracing piece 15 clashes with the position being connected dish 3.
Also being fixedly connected with the horizon bar 13 along side bar 7 length direction in vertical rod 12 at the bottom of beam, horizon bar 13 is fixed in vertical rod 12 at the bottom of beam by fastener 14, makes vertical rod 12 at the bottom of beam form firm entirety.
Beam edge-on bar 2 upper end is fixed with the floor master stupefied 4 of level by adjustable torr support 6, the template of the stupefied 4 pairs of floors 5 of floor master is supported, beam bar 11 is fixed on vertical rod 12 upper end at the bottom of beam by adjustable torr support 6, the height of floor master stupefied 4 and beam bar 11 can be quickly adjusted by adjustable torr support 6, easy to operate, accelerate speed of application, reduction of erection time.
nullAs shown in Figure 3,In the present embodiment, adjustable torr support 6 includes screw rod 603 and leading screw 604,Leading screw 604 is horizontally disposed with,Leading screw 604 is threadeded with screw rod 603,Vertical rod 12 and the upper end of the edge-on bar of beam 2 at the bottom of beam is inserted in screw rod 603 lower end,Leading screw 604 is fixedly supported on outside the upper end of vertical rod 12 at the bottom of beam and the edge-on bar of beam 2,Its axial location at screw rod 603 is regulated by rotational lead screw 604,Thus adjusting screw rod 603 inserts vertical rod 12 at the bottom of beam and the length in the edge-on bar of beam 2,The upper end of screw rod 603 is welded with a supporting plate 601 along side bar 7 length direction,The both sides of supporting plate 601 flip up the support slot 602 forming a rectangle,By support slot 602, beam bar 11 and floor master stupefied 4 are fixed support,Easy to operate,Beam bar 11 and stupefied 4 fixations of floor master are reliable.
The above, it it is only preferred embodiment of the present utility model, being not the restriction that this utility model is made other form, any those skilled in the art are changed possibly also with the technology contents of the disclosure above or are modified as the Equivalent embodiments of equivalent variations.But every without departing from technical solutions of the utility model content, any simple modification, equivalent variations and remodeling above example made according to technical spirit of the present utility model, still fall within the protection domain of technical solutions of the utility model.

Claims (7)

  1. null1. straight cutting dish pin falsework side bar formwork system,Including master at the bottom of the edge-on bar of beam (2) and beam stupefied (10),The edge-on bar of beam (2) is vertically fixed on the inner side of side bar (7),Master at the bottom of beam stupefied (10) is secured transverse to the lower section of side bar (7) along the width of side bar (7),It is characterized in that: also include vertically being fixed on vertical rod (12) at the bottom of the beam of side bar (7) lower section,It is connected by cross bar (1) between vertical rod at the bottom of beam (12) bar edge-on with beam (2),Side bar (7) outside is provided with diagonal brace (9),At the bottom of diagonal brace (9) and beam, the distance between vertical rod (12) is gradually increased from the bottom to top,The two ends of master at the bottom of beam stupefied (10) bar edge-on with beam (2) respectively and diagonal brace (9) are fixed and are connected,Vertical rod at the bottom of beam (12) upper end is fixed with the beam bar (11) arranged along side bar (7) length direction,Beam bar (11) is supported on the downside of master at the bottom of beam stupefied (10).
  2. Straight cutting dish pin falsework side bar formwork system the most according to claim 1, it is characterized in that: vertical rod at the bottom of described beam (12) is fixed with the bracing piece (15) of the width along side bar (7) by fastener (14), and bracing piece (15) two ends are separately fixed on the edge-on bar of beam (2) and diagonal brace (9).
  3. Straight cutting dish pin falsework side bar formwork system the most according to claim 2, it is characterised in that: being additionally provided with the horizon bar (13) of the length direction along side bar (7) in vertical rod at the bottom of described beam (12), horizon bar (13) is fixed by fastener (14).
  4. Straight cutting dish pin falsework side bar formwork system the most according to claim 1, it is characterized in that: the edge-on bar of described beam (2) and the connection dish (3) being respectively fixed with in vertical rod at the bottom of beam (12) for being connected cross bar (1), cross bar (1) two ends are provided with and are connected the straight inserting head that dish (3) coordinates.
  5. Straight cutting dish pin falsework side bar formwork system the most according to claim 1, it is characterised in that: described beam edge-on bar (2) upper end is fixed with the floor master stupefied (4) of level by adjustable torr support (6).
  6. Straight cutting dish pin falsework side bar formwork system the most according to claim 1, it is characterised in that: described beam bar (11) is fixed on vertical rod at the bottom of beam (12) upper end by adjustable torr support (6).
  7. 7. according to the straight cutting dish pin falsework side bar formwork system described in claim 5 or 6, it is characterized in that: the upper end of described adjustable torr support (6) is fixed with the supporting plate (601) along side bar (7) length direction, and the both sides of supporting plate (601) flip up the support slot (602) forming rectangle.
CN201620417184.6U 2016-05-10 2016-05-10 Straight cutting dish pin falsework side bar formwork system Expired - Fee Related CN205742998U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620417184.6U CN205742998U (en) 2016-05-10 2016-05-10 Straight cutting dish pin falsework side bar formwork system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620417184.6U CN205742998U (en) 2016-05-10 2016-05-10 Straight cutting dish pin falsework side bar formwork system

Publications (1)

Publication Number Publication Date
CN205742998U true CN205742998U (en) 2016-11-30

Family

ID=57370992

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620417184.6U Expired - Fee Related CN205742998U (en) 2016-05-10 2016-05-10 Straight cutting dish pin falsework side bar formwork system

Country Status (1)

Country Link
CN (1) CN205742998U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107795125A (en) * 2017-11-28 2018-03-13 广州市快易模板工程有限公司 A kind of construction package supported for beam forms with reinforcing connection
CN107842195A (en) * 2017-11-28 2018-03-27 广州市快易模板工程有限公司 A kind of beam forms bracing reinforcement system
CN107989366A (en) * 2018-01-16 2018-05-04 广州市快易模板工程有限公司 One kind is used for beam form board supporting structure component
CN107989364A (en) * 2018-01-16 2018-05-04 广州市快易模板工程有限公司 A kind of strip Quick Release support system for beam

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107795125A (en) * 2017-11-28 2018-03-13 广州市快易模板工程有限公司 A kind of construction package supported for beam forms with reinforcing connection
CN107842195A (en) * 2017-11-28 2018-03-27 广州市快易模板工程有限公司 A kind of beam forms bracing reinforcement system
CN107795125B (en) * 2017-11-28 2024-04-12 广州市快易模板工程有限公司 A structural component for beam form supports and consolidates and be connected
CN107842195B (en) * 2017-11-28 2024-04-16 广州市快易模板工程有限公司 Beam formwork support reinforcing system
CN107989366A (en) * 2018-01-16 2018-05-04 广州市快易模板工程有限公司 One kind is used for beam form board supporting structure component
CN107989364A (en) * 2018-01-16 2018-05-04 广州市快易模板工程有限公司 A kind of strip Quick Release support system for beam
CN107989366B (en) * 2018-01-16 2024-04-12 广州市快易模板工程有限公司 Be used for beam form bearing structure subassembly
CN107989364B (en) * 2018-01-16 2024-04-16 广州市快易模板工程有限公司 Strip-shaped quick-release supporting system for beam

Similar Documents

Publication Publication Date Title
CN205742998U (en) Straight cutting dish pin falsework side bar formwork system
CN104481144A (en) Beam-bottom form erection system of straightly inserted disk and pin-joined formwork support and construction method thereof
CN206530056U (en) Construction beam adjustable supporting device
CN110409806B (en) Early-dismantling head and template supporting system
CN201991226U (en) Flange template support structure
CN206625260U (en) A kind of detachable late poured band support post
CN110670873B (en) Support system of steel formwork of ultrahigh large-section concrete column and construction method
CN204311749U (en) Formwork system at the bottom of straight cutting dish pin falsework beam
CN210562223U (en) Slope protection template with arch framework
CN204385921U (en) Clear-water concrete wall column joint bar fastening devices
CN106836255A (en) The integral prefabricated structure of basement bottom board catch pit bar-mat reinforcement and method of construction
CN205153321U (en) Raft board steel bar support rod frame
CN203420470U (en) Installation construction structure of short-limb shear-wall formwork supporting system
CN103334582A (en) Method for installing and constructing short-leg shear wall formwork supporting system
CN207193775U (en) A kind of reinforcing shaping equipment of Cast-in-situ Beam exterior sheathing
CN206158145U (en) Elevartor shaft formwork construction trolley frame
CN208586897U (en) A kind of composite floor construction overhanging portion template supporting tool
CN207499434U (en) The bayonet type erecting device of stair step
CN201206332Y (en) Rectangular cross-section chimney slipform
CN201567802U (en) Horizontal structural template supporting system in hoistway
CN206418513U (en) The integral prefabricated structure of basement bottom board catch pit bar-mat reinforcement
CN205224579U (en) Steel framework template and self -supporting truss board combination concrete quick detach system
CN207032681U (en) A kind of detachable architectural engineering baseplate reinforcing bar support frame
CN209308411U (en) Bracing means for aluminum alloy pattern plate Vierendeel girder
CN216974186U (en) Full cast in situ concrete outer wall boundary beam supports with regularization strutting arrangement

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161130