CN205711777U - Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system - Google Patents
Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system Download PDFInfo
- Publication number
- CN205711777U CN205711777U CN201620671832.0U CN201620671832U CN205711777U CN 205711777 U CN205711777 U CN 205711777U CN 201620671832 U CN201620671832 U CN 201620671832U CN 205711777 U CN205711777 U CN 205711777U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- cushion cap
- pipe support
- ultra
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
This utility model belongs to technical field of bridge construction, relate to ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system, including main cushion cap, it is provided with continuous pier stud on described main cushion cap, row's steel pipe support post it is respectively arranged with along continuous pier stud both sides, described steel pipe support post is partially installed on main cushion cap, and at least four steel pipe support posts are arranged on outside main cushion cap surrounding, and these four steel pipe support posts lay respectively under the outboard web of box beam 0# block base plate.On the basis of prior art, the 0# block consolidation system that a kind of cast-in-situ bored pile and steel pipe support post i.e. pile combine is provided, i.e. steel pipe support post requirement need to be set at cushion cap outer ground for ultra-wide box beam direction across bridge, use and first arrange that bored pile foundation and reinforced concrete pile cap connect the design of steel pipe column again, to solve steel pipe column support system uneven subsidence, it is ensured that construction safety is reliable.
Description
Technical field
This utility model belongs to technical field of bridge construction, particularly relates to ultra-wide view picture formula box girder with variable cross section 0# block pile knot
Box-like temporary consolidation system.
Background technology
Along with China Investment in Basic Facilities for Traffic builds steady growth, road and bridge construction achieves and develops rapidly, greatly across
Degree bridge application is more and more extensive, and variable cross-section continuous beam is increasingly becoming the main flow bridge type crossing over the barrier such as river, road.Outstanding
Arm casting method and bracket subsection casting method are main two kinds of construction methods of box girder with variable cross section, and the emphasis that 0# block is constructed especially
With difficult point position.Before Hanging Basket cantilever or segmented support cast-in-place, it is necessary to the continuous pier of temporary consolidation, beam body is converted into static determinacy knot
Structure.
For variable cross-section continuous beam 0# block temporary consolidation, generally use Support Method, cushion cap top steel-pipe pile temporary consolidation, pier
Top, without support temporary consolidation etc., is respectively arranged with its characteristics and available field, and technique is the most ripe.For Support Method, due to bracket basis
Part utilizes cushion cap, and part is ground foundation, is easily formed bigger differential settlement, and is not subject in construction the unbalanced moment produced,
Reduce safety.Steel pipe column for cushion cap top consolidates system, owing to making full use of cushion cap space (or at direction across bridge cushion cap two
Side arranges cast-in-place bracket) arrange steel pipe column support system, apply in general to the following bridge of deck-siding 15m.For pier top supportless
Temporary consolidation technique, the first size to pier stud have certain requirement, otherwise cannot carry out pressure block, anchoring temporarily bundle in pier top
Layout, and when No. 0 block is long, this consolidation technique stress system cannot effectively support.In sum, for ultra-wide
(more than 30m) box girder with variable cross section 0# block, existing temporary consolidation technique all can not reach its construction requirement.
Summary of the invention
Present invention aims to the whole secondary formula variable cross-section continuous beam of ultra-wide (more than deck-siding 30m, cushion cap pier stud size
For broad box girder cross section, smaller), existing 0# block consolidation technique can not effectively solve ultra-wide section temporary support and
Solidification problem, on the basis of prior art, it is provided that the 0# block that a kind of cast-in-situ bored pile and steel pipe support post i.e. pile combine is solid
Knot body system, i.e. need to arrange steel pipe support post requirement at the outer ground of cushion cap for ultra-wide box beam direction across bridge, use and first arrange boring
Bored concrete pile foundation and reinforced concrete pile cap connect the design of steel pipe column again, ask solving steel pipe column support system differential settlement
Topic, it is ensured that construction safety is reliable.
In order to realize above-mentioned purpose, this utility model have employed following technical scheme:
Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system, including main cushion cap, described main cushion cap
On be provided with continuous pier stud, be respectively arranged with row's steel pipe support post along continuous pier stud both sides, described steel pipe support post part is pacified
Being contained on main cushion cap, at least four steel pipe support posts are arranged on outside main cushion cap surrounding, these four steel pipe support posts position respectively
Under the outboard web of box beam 0# block base plate.
As preferably, being provided with 4 interim bored pile foundations outside described main cushion cap surrounding, described interim boring fills
Note pile foundation upper end is provided with interim cushion cap, is arranged on four steel pipe support posts outside main cushion cap surrounding and is fixed on 4 temporarily
On cushion cap.
As preferably, described steel pipe support column bottom is provided with pre-buried finish rolling twisted steel, and pre-buried finish rolling twisted steel is arranged
There is vertical finish rolling screw thread presstressed reinforcing steel, between pre-buried finish rolling twisted steel and vertical finish rolling screw thread presstressed reinforcing steel by branch sleeve even
Connect.
As preferably, described main cushion cap and interim cushion cap being embedded with steel plate, steel pipe support post is directly fixed by steel plate.
As preferably, laterally attached between described steel pipe support post have laterally attached beam, is horizontally connected with lateral connection beam.
Compared with prior art, the invention has the beneficial effects as follows:
1., by designing interim bored pile foundation and interim cushion cap, overcome ultra-wide monoblock type variable cross-section and connect box beam
The uneven subsidence of the outer steel pipe support post of 0# block cushion cap.
2. simple in construction, technical maturity, stress is clear and definite, easy construction.
3. make full use of main pier bearing platform to participate in, outside stress, only needing to arrange 4 large diameter boreholes outside cushion cap surrounding simultaneously
Bored concrete pile foundation, so that it may solving the temporary consolidation of ultra-wide integrated box girder (more than 30m), relatively economical, quality safety is reliable.
Accompanying drawing explanation
Fig. 1 is 0# block pile convolution temporary consolidation system plane graph.
Fig. 2 is 0# block pile convolution temporary consolidation system elevation.
Fig. 3 is 0# block pile convolution temporary consolidation system side view.
Fig. 4 is pre-embedded steel slab drawing.
Detailed description of the invention
Below in conjunction with the accompanying drawings detailed description of the invention of the present utility model is made a detailed explanation.
Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system as shown in Figure 1 to 4, including main
Cushion cap 1, described main cushion cap 1 is provided with continuous pier stud 2, is respectively arranged with row's steel pipe support post 9 along continuous pier stud 2 both sides,
Described steel pipe support post 9 is partially installed on main cushion cap 1, and at least four steel pipe support posts 9 are arranged on outside main cushion cap 1 surrounding
Side, these four steel pipe support posts 9 lay respectively under the outboard web of box beam 0# block 3 base plate.It is provided with 4 outside main cushion cap 1 surrounding
The interim bored pile foundation of root 4, described interim bored pile foundation 4 upper end is provided with interim cushion cap 5, is arranged on main cushion cap
Four steel pipe support posts 9 outside 1 surrounding are fixed on 4 interim cushion caps 5.Pre-buried finish rolling it is provided with bottom steel pipe support post 9
Twisted steel 7, pre-buried finish rolling twisted steel 7 is provided with vertical finish rolling screw thread presstressed reinforcing steel 11, pre-buried finish rolling twisted steel 7 and vertical essence
Roll and connected by branch sleeve 16 between screw thread presstressed reinforcing steel 11.Being embedded with steel plate 6 on main cushion cap 1 and interim cushion cap 5, steel pipe props up
Dagger 9 is directly fixed by steel plate 6.Laterally attached between steel pipe support post 9 have laterally attached beam 14, is horizontally connected with and laterally connects
Connect beam 15.
Making assembling method following steps:
Step one: main pier hold continuous pier stud 2 construct time, note pre-embedded steel slab 6 and pre-buried finish rolling twisted steel 7;
Step 2: interim bored pile foundation 4 and interim cushion cap 5 are constructed.It is pointed to the main extraneous steel pipe of cushion cap 1 prop up
Dagger 9 uses bored pile foundation, according to geology select be suitable for drilling machine carry out pore-forming, clear hole, transfer steel reinforcement cage and
Concrete pouring, then chisel pile crown carries out interim bearing platform construction, notes the pre-buried of top steel plate 6 and pre-buried finish rolling twisted steel 7.
Step 3: steel pipe support post is installed.Use with pre-buried finish rolling twisted steel 7 with flanged plate 10 bottom steel pipe support post 9
Nut 8 is fastenedly connected;Steel pipe support post 9 uses sustaining wall part 13 to be connected with the pre-embedded steel slab 6 of continuous pier stud 2;Steel pipe support post 9 it
Between laterally, lateral use H588 shaped steel to be attached, form laterally attached beam 14, lateral connection beam 15.
Step 4: after 0# block has been constructed, installs cloth in the pre-buried finish rolling every steel pipe of twisted steel 7(in steel pipe support post
Put 4), use branch sleeve 16 spreading to 0# block base plate, use jack tension to anchor to builder's tonnage.
Above content described in this specification is only to this utility model example explanation.This utility model
Described specific embodiment can be made various amendment or supplements or use class by person of ordinary skill in the field
As mode substitute, without departing from the content of this utility model description or surmount model defined in the claims
Enclose, protection domain of the present utility model all should be belonged to.
Claims (5)
1. ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system, it is characterised in that: include main cushion cap
(1), described main cushion cap (1) is provided with continuous pier stud (2), is respectively arranged with row's steel pipe support along continuous pier stud (2) both sides
Post (9), described steel pipe support post (9) is partially installed on main cushion cap (1), and at least four steel pipe support posts (9) are arranged on master
Outside cushion cap (1) surrounding, these four steel pipe support posts (9) lay respectively under the outboard web of box beam 0# block base plate.
Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system the most according to claim 1, it is special
Levy and be: outside described main cushion cap (1) surrounding, be provided with 4 interim bored pile foundations (4), described interim cast-in-situ bored pile
(4) upper end, basis is provided with interim cushion cap (5), is arranged on four steel pipe support posts (9) outside main cushion cap (1) surrounding and is fixed on
On 4 interim cushion caps (5).
Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system the most according to claim 2, it is special
Levy and be: described steel pipe support post (9) bottom is provided with pre-buried finish rolling twisted steel (7), and pre-buried finish rolling twisted steel (7) is provided with
Vertical finish rolling screw thread presstressed reinforcing steel (11), passes through between pre-buried finish rolling twisted steel (7) and vertical finish rolling screw thread presstressed reinforcing steel (11)
Branch sleeve (16) connects.
Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system the most according to claim 2, it is special
Levying and be: be embedded with steel plate (6) on described main cushion cap (1) and interim cushion cap (5), steel pipe support post (9) is direct by steel plate (6)
Fixing.
Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system the most according to claim 2, it is special
Levy and be: laterally attached between described steel pipe support post (9) have laterally attached beam (14), is horizontally connected with lateral connection beam
(15).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620671832.0U CN205711777U (en) | 2016-06-26 | 2016-06-26 | Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620671832.0U CN205711777U (en) | 2016-06-26 | 2016-06-26 | Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205711777U true CN205711777U (en) | 2016-11-23 |
Family
ID=57317415
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620671832.0U Active CN205711777U (en) | 2016-06-26 | 2016-06-26 | Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205711777U (en) |
-
2016
- 2016-06-26 CN CN201620671832.0U patent/CN205711777U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106758841B (en) | A kind of whole construction process of the double rope face low-pylon cable-stayed bridges of double tower | |
CN106677070B (en) | A kind of high-altitude long-span heavy duty construction of beam bracket and construction method | |
CN106012797A (en) | All-ground-anchor type single-tower double-span cable-stayed bridge structure and construction method thereof | |
CN101649604B (en) | Construction bracket of 1# block of inclined pull bridge and constructing method thereof | |
CN105862878B (en) | A kind of support system of deep basal pit | |
CN103556749A (en) | Hanging flexible connection of precast concrete infill wall | |
CN105839536A (en) | Construction method of cable-stayed bridge pylon | |
CN205857032U (en) | The toughened internal stress Construction Support device that a kind of floor stand combines with shelf bracket | |
CN105972313B (en) | One kind is across base pit engineering conduit wiring suspension method and overhung construction | |
CN108505433A (en) | A kind of bridge pier structure and its construction method | |
CN107190627A (en) | Part earth anchored suspension bridge and its construction method | |
CN205778879U (en) | Super-large-section tunnel drilling and blasting method enlarging constructing structure in situ | |
CN203487664U (en) | Prefabricated concrete filled wall suspension type flexible connection | |
CN105113514B (en) | Foundation pit enclosure system with underground continuous wall as vertical cantilever fulcrum and construction method | |
CN109267493A (en) | A kind of construction method installed across river steel lid beam | |
CN108166395A (en) | A kind of construction method that beam bridge is built across Business Line | |
CN205711777U (en) | Ultra-wide view picture formula box girder with variable cross section 0# block pile convolution temporary consolidation system | |
CN107059592A (en) | Pier construction method after a kind of first beam in cable-stayed bridge auxiliary pier pier top section | |
CN106917358A (en) | A kind of cable-stayed bridge main-beam combination constructing method thereof and its counter weight construction system | |
CN101492918A (en) | Beam column node for base pit engineering of topdown construction method | |
CN208266667U (en) | A kind of bridge pier structure | |
CN106049527A (en) | Open cut method can restore three cable subway station structures of three arches | |
CN207143746U (en) | Support beam template system under concrete support trestle plate | |
CN207244425U (en) | Part earth anchored suspension bridge | |
CN206052565U (en) | A kind of beam-column type bracket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |