CN205693277U - Vertical shaft crane span structure - Google Patents

Vertical shaft crane span structure Download PDF

Info

Publication number
CN205693277U
CN205693277U CN201620566086.9U CN201620566086U CN205693277U CN 205693277 U CN205693277 U CN 205693277U CN 201620566086 U CN201620566086 U CN 201620566086U CN 205693277 U CN205693277 U CN 205693277U
Authority
CN
China
Prior art keywords
trailing arm
vertical shaft
crane span
span structure
cover plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620566086.9U
Other languages
Chinese (zh)
Inventor
廖旋
刘向东
冯刚
黄海
祝俊川
王晓秋
陈春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Industrial Equipment Installation Group Co.,Ltd.
Original Assignee
INDUSTRIAL DEVICES INSTALLATION CO SICHUAN PROVINCE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by INDUSTRIAL DEVICES INSTALLATION CO SICHUAN PROVINCE filed Critical INDUSTRIAL DEVICES INSTALLATION CO SICHUAN PROVINCE
Priority to CN201620566086.9U priority Critical patent/CN205693277U/en
Application granted granted Critical
Publication of CN205693277U publication Critical patent/CN205693277U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

This utility model relates to a kind of vertical shaft crane span structure for cabling, belongs to electrical equipment.Described vertical shaft crane span structure includes that the well body surrounded by cover plate that at least two is connected by connecting portion, cover plate and connecting portion connect by being located at the protruding draw-in groove cooperated of junction;Described connecting portion also includes the Axial Mounting Part for securing cover plate.By protruding draw-in groove, only need to simply assemble, vertical shaft crane span structure can be made to have the repeat unit structure being made up of well body and connecting portion, when local goes wrong, only the well body of corresponding unit or connecting portion need to be repaired or replaced, time saving and energy saving and cost-effective.By Axial Mounting Part, can securing cover plate further, the contact making adjacent cover plate is the tightst.

Description

Vertical shaft crane span structure
Technical field
This utility model relates to a kind of vertical shaft crane span structure for cabling, belongs to electrical equipment.
Background technology
In electrical installation project work progress, for preferably fixing and protection cable, crane span structure is to install cable to be musted Indispensable carrier.Cable shaft crane span structure is the cable passage of the widely used a kind of vertical direction of power industry.At present, becoming In the construction of power station, workmen is usually channel direction at cable shaft the most in advance and installs a rectangular steelframe structure, then will Cable passes in the channel direction of vertical shaft, is finally fixed in the peripheral direction of vertical shaft with steel plate etc., and in vertical shaft junction Carry out the measures such as fireproof blocking.This installation method, although technique is simple, but, cable shaft safeguarded in the later stage and During replacing, easily cause cable shaft to be difficult to remove because of problems such as processing technique, affect maintenance and the use of vertical shaft, be somebody's turn to do meanwhile It is the longest that kind of vertical shaft also exists processing, install inconvenient, the shortcomings such as tolerance rate is low are installed.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of simple in construction, construction and easy to maintenance dismantled and assembled The vertical shaft crane span structure of formula.
The technical scheme that the above-mentioned technical problem of this utility model solution is used is, vertical shaft crane span structure leads to including at least two Crossing the well body surrounded by cover plate that connecting portion is connected, cover plate and connecting portion are by being located at the projection-card cooperated of junction Groove connects;Described connecting portion also includes the Axial Mounting Part for securing cover plate.By projection-draw-in groove, only need to simply assemble, Vertical shaft crane span structure can be made to have the repeat unit structure being made up of well body and connecting portion, when local goes wrong, only need right Well body or the connecting portion of answering unit repair or replace, time saving and energy saving and cost-effective.By Axial Mounting Part, one can be entered Step securing cover plate, the contact making adjacent cover plate is the tightst.
Further, the length of the length < well body of described fixture.Described fixture is positioned at the top and bottom of connecting portion, If the connecting portion connecting multiple well body is structure as a whole (i.e. the length of the length of fixture=well body), not only transports and make Cost is high, and once connecting portion goes wrong, and needs integral replacing.If the connecting portion of well body top and the bottom is separate (the most fixing The length of the length < well body of part), not only do not interfere with the effect of securing cover plate, and saved to a great extent making, Transport and maintenance cost.Further, it is fastenedly connected between described fixture and cover plate.
Further, described cover plate is provided with reinforcement structure and/or passage.Described reinforcement structure can be reinforcement or prop up Support etc..The vertical shaft crane span structure being provided with reinforcement structure has higher intensity, can place more cable.Upper containing passage It is stamped and helps heat radiation.
Further, it is provided with cable bundle in described well body.Cable bundle can make cable obtain ordered arrangement and effectively fix.
Further, described cable bundle includes connecting hinge, is individually fixed in the movable leaf both sides of described connection hinge Fix trailing arm, the movable trailing arm being connected with described fixing trailing arm by securing member and be arranged at the fixing of the movable trailing arm other end Steel plate;Described cable bundle is connected with well body by fixation steel plate.The inner space of vertical shaft crane span structure is divided into three by this cable bundle Individual part, and by hinge, the size of each several part can be regulated.
Further, described fixing trailing arm and movable trailing arm be respectively equipped with the regulating tank spacing to movable trailing arm, described tightly Firmware, through fixing trailing arm regulating tank and corresponding movable trailing arm regulating tank, makes fixing trailing arm be connected with movable trailing arm.By adjusting Joint groove can regulate the relative position of fixing trailing arm and movable trailing arm, the placement location of cable bundle of being more convenient for.
Further, it is provided with and can move along regulating tank between the movable trailing arm of described movable leaf both sides and/or between fixing trailing arm Dynamic cable tie seat.Further, described cable tie seat is provided with colligation hole.The purpose so arranged is to make cable obtain more Orderly arrangement is with the most fixing.
Further, in described well body, portion is provided with fire-fighting spray device, and outside is provided with fire fighting alarm device, such as alarm etc., Connected by existing usual manner, vertical shaft crane span structure so can be made to realize automatic fire prevention and early warning.
Vertical shaft portal structure of the present utility model is simple, has and repeats dismountable structure, it is simple to the installation of crane span structure with And maintenance in the future.The internal cable bundle arranged of crane span structure is compared with traditional dividing plate, it is possible to for greater flexibility inside distribution crane span structure Space, wiring when being more conducive to cable laying.
Below in conjunction with detailed description of the invention, above-mentioned utility model content of the present utility model is made the most specifically Bright.But this should not being interpreted as, the scope of the above-mentioned theme of this utility model is only limitted to Examples below.New without departing from this practicality In the case of the above-mentioned technological thought of type, the various replacements made according to ordinary skill knowledge and customary means and change More, all should be included in protection domain of the present utility model.
Accompanying drawing explanation
Fig. 1 is the structural representation (not shown cable bundle) of this utility model vertical shaft crane span structure.
Fig. 2 is the partial enlarged drawing of A in Fig. 1.
Fig. 3 is the structural representation of connecting portion in Fig. 1.
Fig. 4 is the partial enlarged drawing of B in Fig. 3.
Fig. 5 is the structural representation of the cable bundle within Fig. 1.
Fig. 6 is the structural representation of cable bundle in Fig. 5.
Detailed description of the invention
As it is shown in figure 1, vertical shaft crane span structure of the present utility model includes two by being surrounded by cover plate 1 of being connected of connecting portion 2 Well body, cover plate 1 is provided with bar shaped air-vent 13, bar shaped reinforcement 12 and handle 14.As shown in Figure 2, the upper and lower of cover plate 1 It is equipped with protruding 11.From the figure 3, it may be seen that connecting portion 2 also includes the Axial Mounting Part 22 for securing cover plate 1, the length of fixture 22 The length of degree < well body, is fastenedly connected between fixture 22 and cover plate 1.As shown in Figure 4, the upper and lower of connecting portion is equipped with With above-mentioned protruding 11 draw-in grooves 21 mated, cover plate 1 and connecting portion 2 by being located at the protruding 11-draw-in groove cooperated of junction 21 connect.In well body, portion is provided with fire-fighting spray device, and outside is provided with fire protection warning device.
From Fig. 5 and Fig. 6, in well body, it is provided with cable bundle 3.This cable bundle 3 includes connecting hinge 31, fixing respectively Fixing trailing arm 32 in movable leaf 311 both sides of described connection hinge 31, the work being connected with fixing trailing arm 32 by securing member 33 Move trailing arm 34 and be arranged at the fixation steel plate 35 of movable trailing arm 34 other end;Cable bundle 3 is by fixation steel plate 35 with well body even Connect.Being respectively equipped with the regulating tank spacing to movable trailing arm 34 on fixing trailing arm 32 and movable trailing arm 34, described securing member 33 passes Fixing trailing arm regulating tank 36 and corresponding movable trailing arm regulating tank 37, make fixing trailing arm 32 be connected with movable trailing arm 34.Movable leaf The cable tie seat 38 that can move it is provided with along regulating tank between the movable trailing arm 34 of 311 both sides and/or between fixing trailing arm 32, its It is provided with colligation hole 381.
Vertical shaft portal structure of the present utility model is simple, has the structure of repeatable reassembling type, it is simple to installs and ties up in the future Protect.The cable bundle inside set can be according to well body size and number of cables, and the space in portion in distribution well body, contributes to cable neatly When laying connect up.

Claims (10)

1. vertical shaft crane span structure, passes through, including at least two, the well body surrounded by cover plate (1) that connecting portion (2) is connected, it is characterised in that: Cover plate (1) and connecting portion (2) connect by being located at the projection (11) cooperated-draw-in groove (21) of junction;Described connecting portion (2) Axial Mounting Part (22) for securing cover plate (1) is also included.
2. vertical shaft crane span structure as claimed in claim 1, it is characterised in that: the length of the length < well body of described fixture (22).
3. vertical shaft crane span structure as claimed in claim 1, it is characterised in that: between described fixture (22) and cover plate (1), fastening is even Connect.
4. vertical shaft crane span structure as claimed in claim 1, it is characterised in that: described cover plate (1) be provided with reinforcement structure (12) and/or Passage (13).
5. vertical shaft crane span structure as claimed in claim 1, it is characterised in that: it is provided with cable bundle (3) in described well body.
6. vertical shaft crane span structure as claimed in claim 5, it is characterised in that: described cable bundle (3) includes connecting hinge (31), dividing Be not fixed on the fixing trailing arm (32) of movable leaf (311) both sides of described connection hinge (31), by securing member (33) with described Fix the movable trailing arm (34) that trailing arm (32) connects and the fixation steel plate (35) being arranged at movable trailing arm (34) other end;Described Cable bundle (3) is connected with well body by fixation steel plate (35).
7. vertical shaft crane span structure as claimed in claim 6, it is characterised in that: described fixing trailing arm (32) and upper point of movable trailing arm (34) Not being provided with the regulating tank spacing to movable trailing arm (34), described securing member (33) is through fixing trailing arm regulating tank (36) and correspondence Movable trailing arm regulating tank (37), makes fixing trailing arm (32) be connected with movable trailing arm (34).
8. vertical shaft crane span structure as claimed in claim 6, it is characterised in that: the movable trailing arm (34) of described movable leaf (311) both sides Between and/or fixing trailing arm (32) between be provided with the cable tie seat (38) that can move along regulating tank.
Vertical shaft crane span structure the most according to claim 8, it is characterised in that: described cable tie seat (38) is provided with colligation hole (381)。
10. the vertical shaft crane span structure as described in one of claim 1 to 9, it is characterised in that: in described well body, portion is provided with fire-fighting spraying dress Putting, outside is provided with fire protection warning device.
CN201620566086.9U 2016-06-13 2016-06-13 Vertical shaft crane span structure Active CN205693277U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620566086.9U CN205693277U (en) 2016-06-13 2016-06-13 Vertical shaft crane span structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620566086.9U CN205693277U (en) 2016-06-13 2016-06-13 Vertical shaft crane span structure

Publications (1)

Publication Number Publication Date
CN205693277U true CN205693277U (en) 2016-11-16

Family

ID=57427223

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620566086.9U Active CN205693277U (en) 2016-06-13 2016-06-13 Vertical shaft crane span structure

Country Status (1)

Country Link
CN (1) CN205693277U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107579495A (en) * 2017-11-13 2018-01-12 许昌恒科实业发展有限公司 A kind of vertical shaft crane span structure
CN109149470A (en) * 2018-10-17 2019-01-04 贵州建工集团第四建筑工程有限责任公司 A kind of steel construction sidewall support of adjustable support height

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107579495A (en) * 2017-11-13 2018-01-12 许昌恒科实业发展有限公司 A kind of vertical shaft crane span structure
CN109149470A (en) * 2018-10-17 2019-01-04 贵州建工集团第四建筑工程有限责任公司 A kind of steel construction sidewall support of adjustable support height
CN109149470B (en) * 2018-10-17 2024-03-08 贵州建工集团第四建筑工程有限责任公司 Steel structure side wall bracket with adjustable supporting height

Similar Documents

Publication Publication Date Title
CN205693277U (en) Vertical shaft crane span structure
KR20130026849A (en) Cable support apparatus and method for separating power cable using the same
CN106954362A (en) A kind of rack cable management device
CN202876157U (en) Auxiliary device for hook mounting band
CN106300164A (en) Wire harness wire fixing clamp
CN208158042U (en) A kind of layer-by-layer isolated insulation compound cable support of drawer type
CN211151081U (en) Electrical cabinet convenient for wiring
CN103532030B (en) Distribution box with movable slide rail type installing plate
CN104678521A (en) Floor type optical cable distributing box
CN208814440U (en) Elevator weight sensor guard assembly
CN202917819U (en) Distribution box guide rail
CN208750333U (en) A kind of communication apparatus mounting rack
CN208797510U (en) A kind of combination gantry
CN206312834U (en) Coil rack
CN205296883U (en) Opening cover plate assembly used for covering openings
CN201392761Y (en) Load switch protective masking cover on rod
CN207705606U (en) Switchgear
CN104806045B (en) Integrated base station
CN205429552U (en) High -voltage switch cabinet structure
CN204349283U (en) The power distribution cabinet that a kind of space availability ratio is high
CN101527219B (en) Protective shield of pole load switch
CN203589498U (en) Cabinet body structure of outdoor integrated power distribution cabinet
CN104078875A (en) Bus duct installing method
CN205787288U (en) Novel portable optical branching device
CN209244180U (en) A kind of office office building light current well installation system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: No.2, section 3, middle Renmin Road, Chengdu, Sichuan 610000

Patentee after: Sichuan Industrial Equipment Installation Group Co.,Ltd.

Address before: No.2, section 3, middle Renmin Road, Chengdu, Sichuan 610031

Patentee before: SICHUAN PROVINCIAL INDUSTRIAL EQUIPMENT INSTALLATION Co.

CP03 Change of name, title or address