CN205688440U - A kind of spinning steel-pipe pile construction equipment - Google Patents

A kind of spinning steel-pipe pile construction equipment Download PDF

Info

Publication number
CN205688440U
CN205688440U CN201620427539.XU CN201620427539U CN205688440U CN 205688440 U CN205688440 U CN 205688440U CN 201620427539 U CN201620427539 U CN 201620427539U CN 205688440 U CN205688440 U CN 205688440U
Authority
CN
China
Prior art keywords
mast
pipe pile
steel
chain
construction equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620427539.XU
Other languages
Chinese (zh)
Inventor
王海栋
姜文革
郭传新
李志超
张宏磊
李增建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Xin Zuan Rig Co Ltd
Original Assignee
Hebei Xin Zuan Rig Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Xin Zuan Rig Co Ltd filed Critical Hebei Xin Zuan Rig Co Ltd
Priority to CN201620427539.XU priority Critical patent/CN205688440U/en
Application granted granted Critical
Publication of CN205688440U publication Critical patent/CN205688440U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a kind of spinning steel-pipe pile construction equipment, including driving the main frame of steel-pipe pile, the Hydraulic Station providing hydraulic power for main frame and the hydra-electric control piper being connected between Hydraulic Station and main frame, main frame includes chassis, the mast mechanism being arranged on chassis and is arranged on mast mechanism the unit head driving steel-pipe pile.This utility model is applicable to the construction of the soil layers such as mud, clay, sand bed, gravel layer, and it has the advantages such as adaptation special construction place, narrow low latitude, minimum to construction site undisturbed or disturbance, efficiency of construction is high, consolidation effect is preferable, job site is civilized.

Description

A kind of spinning steel-pipe pile construction equipment
Technical field
This utility model relates to a kind of building engineering construction machinery, particularly relates to a kind of for narrow short space buildings ground The foundation improvement rig of the transformation of base basis, process etc..
Background technology
The construction method of existing building ground base enforcement is more, has root pile, prefabricated pile, basis to mend according to reinforcing mode Strong grouting and reinforcing etc..
Root pile is small-sized cast-in-situ bored pile, is divided into circulation deslagging-drilling method, auger boring method according to the mode of boring Deng.After using boring, descending reinforcing cage, injection concrete mode form Small Diameter Pile.
Prefabricated pile is divided into impact pile driving, anchor pole method static pressed pile (pressure pipe method), pit static pressed pile according to the implantation of stake.
Impact pile driving be use drop hammer, the driven precast pile such as diesel hammer, hydraulic hammer enters in soil.Advantage be speed of application relatively Hurry up, but there is the shortcoming that vibration is bigger.Diesel hammer, hydraulic hammer pile driving equipment volume are relatively big, the highest, are suitable for relatively Greatly, higher construction space, generally can not be in the foundation of existing building indoor.
Anchor jacked pile is first to dig piling hole and bolthole on building base plate, installs reaction frame after plantation anchor pole, Utilize building from recast counter-force, with jack, piling bar or prefabricated pile be pressed in soil piecemeal, stake is linked together with basis, Reach improve foundation bearing capacity and control the purpose of building settlement.Pit static pressed pile is the reinforcing side to existing building ground Method, is to use existing building from reforming counter-force, with jack, pile cutoff is pressed into support and change method in soil piecemeal.Domestic pit is quiet The pile body majority of piling uses Prefabricated Reinforced Concrete Square Pile, opening steel pipe.
Existing root pile construction method, when using circulation method for discharging residue drilling construction, equipment is the lightest, conveniently moving, The place being strictly controlled in space is appropriate, and its shortcoming is that work progress has mud to need to process, and needs tight in work progress Lattice manage, thus are restricted.Long auger method efficiency of construction is higher, without mud emission problem, but is not suitable for space Require strict indoor construction.
Anchor jacked pile, pit static pressed pile are suitable for the indoor construction that space requirement is strict, and equipment investment is little, cost of equipment Low, without mud emission problem, but efficiency of construction is low, is not suitable for emergent management engineering.
Foundation strengthened grouting and reinforcing be cement mortar or resinae reinforcement material are injected by pipeline according to certain pressure or Person is infused in existing construction foundation by churning method, to ground reinforcement reinforcement.Owing to slip casting strengthening material reaches one Fixed intensity needs the longer time, thereby increases and it is possible to occurs that in work progress building foundation produces additional settlement because of slip casting, adds Solid lack of homogeneity away from relatively big, thus some engineering is not suitable for being suitable for.
Utility model content
Technical problem to be solved in the utility model is: offer one can be at narrow low spatial sitework, to executing Workshop ground undisturbed or few disturbance, can work with greater efficiency again, the spinning steel-pipe pile construction equipment that the reinforcing duration is shorter.
To achieve these goals, the technical scheme that this utility model is taked is as follows:
A kind of spinning steel-pipe pile construction equipment, including driving the main frame of steel-pipe pile, providing the hydraulic pressure of hydraulic power for main frame The hydra-electric control piper stood and be connected between Hydraulic Station and main frame.
Further improve as this utility model, described main frame includes chassis, the mast mechanism that is arranged on chassis with And it is arranged on mast mechanism the unit head driving steel-pipe pile.
Further improving as this utility model, described unit head bottom is provided with the drive joint of band open slot.
Further improving as this utility model, described mast mechanism includes that mast, the mast being arranged on chassis turn It is arranged on the mast elevating system on mast turning rack to support, lower end.
Further improving as this utility model, described mast includes mast main body and pressurization hoisting mechanism;Described mast Mast sideshake oil cylinder mechanism it is provided with between bar turning rack and mast;The upper mounting plate on described chassis and mast turning rack Between be provided with mast lift ram mechanism.
Further improve as this utility model, described pressurization hoisting mechanism include being positioned at mast body top on lead To sprocket wheel, the lower jockey sprocket in mast lower body part, the oil cylinder chain that is arranged between jockey sprocket and lower jockey sprocket Bar travel multiplier device, the driving hydraulic cylinder of oil cylinder chain travel multiplier device, one end are walked around the jockey sprocket other end and are passed through Lower jockey sprocket is walked around and through oil in lifting chain and one end of walking around lower jockey sprocket after oil cylinder chain travel multiplier device The pressurizing chain of cylinder chain travel multiplier device;
One end of described lifting chain is fixed on the top of unit head, and the other end of described lifting chain is held within mast Bar main body middle and upper part;
One end of described pressurizing chain is fixed on the bottom of unit head, and the other end of described pressurizing chain is fixed on mast master The bottom of body.
Further improve as this utility model, described pressurization hoisting mechanism include being positioned at mast body top on lead To wheel, the drive sprocket in mast lower body part, the chain being arranged between directive wheel and drive sprocket and driving chain The hydraulic motor of bar.
Further improving as this utility model, described steel-pipe pile includes that top connects pipeline section and lower boreholes pipeline section.
Further improving as this utility model, described top connects pipeline section and includes connecting tube body, is positioned at connecting tube The lower contact of body bottom, it is positioned at first top connection on connecting tube body top and is arranged on connecting tube tube wall and position The first block at the first top connection;Described lower boreholes pipeline section include drill pipe body, be positioned at drill pipe body top and The second top connection of matching with lower contact, it is arranged on drill pipe tube wall and is positioned at the second gear at the second top connection Block, the helical blade being arranged on the outer wall of drill pipe body bottom and be arranged on the apex point of drill pipe body lower end.
Further improving as this utility model, the width of described first block and the second block is respectively less than open slot Groove width;The quantity of described first block and the second block is all identical with the quantity of open slot;
Described lower contact, the first top connection and the second top connection are equipped with the connection screw thread matched;
The quantity of described open slot is two or more;
Described chassis is caterpillar band traveling chassis.
Compared with prior art, having the beneficial effect that acquired by this utility model:
This utility model content is a kind of equipment for steel-pipe pile construction, including main frame, Hydraulic Station, steel-pipe pile, hydraulic pressure Electric control lines.Described main frame is by unit head, mast, chassis, pressurization hoisting mechanism, mast leveling device, mast lift Structure, swinging mounting, swinging mounting, hydra-electric control station etc. form.Described steel-pipe pile is driven to pierce by unit head needs improvement Foundation in.The described steel-pipe pile top linkage section by band detachable connector and the boring pipeline section of lower bands helical blade Composition.Described Hydraulic Station provides power for main frame.The unit head of main frame use compact conformation low speed high torque hydraulic motor (or Fluid motor-driven planetary reduction gear), for the high torque driving steel-pipe pile to provide.The pressurization hoisting mechanism of unit head is hydraulic pressure Cylinder drives oil cylinder-chain travel multiplier device or hydraulic motor decelerator device, to drive unit head to lift, overcomes when creeping into Bigger resistance.Driven by Hydraulic Cylinder oil cylinder-chain travel multiplier device or hydraulic motor decelerator device are built in mast, and structure is tight Gather.Mast leveling device is provided with the oscillating oil cylinder making mast left and right directions rotate and a frame oil cylinder of fore-and-aft direction rotation, convenient Rig adjusts the perpendicularity of mast fast and accurately.Mast elevating system is made it at rotating turret assembly by Driven by Hydraulic Cylinder mast Gathering sill in move up and down, can be according to the needs of engineering site condition, when low spatial is constructed, mast moves down to reduce height Degree;Moving on mast when construction space height allows to increase height, the joint length of corresponding steel-pipe pile can lengthen, and reduces Non-cutting time.Chassis is preferably fluid motor-driven crawler travel mode, and equipment shifting walk is flexible.Unit head is provided with down The drive joint of portion's band open slot, it is simple to unit head is quickly connected with steel-pipe pile.Hydraulic Station and main frame are split type, reduce construction Equipment takes up an area space;Hydraulic Station uses hydra-electric control piper and circuit to be connected with main frame, and supporting road wheel is easy to Hydraulic Station Mobile.Steel-pipe pile is more piece package assembly, if being provided with dry joint.Often group joint is preferably made up of a new designs of threaded joints.Steel-pipe pile Coxopodite is provided with helical blade, plays self tapping and buries effect, increases while the pressure crept into, beneficially steel-pipe pile rotate and is pressed into soil In.This utility model is applicable to the construction of the soil layers such as mud, clay, sand bed, gravel layer, and it is special that it has the narrow low latitude of adaptation Construction site, that minimum to construction site undisturbed or disturbance, efficiency of construction is high, consolidation effect is preferable, job site is civilized etc. is excellent Point.
Accompanying drawing explanation
Accompanying drawing 1 is structural representation of the present utility model;
Accompanying drawing 2 is the structural representation of this utility model main frame;
Accompanying drawing 3 is the structural representation of this utility model unit head;
Accompanying drawing 4 is the structural representation of this utility model mast and the embodiment one of pressurization hoisting mechanism;
Accompanying drawing 5 is the structural representation of this utility model mast and the embodiment two of pressurization hoisting mechanism;
Accompanying drawing 6 is the structural representation of this utility model Hydraulic Station;
Accompanying drawing 7 is the structural representation of this utility model steel-pipe pile;
Accompanying drawing 8 is the structural representation of this utility model drive joint;
Accompanying drawing 9 is the generalized section of this utility model drive joint open slot.
In the accompanying drawings:
1 main frame, 1-1 unit head, 1-2 mast, 1-3 mast elevating system, 1-4 mast sideshake oil cylinder mechanism, 1-5 mast Bar turning rack, 1-6 mast lift ram mechanism, 1-7 upper mounting plate, 1-8 hydra-electric control station, 1-9 chassis, 1-1-3 transmission Joint, 1-1-5 open slot, 1-2-1 mast main body, 1-2-2 hydraulic cylinder, 1-2-3 lifting chain, 1-2-4 oil cylinder-chain stroke times Be installed in addition with put, jockey sprocket under 1-2-5 drive sprocket, 1-2-6, the upper jockey sprocket of 1-2-7, the upper directive wheel of 1-2-8,1-2-9 chain, 1-2-10 hydraulic motor, 1-2-11 pressurizing chain, 2 Hydraulic Stations, 3 hydra-electric control pipers, 4 steel-pipe piles, 4-1 connecting tube pipe Body, 4-2 lower contact, 4-3 the first top connection, 4-4 the first block, 4-5 helical blade, 4-6 apex point, 4-7 the second top connection, 4-8 Second block, 4-9 drill pipe body.
Detailed description of the invention
Below in conjunction with accompanying drawing, this utility model is carried out further details of narration.
As shown in accompanying drawing 1-9, a kind of spinning steel-pipe pile construction equipment, including driving the main frame 1 of steel-pipe pile 4, carrying for main frame 1 The Hydraulic Station 2 supplying hydraulic power and the hydra-electric control piper 3 being connected between Hydraulic Station 2 and main frame 1, described main frame 1 The mast mechanism including chassis 1-9, being arranged on the 1-9 of chassis and the unit head being arranged on mast mechanism driving steel-pipe pile 4 1-1, described Hydraulic Station 2 includes vehicle frame, the motor being arranged on vehicle frame, hydraulic pump, fuel tank assembly, is connected to hydraulic pump and fuel tank Pipeline and valve group between assembly and be arranged on the road wheel below vehicle frame.Described unit head 1-1 bottom is provided with band open slot The drive joint 1-1-3 of 1-1-5.The mast turning rack 1-that described mast mechanism includes mast 1-2, is arranged on the 1-9 of chassis 5, lower end is arranged on the mast elevating system 1-3 on mast turning rack 1-5.Described mast 1-2 include mast main body 1-2-1 and Pressurization hoisting mechanism;Mast sideshake oil cylinder mechanism 1-4 it is provided with between described mast turning rack 1-5 and mast 1-2;Institute State and between the upper mounting plate 1-7 of chassis 1-9 and mast turning rack 1-5, be provided with mast lift ram mechanism 1-6.
The embodiment one of pressurization hoisting mechanism, described pressurization hoisting mechanism includes being positioned at mast main body 1-2-1 top Upper jockey sprocket 1-2-7, it is positioned at the lower jockey sprocket 1-2-6 of mast main body 1-2-1 bottom, is arranged on jockey sprocket 1-2-7 And oil cylinder-chain travel multiplier device 1-2-4 between lower jockey sprocket 1-2-6, drive oil cylinder-chain travel multiplier device 1- The jockey sprocket 1-2-7 other end is walked around through oil cylinder-chain travel multiplier device 1-2-4 in the hydraulic cylinder 1-2-2 of 2-4, one end After walk around the lifting chain 1-2-3 of lower jockey sprocket 1-2-6 and lower jockey sprocket 1-2-6 is walked around and through oil cylinder-chain in one end The pressurizing chain 1-2-11 of bar travel multiplier device 1-2-4, one end of described lifting chain 1-2-3 is fixed on unit head 1-1's Top, the other end of described lifting chain 1-2-3 is held within mast main body 1-2-1 middle and upper part, described pressurizing chain 1-2- One end of 11 is fixed on the bottom of unit head 1-1, and the other end of described pressurizing chain 1-2-11 is fixed on mast main body 1-2-1 Bottom.The embodiment two of pressurization hoisting mechanism, described pressurization hoisting mechanism include being positioned at mast main body 1-2-1 top on lead To wheel 1-2-8, it is positioned at the drive sprocket 1-2-5 of mast main body 1-2-1 bottom, is arranged on upper directive wheel 1-2-8 and drive sprocket Chain 1-2-9 between 1-2-5 and the hydraulic motor 1-2-10 of driving chain 1-2-9.
Described steel-pipe pile 4 includes that top connects pipeline section and lower boreholes pipeline section.Described top connects pipeline section and includes connecting tube Body 4-1, it is positioned at the lower contact 4-2 of connecting tube body 4-1 bottom, is positioned at the first top connection 4-3 on connecting tube body 4-1 top And be arranged on connecting tube body 4-1 outer wall and be positioned at the first block 4-4 at the first top connection 4-3;Described lower boreholes Pipeline section includes drill pipe body 4-9, is positioned at drill pipe body 4-9 top and the second top connection 4-matched with lower contact 4-2 7, it is arranged on drill pipe body 4-9 outer wall and is positioned at the second block 4-8 at the second top connection 4-7, be arranged on drill pipe pipe Helical blade 4-5 on the outer wall of body 4-9 bottom and be arranged on the apex point 4-6 of drill pipe body 4-9 lower end.Described first block The width of 4-4 and the second block 4-8 is respectively less than the groove width of open slot 1-1-5;Described first block 4-4's and the second block 4-8 Quantity is all identical with the quantity of open slot 1-1-5, and described lower contact 4-2, the first top connection 4-3 and the second top connection 4-7 are all provided with There is the connection screw thread matched;The quantity of described open slot 1-1-5 is two or more, and described chassis 1-9 is caterpillar band traveling chassis, Described chassis 1-9 is provided with the 1-8 hydra-electric control station for controlling operation equipment hydra-electric.
Working procedure of the present utility model:
1. equipment requires in place according to construction organization, after connecting the hydra-electric control piper 3 of main frame 1 and Hydraulic Station 2, connects Energising source;
2. rig is in place: manipulation hydra-electric control station, starts the motor-driven hydraulic pumps work of Hydraulic Station 2, makes crawler belt Around chassis, walking makes the align piles position, drive joint center of main frame 1, is laterally put by mast lift ram 1-6, mast Dynamic oil cylinder mechanism 1-4 adjusts the perpendicularity of mast 1-2;According to spatial altitude and the length of steel-pipe pile 4, pass through mast elevating system 1-3 adjusts the working depth of mast 1-2.
3. carry power by hydra-electric control piper 3 to rotate to unit head hydraulic motor, driving drive joint 1-1-3 Test run, starts working after working well;
4. drive joint 1-1-3 stops the rotation, and is connected with drive joint 1-1-3 by steel-pipe pile 4 coxopodite;
5. unit head 1-1 drive steel-pipe pile 4 coxopodite, while rotation under press so that it is pierce in soil;
6. unit head 1-1 stops the rotation, by the upper and lower joint of steel-pipe pile 4 single-unit respectively with drive joint 1-1-3 and steel pipe Stake 4 coxopodite connects;
7. unit head 1-1 drive steel-pipe pile 4 single-unit to rotate and under press, make steel-pipe pile 4 pierce in soil, repeat steel-pipe pile 4 single Joint connects, under press through journey, until stopping after being drilled into construction requirement set depth to bore;
8. promote unit head 1-1, main frame is moved on to next stake position, completes a cycle of operation;
9. repeat step 2~8, until completing first workshop section's work;
10., according to place situation, main frame, Hydraulic Station are moved to the precalculated position of next workshop section.
Continue construction according to sequence described above, complete all processes construction.
This utility model content is a kind of equipment for steel-pipe pile construction, including main frame, Hydraulic Station, steel-pipe pile, hydraulic pressure Electric control lines.Described main frame is by unit head, mast, chassis, upper mounting plate, pressurization hoisting mechanism, mast leveling device, mast Elevating mechanism, swinging mounting, swinging mounting, hydra-electric control station etc. form.Described steel-pipe pile is driven by unit head and pierces In the foundation that need to improve.Described steel-pipe pile is made up of the drilling rod of band detachable connector and the drill bit of band helical blade.Institute State Hydraulic Station and provide power for main frame.The unit head of main frame uses low speed high torque hydraulic motor (or fluid motor-driven planet Decelerator), for the high torque driving steel-pipe pile to provide.The pressurization hoisting mechanism of unit head is Driven by Hydraulic Cylinder oil cylinder-chain Travel multiplier device or hydraulic motor decelerator device, to drive unit head to lift, overcome bigger resistance when creeping into.Hydraulic cylinder Oil cylinder-chain travel multiplier device or hydraulic motor decelerator device is driven to be built in mast, compact conformation.Mast leveling device It is provided with the oscillating oil cylinder making mast left and right directions rotate and a frame oil cylinder of fore-and-aft direction rotation, facilitates rig fast and accurately Adjust the perpendicularity of mast.Mast elevating system by Driven by Hydraulic Cylinder, make mast in the gathering sill of rotating turret assembly on move down The dynamic mast that realizes lifts, can be according to the needs of engineering site condition, and when constructing in short space, mast working depth can drop Low;Can increase mast working depth when construction space height allows, corresponding single steel-pipe pile length can lengthen, and reduces Non-cutting time.Chassis is fluid motor-driven crawler travel mode, and rig shifting walk is flexible.Unit head is provided with lower bands The drive joint of open slot, it is simple to unit head is quickly connected with steel-pipe pile.Hydraulic Station and main frame are split type, use hydra-electric Control piper and circuit are connected with main frame.The supporting road wheel of Hydraulic Station is easy to mobile.Steel-pipe pile is more piece package assembly, if being provided with Dry joint.Often group joint is made up of a new designs of threaded joints.Steel-pipe pile coxopodite is provided with helical blade, plays self tapping and buries effect, increases The big pressure crept into, beneficially steel-pipe pile are pressed in soil while rotating.This utility model is applicable to mud, clay, sand bed, ovum The construction of the soil layers such as gravel layer, it has adaptation special construction place, narrow short space, to construction site undisturbed or disturbance The advantage such as minimum, efficiency of construction is high, consolidation effect is preferable, job site is civilized.
The above embodiment is only preferred embodiment of the present utility model, and the not feasible enforcement of this utility model Exhaustive.For persons skilled in the art, on the premise of without departing substantially from this utility model principle and spirit, it is made Any obvious change gone out, within all should being contemplated as falling with claims of the present utility model.

Claims (10)

1. a spinning steel-pipe pile construction equipment, it is characterised in that: it includes driving the main frame (1) of steel-pipe pile (4), for main frame (1) Hydraulic Station (2) of hydraulic power is provided and is connected to the hydra-electric control piper between Hydraulic Station (2) and main frame (1) (3).
A kind of spinning steel-pipe pile construction equipment the most according to claim 1, it is characterised in that: described main frame (1) includes the end Dish (1-9), the mast mechanism being arranged on chassis (1-9) and be arranged on mast mechanism drive steel-pipe pile (4) unit head (1-1).
A kind of spinning steel-pipe pile construction equipment the most according to claim 2, it is characterised in that: under described unit head (1-1) Portion is provided with the drive joint (1-1-3) of band open slot (1-1-5).
A kind of spinning steel-pipe pile construction equipment the most according to claim 2, it is characterised in that: described mast mechanism includes mast Bar (1-2), the mast turning rack (1-5) being arranged on chassis (1-9), lower end are arranged on mast turning rack (1-5) Mast elevating system (1-3).
A kind of spinning steel-pipe pile construction equipment the most according to claim 4, it is characterised in that: described mast (1-2) includes Mast main body (1-2-1) and pressurization hoisting mechanism;It is provided with mast between described mast turning rack (1-5) and mast (1-2) Sideshake oil cylinder mechanism (1-4);It is provided with mast between upper mounting plate and the mast turning rack (1-5) on described chassis (1-9) Lift ram mechanism (1-6).
A kind of spinning steel-pipe pile construction equipment the most according to claim 5, it is characterised in that: described pressurization hoisting mechanism bag The lower guiding include the upper jockey sprocket (1-2-7) being positioned at mast main body (1-2-1) top, being positioned at mast main body (1-2-1) bottom Sprocket wheel (1-2-6), the oil cylinder-chain travel multiplier being arranged between jockey sprocket (1-2-7) and lower jockey sprocket (1-2-6) Drag chain is walked around in device (1-2-4), the driving oil cylinder-hydraulic cylinder (1-2-2) of chain travel multiplier device (1-2-4), one end Wheel (1-2-7) other end walks around the lifting of lower jockey sprocket (1-2-6) after oil cylinder-chain travel multiplier device (1-2-4) Lower jockey sprocket (1-2-6) is walked around and through oil cylinder-chain travel multiplier device (1-2-4) in chain (1-2-3) and one end
Pressurizing chain (1-2-11);
One end of described lifting chain (1-2-3) is fixed on the top of unit head (1-1), described lifting chain (1-2-3) another One end is held within mast main body (1-2-1) middle and upper part;
One end of described pressurizing chain (1-2-11) is fixed on the bottom of unit head (1-1), described pressurizing chain (1-2-11) The other end is fixed on the bottom of mast main body (1-2-1).
A kind of spinning steel-pipe pile construction equipment the most according to claim 5, it is characterised in that: described pressurization hoisting mechanism bag The drive sprocket include the upper directive wheel (1-2-8) being positioned at mast main body (1-2-1) top, being positioned at mast main body (1-2-1) bottom (1-2-5) chain (1-2-9), being arranged between directive wheel (1-2-8) and drive sprocket (1-2-5) and driving chain (1-2-9) hydraulic motor (1-2-10).
A kind of spinning steel-pipe pile construction equipment the most according to claim 1, it is characterised in that: described steel-pipe pile (4) includes Top connects pipeline section and lower boreholes pipeline section.
A kind of spinning steel-pipe pile construction equipment the most according to claim 8, it is characterised in that: described top connects pipeline section bag Include connecting tube body (4-1), be positioned at the lower contact (4-2) of connecting tube body (4-1) bottom, be positioned on connecting tube body (4-1) First top connection (4-3) in portion and be arranged on connecting tube body (4-1) outer wall and be positioned at the of the first top connection (4-3) place One block (4-4);Described lower boreholes pipeline section include drill pipe body (4-9), be positioned at drill pipe body (4-9) top and with under The second top connection (4-7) that joint (4-2) matches, it is arranged on drill pipe body (4-9) outer wall and is positioned at the second top connection (4-7) second block (4-8) at place, the helical blade (4-5) being arranged on the outer wall of drill pipe body (4-9) bottom and setting Apex point (4-6) in drill pipe body (4-9) lower end.
10. according to a kind of spinning steel-pipe pile construction equipment described in claim 9, it is characterised in that: described first block (4- 4) width of and the second block (4-8) is respectively less than the groove width of open slot (1-1-5);Described first block (4-4) and the second block (4-8) quantity is all identical with the quantity of open slot (1-1-5);
Described lower contact (4-2), the first top connection (4-3) and the second top connection (4-7) are equipped with the connection screw thread matched;
The quantity of described open slot (1-1-5) is two or more.
CN201620427539.XU 2016-05-12 2016-05-12 A kind of spinning steel-pipe pile construction equipment Expired - Fee Related CN205688440U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620427539.XU CN205688440U (en) 2016-05-12 2016-05-12 A kind of spinning steel-pipe pile construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620427539.XU CN205688440U (en) 2016-05-12 2016-05-12 A kind of spinning steel-pipe pile construction equipment

Publications (1)

Publication Number Publication Date
CN205688440U true CN205688440U (en) 2016-11-16

Family

ID=57262335

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620427539.XU Expired - Fee Related CN205688440U (en) 2016-05-12 2016-05-12 A kind of spinning steel-pipe pile construction equipment

Country Status (1)

Country Link
CN (1) CN205688440U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105780776A (en) * 2016-05-12 2016-07-20 河北新钻钻机有限公司 Steel pipe pile rotary extrusion construction facility
CN108005061A (en) * 2018-01-31 2018-05-08 广西盛虎金属制品有限公司 Spinning expands the construction method of head steel-pipe pile

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105780776A (en) * 2016-05-12 2016-07-20 河北新钻钻机有限公司 Steel pipe pile rotary extrusion construction facility
CN105780776B (en) * 2016-05-12 2017-10-31 河北新钻钻机有限公司 A kind of spinning steel-pipe pile construction equipment
CN108005061A (en) * 2018-01-31 2018-05-08 广西盛虎金属制品有限公司 Spinning expands the construction method of head steel-pipe pile
CN108005061B (en) * 2018-01-31 2019-04-12 广西盛虎金属制品有限公司 The construction method of spinning expansion head steel-pipe pile

Similar Documents

Publication Publication Date Title
CN105780776B (en) A kind of spinning steel-pipe pile construction equipment
CN102226342B (en) Multi-functional piling machine for jet grouting pile-sinking
CN110374500B (en) Grouped drilling and pile planting construction method
CN105840110B (en) A kind of multifunctional rotary digging machine
CN103510852B (en) A kind of rotary drilling rig
CN102425372B (en) Vibrato-drilling type punching drilling rig
CN205688440U (en) A kind of spinning steel-pipe pile construction equipment
CN107620574A (en) A kind of full circle swinging all casing drill main body and full circle swinging all casing drill
CN105672880A (en) Improved long spiral drilling machine
CN205743733U (en) Drill rod assemblies for the bored enlarged footing of stake machine
CN202039369U (en) Multifunctional pilling machine for jet grouting pile sinking
CN206844193U (en) Bore support integral type pile hole forming device
CN206668161U (en) A kind of boring drill bit device of reducing
CN216950237U (en) Drilling device for piling on soft foundation ground
CN104594339A (en) Construction method for concrete pile
CN208280899U (en) Crawler-type mountain area drilling machine
CN202417302U (en) Vibrating drilling type impact digging drilling machine
CN109098655B (en) Multi-power composite drilling tool, preparation method and pile
CN204419031U (en) A kind of full screw earth auger and Static pressure pile driver all-in-one
CN105840092A (en) Rotary drilling machine double-column structure
CN115822449A (en) Novel crawler-type composite pile machine
CN105804649A (en) Power system of long spiral drilling machine
CN207453885U (en) A kind of multifunctional rotary digging machine
CN215441884U (en) Drilling and hammering integrated machine
CN204875769U (en) Grow degree strength core composite pile and preparation equipment thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161116

Termination date: 20180512