CN205637564U - Sclausura combined strength template - Google Patents

Sclausura combined strength template Download PDF

Info

Publication number
CN205637564U
CN205637564U CN201620506043.1U CN201620506043U CN205637564U CN 205637564 U CN205637564 U CN 205637564U CN 201620506043 U CN201620506043 U CN 201620506043U CN 205637564 U CN205637564 U CN 205637564U
Authority
CN
China
Prior art keywords
connector
clamping part
scope
atresia
combined type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620506043.1U
Other languages
Chinese (zh)
Inventor
郑辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201620506043.1U priority Critical patent/CN205637564U/en
Application granted granted Critical
Publication of CN205637564U publication Critical patent/CN205637564U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a sclausura combined strength template is including two panels, coupling assembling and fixed the knot, wherein, coupling assembling includes two at least connecting pieces, the connecting piece is the strip, along the length direction setting of panel, transverse connection between the connecting piece, two panels respectively with the connecting piece fixed connection at both ends, the connecting piece has at least one clamping part, and the adjacent clamping part symmetry of two adjacent connecting pieces sets up, connects through the fixed staple bolt of detaining. The utility model discloses need not to punch, have simple to operate, freely splice, install the accuracy height, use advantages such as nimble.

Description

A kind of atresia Combined type building template
Technical field
This utility model belongs to building field, relates to a kind of building template, particularly relates to a kind of atresia Combined type building template.
Background technology
Building template is a kind of temporary supporting structure, is the mould of casting concrete molding, with mixed The directly contact of solidifying soil, makes concrete component have required shape, size and surface quality.Mesh Before, assembling by the way of punching and insertion latch between building template, the method easily goes out The problem cannot alignd in existing position, hole, causes that template assemblies is uneven, error occur, affect construction speed Etc. situation.It addition, the position, hole of frame, inner corner trim or external corner reduces the intensity of himself, minimizing makes Use the life-span.Additionally, traditional assembling mode is to be combined by adjacent frame, it is inserted into Latch is fixed, and the frame of merging exists gap, causes producing spillage phenomenon during casting concrete.
Utility model content
This utility model provides a kind of frame atresia Combined type building template, to overcome prior art Defect.
For achieving the above object, this utility model provides a kind of atresia Combined type building template, including Two pieces of panels, connect assembly and clip;Wherein, connect assembly and include at least two connector; Connector is strip, and the length direction along panel is arranged, lateral connection between connector;Two pieces of faces Plate is fixing with the connector at two ends respectively to be connected;Connector has at least one clamping part, and adjacent two The adjacent clamping part of individual connector is symmetrical arranged, and is connected by clip anchor ear.
Further, this utility model provides a kind of atresia Combined type building template, it is also possible to have this The feature of sample: wherein, connector also has the scope of operation;The side of the scope of operation and one end of clamping part Fixing connection, the scope of operation splicing of two adjacent connectors.
Further, this utility model provides a kind of atresia Combined type building template, it is also possible to have this The feature of sample: wherein, the opposite side of the scope of operation of two end connections has embedded groove, and panel is fixed In embedded groove.
Further, this utility model provides a kind of atresia Combined type building template, it is also possible to have this The feature of sample: also include reinforced pipe, is located between the adjacent clamping part of adjacent two connectors, Close the gap between the scope of operation of two splicings.
Further, this utility model provides a kind of atresia Combined type building template, it is also possible to have this The feature of sample: wherein, the other end of clamping part bends towards reinforced pipe, surrounds reinforced pipe.
Further, this utility model provides a kind of atresia Combined type building template, it is also possible to have this The feature of sample: wherein, clamping part has the projection towards clip sidewall;The sidewall tool of clip Have and the protruding groove matched;During two clamping parts of clip anchor ear, projection snaps in groove.
Further, this utility model provides a kind of atresia Combined type building template, it is also possible to have this The feature of sample: wherein, connecting any one or two connectors in assembly is frame connecting pieces;Limit Frame connector has a clamping part, and one end is perpendicularly fixed at the centre position of the scope of operation.
Further, this utility model provides a kind of atresia Combined type building template, it is also possible to have this The feature of sample: wherein, connecting any one connector in assembly is internal corner connector;Inner corner trim connects Part has a clamping part;The scope of operation of internal corner connector vertically bends, have first scope of operation and Second scope of operation;One end of clamping part is perpendicularly fixed at the centre position of first scope of operation.
Further, this utility model provides a kind of atresia Combined type building template, it is also possible to have this The feature of sample: wherein, connecting any one connector in assembly is external corner connecting piece;External corner connects Part has two clamping parts being mutually perpendicular to fix;The scope of operation of external corner connecting piece vertically bends, with Two clamping part Formation cross-sections structure in " ten " font.
Further, this utility model provides a kind of atresia Combined type building template, it is also possible to have this The feature of sample: wherein, external corner connecting piece also has reinforcement;Reinforcement both sides respectively with two sun The clamping part of angle connector is fixed, the structure that formed cross section is triangular in shape.
Having the beneficial effects that of this patent: this utility model provides a kind of atresia Combined type building template, Panel is the most detachably spliced by the connector of lateral connection, wherein, and frame connecting pieces, external corner Connector and internal corner connector are respectively provided with clamping part and the scope of operation, adjacent two connections of clip anchor ear The adjacent clamping part of part, makes the adjacent scope of operation splice, two pieces of panels and the splicing of Partial Jobs face Become plane, inner corner trim or external corner, it is not necessary to punching, improve the intensity of connector, avoid position, hole not simultaneously Cause the problems such as installation difficulty together.Reinforced pipe is located between adjacent two clamping parts, closes two spellings Gap between the scope of operation connect, prevents the concrete spillage poured, and improves the sealing of building template Property.This utility model provides the connector of various structures, can be assembled with independent assortment, uses flexibly.
Accompanying drawing explanation
Fig. 1 is the front view of a kind of atresia Combined type building template that embodiment one provides;
Fig. 2 is the A-A profile of Fig. 1;
Fig. 3 is the profile of a kind of atresia Combined type building template that embodiment two provides;
Fig. 4 is the front view of a kind of atresia Combined type building template that embodiment three provides;
Fig. 5 is the B-B profile of Fig. 4;
Fig. 6 is the B-B profile of Fig. 4.
Detailed description of the invention
Below in conjunction with accompanying drawing, detailed description of the invention of the present utility model is described.
Embodiment one
As illustrated in fig. 1 and 2, the present embodiment provides a kind of atresia Combined type building template, including two Block panel 100, connection assembly, clip 300 and reinforced pipe 400.This example demonstrates that two pieces of faces Plate carries out the detailed description of the invention of plain splice, connects assembly and includes two connectors, is frame Connector 200.
Frame connecting pieces 200 is in strip, and the length direction along panel 100 is arranged, and two frames are even Lateral connection between fitting 200.
Frame connecting pieces 200 has a clamping part 210 and the scope of operation 220.Clamping part 210 1 End is perpendicularly fixed at the centre position of the scope of operation 220 side.The opposite side of the scope of operation 220 has embedding Entering groove 221, panel 100 is fixed in embedded groove 221.
Clip 300 cross section takes the shape of the letter U.Two frame connecting pieces 200 are symmetrical arranged, clip 300 Two clamping parts 210 of anchor ear, two scope of operations 220 are stitched together, and make two frame connecting pieces 200 removably connect.Clamping part 210 also has the projection 211 towards clip 300 sidewall, Gu Surely the sidewall of button 300 has the groove 301 matched with it, clip 300 anchor ear two clamping During portion 210, protruding 211 snap in groove 301.
Reinforced pipe 400 is located between two clamping parts 210, closes the scope of operation 220 of two splicings Between gap, prevent casting concrete leakage.The other end of clamping part 210 is all towards reinforced pipe 400 bendings, surround reinforced pipe 400.
During clip 300 two frame connecting pieces 200 of anchor ear, two pieces of panels 100 realize plane and spell Connect.
Embodiment two
As it is shown on figure 3, the present embodiment provides a kind of atresia Combined type building template, including panel 100a ', panel 100b ', connection assembly, clip 300 ' and reinforced pipe 400 '.This reality Execute example and illustrate that two pieces of panels carry out the specific embodiment mode of inner corner trim splicing, connect assembly and include two Connector, respectively frame connecting pieces 200a ' and internal corner connector 200b '.
Frame connecting pieces 200a ' and internal corner connector 200b ' is all in strip, along panel 100a ' The length direction of (100b ') is arranged, lateral connection between the two.
Frame connecting pieces 200a ' has a clamping part 210a ' and scope of operation 220a '.Clamping 210a ' one end, portion is perpendicularly fixed at the centre position of scope of operation 220a ' side.Scope of operation 220a ' Opposite side there is embedded groove 221a ', panel 100a ' be fixed in embedded groove 221a '.
Internal corner connector 200b ' has a clamping part 210b ' and scope of operation 220b '.Operation Face 220b ' vertically bends, and has the first scope of operation 221b ' and the second scope of operation 222b '.Folder Hold 210b ' one end, portion and be perpendicularly fixed at the centre position of the first scope of operation 221b '.Second scope of operation 222b ' has embedded groove 2221b ', panel 100b ' and is fixed in embedded groove 2221b '.
Clip 300 ' cross section takes the shape of the letter U.Clamping part 210a ' and clamping part 210b ' is symmetrical arranged, Being connected by clip 300 ' anchor ear, scope of operation 220a ' exists with the first scope of operation 221b ' splicing Together, frame connecting pieces 200a ' and internal corner connector 200b ' is made to removably connect.Clamping part 210a ' and clamping part 210b ' is also respectively provided with the protruding 211a ' towards clip 300 ' sidewall With protruding 211b ', the sidewall of clip 300 ' has the groove 301 ' matched with it, Gu When surely detaining 300 ' anchor ear clamping part 210a ' and clamping part 210b ', protruding 211a ' and projection 211b ' is respectively clamped in two grooves 301 '.
Reinforced pipe 400 ' is located between clamping part 210a ' and clamping part 210b ', closes splicing Scope of operation 220a ' and the gap made between the first scope of operation 221b ', prevent casting concrete from leaking Liquid.The other end of clamping part 210a ' and clamping part 210b ' all bends towards reinforced pipe 400 ', Surround reinforced pipe 400 '.
During clip 300 ' anchor ear frame connecting pieces 200a ' and internal corner connector 200b ', panel First scope of operation 221b ' of 100a ', panel 100b ' and internal corner connector 200b ' is spliced into Inner corner trim.
Embodiment three
Such as Fig. 4, shown in 5 and 6, the present embodiment provides a kind of atresia Combined type building template, including Two pieces of panels 100 ", connect assembly, clip 300 " and two reinforced pipes 400 ".This enforcement The specific embodiment mode of example two pieces of panel splicing external corners of explanation, connects assembly and includes three connectors, It is respectively two frame connecting pieces 200a " and external corner connecting piece 200c ".
Frame connecting pieces 200a " and external corner connecting piece 200c " is all in strip, along panel 100 " Length direction is arranged.Between external corner connecting piece 200c " is located at two frame connecting pieces 200a ", three Lateral connection between person.
Frame connecting pieces 200a " has a clamping part 210a " and scope of operation 220a ".Clamping The centre position of portion 210a " one end is perpendicularly fixed at scope of operation 220a " side.Scope of operation 220a " Opposite side there is embedded groove 221a ", in panel 100 " being fixed on embedded groove 221a ".
External corner connecting piece 200c " has two orthogonal clamping part 210c " and the scope of operation 220c″." vertically bending, " Formation cross-section is in " ten " with two clamping part 210c for scope of operation 220c The structure of font.
External corner connecting piece 200c " also has reinforcement 230c ", both sides respectively with two clamping parts 210c " fixing, the structure that formed cross section is triangular in shape.Reinforcement 230c " offer by both sides Have several holes 231c ", be used for inserting clip 300 ".
" cross section takes the shape of the letter U clip 300.Clamping part 210c " and the clamping part being adjacent 210a " being symmetrical arranged, by clip 300 " anchor ear connects, scope of operation 220c " with its both sides Scope of operation 220a " being stitched together respectively, make external corner connecting piece 200c " respectively with the limit at two ends Frame connector 200a " removably connects.Clamping part 210a " has towards clip 300 " sidewall Protruding 211a ", clip 300 " sidewall there is the groove 301 matched with it ", Gu Surely 300 " anchor ear clamping part 210a " and clamping part 210c are detained " time, protruding 211a " snaps in groove 301 " in.
Reinforced pipe 400 " being located at clamping part 210a " and clamping part 210c " between, close splicing Gap between scope of operation 220c " and scope of operation 220a ", prevents casting concrete leakage.Clamping The other end of portion 210a " and clamping part 210c " is all towards reinforced pipe 400, and " bending is surrounded and is strengthened Pipe 400 ".
Clip 300 " anchor ear limit external corner connecting piece 200c respectively " and the frame connector being adjacent 200a " time, two pieces of panels 100 " and scope of operation 220c " are spliced into external corner.

Claims (10)

1. an atresia Combined type building template, it is characterised in that:
Including two pieces of panels, connect assembly and clip;
Wherein, described connection assembly includes at least two connector;
Described connector is strip, along described panel length direction arrange, described connector it Between lateral connection;
Two pieces of described panels are fixed with the described connector at two ends respectively and are connected;
Described connector has at least one clamping part, adjacent two described connectors adjacent Described clamping part is symmetrical arranged, and is connected by described clip anchor ear.
Atresia Combined type building template the most according to claim 1, it is characterised in that:
Wherein, described connector also has the scope of operation;
The side of the described scope of operation is fixing with one end of described clamping part to be connected, two adjacent institutes State the described scope of operation splicing of connector.
Atresia Combined type building template the most according to claim 2, it is characterised in that:
Wherein, the opposite side of the described scope of operation of connector described in two ends has embedded groove, described Panel is fixed in described embedded groove.
Atresia Combined type building template the most according to claim 2, it is characterised in that:
Also include reinforced pipe, be located at adjacent two described connectors adjacent described clamping part it Between, close the gap between the described scope of operation of two splicings.
Atresia Combined type building template the most according to claim 4, it is characterised in that:
Wherein, the other end of described clamping part bends towards described reinforced pipe, surrounds described reinforcement Pipe.
Atresia Combined type building template the most according to claim 1, it is characterised in that:
Wherein, described clamping part has the projection towards described clip sidewall;
The sidewall of described clip has the groove matched with described projection;
During described two described clamping parts of clip anchor ear, described projection snaps in described groove.
Atresia Combined type building template the most according to claim 2, it is characterised in that:
Wherein, in described connection assembly, any one or two described connectors are that frame connects Part;
Described frame connecting pieces has a described clamping part, and one end is perpendicularly fixed at described operation The centre position in face.
Atresia Combined type building template the most according to claim 7, it is characterised in that:
Wherein, in described connection assembly, any one of connector is internal corner connector;
Described internal corner connector has a described clamping part;
The described scope of operation of described internal corner connector vertically bends, and has first scope of operation and second The scope of operation;
One end of described clamping part is perpendicularly fixed at the centre position of described first scope of operation.
Atresia Combined type building template the most according to claim 7, it is characterised in that:
Wherein, in described connection assembly, any one of connector is external corner connecting piece;
Described external corner connecting piece has two described clamping parts being mutually perpendicular to fix;
The described scope of operation of described external corner connecting piece vertically bends, and is formed with two described clamping parts Cross section is in the structure of " ten " font.
Atresia Combined type building template the most according to claim 9, it is characterised in that:
Wherein, described external corner connecting piece also has reinforcement;
Described reinforcement both sides clamping part with two described external corner connecting pieces respectively is fixed, with it The structure that Formation cross-section is triangular in shape.
CN201620506043.1U 2016-05-27 2016-05-27 Sclausura combined strength template Expired - Fee Related CN205637564U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620506043.1U CN205637564U (en) 2016-05-27 2016-05-27 Sclausura combined strength template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620506043.1U CN205637564U (en) 2016-05-27 2016-05-27 Sclausura combined strength template

Publications (1)

Publication Number Publication Date
CN205637564U true CN205637564U (en) 2016-10-12

Family

ID=57051230

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620506043.1U Expired - Fee Related CN205637564U (en) 2016-05-27 2016-05-27 Sclausura combined strength template

Country Status (1)

Country Link
CN (1) CN205637564U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113374254A (en) * 2021-06-28 2021-09-10 中冶建工集团有限公司 Construction method for improving forming quality of junction of new and old cast-in-place concrete walls

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113374254A (en) * 2021-06-28 2021-09-10 中冶建工集团有限公司 Construction method for improving forming quality of junction of new and old cast-in-place concrete walls
CN113374254B (en) * 2021-06-28 2022-12-23 中冶建工集团有限公司 Construction method for improving forming quality of junction of new and old cast-in-place concrete walls

Similar Documents

Publication Publication Date Title
CN110397275A (en) A kind of shear-wall strengthening part
CN205637564U (en) Sclausura combined strength template
CN112081142A (en) Connecting joint and connecting node
CN205804942U (en) A kind of formwork reinforcement steel substitute materials for wood structure
CN106049854A (en) Template reinforcing steel-replacing-wood material structure and usage method
KR200393433Y1 (en) Out corner coupling implement for construction mold panel
CN110130638A (en) A kind of plank sheathing splicing angle steel external member, channel steel external member and construction method
CN206684422U (en) Display surface frame and display
CN212001876U (en) Structure is pour in construction of building
CN214615397U (en) Combined aluminum-wood combined template structure
CN209066881U (en) Assembled architecture to pull-up structure
CN212376282U (en) Pulling-on piece
CN212271585U (en) Locking device of scaffold
CN113550565A (en) Template pulling piece and template structure
CN113356578A (en) Connection structure and template system
CN113006480A (en) Combined template structure connected by connector
KR200321084Y1 (en) Reinforcement structure for euro-form panel
CN113136989A (en) Assembled shear force wall tooth's socket type connection structure
CN207160554U (en) Building template combines the unit
CN204691258U (en) A kind of latch of concrete blinding jockey and jockey
CN210858017U (en) Connecting and locking device for building template
CN212269177U (en) Elevator counterweight housing convenient to install
CN220434051U (en) Form removal-free constructional column and door buttress device
CN214364905U (en) Modularization template to bulky concrete placement
CN219932155U (en) Ventilation shaft template

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161012

Termination date: 20210527

CF01 Termination of patent right due to non-payment of annual fee