CN205629308U - Reserve funnel structure of amorphous wide -band system - Google Patents

Reserve funnel structure of amorphous wide -band system Download PDF

Info

Publication number
CN205629308U
CN205629308U CN201520932849.2U CN201520932849U CN205629308U CN 205629308 U CN205629308 U CN 205629308U CN 201520932849 U CN201520932849 U CN 201520932849U CN 205629308 U CN205629308 U CN 205629308U
Authority
CN
China
Prior art keywords
funnel
steel shoe
funnel body
steel
shoe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520932849.2U
Other languages
Chinese (zh)
Inventor
张念伟
孙钡钡
虞璐
胡柳亮
雷高峰
严密
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zhaojing Electrical Technology Co., Ltd.
Original Assignee
ZHAOJING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHAOJING Co Ltd filed Critical ZHAOJING Co Ltd
Priority to CN201520932849.2U priority Critical patent/CN205629308U/en
Application granted granted Critical
Publication of CN205629308U publication Critical patent/CN205629308U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a reserve funnel structure of amorphous wide -band system, include the filler tube and have the inlet and the funnel body of liquid outlet, the liquid outlet department at the funnel body is connected to the filler tube, the funnel body is inside to be provided with class steel shoe and to cross the steel shoe, it sets up in the funnel body to flow the steel shoe slope, the side of crossing steel shoe one end and flowing the steel shoe offsets, and the other end supports by on the medial surface at the funnel body, the one end of crossing the steel shoe and flowing the steel shoe counterbalance is provided with the opening that can supply the molten steel to pass through, the utility model discloses at amorphous broadband preparation in -process, has the advantage that thermal shock resistance is good, the scour resistance is strong, anti aggressivity is good.

Description

A kind of Amorphous Wide Ribbon preparation funnel structure
Technical field
This utility model belongs to Amorphous Wide Ribbon preparation facilities technical field, relates to a kind of Amorphous Wide Ribbon preparation infundibular ganglion Structure.
Background technology
During non-crystal belt making, molten steel flows out from tundish rising pouring tapping hole, is normally sprayed to spray bag through funnel Band, molten steel temperature is between 1300~1450 DEG C, and funnel must have good thermal shock resistance.In general, the spray band time is about 2.5~4 hours, so, funnel also to possess the antiscour of excellence, corrosion resistance.And existing funnel pours into a mould moment at molten steel With regard to time have the generation of the cracking phenomenons such as bleed-out, once bleed-out can cause siliconit short circuit, molten steel to drip at nozzle and copper roller, causes The adverse consequencess such as spray band interruption, have a strong impact on production efficiency and there is production safety hidden danger.
Summary of the invention
For the problems referred to above, the technical problems to be solved in the utility model is to provide a kind of in Amorphous Wide Ribbon preparation process In, there is the Amorphous Wide Ribbon preparation funnel structure of the advantages such as good thermal shock, scour resistance is strong, corrosion resistance is good.
Amorphous Wide Ribbon preparation funnel structure of the present utility model, including funnel tube and with inlet and the leakage of liquid outlet Bucket body, described funnel tube is connected at the liquid outlet of funnel body, and described funnel body is internally provided with stream steel shoe and mistake Steel shoe, described stream steel shoe is inclined in funnel body, and described steel shoe one end of crossing offsets with the side flowing steel shoe, The other end is resisted against on the medial surface of funnel body, and one end that described steel shoe excessively and stream steel shoe offset is provided with and is available for molten steel The opening passed through;Stream steel shoe can play the cushioning effect to high-temperature molten steel when high-temperature molten steel is washed in funnel, reduces The probability of funnel cracking, improves anti-thermal shock intensity;Cross the opening in steel shoe for allowing molten steel pass through, and molten steel only has Could be prevented molten steel from splashing and accelerating the oxidation of molten steel toward dirty, also reduce molten steel to funnel body simultaneously by this opening The erosion of bottom, improves the service life of funnel body.
Amorphous Wide Ribbon preparation funnel structure of the present utility model, wherein, is provided with at the liquid outlet of described funnel body First step, the upper end periphery wall of described funnel tube is provided with the boss that can coordinate with first step, described funnel tube and leakage Bucket body grafting;Funnel tube is coordinated with the first step in funnel body by boss, is possible to prevent coming off of funnel tube.
Amorphous Wide Ribbon preparation funnel structure of the present utility model, wherein, it also includes one piece of splashproof cover plate, described funnel Being provided with second step at the inlet of body, described splashproof cover plate is embedded in second step;By the setting of splashproof cover plate, It is prevented from molten steel to spill the steel bean of formation when flowing into funnel body from tundish rising pouring tapping hole and beat and draw on chill roll Act the bad phenomenon rushing nozzle.
This utility model has the advantages that 1, stream steel shoe can play when high-temperature molten steel is washed in funnel Cushioning effect to high-temperature molten steel, reduces the probability of funnel cracking, improves anti-thermal shock intensity;Crossing the opening in steel shoe is to use In allowing molten steel pass through, and molten steel only has and could prevent molten steel from splashing and accelerating the oxidation of molten steel toward dirty by this opening, with Time also reduce molten steel to the erosion bottom funnel body, improve the service life of funnel body;2, funnel tube passes through boss Coordinate with the first step in funnel body, be possible to prevent coming off of funnel tube;3, by the setting of splashproof cover plate, it is possible to The steel bean preventing molten steel from spilling formation when flowing into funnel body from tundish rising pouring tapping hole is beaten and is caused punching on chill roll The bad phenomenon of nozzle.
Accompanying drawing explanation
For ease of explanation, this utility model is embodied as and accompanying drawing is described in detail by following.
Fig. 1 is sectional structure schematic diagram of the present utility model;
Fig. 2 is the sectional structure schematic diagram of funnel body;
Fig. 3 is the plan structure schematic diagram of funnel body;
Fig. 4 is the structural representation of stream steel shoe;
Fig. 5 was the structural representation of steel shoe;
Fig. 6 is the structural representation of splashproof cover plate.
Detailed description of the invention
Amorphous Wide Ribbon preparation funnel structure as shown in figs 1 to 6, including funnel tube 1 and with inlet 21 with go out liquid The funnel body 2 of mouth 22, described funnel tube 1 is connected at the liquid outlet 22 of funnel body 2, and described funnel body 2 is internal to be arranged Having stream steel shoe 3 and cross steel shoe 4, described stream steel shoe 3 is inclined in funnel body 2, described cross steel shoe 4 one end with The side of stream steel shoe 3 offsets, and the other end is resisted against on the medial surface of funnel body 2, described steel shoe 4 excessively and stream steel shoe 3 The one end offseted is provided with and is available for the opening 41 that molten steel passes through, and is provided with first step at the liquid outlet 22 of described funnel body 2 23, the upper end periphery wall of described funnel tube 1 is provided with the boss 11 that can coordinate with first step 23, described funnel tube 1 and leakage Struggle against body 2 grafting, and it also includes one piece of splashproof cover plate 5, is provided with second step 24 at the inlet 21 of described funnel body 2, Described splashproof cover plate 5 is embedded in second step 24.
Embodiment described above is only to be described preferred implementation of the present utility model, not to this practicality Novel spirit and scope are defined.On the premise of without departing from this utility model design concept, this area ordinary person couple Various modification that the technical solution of the utility model is made and improvement, all should drop into protection domain of the present utility model, this reality With the novel technology contents being claimed, all record in detail in the claims.

Claims (3)

1. an Amorphous Wide Ribbon preparation funnel structure, including funnel tube (1) and with inlet (21) and liquid outlet (22) Funnel body (2), described funnel tube (1) is connected to liquid outlet (22) place of funnel body (2), it is characterised in that: described funnel Body (2) is internally provided with stream steel shoe (3) and crosses steel shoe (4), and described stream steel shoe (3) is inclined at funnel body (2), in, described steel shoe (4) one end of crossing offsets with the side flowing steel shoe (3), and the other end is resisted against the interior of funnel body (2) On side, one end that described steel shoe (4) excessively and stream steel shoe (3) offset is provided with the opening (41) being available for molten steel and passing through.
Amorphous Wide Ribbon preparation funnel structure the most according to claim 1, it is characterised in that: described funnel body (2) Liquid outlet (22) place is provided with first step (23), and the upper end periphery wall of described funnel tube (1) is provided with can be with first step (23) boss (11) coordinated, described funnel tube (1) and funnel body (2) grafting.
Amorphous Wide Ribbon preparation funnel structure the most according to claim 1 and 2, it is characterised in that: it also includes that one piece is prevented Spattering cover plate (5), inlet (21) place of described funnel body (2) is provided with second step (24), and described splashproof cover plate (5) is embedded In second step (24).
CN201520932849.2U 2015-11-20 2015-11-20 Reserve funnel structure of amorphous wide -band system Active CN205629308U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520932849.2U CN205629308U (en) 2015-11-20 2015-11-20 Reserve funnel structure of amorphous wide -band system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520932849.2U CN205629308U (en) 2015-11-20 2015-11-20 Reserve funnel structure of amorphous wide -band system

Publications (1)

Publication Number Publication Date
CN205629308U true CN205629308U (en) 2016-10-12

Family

ID=57077779

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520932849.2U Active CN205629308U (en) 2015-11-20 2015-11-20 Reserve funnel structure of amorphous wide -band system

Country Status (1)

Country Link
CN (1) CN205629308U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113560515A (en) * 2021-06-21 2021-10-29 杭州电子科技大学 Tundish for rare earth magnetic material rapid-hardening casting belt and casting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113560515A (en) * 2021-06-21 2021-10-29 杭州电子科技大学 Tundish for rare earth magnetic material rapid-hardening casting belt and casting method
CN113560515B (en) * 2021-06-21 2023-01-03 杭州电子科技大学 Tundish for rare earth magnetic material rapid-hardening casting belt and casting method

Similar Documents

Publication Publication Date Title
CN205629308U (en) Reserve funnel structure of amorphous wide -band system
CN203378983U (en) Water outlet nozzle structure for coffee machine
CN207032415U (en) Whirlpool water curtain style scrubs toilet
CN104226973B (en) Continuous casting protection casting device of high-quality steel
CN106492614A (en) A kind of wet purification method of acidic flue gas and device
CN205214986U (en) Novel boil tea set
CN204338360U (en) A kind of self-cleaning type shower nozzle
CN205625851U (en) Spray arm subassembly and including its dish washer
CN204752643U (en) Quench ring device
CN103644324B (en) A kind of automatic drain valve of water heater
CN205165881U (en) Atomizing device is united to pre -alloyed powder aqueous vapor
CN208483209U (en) A kind of magnesium alloy low pressure burning casting furnace
CN106825529A (en) Ferronickel cast iron unit
CN108041977B (en) Jet flow plate for noodle cooking furnace
CN209153551U (en) Water tank and dish-washing machine
CN205463509U (en) Washing tank circulation box of intaking
CN206916495U (en) Steam generator and Garment Steamer Machine
CN207325506U (en) A kind of water-cooling frequency converter internal duct cleaning device
CN208599978U (en) A kind of high-pressure wash machine nozzle of automatic blowdown function
CN205763762U (en) Multifunctional ladle for soup feeding machine
CN210764819U (en) Be applied to water vapor separation structure of water purifier
CN205519521U (en) Special casting die utensil of blast pipe
CN206083450U (en) A water circle device for cooling of wire drawing jar
CN205413729U (en) Cylinder cap belt cleaning device
CN204854366U (en) Metal waste residue decomposition device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190404

Address after: 315301 Xinxing Avenue, Zonghan Street, Xinxing Industrial Cluster District, Cixi City, Ningbo City, Zhejiang Province, 88

Patentee after: Zhejiang Zhaojing Electrical Technology Co., Ltd.

Address before: No. 88 Xinxing Avenue, Zonghan Emerging Industrial Cluster Area, Cixi City, Ningbo City, Zhejiang Province, 315000

Patentee before: ZHAOJING CO., LTD.