CN205591245U - Whole buried bolt positioner in advance of clump of piles high accuracy - Google Patents
Whole buried bolt positioner in advance of clump of piles high accuracy Download PDFInfo
- Publication number
- CN205591245U CN205591245U CN201620288184.0U CN201620288184U CN205591245U CN 205591245 U CN205591245 U CN 205591245U CN 201620288184 U CN201620288184 U CN 201620288184U CN 205591245 U CN205591245 U CN 205591245U
- Authority
- CN
- China
- Prior art keywords
- bolt
- steel frame
- fixed
- steel
- bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model provides a whole buried bolt positioner in advance of clump of piles high accuracy, construct including whole steel frame structure and a plurality of bolt fixed knot of group, whole steel frame structure include steel frame (1) and jackscrew (2), steel frame (1) predetermine the condition of arranging according to on -the -spot pile foundation and make, jackscrew (2) set up on the peripheral frame of steel frame (1), be equipped with adjustable lead screw (3) on jackscrew (2) for support steel frame and adjusted frame frame integral level degree, bolt fixed knot construct the U type is connected including bolt fastening pole (5) with bolt fastening pole (5) buried bolt (4) in advance, bolt fastening pole (5) are through fixed bolt (7) and steel frame attach. The utility model discloses can carry out the multiunit location on simple structure, convenient to use, the steel frame, not confine single parameter to, the material can use repeatedly moreover, and the practicality is strong.
Description
Technical field
This utility model belongs to pre-embedded bolt and installs field of locating technology, is specifically related to a kind of clump of piles high accuracy integral built-in bolt positioning device.
Background technology
Photovoltaic engine components basis is made up of more than 8 single piles the most, area coverage about 20, and each single pile allows offset error to be 25mm, and for making photovoltaic panel normal mounting, the installation accuracy of support requires the highest, and the allowable error of its U-bolt built-in fitting is 2mm.It is all to take single stake to install successively that the pre-embedded bolt of a current this clump of piles is installed, the method not having integral installation, the pre-embedded bolt causing whole photovoltaic module basis does not has globality, it is difficult to meet the installation accuracy requirement of photovoltaic panel, and the Bolt installation method of domestic use is both for the installation of intensive Bolt, the Bolt that this area coverage in inapplicable photovoltaic module basis is wider, and material can not be recycled, it is therefore desirable to provide a kind of new integral built-in bolt secure mounting arrangements, can preferably ensure the position relationship between each built-in fitting, to meet relevant required precision.
Utility model content
The problem existed for prior art, this utility model is that the technical scheme that solution problems of the prior art use is as follows:
A kind of clump of piles high accuracy integral built-in bolt positioning device, including integrated steel frame structure and some groups of bolt fastening structure, it is characterized in that: described integrated steel frame structure includes steel frame 1 and jackscrew 2, described steel frame 1 is preset arrangement situation according to on-the-spot pile foundation and is made, described jackscrew 2 is arranged on the peripheral frame of steel frame 1, jackscrew 2 is provided with adjustable screw 3, in order to Braced Frames and adjust framework integral level degree;
Described bolt fastening structure includes that bar 5 fixed by U-shaped pre-embedded bolt 4 and bolt, described bolt is fixed bar 5 and is provided with the bolt fixing hole 6 passed for U-shaped pre-embedded bolt 4 two ends, described U-shaped pre-embedded bolt 4 is bolted nut 9 and bolt is fixed bar 5 and fixed, and is controlled pre-embedded bolt absolute altitude by the quantity controlling fixing nut;
Described bolt is fixed and is provided with Fixed latches 7 below bar 5 two ends, and steel frame 1 is provided with the latch fixing hole 12 corresponding with Fixed latches 7, and bolt is fixed and fixed nut 8 by latch after bar 5 inserts steel frame and be fixed.
On described steel frame 1, pile body reserved area is provided with casing and fixes steel bar 11, described casing fixes steel bar 11 through the perforate on steel pile casting 10, steel pile casting 10 is erected on steel frame 1, described steel pile casting 10 internal diameter is single stake preset diameters, by steel pile casting 10, single pile is positioned, and ensure the shape after single pile molding.
This utility model has the advantage that
1, each component is attached by bolt and nut, steel frame can be carried out organize location more, makes this utility model be not limited to single parameter, and material can Reusability;
2, position on overall steel framework in advance, without measuring in installing engineering, directly install according to position, hole, make whole device install and remove quick and easy;
3, overall location, installation, eliminates single stake bolt and installs the deviation produced, improve installation accuracy.
Accompanying drawing explanation
Fig. 1 is this utility model overall steel block schematic illustration;
Fig. 2 is jackscrew structural representation on this utility model steel frame;
Fig. 3 is that this utility model pre-embedded bolt fixes component schematic diagram;
Fig. 4 is this utility model pre-embedded bolt stationary state schematic diagram;
Wherein: 1-steel frame, 2-jackscrew, 3-adjustable screw, 4-U type pre-embedded bolt, 5-bolt fixes bar, 6-bolt fixing hole, 7-Fixed latches, and nut fixed by 8-latch, and 9-bolt fixes nut, 10-steel pile casting, and 11-casing fixes steel bar, 12-latch fixing hole.
Detailed description of the invention
Below by example, and combine accompanying drawing, the technical solution of the utility model is described in further detail, as Figure 1-4, a kind of clump of piles high accuracy integral built-in bolt positioning device, including integrated steel frame structure and some groups of bolt fastening structure, it is characterized in that: described integrated steel frame structure includes steel frame 1 and jackscrew 2, described steel frame 1 is preset arrangement situation according to on-the-spot pile foundation and is made, described jackscrew 2 is arranged on the peripheral frame of steel frame 1, jackscrew 2 is provided with adjustable screw 3, in order to Braced Frames and adjust framework integral level degree;
Described bolt fastening structure includes that bar 5 fixed by U-shaped pre-embedded bolt 4 and bolt, described bolt is fixed bar 5 and is provided with the bolt fixing hole 6 passed for U-shaped pre-embedded bolt 4 two ends, described U-shaped pre-embedded bolt 4 is bolted nut 9 and bolt is fixed bar 5 and fixed, and is controlled pre-embedded bolt absolute altitude by the quantity controlling fixing nut;
Described bolt is fixed and is provided with Fixed latches 7 below bar 5 two ends, and steel frame 1 is provided with the latch fixing hole 12 corresponding with Fixed latches 7, and bolt is fixed and fixed nut 8 by latch after bar 5 inserts steel frame and be fixed.
On described steel frame 1, pile body reserved area is provided with casing and fixes steel bar 11, described casing fixes steel bar 11 for connecting steel pile casting 10, described steel pile casting 10 symmetry at the 2cm of upper surface offers two groups of holes, casing fixes steel bar 11 through the perforate on steel pile casting 10, steel pile casting is erected on steel frame 1, described steel pile casting 10 internal diameter is single stake preset diameters, is positioned single pile by steel pile casting, and ensures the shape after single pile molding.
In work progress, overall steel framework is made by the practical situation according to on-the-spot pile foundation, in advance each single pile position and pre-embedded bolt position are positioned on steel frame, carry out overall location according to clump of piles high accuracy integral built-in bolt positioning device disclosed in this utility model afterwards to assemble, the positional precision of each single pile and pre-embedded bolt can be ensured.
Protection domain of the present utility model is not limited to the above embodiments, it is clear that those skilled in the art can carry out various change and deformation without deviating from scope and spirit of the present utility model to this utility model.If these are changed and deformation belongs in the range of this utility model claim and equivalent technologies thereof, intention the most of the present utility model also comprises these and changes and deformation.
Claims (2)
1. a clump of piles high accuracy integral built-in bolt positioning device, including integrated steel frame structure and some groups of bolt fastening structure, it is characterized in that: described integrated steel frame structure includes steel frame (1) and jackscrew (2), described steel frame (1) is preset arrangement situation according to on-the-spot pile foundation and is made, described jackscrew (2) is arranged on the peripheral frame of steel frame (1), jackscrew (2) is provided with adjustable screw (3), in order to Braced Frames and adjust framework integral level degree;
Described bolt fastening structure includes that bar (5) fixed by U-shaped pre-embedded bolt (4) and bolt, described bolt is fixed bar (5) and is provided with the bolt fixing hole (6) passed for U-shaped pre-embedded bolt (4) two ends, and described U-shaped pre-embedded bolt (4) is bolted nut (9) and bolt is fixed bar (5) and fixed;
Described bolt is fixed and is provided with Fixed latches (7) below bar (5) two ends, and steel frame (1) is provided with the latch fixing hole (12) corresponding with Fixed latches (7), and bolt is fixed nut (8) by latch after fixing bar (5) insertion steel frame and is fixed.
2. a kind of clump of piles high accuracy integral built-in bolt positioning device as claimed in claim 1, it is characterized in that: the upper pile body reserved area of described steel frame (1) is provided with casing and fixes steel bar (11), described casing fixes steel bar (11) through the perforate on steel pile casting (10), being erected on steel frame (1) by steel pile casting (10), described steel pile casting (10) internal diameter is single stake preset diameters.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620288184.0U CN205591245U (en) | 2016-04-08 | 2016-04-08 | Whole buried bolt positioner in advance of clump of piles high accuracy |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620288184.0U CN205591245U (en) | 2016-04-08 | 2016-04-08 | Whole buried bolt positioner in advance of clump of piles high accuracy |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205591245U true CN205591245U (en) | 2016-09-21 |
Family
ID=56923342
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620288184.0U Active CN205591245U (en) | 2016-04-08 | 2016-04-08 | Whole buried bolt positioner in advance of clump of piles high accuracy |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205591245U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108222056A (en) * | 2018-03-06 | 2018-06-29 | 防城港中重工有限公司 | Apparatus foundation bolt group's installation method |
-
2016
- 2016-04-08 CN CN201620288184.0U patent/CN205591245U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108222056A (en) * | 2018-03-06 | 2018-06-29 | 防城港中重工有限公司 | Apparatus foundation bolt group's installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100585098C (en) | Underground preburied column high-precision smart verticality-regulating system and mounting construction method | |
CN103526907B (en) | A kind of inclination stone material dry suspending structure and construction method thereof | |
KR20090124950A (en) | Fixture for locating wind turbine equipment on foundation prior to tower installation | |
CN205591245U (en) | Whole buried bolt positioner in advance of clump of piles high accuracy | |
CN205421311U (en) | Rag bolt fixes a position mounting tool | |
JP3194864U (en) | Height adjustable pile | |
CN205421322U (en) | Pre -buried rag bolt crowd's positioning tool | |
JP2013155581A (en) | Pile head joint structure assembling jig and pile head joint structure assembling method using the same | |
CN105773130B (en) | Blade root bolt embedment frock | |
CN203879041U (en) | Embedded plate positioning support frame | |
CN211114901U (en) | Bracket device convenient to precast beam is under construction fast | |
CN105080976B (en) | Vertical mill backing plate installation method and its device | |
CN201891507U (en) | Gas turbine support component and gas turbine generator set provided with same | |
JP2013189784A (en) | Connection structure of superstructure and pile | |
CN203334433U (en) | Concrete vertical face embedded part mounting fixing device | |
CN202372226U (en) | Extensible bracket for ultrasonic liquid level sensor | |
CN103981893B (en) | The hanging reinforced device and method of combustion turbine foundation built-in bolt | |
CN204187217U (en) | A kind of annular bolt collar group integral built-in and positioning tool | |
CN205857234U (en) | The tower kind equipment accurate mounting and positioning device of anchor bolt group | |
CN206657583U (en) | Multifunction label bracket component and apply its shaft tower | |
CN203238652U (en) | Positioning structure for installing and grouting offshore wind turbine jacket foundation | |
CN207500621U (en) | A kind of construction tool structure and construction equipment | |
CN204780985U (en) | Special double -deck hi -Fix crown plate of large -scale rag bolt | |
CN202323987U (en) | Embedded bolt positioning device of tower crane base | |
CN205078927U (en) | Nuclear power station assembled pipeline bracket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |