CN205579625U - Cooling air system is examined to power plant fire - Google Patents
Cooling air system is examined to power plant fire Download PDFInfo
- Publication number
- CN205579625U CN205579625U CN201620263002.4U CN201620263002U CN205579625U CN 205579625 U CN205579625 U CN 205579625U CN 201620263002 U CN201620263002 U CN 201620263002U CN 205579625 U CN205579625 U CN 205579625U
- Authority
- CN
- China
- Prior art keywords
- pipeline
- fire
- main line
- blower fan
- fire inspection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Fire Alarms (AREA)
Abstract
The utility model relates to a cooling air system is examined to power plant fire, it examines the technical field of system to belong to thermal power factory fire, which has the advantages of simple structure, high durability and convenient use, can effectively examine the probe to the fire cools off, prevent the fiery cooling air system is examined to power plant fire that the probe damaged that examines, the technical scheme who adopts examines the fan for the fire and is connected with the main line through first pipeline, it examines the probe to be connected with the fire on the main line, be provided with a three way connection between first pipeline and the main line, a three way connection still is connected with the second pipeline, it examines the fan to be connected with the stock fire on the second pipeline, be provided with the first control valve on the first pipeline, be provided with the second control valve on the second pipeline, the main line still is connected with the third pipeline, connect through the 2nd three way connection between third pipeline and the main line, the third pipeline is connected with cold tuber pipe, be provided with the check valve on the third pipeline, the utility model discloses extensively be used for the fire of thermal power factory to examine the system.
Description
Technical field
This utility model relates to a kind of power plant fire inspection cooling air system, belongs to thermal power plant flame detection system technical field.
Background technology
Each power plant is due to the design problem of fire inspection blower fan at present, and the accident causing fire inspection fan vibration to damage motor frequently occurs, and flame detecting probe coking or scaling loss often occurs, adds the maintenance cost of boiler, and had a strong impact on the safe operation of boiler.
Utility model content
For solving the technical problem that prior art exists, this utility model provides a kind of simple in construction, easy to use, it is possible to effectively to cool down flame detecting probe, prevents the power plant fire inspection cooling air system that flame detecting probe damages.
For achieving the above object, the technical scheme that this utility model is used is power plant fire inspection cooling air system, including fire inspection blower fan and flame detecting probe, described fire inspection blower fan is connected with main line by the first pipeline, connect on described main line and have flame detecting probe, it is provided with the first three way cock between described first pipeline and main line, described first three way cock is also associated with the second pipeline, connect on described second pipeline and have stock fire to examine blower fan, it is provided with the first control valve on described first pipeline, the second control valve it is provided with on second pipeline, described main line is also associated with the 3rd pipeline, connected by the second three way cock between described 3rd pipeline and main line, described 3rd pipeline is connected with cold primary air piping, it is provided with non-return valve on described 3rd pipeline.
Preferably, also include main control unit, being provided with pressure transducer and Pressure gauge on described main line, described fire inspection blower fan, stock fire inspection blower fan, the first control valve, the second control valve, pressure transducer are all connected with main control unit with Pressure gauge, and described main control unit is provided with display screen.
Compared with prior art, this utility model has following technical effect that this utility model simple in construction, easy to use, when boiler is properly functioning, use cold First air that flame detecting probe is cooled down, disable fire inspection blower fan, reduce station service power consumption rate, reduce fire inspection blower fan maintenance cost, greatly reduce the probability of flame detecting probe scaling loss, save cost.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
In order to make technical problem to be solved in the utility model, technical scheme and beneficial effect clearer, below in conjunction with drawings and Examples, this utility model is further elaborated.Should be appreciated that specific embodiment described herein, only in order to explain this utility model, is not used to limit this utility model.
As shown in Figure 1, power plant fire inspection cooling air system, including fire inspection blower fan 1 and flame detecting probe 2, fire inspection blower fan 1 is connected with main line 4 by the first pipeline 3, connect on main line 4 and have flame detecting probe 2, the first three way cock 5 it is provided with between first pipeline 3 and main line 4, first three way cock 5 is also associated with the second pipeline 6, connect on second pipeline 6 and have stock fire to examine blower fan 7, the first control valve 8 it is provided with on first pipeline 3, the second control valve 9 it is provided with on second pipeline 6, main line 4 is also associated with the 3rd pipeline 10, connected by the second three way cock 11 between 3rd pipeline 10 and main line 4, 3rd pipeline 10 is connected with cold primary air piping 12, it is provided with non-return valve 13 on 3rd pipeline 10.
Also include main control unit 14, pressure transducer 17 and Pressure gauge 15 it is provided with on main line 4, fire inspection blower fan 1, stock fire inspection blower fan the 7, first control valve the 8, second control valve 9, pressure transducer 14 are all connected with main control unit 14 with Pressure gauge 15, and main control unit 14 is provided with display screen 16.
When specifically used, when boiler is properly functioning, the first control valve 8 and the second control valve 9 are closed, fire inspection blower fan 1 and stock fire inspection blower fan 7 quit work, and use cold primary air piping to cool down flame detecting probe, thus reduce station service power consumption rate, reduce the maintenance cost of fire inspection blower fan, effectively save cost.Pressure transducer 14 is for the pressure of monitoring main line in real time, Pressure gauge 15 is for the pressure value of display main line in real time, and force value is shown in real time on main control unit, when the force value of main line is less than 6Kpa, main control unit controls open the first control valve and start fire inspection blower fan, cools down flame detecting probe.If operating fire inspection blower fan emergency stop valve trip, main control unit controls to open the second control valve and stock fire inspection blower fan, it is ensured that flame detecting probe safe operation.
The foregoing is only preferred embodiment of the present utility model, not in order to limit this utility model, all any amendment, equivalent and improvement etc. made within spirit of the present utility model and principle, in the range of all should wrapping in this utility model.
Claims (2)
1. power plant fire inspection cooling air system, it is characterized in that: include fire inspection blower fan and flame detecting probe, described fire inspection blower fan is connected with main line by the first pipeline, connect on described main line and have flame detecting probe, it is provided with the first three way cock between described first pipeline and main line, described first three way cock is also associated with the second pipeline, connect on described second pipeline and have stock fire to examine blower fan, it is provided with the first control valve on described first pipeline, the second control valve it is provided with on second pipeline, described main line is also associated with the 3rd pipeline, connected by the second three way cock between described 3rd pipeline and main line, described 3rd pipeline is connected with cold primary air piping, it is provided with non-return valve on described 3rd pipeline.
Power plant the most according to claim 1 fire inspection cooling air system, it is characterized in that: also include main control unit, pressure transducer and Pressure gauge it is provided with on described main line, described fire inspection blower fan, stock fire inspection blower fan, primary air fan, the first control valve are all connected with main control unit with the second control valve, and described main control unit is provided with display screen.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620263002.4U CN205579625U (en) | 2016-03-31 | 2016-03-31 | Cooling air system is examined to power plant fire |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620263002.4U CN205579625U (en) | 2016-03-31 | 2016-03-31 | Cooling air system is examined to power plant fire |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205579625U true CN205579625U (en) | 2016-09-14 |
Family
ID=56867916
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620263002.4U Active CN205579625U (en) | 2016-03-31 | 2016-03-31 | Cooling air system is examined to power plant fire |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205579625U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107917437A (en) * | 2016-10-09 | 2018-04-17 | 上海漕泾热电有限责任公司 | The cooling device of flame-detecting probe |
-
2016
- 2016-03-31 CN CN201620263002.4U patent/CN205579625U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107917437A (en) * | 2016-10-09 | 2018-04-17 | 上海漕泾热电有限责任公司 | The cooling device of flame-detecting probe |
CN107917437B (en) * | 2016-10-09 | 2024-04-09 | 上海漕泾热电有限责任公司 | Cooling device of flame detection probe |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202229893U (en) | Refrigerant leakage detecting system and mobile air conditioner with same | |
WO2021032053A1 (en) | Air conditioner and control method therefor, and storage medium | |
CN205579625U (en) | Cooling air system is examined to power plant fire | |
CN205120374U (en) | Engine platform gas gas supply system that takes a trial run | |
CN202938001U (en) | Steam pipeline drain valve leakage monitoring system | |
CN105334061A (en) | Engine test-driving platform gas supply system | |
CN204006095U (en) | A kind of boiler fire inspection wind system | |
CN206207471U (en) | The cooling device of flame-detecting probe | |
CN203009460U (en) | Uninterruptible power supply overhaul device for hydraulic pressure gauge | |
CN207816537U (en) | The pre- leakage detection apparatus of large-scale low-temperature economizer | |
CN205782035U (en) | Trade effluent pipe network anti-leak warning system | |
CN205424997U (en) | Take backup protection's fire to examine cooling air device | |
KR101365957B1 (en) | Displacement alarm device for expansion joint | |
CN207031468U (en) | A kind of blast-furnace tuyere leading portion that handles blocks up burnt device | |
CN202814653U (en) | System for detecting exhausted steam leakage at entrance of power plant air cooling island | |
CN204663995U (en) | Boiler axle induced-draft fan main bearing box, oil hydraulic cylinder and motor integral cooling unit | |
CN205578729U (en) | Boiler desulfurization seal air system | |
CN204389123U (en) | A kind of boiler tube leak detection blow device | |
CN204062310U (en) | A kind of protective gear of gas pipeline | |
CN203446612U (en) | Protective device for operation in high temperature environment | |
CN202614488U (en) | Pressure testing device for valve of blast-furnace hot blast stove system | |
CN204372422U (en) | A kind of waterpipe couplings for circulating cooling system | |
CN202511924U (en) | Air compressor oil temperature relay function detection device | |
CN205373188U (en) | Detect device that carbon dioxide heat pump unit high -low pressure is collaborated | |
CN215489839U (en) | Plasma fire detection cooling air system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |