CN205575464U - Portable adjustable inclination lift platform of full section operation of power station steel pipe inclined shaft - Google Patents

Portable adjustable inclination lift platform of full section operation of power station steel pipe inclined shaft Download PDF

Info

Publication number
CN205575464U
CN205575464U CN201620119660.6U CN201620119660U CN205575464U CN 205575464 U CN205575464 U CN 205575464U CN 201620119660 U CN201620119660 U CN 201620119660U CN 205575464 U CN205575464 U CN 205575464U
Authority
CN
China
Prior art keywords
inclined shaft
platform
portable
adjustable inclination
hoistable platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620119660.6U
Other languages
Chinese (zh)
Inventor
蒋建国
赵佑初
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Dajiang Machinery Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201620119660.6U priority Critical patent/CN205575464U/en
Application granted granted Critical
Publication of CN205575464U publication Critical patent/CN205575464U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a be applied to portable adjustable inclination lift platform of full section operation of power station steel pipe inclined shaft, include: portable bogie frame, adjustable inclination main platform, lift platform, double -deck telescopic work basket, mark time basket, electric control system down, wherein: portable bogie frame is the basis that this device was walked in the steel pipe inclined shaft, adjustable inclination main platform is when the inclined shaft inclination changes, through levelling mechanism adjustment main platform and platform frame joint contained angle and keep the device of horizontal state, lift platform is the height control equipment when realizing the operation of the interior top of inclined shaft, double -deck telescopic work basket sets up respectively on main platform and lift platform, be used for personnel of bearing or operation utensil to steel pipe inclined shaft middle part, width control's during upper portion side direction operation the device of taking one's place, under mark time the basket and make things convenient for personnel and utensil to carry out the operation to the inclined shaft bottom, electric control system provides electric drive to this device, command control and security assurances.

Description

The portable adjustable inclination angle hoistable platform of power station steel pipe inclined shaft tunneling boring operation
Technical field
This utility model belongs to mechanized equipment technical field, is specifically related to a kind of shifting for power station steel pipe inclined shaft tunneling boring operation Dynamic formula adjustable inclination angle hoistable platform.
Background technology
Inclined shaft is a kind of engineering structure pattern being widely used in water-power plant conduit pipe system.Almost all of large-scale mixed flow Formula hydro-generating Unit or hydroenergy storage station all arrange the diversion steel pipe inclined shaft of major diameter, high inclination-angle.The safe condition of inclined shaft Operational reliability close relation with whole water-power plant.
This inclined shaft is generally after inlet gate well, and after hydroelectric station operation, large-sized power plant cannot be introduced into inclined shaft operation. Via gate shaft or spiral case enter the little micromachine utensil that manhole passes through then cannot meet major diameter, high inclination-angle steel pipe inclined shaft complete disconnected Face job requirements.Before this, scaffold must be manually built in comprehensive Inspection and maintenance operation of large hydropower station steel pipe inclined shaft;Cause Being limited by power scheduling, the power station time between overhauls(TBO) is the most comparatively short.So, for the whole country, large hydropower station steel Pipe inclined shaft can not carry out regularly Inspection and maintenance comprehensively always, is the blind area difficult point of power station safety management.
According to investigations, the engineering such as Liujiaxia Hydropower Station, the Yellow River, Xin'anjiang Hydropower Station has been run more than 50 year, and penstock alreadys more than Design life;The nineties in last century build power station " Five Golden Flowers " (Fujian Shuikou, Yunnan Man Wan, Guangxi Yan Tan, Hubei is every He Yan, Hunan the last five small stream) it is that the large number of large-scale hydroelectric project of representative has run more than 20 year, Yangtze River Gorges water conservancy The giant-scale engineering such as hinge, Xiaolangdi dam project on Yellow River has run more than 10 year, and these power station steel pipe inclined shafts all already more than National standard requires the cycle first comprehensively checked.Whether these large-scale steel pipe inclined shafts exist potential safety hazard, how to carry out comprehensively Examination and maintenance are constructed?This defines serious technological challenge to power station safety management.
Summary of the invention
For the problems referred to above, in conjunction with existing engineering machinery technology, this utility model provides one and is applicable to power station steel pipe inclined shaft The portable adjustable inclination angle hoistable platform of tunneling boring operation.It is characterized in that, including: portable bogie frame, adjustable inclination angle master put down Platform, hoistable platform, double-layer telescopic operation basket, under mark time basket, electric control system.Wherein:
Described portable bogie frame is the basis that this device is walked in steel pipe inclined shaft, is suitable to along at the bottom of the structure of inclined shaft axially-movable Seat and wheel rail system, bogie frame can be moved by external force traction, also can self-powered drive;
The main platform of described adjustable inclination angle is when inclined shaft change of pitch angle, and main platform is adjusted and bogie frame toggle clamp by levelling gear Angle also keeps the device of level;
Height adjustment equipment when described hoistable platform is to realize inclined shaft inner top operation;
Described double-layer telescopic operation basket is respectively arranged on main platform and hoistable platform, is used for the personnel that carry or operating apparatus To in the middle part of inclined shaft, the lateral operation in top time width adjustment positioning apparatus;
Basket of marking time under described facilitates personnel and utensil thereof to carrying out operation bottom inclined shaft;
This device is provided driven by power, instruction to control and safety assurance by described electric control system.
Therefore combining existing engineering machinery technology, this utility model carries out complete in the steel pipe inclined shaft of complicated pipeline, particularly high inclination-angle Section Inspection or safeguard that construction is unusual safety convenient.
Accompanying drawing explanation
Fig. 1 is that this utility model is at horizontal pipe duty front view.
Fig. 2 is that this utility model is at steel pipe inclined shaft duty side view.
Fig. 3 is that this utility model is at horizontal pipe duty side view.
Fig. 4 is that this utility model is at steel pipe inclined shaft motion track figure.
In figure: 1, elevating mechanism (hydraulic pressure scissor elevating mechanism or the multistage lifting body of hydraulic cylinder), 2, double-layer telescopic operation basket (lower part), 3, the main platform of adjustable inclination angle (work platforms), 4, portable bogie frame (shifting foundation platform), 5, under step on Step basket, 6, steel conduit, 7, hoistable platform, 8, double-layer telescopic operation basket (upper part), 9, levelling gear (hydraulic cylinder system System or screw rod movement mechanism), 10, steel pipe inclined shaft, 11, steel pipe inclined shaft centrage, 12, mobile station wheel is at inclined shaft contact internal walls Line.
Detailed description of the invention
In order to more specifically describe this utility model, below in conjunction with the accompanying drawings and detailed description of the invention is to technical side of the present utility model Case is described in detail.
Present embodiment: when needing to carry out the operation in steel pipe inclined shaft, is put into all parts by power station dam facing crane The bottom of gate shaft.Owing to gate shaft space is narrow, before lifting, each parts are taken apart, successively by the portable platform in figure Vehicle frame (4), the main platform of adjustable inclination angle (3), elevating mechanism (1,7,8) and other subsidiary bodies hang in, and then assemble, And connect the circuit of each electrical equipment, debug the motor function of each parts.
In first the equipment that installation and debugging are good being placed in steel pipe inclined shaft in place, external force traction or the power drive that carries make whole device Mobile, operating personnel by levelling gear ensure the level of main platform, by elevating mechanism control hoistable platform height, can By double-deck scalable operation basket adjust in inclined shaft the most in place, pass through under basket of marking time realize bottom steel pipe in place;Coordinate chassis The movement of frame, can carry out steel pipe inclined shaft comprehensive 360 ° without dead angle operation.

Claims (6)

1. the portable adjustable inclination angle hoistable platform being applied to power station steel pipe inclined shaft tunneling boring operation, it is characterized in that, including: portable bogie frame, the main platform of adjustable inclination angle, hoistable platform, double-layer telescopic operation basket, under mark time basket, electric control system, wherein:
Described portable bogie frame is the basis that this device is walked in steel pipe inclined shaft;
The main platform of described adjustable inclination angle is when inclined shaft change of pitch angle, adjusts main platform and the hinged angle of bogie frame by levelling gear and keeps the device of level;
Height adjustment equipment when described hoistable platform is to realize inclined shaft inner top operation;
Described double-layer telescopic operation basket is respectively arranged on main platform and hoistable platform, for carry personnel or operating apparatus in the middle part of steel pipe inclined shaft, the lateral operation in top time the positioning apparatus of width adjustment;
Basket of marking time under described facilitates personnel and utensil thereof to carrying out operation bottom inclined shaft;
This device is provided driven by power, instruction to control and safety assurance by described electric control system.
Portable adjustable inclination angle hoistable platform the most according to claim 1, it is characterised in that: described portable bogie frame has the pier and wheel rail system be suitable to along inclined shaft axially-movable, and bogie frame is moved by external force traction.
Portable adjustable inclination angle hoistable platform the most according to claim 1, it is characterized in that: the main platform of described adjustable inclination angle is unilateral hinged with bogie frame, levelling gear can make main platform at a certain angle with bogie frame shape in the motion of opposite side, thus adapting to the change of inclined shaft axial inclination, levelling gear uses cylinder device or screw rod movement mechanism.
Portable adjustable inclination angle hoistable platform the most according to claim 1, it is characterized in that: described hoistable platform is perpendicularly fixed on main platform, hoistable platform just carries out lifting action when the level inclination of main platform meets safety requirements, when bogie frame moves, hoistable platform is placed in the state landed completely, and the height regulating mechanism of hoistable platform uses hydraulic pressure scissor elevating mechanism or the multistage lifting body of hydraulic cylinder.
Portable adjustable inclination angle hoistable platform the most according to claim 1, it is characterized in that: described double-layer telescopic operation basket is respectively arranged on main platform and hoistable platform, the expansion performance that operating personnel or operating apparatus may utilize work blue carries out operation in place to middle part, the upper top work surface of inclined shaft easily.
Portable adjustable inclination angle hoistable platform the most according to claim 1, it is characterised in that: basket of marking time under described is attached to portable bogie frame, it is simple to operating personnel and utensil thereof carry out operation in place to the most also bottom-working surface safely.
CN201620119660.6U 2016-02-01 2016-02-01 Portable adjustable inclination lift platform of full section operation of power station steel pipe inclined shaft Active CN205575464U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620119660.6U CN205575464U (en) 2016-02-01 2016-02-01 Portable adjustable inclination lift platform of full section operation of power station steel pipe inclined shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620119660.6U CN205575464U (en) 2016-02-01 2016-02-01 Portable adjustable inclination lift platform of full section operation of power station steel pipe inclined shaft

Publications (1)

Publication Number Publication Date
CN205575464U true CN205575464U (en) 2016-09-14

Family

ID=56869857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620119660.6U Active CN205575464U (en) 2016-02-01 2016-02-01 Portable adjustable inclination lift platform of full section operation of power station steel pipe inclined shaft

Country Status (1)

Country Link
CN (1) CN205575464U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106348201A (en) * 2016-02-01 2017-01-25 蒋建国 Frame chassis, mobile trolley and steel pipe inclined shaft maintenance system
CN107973253A (en) * 2016-10-25 2018-05-01 济南恒鼎升降机械有限公司 A kind of novel anti-falling guide rail-type lifting platform
CN108277970A (en) * 2018-02-01 2018-07-13 温州市腾圣建设有限公司 Elevator civil construction mobile platform
CN109594520A (en) * 2018-11-19 2019-04-09 湖北工业大学 Dam runner inspection platform
CN115072633A (en) * 2022-07-13 2022-09-20 广东电网有限责任公司 Aerial work auxiliary platform

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106348201A (en) * 2016-02-01 2017-01-25 蒋建国 Frame chassis, mobile trolley and steel pipe inclined shaft maintenance system
CN107973253A (en) * 2016-10-25 2018-05-01 济南恒鼎升降机械有限公司 A kind of novel anti-falling guide rail-type lifting platform
CN108277970A (en) * 2018-02-01 2018-07-13 温州市腾圣建设有限公司 Elevator civil construction mobile platform
CN109594520A (en) * 2018-11-19 2019-04-09 湖北工业大学 Dam runner inspection platform
CN115072633A (en) * 2022-07-13 2022-09-20 广东电网有限责任公司 Aerial work auxiliary platform

Similar Documents

Publication Publication Date Title
CN205575464U (en) Portable adjustable inclination lift platform of full section operation of power station steel pipe inclined shaft
CN203224347U (en) Towing tank trailer
JP2011112045A (en) Wind turbine fixing and lifting apparatus and movable operating platform on water
CN206267616U (en) A kind of mobile collapsible anemometer tower
CN102394538A (en) Electric motor stator assembly machine
CN108147284A (en) The hanging method and its auxiliary device of wind power generating set impeller
CN105133550A (en) Locking method and device for large gate
CN205653087U (en) Tower crane who possesses solar energy, wind power generation function
CN111457158B (en) Push pipe construction structures convenient to installation
CN202785541U (en) Automatic jacking climbing columns device and automatic jacking wind power equipment maintenance system
CN105818016A (en) Maintenance tool for large water guide mechanism straight cylinder servomotor of hydraulic turbine generator unit
CN104343634A (en) Wind wheel height adjusting mechanism for vertical axis wind turbine and wind energy ship with wind wheel height adjusting mechanism
CN108638303A (en) Riverway sludge curing molding mold
CN109235519B (en) Hydraulic engineering desilting device
CN202441047U (en) Hanging basket guide device on curved surface
CN205936398U (en) Public road bridge roof beam construction drilling platform
CN201991538U (en) Mining hydraulic liftable worktable
CN208843671U (en) A kind of novel wind power tower transloading equipment
CN201625859U (en) Locomotive gearbox assembly and disassembly service cart
CN216141997U (en) A sluice structure that is used for water storage reservoir of water power plant to have regulatory function
CN205630398U (en) A examine and repair frock that is used for large -scale water distributor straight -cylinder servomotor of hydroelectric set
CN103821077A (en) Auto-telescoping trestle bridge applicable to movable platforms
CN203359794U (en) Novel trolley device of crane travelling mechanism
CN201778311U (en) Inclined support type automatic gate locking device
CN105252255A (en) Method for replacing pivotal bearing of floating crane through jacking device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20161201

Address after: Hangzhou City, Zhejiang Province, Gongshu District Kang Road 310015 No. 2 Building 2 room 402

Patentee after: Hangzhou Dajiang Machinery Co., Ltd.

Address before: 1101 room 3, unit 6, wing Feng court, Xiacheng District, Xiacheng District, Zhejiang, Hangzhou, 310023

Patentee before: Jiang Jianguo