CN205575423U CN201620431846.5U CN201620431846U CN205575423U CN 205575423 U CN205575423 U CN 205575423U CN 201620431846 U CN201620431846 U CN 201620431846U CN 205575423 U CN205575423 U CN 205575423U
Authority
CN
China
Prior art keywords
connecting plate
beam main
groups
plate
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620431846.5U
Other languages
Chinese (zh)
Inventor
董伟华
李锋
侯德岞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Pang Yuan Mechanical Engineering Co Ltd
Original Assignee
Shandong Pang Yuan Mechanical Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Pang Yuan Mechanical Engineering Co Ltd filed Critical Shandong Pang Yuan Mechanical Engineering Co Ltd
Priority to CN201620431846.5U priority Critical patent/CN205575423U/en
Application granted granted Critical
Publication of CN205575423U publication Critical patent/CN205575423U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a curb girder structure of tower crane attachment frame corresponds ground four group link board fixed connection s with the position relation of upper and lower parallel around by shape, the identical upper plate of size and hypoplastron and constitutes the roof beam main part, wherein, four group link boards are the big connecting plate of 2 little connecting plates of group and 2 groups respectively, big connecting plate is established the both ends of roof beam main part, little connecting plate is established the centre of roof beam main part, the space width between connecting plate and the connecting plate equals, little connecting plate with be equipped with support piece between the big connecting plate, support piece's one end is inserted perpendicularly the roof beam main part, the other end is followed stretch out the front side of roof beam main part, the both ends of upper plate still correspond and are equipped with two couples, the both ends of upper plate and hypoplastron still are equipped with three group's holes respectively, wherein, three group's holes are located the outside of couple. Its non -deformable, long service life, and can bear more on a large scale, the more operation of high load capacity.

Description

A kind of side beam structure of tower crane attachment framework
Technical field
This utility model relates to building machinery field, particularly relates to the side beam structure of a kind of tower crane attachment framework.
Background technology
Tower crane, is the common device on a kind of heavy construction building site, is mainly used in promoting construction material, Architectural Equipment etc..In actually used engineering, after derrick crane reach a certain height, if needing to continue to increase height, in order to ensure job safety, it is necessary to use a kind of attachment device to stablize derrick crane.At present, the adhesion frame apparatus structure form for derrick crane of commercial type is different, but all there is the problems such as such as structure changeableness, easy fracture, use cycle be short, the most each director's girder construction part, owing to structure is excessively simple, it is not provided with or is seldom provided with appurtenances so that it is being easy to that deformation, the problem of fracture occur, obviously, the generation of these rough sledding cannot ensure the safety of operation.
Therefore, how to be modified to the attachment device structure of derrick crane, especially as the side beam structure of the ingredient of attachment device structure, with the effective job safety ensureing derrick crane, be the Important Problems of current those skilled in the art research.
Utility model content
In order to overcome various shortcomings and drawback present in prior art, this utility model is by improving the side beam structure of tower crane attachment framework, obtain the side beam structure of a kind of tower crane attachment framework, be unlikely to deform, service life long, and the operation of larger-scale, more high load capacity can be born.
The technical solution of the utility model is: the side beam structure of a kind of tower crane attachment framework, beam main body is connected and composed with the most parallel position relationship by the most accordingly four groups of connecting plates are fixing by shape, the identical upper plate of size and lower plate, wherein, described four groups of connecting plates are respectively 2 groups of little connecting plates and 2 groups of big connecting plates, described big connecting plate is located at the two ends of described beam main body, described little connecting plate is located at the centre of described beam main body, and the gap length between connecting plate with connecting plate is equal;Being provided with support member between described little connecting plate and described big connecting plate, one end of described support member is inserted perpendicularly into described beam main body, and the other end stretches out from the front side of described beam main body;The two ends of described upper plate are also correspondingly provided with two hooks;The two ends of described upper plate and lower plate further respectively have three groups of holes, and wherein, described three groups of holes are positioned at the outside of described hook.
In one embodiment, described support member stretches out the front side section length of described beam main body more than described upper plate or the width of described lower plate.
In another embodiment, the length of described big connecting plate is the twice of length of little connecting plate.
Side beam structure is improved by this utility model, wherein, adds hook structure, in order to operation;The setting of many places connecting plate so that the bearing capacity of beam main body is greatly promoted;Additionally, this utility model is additionally provided with support member, than the heavy burden being easily carried other structure.
Accompanying drawing explanation
Fig. 1 is the front view of the side beam structure of tower crane attachment framework described in the utility model;
Fig. 2 is the top view of the side beam structure of tower crane attachment framework described in the utility model.
Detailed description of the invention
This utility model provides the side beam structure of a kind of tower crane attachment framework, beam main body is connected and composed with the most parallel position relationship by the most accordingly four groups of connecting plates are fixing by shape, the identical upper plate of size 1 and lower plate 2, wherein, described four groups of connecting plates are respectively 2 groups little connecting plates 3 and 2 groups of big connecting plates 4, described big connecting plate 4 is located at the two ends of described beam main body, described little connecting plate 3 is located at the centre of described beam main body, and the gap length between connecting plate with connecting plate is equal;Being provided with support member 6 between described little connecting plate 3 and described big connecting plate 4, one end of described support member 6 is inserted perpendicularly into described beam main body, and the other end stretches out from the front side of described beam main body;The two ends of described upper plate 1 are also correspondingly provided with two hooks 5;The two ends of described upper plate 1 and lower plate 2 further respectively have three groups of holes 7, and wherein, described three groups of holes 7 are positioned at the outside of described hook 5.
In one embodiment, a kind of side beam structure of tower crane attachment framework, beam main body is connected and composed with the most parallel position relationship by the most accordingly four groups of connecting plates are fixing by shape, the identical upper plate of size 1 and lower plate 2, wherein, described four groups of connecting plates are respectively 2 groups little connecting plates 3 and 2 groups of big connecting plates 4, described big connecting plate 4 is located at the two ends of described beam main body, and described little connecting plate 3 is located at the centre of described beam main body, and the gap length between connecting plate with connecting plate is equal;Being provided with support member 6 between described little connecting plate 3 and described big connecting plate 4, one end of described support member 6 is inserted perpendicularly into described beam main body, and the other end stretches out from the front side of described beam main body;The two ends of described upper plate 1 are also correspondingly provided with two hooks 5;The two ends of described upper plate 1 and lower plate 2 further respectively have three groups of holes 7, and wherein, described three groups of holes 7 are positioned at the outside of described hook 5;Described support member 6 stretches out the front side section length of described beam main body more than described upper plate 1 or the width of described lower plate 2.
In another embodiment, a kind of side beam structure of tower crane attachment framework, beam main body is connected and composed with the most parallel position relationship by the most accordingly four groups of connecting plates are fixing by shape, the identical upper plate of size 1 and lower plate 2, wherein, described four groups of connecting plates are respectively 2 groups little connecting plates 3 and 2 groups of big connecting plates 4, described big connecting plate 4 is located at the two ends of described beam main body, and described little connecting plate 3 is located at the centre of described beam main body, and the gap length between connecting plate with connecting plate is equal;Being provided with support member 6 between described little connecting plate 3 and described big connecting plate 4, one end of described support member 6 is inserted perpendicularly into described beam main body, and the other end stretches out from the front side of described beam main body;The two ends of described upper plate 1 are also correspondingly provided with two hooks 5;The two ends of described upper plate 1 and lower plate 2 further respectively have three groups of holes 7, and wherein, described three groups of holes 7 are positioned at the outside of described hook 5;The length of described big connecting plate 4 is the twice of the length of little connecting plate 3.
Being described in detail specific embodiment of the utility model above, but it is only used as example, this utility model is not restricted to particular embodiments described above.To those skilled in the art, any equivalent modifications carrying out this practicality and replacement are the most all among category of the present utility model.Therefore, the impartial conversion made under without departing from spirit and scope of the present utility model and amendment, all should contain in the range of this utility model.

Claims (3)

1. the side beam structure of a tower crane attachment framework, it is characterized in that, beam main body is connected and composed with the most parallel position relationship by the most accordingly four groups of connecting plates are fixing by shape, the identical upper plate of size and lower plate, wherein, described four groups of connecting plates are respectively 2 groups of little connecting plates and 2 groups of big connecting plates, described big connecting plate is located at the two ends of described beam main body, and described little connecting plate is located at the centre of described beam main body, and the gap length between connecting plate with connecting plate is equal;Being provided with support member between described little connecting plate and described big connecting plate, one end of described support member is inserted perpendicularly into described beam main body, and the other end stretches out from the front side of described beam main body;The two ends of described upper plate are also correspondingly provided with two hooks;The two ends of described upper plate and lower plate further respectively have three groups of holes, and wherein, described three groups of holes are positioned at the outside of described hook.
The side beam structure of tower crane attachment framework the most according to claim 1, it is characterised in that described support member stretches out the front side section length of described beam main body more than described upper plate or the width of described lower plate.
The side beam structure of tower crane attachment framework the most according to claim 1, it is characterised in that the length of described big connecting plate is the twice of the length of little connecting plate.
CN201620431846.5U 2016-05-13 2016-05-13 Curb girder structure of tower crane attachment frame Expired - Fee Related CN205575423U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620431846.5U CN205575423U (en) 2016-05-13 2016-05-13 Curb girder structure of tower crane attachment frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620431846.5U CN205575423U (en) 2016-05-13 2016-05-13 Curb girder structure of tower crane attachment frame

Publications (1)

Publication Number Publication Date
CN205575423U true CN205575423U (en) 2016-09-14

Family

ID=56856295

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620431846.5U Expired - Fee Related CN205575423U (en) 2016-05-13 2016-05-13 Curb girder structure of tower crane attachment frame

Country Status (1)

Country Link
CN (1) CN205575423U (en)

Similar Documents

Publication Publication Date Title
CN203715054U (en) 3,000t combinable lifting balance beam
CN205575423U (en) Curb girder structure of tower crane attachment frame
CN103979429A (en) Cantilever type portal crane
CN207749839U (en) A kind of detachable five feet support jig
CN203132908U (en) Loading device of template support system
CN205662265U (en) Back beam structure of tower crane attachment frame
CN202967874U (en) Overall girder transporting vehicle lifting spreader
CN205663282U (en) Light -duty lattice formula steel column of large capacity
CN204823738U (en) Two roof beam electric hoist formula hoist girder orthotic devices
RU137025U1 (en) CRANE SUPPORT
CN205662266U (en) Preceding girder construction of tower crane attachment frame
CN205603100U (en) Staple bolt structure of tower crane attachment frame
CN203896253U (en) High-strength single-column photovoltaic support
CN203755623U (en) Load overhauling bent frame convenient to assemble and disassemble
CN201882809U (en) Door type cantilever steel frame hoisting equipment used for high hoisting
CN204847843U (en) Hoist traveling carriage bearing structure
CN207293997U (en) A kind of chassis suitable for ultra-large type derrick crane
CN205662258U (en) A adhere to frame assembly for tower crane
CN201952103U (en) Steel-bar lifting frame
CN203845714U (en) Cantilever type portal crane
CN205894284U (en) Truss member
CN104002075B (en) Link welding tooling
CN206517337U (en) A kind of suspension cable mounting structure of photovoltaic plant
CN203271237U (en) Balancing weight structure of lift single-pipe tower
CN204265249U (en) A kind of transfer crane and portal frame thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160914