CN205558304U - Hoist and mount system of large -scale steel gallery truss - Google Patents
Hoist and mount system of large -scale steel gallery truss Download PDFInfo
- Publication number
- CN205558304U CN205558304U CN201620077673.1U CN201620077673U CN205558304U CN 205558304 U CN205558304 U CN 205558304U CN 201620077673 U CN201620077673 U CN 201620077673U CN 205558304 U CN205558304 U CN 205558304U
- Authority
- CN
- China
- Prior art keywords
- lifting
- truss
- steel
- point
- main structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 207
- 239000010959 steel Substances 0.000 title claims abstract description 207
- 238000003466 welding Methods 0.000 claims description 9
- 239000010720 hydraulic oil Substances 0.000 claims description 8
- 230000002787 reinforcement Effects 0.000 claims description 5
- 230000035515 penetration Effects 0.000 claims description 2
- 238000010276 construction Methods 0.000 abstract description 26
- 238000000034 method Methods 0.000 abstract description 14
- 238000010586 diagram Methods 0.000 description 12
- 238000006073 displacement reaction Methods 0.000 description 8
- 238000007689 inspection Methods 0.000 description 7
- 238000005259 measurement Methods 0.000 description 6
- 230000001360 synchronised effect Effects 0.000 description 6
- 238000009434 installation Methods 0.000 description 4
- 239000003921 oil Substances 0.000 description 4
- 238000004364 calculation method Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 230000003014 reinforcing effect Effects 0.000 description 3
- 230000002159 abnormal effect Effects 0.000 description 2
- 238000004458 analytical method Methods 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 230000009970 fire resistant effect Effects 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 238000004886 process control Methods 0.000 description 1
- 238000013102 re-test Methods 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本实用新型公开了一种大型钢连廊桁架的吊装系统,吊装系统包括提升点、吊点和安装在两者之间的千斤顶提升设备,提升点包括与主体结构一连接的第一提升架和与主体结构二连接的第二提升架,两提升架内均有两根等高且平行设置的预埋型钢梁,其端部设为提升点,提升点梁体的两侧各焊接一个箱型牛腿,每个箱型牛腿上安装一个千斤顶,内侧的两个箱型牛腿之间焊接一根抗扭钢梁;钢连廊桁架上设四个分别与架体上的提升点竖向对应的吊点,钢绞线自上往下穿过箱型牛腿,下行穿过吊点后用锚具固定。施工时四个吊点同步提升。本实用新型设计合理操作简单,有效解决了大型钢连廊桁架吊装过程中面临的占地面积大、自重大、平衡性差的问题。
The utility model discloses a hoisting system for a large-scale steel corridor truss. The hoisting system includes a hoisting point, a hoisting point and a jack hoisting device installed between the two. The hoisting point includes a first hoisting frame connected to a main structure and a The second lifting frame connected with the main structure two, there are two embedded steel beams of the same height and parallel in the two lifting frames, the ends of which are set as lifting points, and a box is welded on both sides of the lifting point beam body A jack is installed on each box-shaped corbel, and a torsion-resistant steel beam is welded between the two box-shaped corbels on the inner side; To the corresponding lifting point, the steel strand passes through the box-shaped corbel from top to bottom, and is fixed with anchors after going down through the lifting point. During construction, the four lifting points are lifted synchronously. The utility model has reasonable design and simple operation, and effectively solves the problems of large occupied area, heavy weight and poor balance faced in the hoisting process of the large-scale steel corridor truss.
Description
技术领域 technical field
本实用新型涉及桁架吊装施工技术领域,具体涉及一种大型钢连廊桁架的吊装系统。 The utility model relates to the technical field of truss hoisting construction, in particular to a hoisting system of a large-scale steel corridor truss.
背景技术 Background technique
连廊是复杂高层建筑结构体系的一种,它一般指两幢或几幢高层建筑之间由架空连接体相互连接,以满足建筑造型及使用功能的要求。连接体即连廊。其跨度有几米长,也有几十米长。连廊沿建筑物竖向有布置一个的,也有布置几个的。连廊设置一方面出于建筑功能上的要求,它可以方便两主体结构之间的联系。同时连体具有良好的采光效果和广阔的视野而可以用做观光走廊或休闲咖啡厅等;另一方面,由于连廊的设置,可以使建筑外观上更具特色,并能营造出一种更加和谐的建筑氛围。此外,还有消防连廊,起到安全通道的作用,对防火要求很高,必须全部用防火材料制作。 Corridor is a kind of complex high-rise building structure system. It generally refers to the connection between two or several high-rise buildings by overhead connectors to meet the requirements of building shape and use function. The connecting body is the corridor. Its span is several meters long, also has tens of meters long. There are one or several corridors arranged vertically along the building. On the one hand, the setting of the corridor is due to the requirements of architectural functions, and it can facilitate the connection between the two main structures. At the same time, the conjoined body has good lighting effects and a wide view, so it can be used as a sightseeing corridor or a leisure coffee shop; on the other hand, due to the setting of the corridor, it can make the appearance of the building more distinctive and create a more Harmonious architectural atmosphere. In addition, there is a fire corridor, which serves as a safe passage, and has high requirements for fire protection, so it must be made of fire-resistant materials.
目前,大型钢连廊桁架一般采用地面拼装后整体提升的方法,但在整体进行提升时,由于钢连廊桁架占地面积大、自重大、稳定性差,存在难以进行吊装施工的问题,吊装过程中极易出现平衡性不易控制或安全性不能保证的技术难题。 At present, the large-scale steel corridor truss generally adopts the method of overall lifting after ground assembly, but when the overall lifting is carried out, due to the large area occupied by the steel corridor truss, heavy weight, and poor stability, it is difficult to carry out hoisting construction. The hoisting process It is very easy to have technical problems in which the balance is difficult to control or the safety cannot be guaranteed.
实用新型内容 Utility model content
本实用新型的目的是提供一种大型钢连廊桁架的吊装系统,解决现有技术中由于大型钢连廊桁架占地面积大、自重大、稳定性差、难以进行吊装施工的问题,有效解决大型钢连廊桁架吊装过程中极易出现平衡性不易控制好人安全性不能保证的技术难题。 The purpose of this utility model is to provide a hoisting system for a large-scale steel corridor truss, which solves the problems in the prior art that the large-scale steel corridor truss occupies a large area, is heavy, has poor stability, and is difficult to carry out hoisting construction, and effectively solves the problems of large-scale steel corridor truss During the hoisting process of steel corridor trusses, it is very easy to have technical problems that the balance is difficult to control, and the safety cannot be guaranteed.
为实现上述技术目的,本实用新型采取如下技术方案: In order to achieve the above technical purpose, the utility model takes the following technical solutions:
一种大型钢连廊桁架的吊装系统,用于将钢连廊桁架提升至主体结构的预定高度,所述主体结构包括位于两侧的主体结构一和主体结构二,其特征在于,吊装系统包括提升点、吊点和安装在两者之间的千斤顶提升设备; A hoisting system for a large-scale steel corridor truss, which is used to lift the steel corridor truss to a predetermined height of a main structure, the main structure includes a main structure 1 and a main structure 2 located on both sides, and is characterized in that the hoisting system includes Lifting points, lifting points and jack lifting equipment installed between them;
所述提升点包括第一提升架、第二提升架和抗扭钢梁: The lifting point includes a first lifting frame, a second lifting frame and a torsion steel beam:
第一提升架包括水平伸出主体结构一的两根预埋型钢梁一,两根预埋型钢梁一的预埋高度及外挑长度都相等,其端部分别对应设置为第一提升点和第二提升点;所述第一提升点和第二提升点的端部梁体两侧各焊接一个用于固定千斤顶的箱型牛腿; The first lifting frame includes two pre-embedded steel beams 1 extending horizontally from the main structure 1. The pre-embedded heights of the two pre-embedded steel beams 1 are equal to the length of the overhang, and the ends of the two pre-embedded steel beams 1 are respectively set as the first lifting frame. point and the second lifting point; both sides of the end beam body of the first lifting point and the second lifting point are respectively welded with a box-shaped corbel for fixing the jack;
第二提升架包括水平伸出主体结构二的两根预埋型钢梁一,两根预埋型钢梁二的预埋高度及外挑长度都相等,其端部分别对应设置为第三提升点和第四提升点;所述第三提升点和第四提升点的端部梁体两侧各焊接一个用于固定千斤顶的箱型牛腿; The second lifting frame includes two pre-embedded steel beams 1 horizontally protruding from the main structure 2. The pre-embedded heights and overhang lengths of the two pre-embedded steel beams 2 are equal, and their ends are respectively set as the third hoisting frame. point and the fourth lifting point; the end beam body both sides of the third lifting point and the fourth lifting point are respectively welded a box-shaped corbel for fixing the jack;
抗扭钢梁为水平设置梁体,共两条,一条固定在第一提升架的两根预埋型钢梁一之间;另一条固定在第二提升架的两根预埋型钢梁二之间; The torsional steel beams are horizontal beams, and there are two in total. One is fixed between the two pre-embedded steel beams 1 of the first lifting frame; the other is fixed between the two pre-embedded steel beams 2 of the second lifting frame. between;
所述吊点设在钢连廊桁架上,共有四个: The lifting points are set on the steel corridor trusses, and there are four in total:
第一吊点和第二吊点位于钢连廊桁架一侧,分别与第一提升架的两个架体的第一提升点和第二提升点竖向对应; The first lifting point and the second lifting point are located on one side of the steel corridor truss, respectively vertically corresponding to the first lifting point and the second lifting point of the two frame bodies of the first lifting frame;
第三吊点和第四吊点位于钢连廊桁架的另一侧,分别与第二提升架的两个架体的第三提升点和第四提升点竖向对应; The third lifting point and the fourth lifting point are located on the other side of the steel corridor truss, corresponding to the third lifting point and the fourth lifting point of the two frame bodies of the second lifting frame respectively;
千斤顶提升设备包括千斤顶、钢绞线、液压油泵和液压控制装置: Jack lifting equipment includes jacks, steel strands, hydraulic oil pumps and hydraulic control devices:
所述千斤顶共8台,每个提升点设置2台,分别固定在预埋型钢梁一和预埋型钢梁二端部四个提升点两侧的箱型牛腿上; There are 8 jacks in total, and 2 jacks are set at each lifting point, which are respectively fixed on the box-shaped corbels on both sides of the four lifting points at the ends of the first embedded steel beam and the second end of the embedded steel beam;
钢绞线自上往下穿过提升架的梁体,下行穿过钢连廊桁架吊点后用锚具固定; The steel strand passes through the beam body of the lifting frame from top to bottom, goes down through the hanging point of the steel corridor truss and fixes it with anchors;
液压油泵为芯式千斤顶提供动力,用于驱动千斤顶运行; The hydraulic oil pump provides power for the core jack to drive the jack to run;
液压控制装置用于控制千斤顶的运行。 The hydraulic control device is used to control the operation of the jack.
设置时,每个提升点处的两台千斤顶之间彼此并行设置。 When set up, the two jacks at each lifting point are set parallel to each other.
优选的,四个吊点的设置位置对应,可以都设在钢连廊桁架的上弦或中弦上,吊点位置设临时加强杆件进行加强。 Preferably, the setting positions of the four lifting points correspond to each other, and they can all be set on the upper chord or middle chord of the steel corridor truss, and temporary reinforcing rods are set at the lifting points for reinforcement.
其中,所述抗扭钢梁为箱型梁,两端分别与两根预埋型钢梁一或两根预埋型钢梁二之间的两个箱型牛腿全熔透焊接。 Wherein, the torsion-resistant steel beam is a box-shaped beam, and its two ends are respectively welded with two box-shaped corbels between the two pre-embedded steel beams 1 or 2 pre-embedded steel beams 2 through full penetration.
作为优选的一种技术方案,所述第一提升架或第二提升架还包括支撑在预埋型钢梁一的外端与主体结构一之间的桁架立面斜撑一和连接在主体结构一与桁架立面斜撑一之间的劲性柱牛腿一,桁架立面斜撑一和劲性柱牛腿一为预埋型钢梁一或预埋型钢梁二提供强度支撑。 As a preferred technical solution, the first lifting frame or the second lifting frame also includes a truss façade bracing supported between the outer end of the embedded steel beam 1 and the main structure 1 and connected to the main structure Stiff column corbel 1 between truss facade diagonal brace 1, truss facade diagonal brace 1 and rigid column corbel 1 provide strength support for pre-embedded steel beam 1 or pre-embedded steel beam 2.
作为另一种技术方案,所述第一提升架或第二提升架还包括支撑在预埋型钢梁二外端与主体结构二之间的桁架立面斜撑二、连接在主体结构二与桁架立面斜撑二之间的劲性柱牛腿二、连接在预埋型钢梁二与劲性柱牛腿二之间的竖向支撑以及连接在桁架立面斜撑二与主体结构二之间的横向连杆,为预埋型钢梁一或预埋型钢梁二提供强度支撑。 As another technical solution, the first lifting frame or the second lifting frame also includes a truss façade bracing 2 supported between the outer end of the embedded steel beam 2 and the main structure 2, connected between the main structure 2 and the main structure 2. Stiff column corbel 2 between truss facade diagonal brace 2, vertical support connected between pre-embedded steel beam 2 and rigid column corbel 2, and connection between truss facade diagonal brace 2 and main structure 2 The transverse connecting rod between them provides strength support for the first embedded steel beam or the second embedded steel beam.
所述第一提升架或第二提升架的高度可以等于一个楼层高度,所述预埋型钢梁一或预埋型钢梁二的标高与上层楼板的标高相同,所述桁架立面斜撑一或桁架立面斜撑二的底端标高与下层楼板的标高相同。 The height of the first lifting frame or the second lifting frame can be equal to the height of a floor, the elevation of the embedded steel beam 1 or the embedded steel beam 2 is the same as that of the upper floor, and the truss facade is diagonally braced. The elevation of the bottom end of the first or second truss façade diagonal bracing is the same as that of the lower floor.
所述第一提升架或第二提升架的高度也可以等于两个楼层高度,所述预埋型钢梁一或预埋型钢梁二的标高与最上层楼板的标高相同,所述桁架立面斜撑一或桁架立面斜撑二的底端标高与最下层楼板的标高相同,所述横向连杆的标高与中间层楼板的标高相同。 The height of the first lifting frame or the second lifting frame can also be equal to the height of two floors, the elevation of the embedded steel beam 1 or the embedded steel beam 2 is the same as that of the uppermost floor, and the vertical truss The elevation of the bottom end of the first diagonal brace or the second diagonal brace of the truss facade is the same as that of the lowest floor, and the elevation of the transverse connecting rod is the same as that of the middle floor.
优选的,所述千斤顶的底端与箱型牛腿的上端面点焊固定,所述锚具的四周在钢连廊桁架的上弦或中弦的下翼缘上焊接锚具限位板。 Preferably, the bottom end of the jack is fixed to the upper end surface of the box corbel by spot welding, and the anchor limiting plate is welded on the upper chord or the lower flange of the middle chord of the steel corridor truss around the anchorage.
与现有技术相比,本实用新型的有益效果如下: Compared with the prior art, the beneficial effects of the utility model are as follows:
1、提升架上设抗扭钢梁:提升点包括与主体结构一连接的第一提升架和与主体结构二连接的第二提升架,两提升架内均有两根等高且平行设置的预埋型钢梁,其端部设为提升点,提升点梁体的两侧各焊接一个箱型牛腿,每个箱型牛腿上安装一个千斤顶,内侧的两个箱型牛腿之间焊接一根抗扭钢梁,抗扭钢梁两端分别与箱型牛腿全熔透焊接,抗扭钢梁的设置大大加强了提升架的强度和稳定性; 1. The torsion-resistant steel beam is installed on the lifting frame: the lifting point includes the first lifting frame connected with the main structure one and the second lifting frame connected with the main structure two. The pre-embedded steel beam, the end of which is set as a lifting point, a box corbel is welded on both sides of the lifting point beam body, and a jack is installed on each box corbel. A torsion-resistant steel beam is welded, and the two ends of the torsion-resistant steel beam are fully penetrated and welded with the box-shaped corbel. The setting of the torsion-resistant steel beam greatly enhances the strength and stability of the lifting frame;
2、强度高:提升点处,第一提升架和第二提升架的劲性柱牛腿和型钢梁均为高强度预埋结构,保证提升架与主体结构的连接牢固度和强度;吊点周围桁架均通过临时加强杆件进行加强;千斤顶和锚具均采取限位措施,将千斤顶的底端与箱型牛腿的上端面点焊固定,所述锚具的四周在钢连廊桁架的上弦或中弦的下翼缘上焊接锚具限位板; 2. High strength: At the lifting point, the rigid column corbels and steel beams of the first lifting frame and the second lifting frame are all high-strength pre-embedded structures to ensure the firmness and strength of the connection between the lifting frame and the main structure; The trusses around the point are strengthened by temporary reinforcing rods; the jack and the anchorage are all taken with limit measures, and the bottom end of the jack is spot-welded to the upper end of the box-shaped corbel. Anchor limiting plates are welded on the lower flange of the upper chord or middle chord;
3、提升过程稳定性有保障:提升过程中,正常提升时每2米停机一次,检查各点之间误差是否控制在50mm以内,如位移相差过大则对提升较慢点单独供油,以保证各点同步性,为确保提升的同步,在提升现场增加全站仪对结构吊点位移差进行测量,作为辅助测量措施。 3. The stability of the lifting process is guaranteed: during the lifting process, stop once every 2 meters during normal lifting, check whether the error between each point is controlled within 50mm, if the displacement difference is too large, supply oil separately to the slower lifting point to ensure To ensure the synchronization of each point, in order to ensure the synchronization of the lifting, a total station is added at the lifting site to measure the displacement difference of the lifting points of the structure as an auxiliary measurement measure.
综上,本实用新型针对大型钢连廊桁架体型大、自重大、稳定性差的问题,设计了专用的吊装系统及配套的施工方法,吊装系统结构强度高,设计合理,操作过程控制方便有效,稳定性好,对大型桁架的吊装施工具有重要的指导意义。 To sum up, this utility model aims at the problems of large size, self-heavyness and poor stability of large-scale steel corridor trusses, and designs a special hoisting system and supporting construction methods. The hoisting system has high structural strength, reasonable design, and convenient and effective operation process control. It has good stability and has important guiding significance for the hoisting construction of large trusses.
附图说明 Description of drawings
图1为本实用新型一种实施例的大型钢连廊桁架的吊装系统的整体结构示意图; Fig. 1 is the overall structure schematic diagram of the hoisting system of the large-scale steel corridor truss of an embodiment of the utility model;
图2为本实用新型一种实施例的钢连廊桁架1的平面示意图; Fig. 2 is a schematic plan view of a steel corridor truss 1 according to an embodiment of the present invention;
图3为本实用新型一种实施例的钢连廊桁架1的立面示意图; Fig. 3 is a schematic elevation view of a steel corridor truss 1 according to an embodiment of the present invention;
图4为本实用新型一种实施例的钢连廊桁架1上四个吊点的布置示意图; Fig. 4 is a schematic diagram of the arrangement of four hanging points on the steel corridor truss 1 according to an embodiment of the present invention;
图5为本实用新型一种实施例的千斤顶8在提升点的设置示意图; Fig. 5 is a schematic diagram of the setting of the jack 8 at the lifting point according to an embodiment of the present invention;
图6为本实用新型一种实施例的钢绞线6在吊点的设置示意图; Fig. 6 is a schematic diagram of the installation of the steel strand 6 at the lifting point of an embodiment of the utility model;
图7为本实用新型一种实施例的第一提升架4的两个架体与抗扭钢梁7的立体结构图; Fig. 7 is a three-dimensional structure diagram of the two frame bodies and the torsion-resistant steel beam 7 of the first lifting frame 4 of an embodiment of the present invention;
图8为本实用新型一种实施例的第一提升架4与主体结构一2的连接示意图; Fig. 8 is a schematic diagram of the connection between the first lifting frame 4 and the main structure-2 according to an embodiment of the present invention;
图9为本实用新型一种实施例的第一提升架4在吊装完成后与钢连廊桁架1的连接示意图; Fig. 9 is a schematic diagram of the connection between the first lifting frame 4 and the steel corridor truss 1 after hoisting is completed in an embodiment of the present invention;
图10为本实用新型一种实施例的第二提升架5的两个架体与抗扭钢梁7的立体结构图; Fig. 10 is a three-dimensional structure diagram of the two frame bodies and the torsion-resistant steel beam 7 of the second lifting frame 5 according to an embodiment of the present invention;
图11是本实用新型一种实施例的第二提升架5与主体结构二3的连接示意图; Fig. 11 is a schematic diagram of the connection between the second lifting frame 5 and the main structure 2 3 according to an embodiment of the present invention;
图12为本实用新型一种实施例的第二提升架5在吊装完成后与钢连廊桁架1的连接示意图。 Fig. 12 is a schematic diagram of the connection between the second lifting frame 5 and the steel corridor truss 1 after hoisting is completed in an embodiment of the present invention.
附图标记:1-钢连廊桁架、2-主体结构一、3-主体结构二、4-第一提升架、41-预埋型钢梁一、42-桁架立面斜撑一、43-劲性柱牛腿一、5-第二提升架、51-预埋型钢梁二、52-桁架立面斜撑二、53-劲性柱牛腿二、54-竖向支撑、55-横向连杆、6-钢绞线、7-抗扭钢梁、8-千斤顶、9-第一提升点、10-第二提升点、11-第三提升点、12-第四提升点、13-第一吊点、14-第二吊点、15-第三吊点、16-第四吊点、17-锚具、18-楼板、19-箱型牛腿。 Reference signs: 1-steel corridor truss, 2-main structure 1, 3-main structure 2, 4-first lifting frame, 41-embedded steel beam 1, 42-truss facade diagonal brace 1, 43- Rigid column corbel 1, 5-second lifting frame, 51-embedded steel beam 2, 52-truss facade oblique bracing 2, 53-stiff column corbel 2, 54-vertical support, 55-transverse Connecting rod, 6-steel strand, 7-torsion steel beam, 8-jack, 9-first lifting point, 10-second lifting point, 11-third lifting point, 12-fourth lifting point, 13- The first lifting point, 14-the second lifting point, 15-the third lifting point, 16-the fourth lifting point, 17-anchor, 18-floor, 19-box corbel.
具体实施方式 detailed description
在下文中,将参照附图描述本实用新型涉及的大型钢连廊桁架的吊装系统的一个实施例。 Hereinafter, an embodiment of the hoisting system of the large-scale steel corridor truss involved in the present invention will be described with reference to the accompanying drawings.
在此记载的实施例为本实用新型的特定的具体实施方式,用于说明本实用新型的构思,均是解释性和示例性的,不应解释为对本实用新型实施方式及本实用新型范围的限制。除在此记载的实施例外,本领域技术人员还能够基于本申请权利要求书和说明书所公开的内容采用显而易见的其它技术方案,这些技术方案包括采用对在此记载的实施例的做出任何显而易见的替换和修改的技术方案。 The embodiments described here are specific specific implementations of the present utility model, and are used to illustrate the concept of the present utility model. They are all explanatory and exemplary, and should not be construed as limitations on the implementation of the present utility model and the scope of the present utility model. limit. In addition to the embodiments described here, those skilled in the art can also adopt other obvious technical solutions based on the claims of the application and the contents disclosed in the description, and these technical solutions include adopting any obvious changes made to the embodiments described here. Replacement and modified technical solutions.
本说明书的附图为示意图,辅助说明本实用新型的构思,示意性地表示各部分的形状及其相互关系。请注意,为了便于清楚地表现出本实用新型实施例的各部件的结构,各附图之间并未按照相同的比例绘制。相同的参考标记用于表示相同的部分。 The accompanying drawings in this specification are schematic diagrams, which assist in explaining the concept of the utility model, and schematically represent the shapes of various parts and their interrelationships. Please note that in order to clearly show the structures of the components in the embodiment of the present invention, the drawings are not drawn in the same scale. The same reference numerals are used to designate the same parts.
如图1,涉及一种大型钢连廊桁架的吊装系统,用于将钢连廊桁架1提升至主体结构的预定高度,图2为本实用新型一种实施例的钢连廊桁架1的平面示意图,图3为本实用新型一种实施例的钢连廊桁架1的立面示意图,是劲性柱加钢桁架结构,其中劲性柱前期已施工完毕,钢结构构件主要形式有H型,钢连廊平面尺寸为42.0m×15.4m,跨度为42米,整个桁架高度为9米,钢连廊桁架1整体提升时,钢构件重量为329.8吨,加上底层楼承板的重量1.2mm厚YX-200-600,约650平方米10.5吨,栓钉等3吨,合计钢连廊整体提升最大重量为343.3吨;所述主体结构包括分位于两侧的主体结构一2和主体结构二3,主体结构一2地上16层,主体结构二3地上14层,其在钢连廊桁架1预吊装标高处伸出劲性柱牛腿,用于与钢连廊桁架1的对接固定,提升架部分均可以作为原来钢连廊的一部分,提升就位后各个端部对应焊接,形成完整的刚连廊桁架结构,吊装系统包括提升点、吊点和上吊点之间的千斤顶提升设备; As shown in Figure 1, it involves a hoisting system for a large-scale steel corridor truss, which is used to lift the steel corridor truss 1 to the predetermined height of the main structure, and Figure 2 shows the plane of the steel corridor truss 1 according to an embodiment of the present invention Schematic diagram, Figure 3 is a schematic elevation view of a steel corridor truss 1 according to an embodiment of the present invention, which is a stiff column plus steel truss structure, wherein the stiff column has been constructed in the early stage, and the main form of the steel structural member is H-shaped, The plane size of the steel corridor is 42.0m×15.4m, the span is 42 meters, and the height of the entire truss is 9 meters. When the steel corridor truss 1 is lifted as a whole, the weight of the steel member is 329.8 tons, plus the weight of the floor deck on the ground floor is 1.2mm Thick YX-200-600, about 650 square meters, 10.5 tons, 3 tons of studs, etc., the total maximum lifting weight of the steel corridor is 343.3 tons; the main structure includes the main structure 1 and the main structure 2 located on both sides. 3. Main structure 1 2 has 16 floors above ground, and main structure 2 3 has 14 floors above ground. The stiff column corbels protrude from the pre-hoisting elevation of steel corridor truss 1 for docking and fixing with steel corridor truss 1, lifting The truss part can be used as a part of the original steel corridor. After being lifted into place, each end is welded correspondingly to form a complete rigid corridor truss structure. The hoisting system includes the lifting point, the lifting point and the jack lifting equipment between the lifting point;
所述提升点包括三部分:第一提升架4、第二提升架5和抗扭钢梁7:第一提升架4包括水平伸出主体结构一2的两根预埋型钢梁一41,两根预埋型钢梁一41的预埋高度及外挑长度都相等,其端部分别对应设置为第一提升点9和第二提升点10;所述第一提升点9和第二提升点10的端部梁体两侧各焊接一个用于固定千斤顶8的箱型牛腿19;同样,第二提升架5包括水平伸出主体结构二3的两根预埋型钢梁一41,两根预埋型钢梁二51的预埋高度及外挑长度都相等,其端部分别对应设置为第三提升点11和第四提升点12;所述第三提升点11和第四提升点12的端部梁体两侧各焊接一个用于固定千斤顶8的箱型牛腿19;抗扭钢梁7水平设置,共两条,一条固定安装在第一提升架4的两根预埋型钢梁一41之间;另一条固定安装在第二提升架5的两根预埋型钢梁二51之间; The lifting point includes three parts: the first lifting frame 4, the second lifting frame 5 and the torsion steel beam 7: the first lifting frame 4 includes two pre-embedded steel beams 41 extending horizontally from the main structure 2, The pre-embedded heights and overhang lengths of the two pre-embedded steel beams-41 are all equal, and their ends are respectively set as the first lifting point 9 and the second lifting point 10; the first lifting point 9 and the second lifting point A box-shaped corbel 19 for fixing the jack 8 is respectively welded on both sides of the end beam body at point 10; similarly, the second lifting frame 5 includes two pre-embedded steel beams 141 extending horizontally out of the main structure 23, The pre-embedded heights and overhanging lengths of the two pre-embedded steel beams 2 51 are all equal, and their ends are respectively set as the third lifting point 11 and the fourth lifting point 12; the third lifting point 11 and the fourth lifting point A box-shaped corbel 19 for fixing the jack 8 is welded on both sides of the end beam body at point 12; the torsion-resistant steel beam 7 is horizontally arranged, and there are two in total, and one is fixedly installed on the two pre-embedded jacks of the first lifting frame 4 Between the steel beams one 41; the other is fixedly installed between two pre-embedded steel beams two 51 of the second lifting frame 5;
所述吊点设在钢连廊桁架1上,包括四个吊点,如图4所示,第一吊点13和第二吊点14位于钢连廊桁架1一侧,分别与第一提升架4的两个架体的第一提升点9和第二提升点10竖向对应;第三吊点15和第四吊点16位于钢连廊桁架1另一侧,分别与第二提升架5的两个架体的第三提升点11和第四提升点12竖向对应;在所述钢连廊桁架1上、四个吊点的周围设置临时加强结构; The hanging point is set on the steel corridor truss 1, including four lifting points, as shown in Figure 4, the first lifting point 13 and the second lifting point 14 are located on the side of the steel corridor truss 1, respectively connected to the first hoisting point The first lifting point 9 and the second lifting point 10 of the two frame bodies of the frame 4 correspond vertically; the third lifting point 15 and the fourth lifting point 16 are located on the other side of the steel corridor truss 1, and are respectively connected to the second lifting frame The third lifting point 11 and the fourth lifting point 12 of the two frames of 5 correspond vertically; on the steel corridor truss 1, a temporary reinforcement structure is set around the four hanging points;
千斤顶提升设备包括千斤顶8、钢绞线6、液压油泵和液压控制装置:如图5和图6,千斤顶8固定在四个提升点处两根预埋型钢梁一41或预埋型钢梁一51的端部两侧的箱型牛腿19上,每个提升点设置两台,共8台;钢绞线6所述钢绞线6自上往下穿过提升架的梁体,下行穿过钢连廊桁架1吊点后用锚具17固定;液压油泵为芯式千斤顶8提供动力,用于驱动千斤顶8运行;液压控制装置用于控制千斤顶8的运行。 Jack lifting equipment includes jack 8, steel strand 6, hydraulic oil pump and hydraulic control device: as shown in Figure 5 and Figure 6, jack 8 is fixed on two pre-embedded steel beams at four lifting points-41 or pre-buried steel beams On the box-shaped corbels 19 on both sides of the end of a 51, two sets are arranged at each lifting point, a total of 8 sets; the steel strand 6 passes through the beam body of the lifting frame from top to bottom, and goes down After passing through the hanging point of the steel corridor truss 1, it is fixed with an anchor 17; the hydraulic oil pump provides power for the core jack 8, and is used to drive the operation of the jack 8; the hydraulic control device is used to control the operation of the jack 8.
其中,本实施例作为优选的技术方案,如图4,本实施例中所述千斤顶8固定安装在四个提升点上,每个提升点设置两台,两台之间彼此并行设置;所述吊点设在钢连廊桁架1的上弦或中弦上;抗扭钢梁7采用箱型梁,两端分别与两根预埋型钢梁中间的箱型牛腿19全熔透焊接,规格为口600*500*16。 Wherein, the present embodiment is as a preferred technical solution, as shown in Figure 4, the jacks 8 described in the present embodiment are fixedly installed on four lifting points, each lifting point is provided with two sets, and the two sets are arranged in parallel with each other; The lifting point is set on the upper chord or middle chord of the steel corridor truss 1; the torsional steel girder 7 is a box-shaped girder, and the two ends are respectively fully penetrated and welded with the box-shaped corbel 19 in the middle of the two pre-embedded steel girders. For the mouth 600*500*16.
所述第一提升架4或第二提升架5还可以包括支撑在预埋型钢梁一41的外端与主体结构一2之间的桁架立面斜撑一42以及连接在主体结构一2与桁架立面斜撑一42之间的劲性柱牛腿一43组成;除了这个种形式,还可以是包括支撑在预埋型钢梁二51的外端与主体结构二3之间的桁架立面斜撑二52、连接在主体结构二3与桁架立面斜撑二52之间的劲性柱牛腿二53、连接在预埋型钢梁二51与劲性柱牛腿二53之间的竖向支撑54以及连接在桁架立面斜撑二52与主体结构二3之间的横向连杆55组成。 The first lifting frame 4 or the second lifting frame 5 may also include a truss façade bracing 42 supported between the outer end of the embedded steel beam 41 and the main structure 2 and connected to the main structure 2. It is composed of a stiff column corbel 1 43 between the truss façade brace 1 42; in addition to this form, it can also include a truss supported between the outer end of the pre-embedded steel beam 2 51 and the main structure 2 3 Facade diagonal brace 2 52, rigid column corbel 2 53 connected between the main structure 2 3 and truss facade diagonal brace 2 52, connected between the pre-embedded steel beam 2 51 and stiff column corbel 2 53 The vertical support 54 between them and the transverse connecting rod 55 connected between the truss façade brace 2 52 and the main structure 2 3 are composed.
所述第一提升架4或第二提升架5的每个架体的高度可以等于一个楼层高度,所述预埋型钢梁一41或预埋型钢梁二51的标高与上层楼板的标高相同,所述桁架立面斜撑一42或桁架立面斜撑二52的底端标高与下层楼板的标高相同;也可以等于两个楼层高度,所述预埋型钢梁一41或预埋型钢梁二51的标高与最上层的楼板18的标高相同,所述桁架立面斜撑一42或桁架立面斜撑二52的底端标高与最下层的楼板18的标高相同,所述横向连杆55的标高与中间层的楼板18的标高相同。 The height of each frame body of the first lifting frame 4 or the second lifting frame 5 can be equal to a floor height, and the elevation of the embedded steel beam one 41 or the embedded steel beam two 51 is the same as the elevation of the upper floor. Same, the elevation of the bottom end of the truss façade brace 1 42 or the truss facade brace 2 52 is the same as the elevation of the lower floor; it can also be equal to the height of two floors, and the pre-embedded steel beam 1 41 or pre-embedded The elevation of the shaped steel beam two 51 is the same as that of the uppermost floor slab 18, and the elevation of the bottom end of the truss facade diagonal brace 1 42 or the truss facade diagonal brace 2 52 is the same as the elevation of the lowermost floor slab 18. The elevation of the transverse link 55 is the same as that of the floor slab 18 of the middle floor.
支撑架的高度和形状与实施施工中主体结构的情况及施工受力情况共同决定,本实施例中,如图7、图8和图9,第一提升架4的高度等于一个楼层高度,包括水平悬挑在主体结构一2的外的预埋型钢梁一41、支撑在预埋型钢梁一41的外端与主体结构一2之间的桁架立面斜撑一42以及连接在主体结构一2与桁架立面斜撑一42之间的劲性柱牛腿一43,所述预埋型钢梁一41的标高与上层楼板的标高相同,所述桁架立面斜撑一42的底端标高与下层楼板的标高相同;如图10、图11和图12,第二提升架5的高度等于两个楼层高度,包括水平悬挑在主体结构二3外的预埋型钢梁二51、支撑在预埋型钢梁二51的外端与主体结构二3之间的桁架立面斜撑二52、连接在主体结构二3与桁架立面斜撑二52之间的劲性柱牛腿二53、连接在预埋型钢梁二51与劲性柱牛腿二53之间的竖向支撑54以及连接在桁架立面斜撑二52与主体结构二3之间的横向连杆55,所述预埋型钢梁二51的标高与最上层楼板的标高相同,所述桁架立面斜撑二52的底端标高与最下层楼板的标高相同,所述横向连杆55的标高与中间层楼板的标高相同, 预埋型钢梁二51与桁架立面斜撑二52之间还可以设置临时加强杆件。 The height and shape of the support frame are jointly determined by the situation of the main structure in the construction and the stress situation of the construction. In this embodiment, as shown in Fig. 7, Fig. 8 and Fig. 9, the height of the first lifting frame 4 is equal to the height of a floor, including The pre-embedded steel girder-41 suspended horizontally outside the main structure-2, the truss façade bracing-42 supported between the outer end of the pre-embedded steel beam-41 and the main structure-2 and connected to the main body The stiff column corbel-43 between structure-2 and truss facade brace-42, the elevation of the pre-embedded steel beam-41 is the same as that of the upper floor, the truss facade brace-42 The elevation of the bottom end is the same as that of the lower floor; as shown in Fig. 10, Fig. 11 and Fig. 12, the height of the second hoisting frame 5 is equal to the height of two floors, including the pre-embedded steel beam 2 suspended horizontally outside the main structure 2 3 51. The truss façade bracing 2 52 supported between the outer end of the pre-embedded steel beam 2 51 and the main structure 2 3, and the stiff column connected between the main structure 2 3 and the truss façade bracing 2 52 The second corbel 53, the vertical support 54 connected between the pre-embedded steel beam 2 51 and the stiff column corbel 2 53, and the transverse connecting rod connected between the diagonal brace 2 52 of the truss facade and the main structure 2 3 55. The elevation of the pre-embedded steel beam 2 51 is the same as that of the uppermost floor, the elevation of the bottom end of the truss façade brace 2 52 is the same as that of the lowermost floor, and the elevation of the transverse connecting rod 55 The elevation of the middle floor is the same as that of the middle floor, and temporary reinforcement members can also be set between the pre-embedded steel girder 2 51 and the truss façade diagonal brace 2 52.
为了确保安全,所述千斤顶8和锚具17均采取限位措施,所述千斤顶8的底端与提升架钢梁7的上翼缘点焊固定,所述锚具17的四周在钢连廊桁架1的上弦或中弦的下翼缘上焊接锚具限位板。同时提升就位后,焊接作业时,对钢绞线采用防火布进行包裹,防止由于焊接导致钢绞线损伤。 In order to ensure safety, the jack 8 and the anchorage 17 all take limit measures, the bottom end of the jack 8 is spot welded to the upper flange of the lifting frame steel beam 7, and the anchorage 17 is surrounded by steel corridors. Weld the anchor limiting plate on the lower flange of the upper chord or middle chord of the truss 1. At the same time, after being lifted into place, during welding operations, the steel strands are wrapped with fireproof cloth to prevent damage to the steel strands due to welding.
上述的大型钢连廊桁架的吊装系统进行吊装施工时,根据施工现场条件及钢结构整体拼装方案,选择将钢结构连廊地面整体拼装焊接成型后,一次提升就位的施工工艺,本工程采用钢连廊液压整体提升,在提升过程中,各吊点之间的同步控制要求比较严格,各吊点的荷载要控制在与理论计算基本一致的范围内,钢结构整体同步提升过程中,应实时监测各提升吊点的位移,以整体提升的同步位移量控制为主,同时监控各个提升点处力值变化。施工时应对关键位置点位严格监控同时兼顾力值的参考,保证提升时结构位移控制精确,同时提升力值满足设计要求。由于同步提升采用计算机控制,若提升不同步,超出设计值,提升则会自动停止。包括如下步骤: When the hoisting system of the above-mentioned large-scale steel corridor truss is used for hoisting construction, according to the construction site conditions and the overall assembly plan of the steel structure, the construction process of one-time lifting in place after the overall assembly and welding of the ground of the steel structure corridor is selected. The hydraulic overall lifting of the steel corridor. During the lifting process, the synchronous control requirements between the lifting points are relatively strict. The load of each lifting point should be controlled within the range basically consistent with the theoretical calculation. During the overall synchronous lifting of the steel structure Monitor the displacement of each hoisting point in real time, focus on the synchronous displacement control of the overall hoisting, and monitor the force value changes at each hoisting point at the same time. During construction, the key positions should be strictly monitored while taking into account the reference of the force value, so as to ensure that the structural displacement control is accurate during lifting, and the lifting force value meets the design requirements. Since the synchronous lifting is controlled by computer, if the lifting is out of sync and exceeds the design value, the lifting will stop automatically. Including the following steps:
步骤一、施工计算解析:施工前对整体设计进行计算解析,保证施工过程的安全性; Step 1. Construction calculation and analysis: calculate and analyze the overall design before construction to ensure the safety of the construction process;
步骤二、现场平面布置:依据施工计算解析的结果,对现场进行平面布置; Step 2. Site layout: according to the results of construction calculation and analysis, carry out the site layout;
步骤三、钢连廊桁架1的制作:进行钢连廊桁架的分单元制作,形成待拼接的单元块; Step 3. Fabrication of steel corridor truss 1: Carry out sub-unit fabrication of steel corridor truss to form unit blocks to be spliced;
步骤四、辅配件制作:包括在钢连廊桁架上交进行临时加强结构设置; Step 4. Production of auxiliary parts: including temporary reinforcement structure setting on the steel corridor truss;
步骤五、千斤顶提升设备的进场前调试:对千斤顶提升设备进行进场前调试,确认其具备进场条件;本工程提升系统在进场前,在车间必须进行软件、硬件的调试,再进行单机、整体联机调试,确保提升过程的顺利进行,锚具进场须经检验合格,单个千斤顶8提升吨位250吨,采用液压千斤顶整体同步提升技术; Step 5. Pre-entry commissioning of the jack lifting equipment: Debug the jack lifting equipment before entering the site to confirm that it meets the entry conditions; before the lifting system of this project enters the site, the software and hardware must be debugged in the workshop, and then Single machine and overall online debugging to ensure the smooth progress of the lifting process. The anchorage must pass the inspection when entering the site. The tonnage of a single jack 8 is 250 tons, and the overall synchronous lifting technology of hydraulic jacks is adopted;
步骤六、施工平台布置:布置并搭设施工操作平台,操作平台两侧进行安全护栏的安装,安全护栏采用脚手管搭设,并使用安全网进行封闭,经检查验收合格后方可上人实施操作。在提升点千斤顶周边增加焊接钢板保护措施; Step 6. Construction platform layout: Arrange and set up the construction operation platform, and install safety guardrails on both sides of the operation platform. The safety guardrails are erected with scaffolding tubes and closed with safety nets. Only after passing the inspection and acceptance can the operator carry out the operation. Add welded steel protection measures around the lifting point jack;
步骤七、工装设备进场:施工操作平台布置完成后,将质检合格的工装设备进场; Step 7. Tooling equipment enters the site: After the construction operation platform is arranged, the tooling equipment that has passed the quality inspection is brought into the site;
步骤八、钢连廊桁架1的地面拼装:利用底部的支撑胎架,将单元模块拼装成整体,在吊点位置设置临时加强杆件; Step 8. Ground assembly of the steel corridor truss 1: use the supporting tire frame at the bottom to assemble the unit modules into a whole, and set temporary reinforcing rods at the lifting points;
步骤九、提升架的安装:提升前,需要对提升支架进行安装,安装严格按照设计图纸进行,分别在主体结构一2和主体结构二3上安装成对的架体作为第一提升架4和第二提升架5,分别在第一提升架和第二提升架的两预埋型钢梁之间焊接一根抗扭钢梁7;提升架的端部在提升点两边分别焊接用于安装千斤顶8的箱型牛腿19,在内侧两个箱型牛腿19之间焊接一根抗扭钢梁7,抗扭钢梁7使用主体结构二3东侧的塔吊就位后,与桁架内侧箱型牛腿19上下翼缘及腹板采用等强坡口对接焊连接,通过抗扭钢梁将两个提升点连成整体,抗扭钢梁7截面箱型600*500*16*16,本工程一侧使用钢连廊桁架1的上弦主梁作为提升支架,另一侧使用劲性柱伸出的钢牛腿作为提升支架; Step 9. Installation of the lifting frame: before lifting, the lifting frame needs to be installed. The installation is carried out in strict accordance with the design drawings, and the paired frames are respectively installed on the main structure 1 2 and the main structure 2 3 as the first lifting frame 4 and The second lifting frame 5 welds a torsion-resistant steel beam 7 between the two pre-embedded steel beams of the first lifting frame and the second lifting frame; the ends of the lifting frame are respectively welded on both sides of the lifting point for installing the jack 8 box-shaped corbels 19, a torsion-resistant steel beam 7 is welded between the two box-shaped corbels 19 on the inner side. The upper and lower flanges and webs of corbel 19 are connected by equal-strength groove butt welding, and the two lifting points are connected into a whole through torsion-resistant steel beams. On one side of the project, the upper chord girder of the steel corridor truss 1 is used as the lifting support, and on the other side, the steel corbel protruding from the stiff column is used as the lifting support;
步骤十、千斤顶提升设备的安装与调试:在提升支架上提升点两侧的箱型牛腿19上安装千斤顶8等提升装置,同时布置液压油泵和液压控制装置,千斤顶8为穿芯式千斤顶,带有一套提升用顶压器、一套锚固用顶压器以及一套安全用自动工具锚,安装各种传感器,连接设备,进行现场空载调试;每个提升点处设有两台千斤顶共同完成工作,并由一台液压油泵控制,即1#、2#千斤顶放在一个提升点处, 3#、4#千斤顶放在一个提升点处,由一台油泵控制2个提升点;5#、6#千斤顶放在一个提升点处;7#、8#千斤顶放在一个提升点处,由一台油泵控制控制2个提升点。施工需要液压泵站2台,液压千斤顶8台。另外配备相应的主控系统1台,分控制箱2台以及若干传感器等设备,施工时泵站放置在已有结构上靠近施工操作点的地方,要在此处放置电闸箱;每组开泵人员站在泵站所在的已有结构上;每组测量人员要站在提前搭好的施工操作平台上,即提升点处,1人观测一个提升点; Step 10. Installation and commissioning of jack lifting equipment: Install jack 8 and other lifting devices on the box-shaped corbels 19 on both sides of the lifting point on the lifting bracket, and arrange hydraulic oil pumps and hydraulic control devices at the same time. Jack 8 is a core-through jack. It is equipped with a set of jacking presses for lifting, a set of jacking presses for anchoring, and a set of automatic tool anchors for safety. Various sensors are installed, equipment is connected, and on-site no-load debugging is carried out; two jacks are installed at each lifting point. The work is completed and controlled by a hydraulic oil pump, that is, 1# and 2# jacks are placed at one lifting point, 3# and 4# jacks are placed at one lifting point, and two lifting points are controlled by one oil pump; 5# , 6# jacks are placed at one lifting point; 7#, 8# jacks are placed at one lifting point, and two lifting points are controlled by one oil pump. Construction requires 2 hydraulic pump stations and 8 hydraulic jacks. In addition, it is equipped with 1 corresponding main control system, 2 sub-control boxes and several sensors and other equipment. During construction, the pump station is placed on the existing structure close to the construction operation point, and the electric switch box should be placed here; each group of pumps Personnel stand on the existing structure where the pump station is located; each group of surveyors must stand on the construction operation platform set up in advance, that is, at the lifting point, and one person observes one lifting point;
步骤十一、钢绞线6的穿束与预紧:所述钢绞线6自上往下穿过,下行穿过箱型牛腿19和钢连廊桁架1吊点后用锚具17固定,本实施例使用Φ15.2mm1860级的钢绞线6进行提升,每台千斤顶8采用7根Φ15.2mm 1860级的钢绞线6,下料仔细检查钢绞线6,不得有锈蚀、泥污、尘土等,确保提升安全可靠,根据钢连廊桁架1需要提升的高度和提升装置所需的高度对钢绞线6下料,应保证足够的富余长度,以便于钢绞线的穿束; Step 11. Threading and pretensioning of the steel strand 6: the steel strand 6 passes through from top to bottom, and goes down through the box-shaped corbel 19 and the hanging point of the steel corridor truss 1, and then fixes it with the anchor 17 , the present embodiment uses Φ15.2mm 1860-grade steel strand 6 for lifting, and each jack 8 adopts 7 Φ15.2mm 1860-grade steel strand 6, and carefully checks the steel strand 6 for blanking, and there must be no rust or mud , dust, etc., to ensure safe and reliable lifting, according to the height of the steel corridor truss 1 that needs to be lifted and the height required by the lifting device, the steel strand 6 should be cut, and sufficient excess length should be ensured to facilitate the threading of the steel strand;
步骤十二、钢连廊桁架1整体试提升:按试提升时的步骤进行,如果发现有不正常现象,马上停止,分析原因,解决后继续进行;施工人员进入各自岗位,所有控制指令全部由主控台下达,试提升的时间应为所有前期准备工作完毕,并依据气象预报选取无风的晴天上午,试提升的高度为30cm,稳定时间为1小时,提升速度5mm/min。对整个提升系统进行全面检查,采取有效措施确保每个吊点每根钢绞线受力均匀,避免部分钢绞线处于松弛或受力较小状态,如出现上述现象,应立即对松弛或受力较小的钢绞线采用千斤顶单独张拉,使其处于张紧状态,以达到每根钢绞线受力均匀的状态。试提升时应准备好安全垛,其采用热轧型钢H300*300*10*15,长度为500mm,共计设置8个安全垛支垫;钢桁架脱离拼装胎架后,需要对钢桁架的整体挠度进行测量,待检查无误后方可进行同步提升,在提升的位置,在其四个提升点的底部对应位置放悬挂刻度尺,实时读取提升值,要求其水平偏摆值小于5mm,要求四个提升点的不同步值小于5mm,试提升时检查项目如表1: Step 12. The overall trial lifting of the steel corridor truss 1: proceed according to the steps during the trial lifting. If any abnormal phenomenon is found, stop immediately, analyze the cause, and continue after solving it; the construction personnel enter their respective positions, and all control instructions are issued by According to the instructions from the main console, the trial lifting time should be when all preliminary preparations have been completed, and a windless sunny morning should be selected according to the weather forecast. The trial lifting height is 30cm, the stabilization time is 1 hour, and the lifting speed is 5mm/min. Carry out a comprehensive inspection of the entire lifting system, take effective measures to ensure that each steel strand at each lifting point is evenly stressed, and prevent some steel strands from being in a state of slack or less stress. The steel strands with less force are individually tensioned by a jack to make them in a tensioned state, so as to achieve a state where each steel strand is evenly stressed. Safety stacks should be prepared during the lifting trial, which uses hot-rolled steel H300*300*10*15, with a length of 500mm, and a total of 8 safety stack pads are set; after the steel truss is separated from the assembled tire frame, the overall deflection of the steel truss needs to be adjusted Carry out measurement, and the synchronous lifting can only be carried out after the inspection is correct. At the lifting position, place a hanging scale at the corresponding position at the bottom of the four lifting points, and read the lifting value in real time. It is required that the horizontal deflection value is less than 5mm, and four The out-of-sync value of the lifting point is less than 5mm, and the items to be checked when trying to lift are shown in Table 1:
表1.试提升时检查项目表 Table 1. List of inspection items when trying to lift
步骤十三、钢连廊桁架1整体正式提升:试提升全面检查无误后进入提升过程。按试提升时的步骤进行,如果发现有不正常现象,马上停止,分析原因,解决后继续进行。正常提升时每2米停机一次,检查各点之间误差是否控制在50mm以内,如位移相差过大则对提升较慢点单独供油,以保证各点同步性,为确保提升的同步,在提升现场增加全站仪对结构吊点位移差进行测量,作为辅助测量措施,可以四个吊点位置钢柱上悬挂钢尺,在每提升两层楼时,为了保证提升同步,对四个点进行标高测量; Step 13, the steel corridor truss 1 is formally lifted as a whole: after a trial lift, the overall inspection is correct and the lifting process is entered. Proceed according to the steps during the trial lifting. If any abnormal phenomenon is found, stop immediately, analyze the cause, and continue after solving it. Stop once every 2 meters during normal lifting, check whether the error between each point is controlled within 50mm, if the displacement difference is too large, supply oil to the slower lifting point separately to ensure the synchronization of each point, in order to ensure the synchronization of lifting, in A total station is added to the lifting site to measure the displacement difference of the structural lifting points. As an auxiliary measurement measure, steel rulers can be hung on the steel columns at the positions of the four lifting points. take elevation measurements;
步骤十四、提升至设计结构标高:待钢连廊桁架1整体提升至设计标高下方50~150mm处时,停止提升; Step 14. Elevate to the design structural elevation: When the overall steel corridor truss 1 is elevated to 50-150mm below the design elevation, stop the elevation;
步骤十五、标高复测及焊接前的准备:对钢连廊桁架1的整体情况进行复测,其中主要包括钢连廊桁架1的挠度、钢桁架四个吊点的高差情况,同时对于钢连廊桁架1整体的偏移情况进行复测,制定相应的纠偏措施,此过程中需要上方施工人员与设备控制人员统一协调行动;设备控制人员根据施工人员测量结果点动调整设备进而调整钢连廊桁架1的四点位移,最终达到设定标高; Step 15. Elevation re-measurement and preparation before welding: Re-measure the overall situation of the steel corridor truss 1, which mainly includes the deflection of the steel corridor truss 1 and the height difference of the four lifting points of the steel truss. Retest the overall deviation of the steel corridor truss 1, and formulate corresponding correction measures. In this process, the construction personnel above and the equipment control personnel need to coordinate and act; the equipment control personnel adjust the equipment according to the measurement results of the construction personnel, and then adjust the steel. The four-point displacement of corridor truss 1 finally reaches the set elevation;
步骤十六、焊接成型,拆除工装:如图8和图10,钢连廊桁架1提升就位后,将钢连廊桁架1与提升架合拢连接,合拢处构件通过塔吊进行安装,腹板用高强螺栓固定,钢梁上下翼缘焊接连接,最后拆卸提升设备及工装,至此,完成整个吊装过程。第一提升架2和第二提升架3的主要受力杆件均为原结构杆件,与从主体结构伸出的预埋型钢梁一41或预埋型钢梁二51连接,连接节点均为刚性连接,翼缘采用等强焊接,腹板采用高强度螺栓连接。提升架上的杆件均可以看成是原来钢连廊的一部分,提升就位后各个端部对应焊接,形成完整的刚连廊桁架结构。 Step 16. Welding and forming, removal of tooling: As shown in Figure 8 and Figure 10, after the steel corridor truss 1 is lifted into place, the steel corridor truss 1 and the lifting frame are closed and connected, and the components at the closed place are installed by the tower crane, and the web is used The high-strength bolts are fixed, the upper and lower flanges of the steel beam are welded and connected, and finally the lifting equipment and tooling are disassembled. So far, the entire hoisting process is completed. The main force-bearing members of the first lifting frame 2 and the second lifting frame 3 are all original structural members, which are connected with the pre-embedded steel beam 1 41 or the pre-embedded steel beam 2 51 protruding from the main structure, and the connection nodes All are rigidly connected, the flange is welded with equal strength, and the web is connected with high-strength bolts. The rods on the lifting frame can be regarded as a part of the original steel corridor. After being lifted into place, each end is welded correspondingly to form a complete rigid corridor truss structure.
上述披露的各技术特征并不限于已披露的与其它特征的组合,本领域技术人员还可根据实用新型之目的进行各技术特征之间的其它组合,以实现本实用新型之目的为准。 The technical features disclosed above are not limited to the disclosed combination with other features, and those skilled in the art can also make other combinations among the technical features according to the purpose of the utility model, which shall prevail in order to achieve the purpose of the utility model.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620077673.1U CN205558304U (en) | 2016-01-27 | 2016-01-27 | Hoist and mount system of large -scale steel gallery truss |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620077673.1U CN205558304U (en) | 2016-01-27 | 2016-01-27 | Hoist and mount system of large -scale steel gallery truss |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN205558304U true CN205558304U (en) | 2016-09-07 |
Family
ID=56821360
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201620077673.1U Expired - Fee Related CN205558304U (en) | 2016-01-27 | 2016-01-27 | Hoist and mount system of large -scale steel gallery truss |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN205558304U (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105507600A (en) * | 2016-01-27 | 2016-04-20 | 中国中铁航空港建设集团有限公司 | Hoisting system and hoisting construction method for large steel corridor trusses |
| CN107842246A (en) * | 2017-12-20 | 2018-03-27 | 西北电力建设第四工程有限公司 | A kind of chimney steel beam hydraulic lifting high-altitude integral slipping hanging apparatus and method |
| CN108166626A (en) * | 2017-12-27 | 2018-06-15 | 中国核工业二四建设有限公司 | A kind of big load form bracing system construction method of high-supported formwork multi-composite type |
| CN108532963A (en) * | 2018-04-24 | 2018-09-14 | 共享钢构有限责任公司 | The hydraulic lifting installation method of large span high-altitude steel frame gallery structure |
| CN113152687A (en) * | 2021-04-21 | 2021-07-23 | 上海宝冶集团南京建筑有限公司 | Structure and method for improving layering reverse order of hollow steel gallery |
| CN114215170A (en) * | 2022-01-07 | 2022-03-22 | 浙江精工钢结构集团有限公司 | Method for lifting super-altitude giant hanging multi-layer connected structure |
| CN115075399A (en) * | 2022-08-04 | 2022-09-20 | 上海市机械施工集团有限公司 | Active unloading method |
| CN115506487A (en) * | 2022-10-31 | 2022-12-23 | 中冶(上海)钢结构科技有限公司 | The method of overall lifting and installation after overlapping and assembling double-layer steel trusses on the ground |
-
2016
- 2016-01-27 CN CN201620077673.1U patent/CN205558304U/en not_active Expired - Fee Related
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105507600A (en) * | 2016-01-27 | 2016-04-20 | 中国中铁航空港建设集团有限公司 | Hoisting system and hoisting construction method for large steel corridor trusses |
| CN107842246A (en) * | 2017-12-20 | 2018-03-27 | 西北电力建设第四工程有限公司 | A kind of chimney steel beam hydraulic lifting high-altitude integral slipping hanging apparatus and method |
| CN108166626A (en) * | 2017-12-27 | 2018-06-15 | 中国核工业二四建设有限公司 | A kind of big load form bracing system construction method of high-supported formwork multi-composite type |
| CN108532963A (en) * | 2018-04-24 | 2018-09-14 | 共享钢构有限责任公司 | The hydraulic lifting installation method of large span high-altitude steel frame gallery structure |
| CN113152687A (en) * | 2021-04-21 | 2021-07-23 | 上海宝冶集团南京建筑有限公司 | Structure and method for improving layering reverse order of hollow steel gallery |
| CN114215170A (en) * | 2022-01-07 | 2022-03-22 | 浙江精工钢结构集团有限公司 | Method for lifting super-altitude giant hanging multi-layer connected structure |
| CN115075399A (en) * | 2022-08-04 | 2022-09-20 | 上海市机械施工集团有限公司 | Active unloading method |
| CN115506487A (en) * | 2022-10-31 | 2022-12-23 | 中冶(上海)钢结构科技有限公司 | The method of overall lifting and installation after overlapping and assembling double-layer steel trusses on the ground |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN205558304U (en) | Hoist and mount system of large -scale steel gallery truss | |
| CN106836498B (en) | Hoisting construction method for steel truss of grand stand roof of super-large span stadium | |
| CN103291076B (en) | Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame | |
| CN201158933Y (en) | High-rise maintaining scaffold device with extruding structure | |
| CN105507600A (en) | Hoisting system and hoisting construction method for large steel corridor trusses | |
| CN103410322B (en) | The parallel Truss Steel corridor construction method of large span | |
| CN114232805B (en) | Construction method of ultrahigh-height large-span steel concrete beam hanging structure | |
| CN106193618B (en) | A kind of aerial steel structure truss construction of Long span | |
| CN104088467B (en) | A kind of large Steel Cantilever truss structure high-altitude construction Deformation monitoring method | |
| CN102535845A (en) | Construction method of bearing frame of corridor structure | |
| CN114215170B (en) | Lifting method for ultrahigh-altitude giant-suspension multilayer conjoined structure | |
| CN103225408A (en) | Construction method for long-span net rack multiple-mast independent type integral lifting | |
| CN112575948B (en) | A roof truss composed of a string beam and a cantilever truss and a construction method thereof | |
| CN205476401U (en) | Elevator well type steel protection construction platform | |
| CN110847375A (en) | A large-span truss construction method and large-span truss structure | |
| CN114775882B (en) | Membrane-stainless steel-aluminum alloy-inhaul cable combined structure | |
| CN110905261B (en) | Ultra-large span closed material yard structure for multiple stackers and reclaimers and construction method thereof | |
| CN205558306U (en) | Big profiled steel structure vestibule hoist and mount hoisting frame | |
| CN111980165A (en) | Large-span net rack external-expanding splicing integral jacking construction method | |
| CN102337782B (en) | Lift system for constructing truss platform on top of tall and large space | |
| WO2025000948A1 (en) | Large-span venue steel structure and building process therefor | |
| CN110318344B (en) | Novel steel box girder No. 0 block support and No. 0 block erection construction method | |
| CN107558719A (en) | For high-rise frame steel construction adjustable mobile operating platform and its construction method | |
| CN117702899A (en) | Installation construction method of ultra-large span heavy steel corridor | |
| CN115787996A (en) | Overhung construction method and overhung frame for super-high building |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160907 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |