CN205558239U - Foldable self-climbing mechanism - Google Patents
Foldable self-climbing mechanism Download PDFInfo
- Publication number
- CN205558239U CN205558239U CN201620180950.1U CN201620180950U CN205558239U CN 205558239 U CN205558239 U CN 205558239U CN 201620180950 U CN201620180950 U CN 201620180950U CN 205558239 U CN205558239 U CN 205558239U
- Authority
- CN
- China
- Prior art keywords
- climbing
- platform
- fixed
- folding
- lifting rail
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000009194 climbing Effects 0.000 claims abstract description 37
- 238000010276 construction Methods 0.000 claims abstract description 27
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 20
- 239000010959 steel Substances 0.000 claims abstract description 20
- 241000282326 Felis catus Species 0.000 claims description 3
- 239000000463 material Substances 0.000 abstract description 4
- 238000009435 building construction Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000006073 displacement reaction Methods 0.000 description 2
- 230000000630 rising effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008602 contraction Effects 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000011017 operating method Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Ladders (AREA)
Abstract
The utility model is suitable for a construction technical field provides a collapsible self-climbing mechanism. It is including climbing the platform, from the system of climbing and be used for the fixed subassembly of platform of fixed mounting on the steel construction, but the slidable connection of platform that climbs is on the fixed subassembly of platform, the platform that climbs is including climbing the guide rail, the fixed platform frame, folding platform frame and folding support piece, the guide rail that climbs through the system control of climbing certainly, fixed platform frame fixed mounting is on the guide rail that climbs, the one end of folding platform frame is rotationally installed on the fixed platform frame, folding support piece's one end detachably installs on the guide rail that climbs, the other end is rotationally installed on folding platform frame. The utility model discloses can fold folding platform frame and folding platform frame to can pass narrow limited space and arrive after suitable position, expand the construction with folding platform frame again, its operation is simple and direct, reduced manpower and material resources consumption, shortened the construction greatly consuming time, guaranteed the construction progress.
Description
Technical field
This utility model belongs to technical field of building construction, particularly relates to a kind of collapsible self-climbing mechanism.
Background technology
In high-building construction, use set up by operating platform is inevitable.In order to improve efficiency of construction,
Staff can select as much as possible to pacify and tear simple and direct, the operating platform of simple in construction open.The most easy from climbing
Platform use in high-building construction is the most commonplace, but the use of these platforms is essentially all
Outside building, platform is not limited by space structure.
Existing one supporting mechanism of can creeping includes lifting device, bracing frame, climb column and hydraulic system.
Drive lifting device to climb under hydraulic system jacking, bracing frame is provided with telescopic mounting, scalable dress
Putting and include slide unit, power part and telescope support, slide unit is arranged on connecing of expansion bracket and bracing frame
In contacting surface, power part is arranged on bracing frame.This telescopic mounting can be according to dependence structure sectional dimension
Change adjust in time the relative displacement between column and support of climbing, thus realize Telescopic.
But, said mechanism structure is complicated, and weight is relatively big, and installing/dismounting operation and operating procedure are complicated, machine
Structure flexible limited in one's ability, is only suitable in unscreened construction surface construction, and when small space is constructed,
This supporting mechanism of can creeping is difficult to play its advantage.Therefore, steel pipe scaffold be still main constructing operation put down
Platform.And the steel pipe scaffold that carries out repeatedly is set up and can be expended substantial amounts of manpower and materials undoubtedly, especially unsettled and
Narrow space set up safety and reliability it is difficult to ensure that.
Utility model content
Technical problem to be solved in the utility model is that offer one is simple to operation, can pass narrow space
That constructs is collapsible from climbing platforms.
This utility model is achieved in that a kind of collapsible self-climbing mechanism, including climbing platforms and control
Described climbing platforms climb from climbing system, also include fixing for the platform being fixedly mounted on steel construction
Assembly, described climbing platforms slidable connection is on described platform fixation kit, and described climbing platforms includes climbing
Rising guide rail, fixed platform frame, folded flat stand and folding support member, described lifting rail is climbed certainly by described
The system of liter controls to climb, and described fixed platform frame is fixedly mounted on described lifting rail, described folding
One end of paralell is installed in rotation on described fixed platform frame, and one end of described folding support member is removable
Being arranged on unloading on described lifting rail, the other end is installed in rotation on described folded flat stand.
Further, described folding support member is gaily decorated basket screw rod.
Further, the other end of described folded flat stand is rotatably mounted with folding guard rail bar.
Further, one end of described folding guard rail bar is fixed with steel disc page, and described steel disc page is fixing with described
Fixed by securing member between paralell.
Further, being welded with prestressed bolt on described steel construction, described platform fixation kit is with described
It is threaded connection fastening between prestressed bolt.
Further, described platform fixation kit includes flag nut, hangs box and quit, described flag nut
Fixing with described prestressed bolt being connected, described extension box is fixedly connected on described flag nut, described in quit
Be fixedly connected on described extension box, described lifting rail be slidably attached at described in quit on.
Further, it is installed with between described fixed platform frame and is easy to the cat ladder that workmen climbs.
Further, it is erected with inclined support bar between described fixed platform frame and described lifting rail.
Further, described lifting rail at least has two, is connected by bearing pin between described lifting rail,
It is fixedly connected with gaily decorated basket screw rod between two adjacent fixed platform framves on said two lifting rail.
Further, described from climbing system include hydraulic jack and control described hydraulic jack work
Hydraulic control panel, described hydraulic control panel is arranged on described climbing platforms, one end of described hydraulic jack
Being fixed on described lifting rail, the other end is fixed on described platform fixation kit.
This utility model compared with prior art, has the beneficial effects that: this utility model is solid by fixed platform frame
Dingan County is contained on lifting rail, and folded flat stand is all rotatably connected with fixed platform frame, folding support member,
When running into narrow restricted clearance, folding support member is dismantled from lifting rail, folded flat stand and folding
Paralell can be naturally drooped by Gravitative Loads, thus reduces taking up room of folded flat stand, by from climbing
Under the drive of the system of liter, climbing platforms upwards climbs, and after arriving correct position through narrow space, again will
Folding support member is fixed on the correct position on lifting rail, thus launches to support by folded flat stand
Constructing, it has advantage simple to operation, reduces man power and material and consumes, substantially reduces construction time-consuming,
Ensure that construction speed.
Accompanying drawing explanation
Fig. 1 is that the collapsible self-climbing mechanism structure in the deployed state that this utility model embodiment provides is shown
It is intended to;
Fig. 2 is the structural representation under folding climb mode of the collapsible self-climbing mechanism of embodiment illustrated in fig. 1
Figure;
Fig. 3 is the A portion structure for amplifying schematic diagram in embodiment illustrated in fig. 2;
Fig. 4 is the B portion structure for amplifying schematic diagram in embodiment illustrated in fig. 2;
Fig. 5 is the structural representation of the folding guard rail bar in embodiment illustrated in fig. 1.
Detailed description of the invention
In order to make the purpose of this utility model, technical scheme and advantage clearer, below in conjunction with accompanying drawing
And embodiment, this utility model is further elaborated.Should be appreciated that described herein specifically
Embodiment, only in order to explain this utility model, is not used to limit this utility model.
As shown in Figure 1 to Figure 3, it is that the one of a kind of collapsible self-climbing mechanism of the present utility model is preferably implemented
Example, it include climbing platforms, control climbing platforms climb from climbing system and for being fixedly mounted on steel
Platform fixation kit 2 in structure.Climbing platforms slidable connection, on platform fixation kit 2, is climbed flat
Platform includes lifting rail 3, fixed platform frame 4, folded flat stand 5 and folding support member 6.Lifting rail 3
By controlling to climb from climbing system, fixed platform frame 4 is fixedly mounted on lifting rail 3, fixing
It is installed with between paralell 4 and is easy to the cat ladder 10 that workmen climbs.One end of folded flat stand 5
Being installed in rotation on fixed platform frame 4, one end of folding support member 6 is removably mounted on to climb and leads
On rail 3, the other end is installed in rotation on folded flat stand 5.
In the present embodiment, folded flat stand 5 is revolved with fixed platform frame 4 by bearing pin (not indicating in figure)
Turning and connect, folding support member 6 is rotatably connected with folded flat stand 5 by bearing pin, in order to installation and removal.
Owing to fixed platform frame 4 is fixedly mounted on lifting rail 3, folded flat stand 5 and fixed platform frame 4,
Folding support member 6 is all rotatably connected.When running into narrow restricted clearance, by folding support member 6 with climb
One end that guide rail 3 connects is dismantled, owing to folded flat stand 5 and folding support member 6 are equal from lifting rail 3
By Gravitative Loads, folded flat stand 5 rotates around fixed platform frame 4 and naturally droops, folding support member 6 around
Folded flat stand 5 rotates and naturally droops, thus forms folded state (as shown in Figure 2), decreases folding
Taking up room of folded paralell 5.Therefore, under the drive of climbing system, climbing platforms upwards climbs,
, again folding support member 6 can be fixed on lifting rail 3 after arriving correct position through narrow space
Correct position, thus folded flat stand 5 is launched Construction of Supporting (as shown in Figure 1).Above-mentioned from climbing
Mechanism has advantage simple to operation, reduces man power and material and consumes, substantially reduce construction time-consuming, protects
Demonstrate,prove construction speed.
In above-described embodiment, folding support member 6 uses gaily decorated basket screw rod to be supported folding paralell 5, logical
The length overregulating gaily decorated basket screw rod can regulate the gradient of folded flat stand 5 at any time, with satisfied construction needs,
Ensure that this climbing device is reliably constructed on the steel construction tilted.In other embodiments, folding support member
6 be used as different pull bars or drag-line, stay cord replaces, as long as displacement function can be completed.
In above-described embodiment, for ensure work progress safety, folded flat stand 5 the other end rotationally
Connect and have folding guard rail bar 7.Specifically, please referring collectively to Fig. 5, one end of folding guard rail bar 7 is fixed with
Steel disc page 71, is fixed by securing member (not indicating in figure) between steel disc page 71 and folded flat stand 5.
Securing member in the present embodiment uses bolt, is fixed with folded flat stand 5 by steel disc page 71 by bolt
Connecting, when needs doubling stack guard railing 7 folds, the bolt released on steel disc page 71 is fixed, will
Folding guard rail bar 7 Guan Bi is folded on folded flat stand 5, then carries out bolt and fix, it is achieved to folding guard rail
The convenient folding of bar 7.
In above-described embodiment, steel construction 1 is welded with some prestressed bolts 11, platform fixation kit 2
And it is threaded connection fastening between prestressed bolt 11.During climbing, platform fixation kit 2
Can be recycled, after rising to certain altitude, by being manually placed on the platform of this climbing device lower end
Fixation kit 2 is dismantled, and moves it to the position carrying out and constructing required above, and on steel construction 1, welding is good pre-
After stressed bolt 11, platform fixation kit 2 is fixedly connected on this prestressed bolt 11, then with even
Lifting rail 3 is attached, and its bonding strength is high, safe and reliable, easy construction.Specifically, the most together
Refering to Fig. 4, platform fixation kit 2 includes flag nut 22, hangs box 23 and quit 21.Flag nut
22 fixing with prestressed bolt 11 are connected, and extension box 23 is fixedly connected on flag nut 22, quit 21
Being fixedly connected on extension box 22, lifting rail 3 is slidably attached at quits on 21.
In above-described embodiment, between fixed platform frame 4 and lifting rail 3, it is erected with inclined support bar 8, thus
Strengthen the stability of fixed platform frame 4.Lifting rail 3 is set at least have two, lifting rail 3 it
Between connected by bearing pin, be fixedly connected with between two adjacent fixed platform framves 4 on two lifting rails 3
Gaily decorated basket screw rod 9.When needs carry out on steel construction 1 broken line climb time, by the elongation of gaily decorated basket screw rod 9 or
Person shortens, and the lifting rail 3 of top can be made to rotate certain angle around bearing pin, thus changes two and climb and lead
Angle between rail 3, and then the angle of fixed platform frame 4 can be changed, it is possible to convenient construction demand.
In above-described embodiment, include that hydraulic jack 13 and control hydraulic jack 13 work from climbing system
Hydraulic control panel 12.Hydraulic control panel 12 is arranged on climbing platforms, one end of hydraulic jack 13
Being fixedly installed on lifting rail 3, the other end is fixedly installed on platform fixation kit 2.Specifically, should
One end of hydraulic jack 13 21 is connected with lifting rail 3 by quitting, and the other end passes through connector 14
It is fixed on extension box 23.Therefore, lifting rail 3 can be driven by the contraction of control hydraulic jack 13
Climb, when the certain altitude that climbs carry out construction complete to need afterwards to continue up climb construction time, logical
Cross and manually the upper of this self-climbing mechanism is delivered in hydraulic jack 13 dismounting from lifting rail 3 and extension box 23
End, is fixed on the platform fixation kit 2 and lifting rail 3 being mounted above such that it is able to by this
Hydraulic jack 13 drives this self-climbing mechanism to continue up and climbs.
The foregoing is only preferred embodiment of the present utility model, not in order to limit this utility model,
All any amendment, equivalent and improvement etc. made within spirit of the present utility model and principle, all should
Within being included in protection domain of the present utility model.
Claims (10)
1. a collapsible self-climbing mechanism, including climbing platforms and control described climbing platforms climb from
Climbing system, it is characterised in that: described self-climbing mechanism also includes flat for be fixedly mounted on steel construction
Platform fixation kit, described climbing platforms slidable connection on described platform fixation kit, described climbing platforms
Including lifting rail, fixed platform frame, folded flat stand and folding support member, described lifting rail passes through institute
Stating and control to climb from climbing system, described fixed platform frame is fixedly mounted on described lifting rail, institute
The one end stating folded flat stand is installed in rotation on described fixed platform frame, the one of described folding support member
End is removably mounted on described lifting rail, and the other end is installed in rotation on described folded flat stand.
Collapsible self-climbing mechanism the most as claimed in claim 1, it is characterised in that: described folding support
Part is gaily decorated basket screw rod.
Collapsible self-climbing mechanism the most as claimed in claim 1, it is characterised in that: described folding platform
The other end of frame is rotatably mounted with folding guard rail bar.
Collapsible self-climbing mechanism the most as claimed in claim 3, it is characterised in that: described folding guard rail
One end of bar is fixed with steel disc page, is fixed by securing member between described steel disc page and described fixed platform frame.
Collapsible self-climbing mechanism the most as claimed in claim 1, it is characterised in that: at described steel construction
On be welded with prestressed bolt, be threaded connection between described platform fixation kit and described prestressed bolt
Fastening.
Collapsible self-climbing mechanism the most as claimed in claim 5, it is characterised in that: described platform is fixed
Assembly includes flag nut, hangs box and quit, and described flag nut is fixing with described prestressed bolt to be connected,
Described extension box is fixedly connected on described flag nut, described in quit and be fixedly connected on described extension box, described
Lifting rail be slidably attached at described in quit on.
Collapsible self-climbing mechanism the most as claimed in claim 1, it is characterised in that: described fixed platform
It is installed with between frame and is easy to the cat ladder that workmen climbs.
Collapsible self-climbing mechanism the most as claimed in claim 1, it is characterised in that: described fixed platform
It is erected with inclined support bar between frame and described lifting rail.
Collapsible self-climbing mechanism the most as claimed in claim 1, it is characterised in that: described lifting rail
At least there are two, connected by bearing pin between described lifting rail, two on said two lifting rail
It is fixedly connected with gaily decorated basket screw rod between adjacent fixed platform frame.
Collapsible self-climbing mechanism the most as claimed in claim 1, it is characterised in that: described certainly climbing is
System includes hydraulic jack and controls the hydraulic control panel of described hydraulic jack work, described hydraulic jack
One end be fixed on described lifting rail, the other end is fixed on described platform fixation kit.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620180950.1U CN205558239U (en) | 2016-03-09 | 2016-03-09 | Foldable self-climbing mechanism |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620180950.1U CN205558239U (en) | 2016-03-09 | 2016-03-09 | Foldable self-climbing mechanism |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205558239U true CN205558239U (en) | 2016-09-07 |
Family
ID=56817148
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620180950.1U Active CN205558239U (en) | 2016-03-09 | 2016-03-09 | Foldable self-climbing mechanism |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205558239U (en) |
-
2016
- 2016-03-09 CN CN201620180950.1U patent/CN205558239U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10479656B2 (en) | Modular, adaptable and foldable apparatus for a climbing crane | |
US20150292263A1 (en) | Supply Frame for a Tower; Tower with a Supply Frame and Method for Erecting a Supply Frame in the Interior of a Tower | |
US11028602B2 (en) | Suspended scaffolding system | |
CN208965998U (en) | Scaffold | |
CN102597390A (en) | Tubular building structure with hingedly connected platform segment | |
JP5201633B2 (en) | Two-stage handrail leading structure in construction scaffolding | |
CN205558239U (en) | Foldable self-climbing mechanism | |
KR200378217Y1 (en) | Scaffolding for the high ground working | |
CN202899589U (en) | Foldable lifting scaffold | |
US20210040749A1 (en) | Ladder-based winch-powered plank scaffold | |
CN105883645A (en) | Disassembling method for tower crane attaching devices | |
CN211872658U (en) | Modular asynchronous construction hangs basket | |
CN203795885U (en) | Tower-type large-height-building demolition machine | |
CN106337652A (en) | Electric power maintenance ladder | |
RU2618853C1 (en) | Compact hoisting machine "bogatyr" and method of its installation | |
CN214364852U (en) | Integrated device for mounting steel jacking structure of high and large concrete column | |
KR101800622B1 (en) | Multi-type lifting scaffold | |
CN212000637U (en) | Movable operating platform for movable support | |
CN212865625U (en) | Construction platform for bridge engineering | |
KR20130099581A (en) | Stanchion integrated scaffolding stage bracket | |
CN218522190U (en) | Movable quick-release operation platform suitable for high-altitude edge-facing operation | |
CN219569531U (en) | Construction platform for additionally installing elevator | |
CN215101635U (en) | Tower crane with safety channel introduced into outer sleeve frame | |
CN102040169A (en) | Collapsible tower | |
CN218643809U (en) | Stabilizing support for high-altitude operation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |