CN205557543U CN201620395837.5U CN201620395837U CN205557543U CN 205557543 U CN205557543 U CN 205557543U CN 201620395837 U CN201620395837 U CN 201620395837U CN 205557543 U CN205557543 U CN 205557543U
Authority
CN
China
Prior art keywords
bank protection
retaining structure
soil
anchor slab
girt strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620395837.5U
Other languages
Chinese (zh)
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201620395837.5U priority Critical patent/CN205557543U/en
Application granted granted Critical
Publication of CN205557543U publication Critical patent/CN205557543U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a do bank protection retaining structure, characterized by bank protection post stretch into basement elevation following 2 2.5 rice, the bank protection post outside set up the bank protection board, and the bank protection board is dull and stereotyped, set up towards native face and keep off native board, keeping off native board and staying and establish the outlet, keep off and set up the girt strip between native board and the bank protection post, bank protection post, bank protection board, girt strip, fender soil plate -type become the cancelled structure, and the cancelled structure top sets up the roof beam that bears down on one, and 13 overall height positions on the bank protection upper portion set up the filler, right side soil body excavation sloping, and geotechnological cloth is laid on the slope surface, sets up native anchor slab above the geotechnological cloth, the vaulting pole right -hand member withstands native anchor slab, fixes at the bank protection board with the crab -bolt behind the vaulting pole left end prestress application. The utility model discloses the security performance is good, and engineering cost is low.

Description

A kind of bank protection retaining structure
Technical field
This utility model relates to a kind of retaining structure, particularly to a kind of bank protection retaining structure.
Background technology
Bank protection retaining structure is to prevent soil body landslide or a kind of structure of deformation instability, is that Geotechnical Engineering is important One of research topic.Gravity type retaining structure is the most ancient barrier wall structure, has and gathers materials on the spot, easy construction Etc. significant advantage, but it is increasing to be as construction scale of projects, Gravity Retaining Wall oneself do not adapt to engineering bar The part complex area needs to retaining structure, higher mainly due to Gravity Retaining Wall cost, and in construction During due to excavate more meeting cause foundation instability, how to save construction costs, ensure that engineering safety is engineering The problem that personnel face.
Utility model content
This utility model is to provide a kind of bank protection retaining structure, solves bank protection retaining structure dangerous high with cost Problem.
This utility model carries out unloading soil at 1/3 bank protection height, makes the right side by the bank protection soil body on the right side of prestressing force pushing tow The side bank protection soil body is in poised state, uses latticed members that soil-baffling structure is integrally formed, protects in latticed members Active earth pressure is efficiently transferred to deep soil by slope post.Bottom uses broken line towards the Slope protection plate at soil body position Form, makes this region soil body form soil arch in load-bearing moving process, and the top soil body uses strut pushing tow soil anchor slab The soil body is made to remain stable.
Bank protection post stretches into below substrate absolute altitude 2-2.5 rice, and bank protection post setting space is 4-6m, and bank protection column section is Square, square a length of 200-250mm, Slope protection plate is set outside bank protection post, Slope protection plate thickness is 60-80mm, Slope protection plate is flat board, arranges breast boards towards soil face, and breast boards is flap, and flap angle is 150-160 Degree, forms the triangle soil of different units, there will be certain change under triangle soil body thrust outside on the right side of flap Shape, forms the relieving arch of horizontal direction, and the horizontal thrust that in relieving arch, the soil body produces is born by broken line plate.Gear soil Plate stays and sets spilled water hole, and spilled water hole arrangement pitch is 1 every square, a diameter of 6-8mm of spilled water hole, breast boards And arranging girt strip between bank protection post, girt strip height is 150-250mm, most descend row's girt strip from substrate Altitude For 400-500mm, the vertical spacing of adjacent row girt strip is 600-800mm.Bank protection post, Slope protection plate, girt strip, Breast boards forms cancelled structure, and cancelled structure top arranges capping beam, and capping beam height is 400-600mm, Total height position, bank protection top 1/3 arranges filler, and filler width is 0.6-0.8m, soil excavation sloping, right side, Slope and horizontal angle are 70-80 degree, and ramped surfaces lays geotextiles, and geotextiles is arranged above with soil anchor slab, Soil anchor slab is shaped as triangle line, and soil anchor slab is the armoured concrete slab of thickness 12-18mm, and soil anchor slab is with three Root dowel, a diameter of 14-16mm of dowel, a length of 400-600mm of dowel, dowel stretches into the right side soil body. Strut right-hand member withstands soil anchor slab, is fixed on Slope protection plate by crab-bolt after strut left end Shi Hanzhang, and strut uses straight Footpath is the reinforcing bar of 28mm or 32mm, and adjacent struts distance is 0.7-0.9m.Filler uses sand rubble, and sand is broken Stone particle diameter is not more than 80mm, and sand rubble should be less than 15% by the grogs of 0.07mm sieve aperture, although or many In 15% but should be less than 10% by the grogs of 0.015mm sieve aperture.
This utility model security performance is good, and construction costs is low.
Accompanying drawing explanation
Fig. 1 is bank protection retaining structure elevational schematic view, and Fig. 2 is retaining structure floor map, and Fig. 3 is soil anchor Board plane schematic diagram, Fig. 4 is soil anchor slab elevational schematic view.
In each accompanying drawing: 1, bank protection post, 2, Slope protection plate, 3, girt strip, 4, breast boards, 5, strut, 6, anchor Bolt, 7, soil anchor slab, 8, geotextiles, 9, capping beam, 10, filler.
Detailed description of the invention
In embodiment, bank protection post 1 stretches into below substrate absolute altitude 2 meters, and bank protection post 1 setting space is 5m, bank protection Post 1 cross section is square, and square a length of 250mm arranges Slope protection plate 2, Slope protection plate outside bank protection post 1 2 thickness are 80mm, and Slope protection plate 2 is flat board, arrange breast boards 4 towards soil face, and breast boards 4 is flap, folding Plate angle is 160 degree.Breast boards 4 stays and sets spilled water hole, and spilled water hole arrangement pitch is 1 every square, spilled water hole A diameter of 7mm, arranges girt strip 3 between breast boards 4 and bank protection post 1, girt strip 3 height is 200mm, Lower row's girt strip 3 is 450mm from substrate Altitude, and the vertical spacing of adjacent row girt strip 3 is 700mm.Bank protection Post 1, Slope protection plate 2, girt strip 3, breast boards 4 form cancelled structure, and cancelled structure top is arranged bears down on one Beam 9, capping beam 9 height is 400mm, and the earthwork is hollowed out by total height position, bank protection top 1/3, and the earthwork hollows out Width is 0.7m, soil excavation sloping, right side, and slope and horizontal angle are 75 degree, and ramped surfaces spreads If geotextiles 8, geotextiles 8 is arranged above with soil anchor slab 7, and soil anchor slab 7 is shaped as triangle line, and soil anchor slab 7 is The armoured concrete slab of thickness 16mm, soil anchor slab 7 is with three dowels, a diameter of 14mm of dowel, dowel A length of 500mm, dowel stretches into the right side soil body.Strut 5 right-hand member withstands soil anchor slab 7, and strut 5 left end applies Being fixed on Slope protection plate 2 by crab-bolt 6 after prestressing force, strut 5 uses the reinforcing bar of a diameter of 28mm or 32mm, Adjacent struts 5 is apart from for 0.8m.The earthwork hollows out position and fills filler 10, and filler 10 uses sand rubble, and sand is broken Stone particle diameter is not more than 80mm, and sand rubble should be less than 15% by the grogs of 0.07mm sieve aperture.

Claims (8)

1. a bank protection retaining structure, is characterized in that bank protection post stretches into below substrate absolute altitude 2-2.5 rice, and bank protection post sets Putting spacing is 4-6m, and bank protection column section is square, and square a length of 200-250mm sets outside bank protection post Putting Slope protection plate, Slope protection plate thickness is 60-80mm, and Slope protection plate is flat board, arranges breast boards towards soil face;Breast boards stays If spilled water hole, arranging girt strip between breast boards and bank protection post, girt strip height is 150-250mm, descend most row's girt strip from Substrate Altitude is 400-500mm, and the vertical spacing of adjacent row girt strip is 600-800mm;Bank protection post, bank protection Plate, girt strip, breast boards form cancelled structure, and cancelled structure top arranges capping beam, and capping beam height is 400-600mm, total height position, bank protection top 1/3 arranges filler, soil excavation sloping, right side, ramped surfaces Laying geotextiles, geotextiles is arranged above with soil anchor slab;Strut right-hand member withstands soil anchor slab, strut left end Shi Hanzhang Being fixed on Slope protection plate by crab-bolt afterwards, adjacent struts distance is 0.7-0.9m.
Bank protection retaining structure the most according to claim 1, is characterized in that spilled water hole arrangement pitch is every square 1 Individual, a diameter of 6-8mm of spilled water hole.
Bank protection retaining structure the most according to claim 1, is characterized in that breast boards is flap, flap angle For 150-160 degree.
Bank protection retaining structure the most according to claim 1, is characterized in that filler width is 0.6-0.8m.
Bank protection retaining structure the most according to claim 1, is characterized in that slope with horizontal angle is 70-80 degree.
Bank protection retaining structure the most according to claim 1, is characterized in that soil anchor slab is shaped as triangle line, soil Anchor slab is the armoured concrete slab of thickness 12-18mm, and soil anchor slab is with three dowels, and dowel is a diameter of 14-16mm, a length of 400-600mm of dowel, dowel stretches into the right side soil body.
Bank protection retaining structure the most according to claim 1, it is characterized in that strut use a diameter of 28mm or The reinforcing bar of 32mm.
Bank protection retaining structure the most according to claim 1, is characterized in that filler uses sand rubble, sand rubble Particle diameter is not more than 80mm, and sand rubble should be less than 15% by the grogs of 0.07mm sieve aperture, although or more than 15% But should be less than 10% by the grogs of 0.015mm sieve aperture.
CN201620395837.5U 2016-04-12 2016-04-12 Bank protection retaining structure Expired - Fee Related CN205557543U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620395837.5U CN205557543U (en) 2016-04-12 2016-04-12 Bank protection retaining structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620395837.5U CN205557543U (en) 2016-04-12 2016-04-12 Bank protection retaining structure

Publications (1)

Publication Number Publication Date
CN205557543U true CN205557543U (en) 2016-09-07

Family

ID=56805640

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620395837.5U Expired - Fee Related CN205557543U (en) 2016-04-12 2016-04-12 Bank protection retaining structure

Country Status (1)

Country Link
CN (1) CN205557543U (en)

Similar Documents

Publication Publication Date Title
CN103669398B (en) A kind of monoblock type cutting retaining wall
CN102041845B (en) United draining system for effectively lowering seepage lines in fill dam of tailing reservoir
CN106049511B (en) A kind of composite reinforcement method suitable for non-coal open-pit slope landslide control
CN105672240B (en) Inclining destruction type Dangerous Rock Body administering method
CN205557543U (en) Bank protection retaining structure
CN105862659A (en) High-frequency debris flow shore protection and diversion method
CN204435407U (en) A kind of batter post group anchor formula rock foundation
CN207047796U (en) A kind of light-duty mud-rock flow arch blocking dam
CN205776258U (en) A kind of Pile-Anchor Supporting for Deep Excavation system
CN108179762A (en) A kind of retaining wall reinforcement device and reinforced construction method
CN109930550A (en) Lattice guest's cage barrier wall structure and construction method
CN107700434A (en) A kind of dome grating formula armored concrete mud-rock flow blocking dam and its construction process
CN105525595A (en) Gabion-piled slab type debris flow retaining structure and implementation method thereof
CN207685782U (en) Lattice guest's cage barrier wall structure
CN216275591U (en) Anti-settlement structure adopting prestressed concrete pipe pile composite foundation
CN108018825A (en) A kind of shore protection
CN105839650B (en) Bank protection retaining structure
CN205776274U (en) A kind of abrupt slope rate broadens platform draining edge slope structure
CN210886796U (en) Subgrade is consolidated to weak soil
CN205369276U (en) Osmosis membrane cofferdam is prevented to preceding landing leg shaped steel
CN208701738U (en) A kind of solid reinforcement combination of rigidity and flexibility ecology retaining wall
CN204212163U (en) Karst depression talus off-load reinforced structure
CN211143115U (en) Novel implanted stiff skeleton pile plate retaining wall
CN211773851U (en) Slope-inclined type special-shaped gabion retaining wall structure of passive soil pressure high-backfill track
CN104480897B (en) Flood prevention wall with small land occupation and wide application range

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160907

Termination date: 20170412