CN205534624U - Fixed hanging of cable is pressed from both sides in tunnel - Google Patents
Fixed hanging of cable is pressed from both sides in tunnel Download PDFInfo
- Publication number
- CN205534624U CN205534624U CN201620403467.5U CN201620403467U CN205534624U CN 205534624 U CN205534624 U CN 205534624U CN 201620403467 U CN201620403467 U CN 201620403467U CN 205534624 U CN205534624 U CN 205534624U
- Authority
- CN
- China
- Prior art keywords
- plate
- tunnel
- fixation clamp
- clip
- inner cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a fixed hanging of cable is pressed from both sides in tunnel relates to clamping device technical field, the utility model discloses a mounting panel, mounting panel are the L shape board of bending, and the mounting panel includes horizontal mounting plate and vertical mounting panel, and horizontal mounting plate top detachable is provided with the earth connection support, vertical mounting panel one side is provided with fixation clamp A and fixation clamp B, the utility model has the advantages of simple structure, easy to assemble, with low costs.
Description
Technical field
This utility model relates to clamping device field, fixes clip more particularly to a kind of tunnel inner cable.
Background technology
After the fixing clip of tunnel inner high voltage cable is installed, needing to carry out ground protection for operation security, earth lead passes through
Leading to and install in tunnel, two ends are connected with the earth by earthing pole.Earth lead is generally mounted to cable and fixes clip top, with chemistry
Crab-bolt is fixed by ground wire clip, and each cable is fixed clip and is required for individually being connected with earth lead, thus is grounded protection
Function.
But the wiring of this kind of mounting means is relatively mixed and disorderly, uses and connect accessory and connector that the many needs of fixture are used, solid
Locking member has: parallel groove clamp, line nose, wire clip, chemical anchor bolts, wherein chemical anchor bolts usage quantity is many, need punching, perfusion
Quantity many, working procedure is more complicated.
How to solve above-mentioned technical problem and become the striving direction of those skilled in the art.
Utility model content
This utility model is in order to overcome above-mentioned technical deficiency, it is provided that a kind of simple in construction, convenient installation, the tunnel of low cost
Inner cable fixes clip.
This utility model to achieve these goals concrete the most by the following technical solutions:
A kind of tunnel inner cable fixes clip, and including installing plate, installing plate is L-shaped bending plate, and installing plate includes laterally pacifying
Dress plate and vertically-mounted plate, be transversely mounted dismountable earth lead bearing that is provided with above plate, and described vertically-mounted plate side sets
It is equipped with fixation clamp A and fixation clamp B.
Further, described earth lead bearing includes upper wiring board and lower patch panel, and upper wiring board lower surface is provided with
Upper wiring arcuate groove, lower patch panel upper surface is provided with the lower wiring arcuate groove corresponding with upper wiring arcuate groove, upper wiring arc
Groove and lower wiring arcuate groove constitute the lock chamber for fixing ground wire.
Further, described be transversely mounted plate, fixation clamp A and fixation clamp B are positioned at the same side of vertically-mounted plate.
Further, described fixation clamp A and fixation clamp B all includes train wheel bridge and lower plate, and train wheel bridge lower surface is arranged
Arc groove A, lower plate upper surface is had to be provided with the arc groove B coordinated with arc groove A, arc groove A and arc groove B
Constitute the holding chamber for clamping cable, in arc groove A and arc groove B, be provided with rubber packing, train wheel bridge and lower folder
Plate two ends are fixed by fixing bolt.
Further, described lower plate is arranged on vertically-mounted plate by welding manner.
The lowest, upper wiring board and lower patch panel are bolted on and are transversely mounted on plate.
Further, fixation clamp A is positioned at above fixation clamp B.
Further, described vertically-mounted plate is provided with crab-bolt fixing hole.
The beneficial effects of the utility model are as follows:
1, this utility model changes original tunnel inner cable and fixes the version of clip, makes original ground connection wire fixing clip
Son is fixed clip with cable and is integrated, and after the checking computations such as designer's structure, electric conductivity are qualified, fully meets cable load-bearing
And the requirement of the aspect such as ground wire water conservancy diversion.
2, after this utility model is implemented at the construction field (site), decrease the usage quantity of chemical anchor bolts, decrease tunnel internalization
Learn crab-bolt punching, perfusion quantity, decrease workman's engineering time, save material cost.
3, the wiring effect neat appearance of Integral cable after construction, it is adaptable to various high and low pressure cable sidewalls in tunnel
Install, due to remarkable in economical benefits, there is extremely strong promotional value.
4, after clip innovation fixed by cable, earth lead is directly mounted at inside the earth lead bearing of clip top, it is not necessary to single
Solely set up earth lead fixture, thus decrease the operations such as the punching of corresponding chemical crab-bolt, perfusion and pull-out test.Also reduce simultaneously
Installing the working procedures such as ground wire clip, parallel groove clamp, connecting line and compression bonded line nose, site operation quantities will subtract significantly
Few.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the structural representation of earth lead bearing;
Reference: 1-installing plate, the vertically-mounted plate of 1-1-, 1-1.1-crab-bolt fixing hole, 1-2-is transversely mounted plate, 4-
Bolt, 5-earth lead bearing, patch panel under 5-1-, wiring arcuate groove under 5-1.1-, 5-2-upper wiring board, the upper multiple frame of 5-2.1-
Shape groove, 6-fixation clamp A, 6-1-fix bolt, 6-2-train wheel bridge, 6-3-lower plate, 7-rubber packing, 8-fixation clamp B.
Detailed description of the invention
In order to those skilled in the art are better understood from this utility model, below in conjunction with the accompanying drawings with following example to this
Utility model is described in further detail.
Embodiment 1
As illustrated in fig. 1 and 2, the present embodiment provides a kind of tunnel inner cable to fix clip, and including installing plate 1, its feature exists
In, installing plate 1 is L-shaped bending plate, and installing plate 1 includes being transversely mounted plate 1-2 and vertically-mounted plate 1-1, is transversely mounted on plate 1-2
Dismountable earth lead bearing 5 that is provided with, described vertically-mounted plate 1-1 side is provided with fixation clamp A6 and fixation clamp B8.
Described earth lead bearing 5 includes upper wiring board 5-2 and lower patch panel 5-1, and upper wiring board 5-2 lower surface is provided with
Upper wiring arcuate groove 5-2.1, lower patch panel 5-1 upper surface is provided with the lower wiring arc corresponding with upper wiring arcuate groove 5-2.1
Groove 5-1.1, upper wiring arcuate groove 5-2.1 and lower wiring arcuate groove 5-1.1 constitute lock chamber.
In the present embodiment, change original tunnel inner cable and fix the version of clip, make original ground connection wire fixing clip
Son is fixed clip with cable and is integrated, and after the checking computations such as designer's structure, electric conductivity are qualified, fully meets cable load-bearing
And the requirement of the aspect such as ground wire water conservancy diversion.
Embodiment 2
It is further optimized, specifically on the basis of the tangible embodiment of the present embodiment 1:
Described be transversely mounted plate 1-2, fixation clamp A6 and fixation clamp B8 are positioned at the same side of vertically-mounted plate 1-1.
Described fixation clamp A6 and fixation clamp B8 all includes that train wheel bridge 6-2 and lower plate 6-3, train wheel bridge 6-2 lower surface set
Being equipped with arc groove A, lower plate 6-3 upper surface is provided with the arc groove B coordinated with arc groove A, arc groove A and arc
Groove B constitutes the holding chamber for clamping cable, is provided with rubber packing 7, train wheel bridge in arc groove A and arc groove B
6-2 and lower plate 6-3 two ends are fixed by fixing bolt 6-1.
Described lower plate 6-3 is arranged on vertically-mounted plate 1-1 by welding manner.
Upper wiring board 5-2 and lower patch panel 5-1 is fixed on by bolt 4 and is transversely mounted on plate 1-2.
Fixation clamp A6 is positioned at above fixation clamp B8.
It is provided with crab-bolt fixing hole 1-1.1 on described vertically-mounted plate 1-1.
The above, preferred embodiment the most of the present utility model, not in order to limit this utility model, this utility model
Scope of patent protection be as the criterion with claims, the equivalent that every utilization description of the present utility model and accompanying drawing content are made
Structure changes, and in like manner should be included in protection domain of the present utility model.
Claims (8)
1. tunnel inner cable fixes a clip, including installing plate (1), it is characterised in that installing plate (1) is L-shaped bending plate,
Installing plate (1) includes being transversely mounted plate (1-2) and vertically-mounted plate (1-1), is transversely mounted the most dismountable on plate (1-2) being provided with
Earth lead bearing (5), described vertically-mounted plate (1-1) side is provided with fixation clamp A(6) and fixation clamp B (8).
Tunnel the most according to claim 1 inner cable fixes clip, it is characterised in that described earth lead bearing (5) bag
Including upper wiring board (5-2) and lower patch panel (5-1), upper wiring board (5-2) lower surface is provided with wiring arcuate groove (5-2.1),
Lower patch panel (5-1) upper surface is provided with the lower wiring arcuate groove (5-1.1) corresponding with upper wiring arcuate groove (5-2.1), above connects
Line arcuate groove (5-2.1) and lower wiring arcuate groove (5-1.1) constitute lock chamber.
Tunnel the most according to claim 1 inner cable fixes clip, it is characterised in that described be transversely mounted plate (1-2),
Fixation clamp A(6) and fixation clamp B (8) be positioned at the same side of vertically-mounted plate (1-1).
Tunnel the most according to claim 1 inner cable fixes clip, it is characterised in that described fixation clamp A(6) and fixing
Folder B (8) all includes train wheel bridge (6-2) and lower plate (6-3), and train wheel bridge (6-2) lower surface is provided with arc groove A, lower plate
(6-3) upper surface be provided with the arc groove B coordinated with arc groove A, arc groove A and arc groove B constitute be used for clamping
Rubber packing (7), train wheel bridge (6-2) and lower plate (6-it is provided with in the holding chamber of cable, arc groove A and arc groove B
3) two ends are fixed by fixing bolt (6-1).
Tunnel the most according to claim 4 inner cable fixes clip, it is characterised in that described lower plate (6-3) passes through
Welding manner is arranged on vertically-mounted plate (1-1).
Tunnel the most according to claim 4 inner cable fixes clip, it is characterised in that upper wiring board (5-2) and lower wiring
Plate (5-1) is fixed on by bolt (4) and is transversely mounted on plate (1-2).
7. the tunnel inner cable stated according to claim 1 fixes clip, it is characterised in that fixation clamp A(6) it is positioned at fixation clamp B (8)
Top.
8. the tunnel inner cable stated according to claim 1 fixes clip, it is characterised in that on described vertically-mounted plate (1-1)
It is provided with crab-bolt fixing hole (1-1.1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620403467.5U CN205534624U (en) | 2016-05-06 | 2016-05-06 | Fixed hanging of cable is pressed from both sides in tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620403467.5U CN205534624U (en) | 2016-05-06 | 2016-05-06 | Fixed hanging of cable is pressed from both sides in tunnel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205534624U true CN205534624U (en) | 2016-08-31 |
Family
ID=56795465
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620403467.5U Active CN205534624U (en) | 2016-05-06 | 2016-05-06 | Fixed hanging of cable is pressed from both sides in tunnel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205534624U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107171087A (en) * | 2017-06-12 | 2017-09-15 | 武城县光明电力工程有限公司 | A kind of electric power parallel groove clamp |
CN110247342A (en) * | 2019-07-22 | 2019-09-17 | 通号电缆集团有限公司 | A kind of leakage cable suspender with dual-purpose structure |
-
2016
- 2016-05-06 CN CN201620403467.5U patent/CN205534624U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107171087A (en) * | 2017-06-12 | 2017-09-15 | 武城县光明电力工程有限公司 | A kind of electric power parallel groove clamp |
CN110247342A (en) * | 2019-07-22 | 2019-09-17 | 通号电缆集团有限公司 | A kind of leakage cable suspender with dual-purpose structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104315255B (en) | Anti-seismic connecting support combined structure | |
CN205118448U (en) | Individual layer cable fastening clip utensil | |
CN205534624U (en) | Fixed hanging of cable is pressed from both sides in tunnel | |
CN204176142U (en) | A kind of antidetonation connects substrate and antidetonation connection bracket composite structure | |
CN207421538U (en) | One kind is directed to suspension and support erecting device | |
CN201575234U (en) | Hose fixing device | |
CN102582441A (en) | Crossbeam for automobile dashboard | |
CN204960869U (en) | Simple and easy wellhead assembly of clamp formula | |
CN204858482U (en) | Simple and easy high -voltage line cable clamp with adjustable | |
CN204828960U (en) | A a support formula gallows that is used for pipeline classification rationally to arrange | |
CN103542178A (en) | Pipe clamp for automotive chassis hydraulic braking system | |
CN204611102U (en) | A kind of combined type fixing device | |
CN202834394U (en) | Quick-mounting U-shaped clip for electric wire conduit of steel workshop | |
CN105071016B (en) | A kind of antenna holder | |
CN205278551U (en) | Fixed frame | |
CN206313378U (en) | A kind of angle steel tower bracket fixing device | |
CN202840313U (en) | Outdoor box body installation structure | |
CN206859799U (en) | Special purpose device is changed in a kind of 500kV Guywire towers bracing wire | |
CN204046302U (en) | Generator support | |
CN205637785U (en) | Wire pole hood | |
CN206441992U (en) | The electric mounting frame of distribution box | |
CN205509929U (en) | Photovoltaic strutting arrangement | |
CN204345113U (en) | A kind of oil tube connection device | |
CN205594032U (en) | Combination switch mounting fixture | |
CN204986314U (en) | A support for installing new line display |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |