CN205530820U - Steel construction wall body component with brace of putting more energy into - Google Patents

Steel construction wall body component with brace of putting more energy into Download PDF

Info

Publication number
CN205530820U
CN205530820U CN201620358746.4U CN201620358746U CN205530820U CN 205530820 U CN205530820 U CN 205530820U CN 201620358746 U CN201620358746 U CN 201620358746U CN 205530820 U CN205530820 U CN 205530820U
Authority
CN
China
Prior art keywords
wall
square
plate
steel
brace
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620358746.4U
Other languages
Chinese (zh)
Inventor
乔俊良
陈照锡
邱慧云
王金鑫
陈海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Xinghe Steel Structure Co Ltd
Original Assignee
Shandong Xinghe Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Xinghe Steel Structure Co Ltd filed Critical Shandong Xinghe Steel Structure Co Ltd
Priority to CN201620358746.4U priority Critical patent/CN205530820U/en
Application granted granted Critical
Publication of CN205530820U publication Critical patent/CN205530820U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model discloses a steel construction wall body component with brace of putting more energy into, including wall unit and square steel tube, wall unit has a plurality ofly, and every wall unit comprises with the back wallboard vertical parallel arrangement's preceding wallboard, and preceding wallboard is connected through adding the muscle brace with the back wallboard. Between arbitrary two adjacent wall unit, H shaped steel head and the tail through vertical layout are transverse connection in proper order, constitutes the wall body main part. The square steel tube has two, is located the both ends of controlling of wall body main part respectively. The vertical wall unit with being located the first time of square steel tube is connected, and another square steel tube vertical wall unit with being located last precedence be connected. The utility model discloses a steel member factory produced, site assembly construction, the concrete that pour inside be one whole, pours the convenience, need not the formwork, has saved the time of a large amount of plank sheathings and installation and dismantlement template, does not also need the artifical ligature of a large amount of reinforcing bars, can realize industrial production and prefabricated construction, very big improvement building speed.

Description

A kind of steel construction wall component with stiffener brace
Technical field
This utility model relates to long strands field, is specifically related to a kind of steel construction wall component with stiffener brace.
Background technology
Shear wall is main lateral resistant member in building structure, is widely used, traditional shearing in structural seismic, wind force proofing design In wall system, how based on reinforced concrete structure, but, the form of construction work of xoncrete structure needs a large amount of plank sheathings and bamboo glue The forest reserves are damaged by plate, and to environment, and substantial amounts of reinforcing bar needs artificial colligation, and manual manufacture still accounts for Sizable proportion, does not meets the industrialized mode of production, and node region deals with complex, room in dwelling house system Inside have salient angle, make troubles to interior space layout.Additionally, traditional house wall system exists, steel using amount is big, cost of manufacture Higher, make the shortcoming that needs complicated, on-the-spot are the most artificial, difficulty of construction is big and economic performance is poor, limit traditional structure Development and application.
Steel building is the building system of a kind of novel energy-conserving and environment-protective, is the building system of a kind of industrialization, meets standardization Design, factorial praluction, prefabricated construction, the building industrialization standard-required of information system management, be described as the " green of 21 century One of color is built ", it is a kind of energy saving and environment friendly, the building structure that can recycle.If steel construction is had with xoncrete structure Effect combines, and studies a kind of novel house wall construction, and the advantage giving full play to concrete and steel construction, to building knot at present Shortcoming in structure system, is a good solution.
Utility model content
Big in order to overcome existing lateral resistant member to there is steel using amount, make complexity, on-the-spot need a large amount of artificial, difficulty of construction big and The shortcomings such as economic performance difference, the utility model proposes a kind of steel construction wall component with stiffener brace, this wall body structure steel Amount economy, structure manufacture is simple, convenient and quick construction, it is simple to industrialized production, and can improve speed and the matter of production and construction Amount.
In order to solve above-mentioned technical problem, this utility model be the technical scheme is that
A kind of steel construction wall component with stiffener brace, including wall element and square steel tube, described wall element has multiple, Between two wall elements of arbitrary neighborhood, by the H profile steel head and the tail lateral connection successively being vertically arranged, constitute body of wall main body.Institute State square steel tube and have two, lay respectively at the two ends, left and right of body of wall main body.One vertical wall element secondary with being positioned at first place of square steel tube Connecting, another square steel tube is vertically connected with the wall element being positioned at end precedence.
Preferably, each wall element includes four pieces of square plates, two vertical side equal the same side bending shapes of each square plate The flanging become.Wherein the vertical side of two pieces of square plates is fixing connects, and forms front wallboard, other two pieces of square plates vertical Side is also fixing to be connected, and forms rear wall plate.Between described front wallboard and rear wall plate, be vertically intervally arranged multiple stiffener brace, Each stiffener brace two ends are respectively fixedly connected with the flanging in the middle part of front wallboard and rear wall plate.
Preferably, the both sides of the upper flange of each H profile steel, the one end with the rear wall plate being positioned at its both sides is welded respectively, each H profile steel The both sides of lower wing plate, the one end with the front wallboard being positioned at its both sides is welded respectively, and being formed can the cavity of casting concrete.
It is preferably located at front wallboard and the left side of rear wall plate of the wall element of the first time, respectively with the right side wall of a square steel tube Welding, being formed can the cavity of casting concrete.Be positioned at the front wallboard of wall element and the right side of rear wall plate of end precedence, respectively with The left side wall welding of one square steel tube, also being formed can the cavity of casting concrete.
Preferably, two pieces of square plates of composition front wallboard, in a plane, constitute two pieces of square plates of rear wall plate at another In plane.The plane at described front wallboard and rear wall plate place is parallel to each other, and forward is relative.
By using preceding solution, Advantageous Effects of the present utility model is: the steel beam column factory that this utility model uses Making, assembled in situ is constructed, and the concrete that inside pours is an entirety, pours conveniently, it is not necessary to formwork, saves a large amount of wooden model Plate, protects the forest reserves, and need not the artificial colligation of a large amount of reinforcing bar, can realize industrialized production and prefabricated construction, Greatly improve building speed.The problems such as concrete and exterior wall unsticking can be improved, it is achieved concrete works with steel collaborative, Compound action is reliable, and bending resistance, resistance to compression, shear resistant capacity improve, reliable product quality.This utility model can not only be used for vertically Supporting member, again as lateral resistant member, flexible arrangement, indoor large space can be realized, instead of part external and internal wall and separation Wall, saves material and reduces construction cost.
Accompanying drawing explanation
Fig. 1 is the structural principle schematic diagram of a kind of steel construction wall component with stiffener brace of this utility model.
Fig. 2 is the structural principle schematic diagram of certain part in Fig. 1, thus it is shown that wall element.
Fig. 3 is the structural principle schematic diagram of another part in Fig. 1, thus it is shown that H profile steel.
Detailed description of the invention
Below in conjunction with the accompanying drawings this utility model is described in detail:
In conjunction with Fig. 1 to Fig. 3, a kind of steel construction wall component with stiffener brace, including wall element 1 and square steel tube 2, institute Stating wall element 1 and have 3, each wall element 1 includes four pieces of square plates 5, two vertical sides of each square plate 5 The flanging 14 that the bending of equal the same side, limit is formed, described this side 14 strengthens the adhesion strength of square plate 5 and concrete wall, also The effect strengthening this utility model self-strength can be played.Wherein the flanging of two pieces of square plates 5 is fixing connects, and forms front wallboard 11, the flanging of other two pieces of square plates 5 is also fixing to be connected, and forms rear wall plate 12.Described front wallboard 11 and rear wall plate 12 it Between, longitudinally spaced be placed with multiple stiffener brace 13, the two ends of each stiffener brace 13 respectively fixing be welded to front wallboard 11 and after Flanging 14 in the middle part of wallboard 12.
Two pieces of square plates 5 of composition front wallboard 11, in a plane, constitute two pieces of square plates 5 of rear wall plate 12 separately In one plane.Two planes at described front wallboard 11 and rear wall plate 12 place are parallel to each other, and forward is relative.Arbitrary neighborhood two Between individual wall element 1, by the H profile steel 3 head and the tail lateral connection successively being vertically arranged, constitute body of wall main body.Each H profile steel The left and right sides of the upper flange 31 of 3, the one end with the rear wall plate 12 being positioned at its both sides is welded respectively, the bottom wing of each H profile steel 3 The left and right sides of plate 32, the one end with the front wallboard 11 being positioned at its both sides is welded respectively, in the inside of body of wall main body, by front wall Plate 11 and rear wall plate 12 and H profile steel 3 connect that formed can multiple cavitys of casting concrete.
Described square steel tube 2 has two, lays respectively at the two ends, left and right of body of wall main body.Wherein, square steel tube 2 vertically be positioned at The wall element 1 of the first time connects, another square steel, and 2 are vertically connected with the wall element 1 being positioned at end precedence.It is positioned at the first time The front wallboard 11 of wall element 1 and the left side of rear wall plate 12, the right side wall with a square steel tube 2 welds respectively, is positioned at head The wall element 1 of precedence surrounds into square steel tube 2 can the cavity of casting concrete.It is positioned at the front wall of the wall element 1 of end precedence Plate 11 and the right side of rear wall plate 12, the left side wall with another square steel tube 2 welds respectively, and also being formed can the sky of casting concrete Chamber.Meanwhile, the internal cavities of two square steel tubes 2 can also casting concrete.
According to upper type, each parts of composition wall body construction are linked together, at each cavity and two square steel tubes of body of wall main body Casting concrete in the internal cavities of 2, the preferred normal concrete of concrete poured, it would however also be possible to employ high-strength concrete, light Aggregate concrete or self-compacting concrete.After concrete setting, with the front wallboard 11 being connected stiffener brace 13 and rear wall plate 12 structure Become combinative structure, common stress, give full play to material property.Stiffener brace 13 adds front wallboard 11 and rear wall plate 12 rigidity, Also enhance the adhesion strength between wallboard and concrete, owing to the size of the wallboard of stiffener brace 13 connection is relatively big, therefore can pole Improve greatly concrete and exterior wall unsticking problem, promote both collaborative works.The steel beam column factory that this utility model uses makes, existing Field assembling construction, the concrete that inside pours is an entirety, pours conveniently, it is not necessary to formwork, saves a large amount of plank sheathing, protects The forest reserves, and need not the artificial colligation of a large amount of reinforcing bar, industrialized production and prefabricated construction can be realized, carry greatly High building speed.The problems such as concrete and exterior wall unsticking can be improved, it is achieved concrete works with steel collaborative, compound action Reliably, bending resistance, resistance to compression, shear resistant capacity improve, reliable product quality.This utility model can not only be used for vertical supporting member, Again as lateral resistant member, flexible arrangement, indoor large space can be realized, instead of part external and internal wall and dividing wall, save material Material and reduction construction cost.
Certainly, described above is not to restriction of the present utility model, and this utility model is also not limited to the example above, this skill Change that the technical staff in art field is made in essential scope of the present utility model, retrofit, add or replace, also should belong to Protection domain of the present utility model.

Claims (5)

1. with a steel construction wall component for stiffener brace, including wall element and square steel tube, it is characterised in that described wall Body unit at least two, between two wall elements of arbitrary neighborhood, by the H profile steel head and the tail lateral connection successively being vertically arranged, Constitute body of wall main body;Described square steel tube has two, is vertically provided at the left and right sides of body of wall main body respectively;One square steel be positioned at The lateral wall of the first secondary wall element is fixing to be connected, and another square steel is fixing with the lateral wall of the wall element being positioned at end precedence to be connected Connect.
A kind of steel construction wall component with stiffener brace the most according to claim 1, it is characterised in that each body of wall Unit includes four pieces of square plates, the flanging that two vertical side equal the same side bendings of each square plate are formed;Wherein two pieces of sides The vertical side of shape steel plate is fixing to be connected, and forms front wallboard, and the vertical side of other two pieces of square plates is also fixing to be connected, and is formed Rear wall plate;Between described front wallboard and rear wall plate, be vertically intervally arranged multiple stiffener brace, and each stiffener brace two ends are solid respectively Surely the flanging in the middle part of front wallboard and rear wall plate is connected.
A kind of steel construction wall component with stiffener brace the most according to claim 1, it is characterised in that each H profile steel The both sides of upper flange, the one end with the rear wall plate being positioned at its both sides is welded respectively, the both sides of the lower wing plate of each H profile steel, respectively Welding with the one end of the front wallboard being positioned at its both sides, being formed can the cavity of casting concrete.
A kind of steel construction wall component with stiffener brace the most according to claim 1, it is characterised in that be positioned at first place The left side of two block plates of secondary wall element, the right side wall with a square steel tube welds respectively, and being formed can the sky of casting concrete Chamber;Being positioned at the left side of two block plates of the wall element of end precedence, the right side wall with a square steel tube welds respectively, and also being formed can The cavity of casting concrete.
A kind of steel construction wall component with stiffener brace the most according to claim 2, it is characterised in that constitute front wall Two pieces of square plates of plate, in a plane, constitute two pieces of square plates of rear wall plate in another plane;Described front wallboard and The plane at rear wall plate place is parallel to each other, and forward is relative.
CN201620358746.4U 2016-04-26 2016-04-26 Steel construction wall body component with brace of putting more energy into Expired - Fee Related CN205530820U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620358746.4U CN205530820U (en) 2016-04-26 2016-04-26 Steel construction wall body component with brace of putting more energy into

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620358746.4U CN205530820U (en) 2016-04-26 2016-04-26 Steel construction wall body component with brace of putting more energy into

Publications (1)

Publication Number Publication Date
CN205530820U true CN205530820U (en) 2016-08-31

Family

ID=56797452

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620358746.4U Expired - Fee Related CN205530820U (en) 2016-04-26 2016-04-26 Steel construction wall body component with brace of putting more energy into

Country Status (1)

Country Link
CN (1) CN205530820U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109057038A (en) * 2018-09-21 2018-12-21 苏州光彩建筑钢品有限公司 A kind of integrated-type steel moald-cavity convenient for construction
CN109138220A (en) * 2018-07-27 2019-01-04 肇庆三乐集成房屋制造有限公司 The compound assembled skeleton of fiber cement board, wall component and assembled steel reinforced concrete shear wall

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109138220A (en) * 2018-07-27 2019-01-04 肇庆三乐集成房屋制造有限公司 The compound assembled skeleton of fiber cement board, wall component and assembled steel reinforced concrete shear wall
CN109138220B (en) * 2018-07-27 2020-02-18 肇庆三乐集成房屋制造有限公司 Fiber cement board composite assembled framework, wall body component and assembled steel-concrete shear wall
CN109057038A (en) * 2018-09-21 2018-12-21 苏州光彩建筑钢品有限公司 A kind of integrated-type steel moald-cavity convenient for construction

Similar Documents

Publication Publication Date Title
CN211396208U (en) Green type coincide floor's mosaic structure
CN104179250B (en) Light-board house system and construction method thereof
CN103821256B (en) A kind of steel pipe bundle and steel plate concrete combined shear wall structural system
CN102094386A (en) PBL (perfobond leiste) shear connector stiffened steel pipe concrete arch
CN205530820U (en) Steel construction wall body component with brace of putting more energy into
CN103912074B (en) A kind of framework-steel pipe bundle and steel plate concrete shear wall combined structure system
CN203684526U (en) PBL stiffened rectangular steel tube concrete space truss
CN204001194U (en) Light steel truss structure integrated building system
CN109372109A (en) A kind of assembled beam-column connecting node
CN207525933U (en) A kind of steel plate combined shear wall splices node
CN205617611U (en) Confined concrete's steel construction dividing wall component
CN108360682A (en) A kind of construction process of three-dimensional building module and three-dimensional building module
CN205591399U (en) Confined concrete 's steel construction wall body component
CN203808296U (en) Framework-steel pipe bundle and steel plate concrete shear wall combination structure system
CN205637139U (en) Support flat push formula multicavity steel pipe -concrete composite post braced frame system
CN105821966B (en) A kind of support flat push type multi-cavity steel tube concrete coupled column braced frame system
CN205530848U (en) Steel construction turning wall component with brace of putting more energy into
CN205976089U (en) Multicavity steel column shear wall structure
CN209457259U (en) A kind of frame and window border structure of cold-prevention bridge assembled out-hung panel
CN211849963U (en) Self-riveting type node of aluminum alloy space grid structure
CN103850349A (en) Frame-steel pipe bundle combined structure system for industrial residential building
CN204225267U (en) A kind of light weight board building systems
CN209457258U (en) The connection structure in gap between a kind of two neighboring assembled out-hung panel
CN209277287U (en) A kind of assembly concrete-filled steel tube wall frame building integrated morphology
CN205663064U (en) But concreting's steel construction turning wall component

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160831

Termination date: 20210426

CF01 Termination of patent right due to non-payment of annual fee