CN205401090U
CN205401090U CN201620164671.6U CN201620164671U CN205401090U CN 205401090 U CN205401090 U CN 205401090U CN 201620164671 U CN201620164671 U CN 201620164671U CN 205401090 U CN205401090 U CN 205401090U
Authority
CN
China
Prior art keywords
water pump
support bar
side support
articulated slab
pipe body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201620164671.6U
Other languages
Chinese (zh)
Inventor
蔡晓勇
胡辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Loncin Motor Co Ltd
Loncin General Dynamics Co Ltd
Original Assignee
Loncin General Dynamics Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Loncin General Dynamics Co Ltd filed Critical Loncin General Dynamics Co Ltd
Priority to CN201620164671.6U priority Critical patent/CN205401090U/en
Application granted granted Critical
Publication of CN205401090U publication Critical patent/CN205401090U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Details Of Rigid Or Semi-Rigid Containers (AREA)

Abstract

The utility model discloses a hand (hold) pipe on water pump mounting bracket, including hand (hold) body and frame body, the frame body includes that the rear side supports, left side side support bar and right side support bar, wherein, a left side, right side side support bar's upper end is less than the upper end that the rear side supported, a left side, on the side support bar of the right side, both ends are all supported with the rear side through the connecting rod and are connected down, the hand (hold) body is the U -shaped, two ends of hand (hold) body are respectively through hinge hinge on a left side, right side side support bar's upper end, when the push -and -pull frame body makes the water pump remove, the bending segment of hand (hold) body is in along a left side, the state of frame body is stretched out in the place ahead of right side side support bar, during fortune water pump, two ends of hand (hold) body and a left side, align in right side side support bar's upper end, and the bending segment of hand (hold) body is shelved in the upper end that the rear side supported. The utility model discloses can use as the transportation horizontal pole when the packing transportation of water pump, can use as the handle when push -and -pull movable water pump again.

Description

Handle pipe on water pump installing rack
Technical field
This utility model belongs to water pump assembling technical field of transportation, particularly relates to the handle pipe on a kind of large tank water pump installing rack.
Background technology
Water pump with fuel tank is a kind of plumbing equipment common in daily productive life;Fuel tank at water pump is installed, and when especially large tank is installed, for ease of the assembling of large tank, water pump needs configuration shipping beams in frame in the process of packed and transported.Existing large tank water pump majority has shipping beams on the market, but but moves handle during water pump not used for push-and-pull, and when being configured with wheel for water pump, handle is very necessary.In view of this, design one both can regard shipping beams use, can become this those skilled in the art's problem demanding prompt solution as the handle pipe of the handle of mobile push-and-pull water pump again.
Utility model content
The purpose of this utility model is in that to solve above-mentioned technical problem, it is provided that the handle pipe on a kind of water pump installing rack, and the handle pipe on this water pump installing rack can use as shipping beams when water pump packed and transported, can use as handle when water pump is moved in push-and-pull again.
The technical solution of the utility model is as follows:
Handle pipe on a kind of water pump installing rack, including handgrip pipe body and frame body;Frame body includes Backside support, Left-side support bar and Right side support bar, wherein, left, the upper end of Right side support bar is lower than the upper end of Backside support, left, Right side support bar upper, lower two ends are connected with Backside support each through connecting rod, handgrip pipe body takes the shape of the letter U, two terminations of handgrip pipe body respectively through hinge on a left side, the upper end of Right side support bar, when sliding frame support body makes water pump move, the bending segment of handgrip pipe body is in along left, the state of frame body is stretched out in the front of Right side support bar, during transport water pump, two terminations of handgrip pipe body are with left, the upper end alignment of Right side support bar, and the bending segment of handgrip pipe body is shelved on the upper end of Backside support.
Further, described hinge includes the first articulated slab, the second articulated slab and jointed shaft;The bottom surface of described first articulated slab is fixed on the upper end of described left and right side support bar, the upper surface of the first articulated slab has groove, described second articulated slab is positioned at groove and hinged by jointed shaft and the first articulated slab, and described second articulated slab is fixed in the two ends of described handgrip pipe body.
Further, described first articulated slab and the second articulated slab are provided with mutually corresponding pin-and-hole, when handgrip pipe body is in and stretches out state, are inserted with alignment pin in described pin-and-hole, carry out spacing by alignment pin to handgrip pipe body.
Further, the plunger end of described alignment pin is provided with the spacing steel ball being positioned at outside the first articulated slab, and spacing steel ball carries out resiliency supported by the spring arranged in plunger end.
Further, the pin tail end at alignment pin is provided with connection ring, and described connection ring is connected with jointed shaft by metallic bond.
Further, described handgrip pipe body includes the first body and the second body;First and second body all takes the shape of the letter U, and the A/F of the second body is less than the A/F of the first body, and two terminations of the second body are fixed on the horizontal edge of the first body, and two terminations of the first body are respectively hinged at the upper end of left and right side support bar.
The beneficial effects of the utility model: handle pipe is hinged on framework by this utility model, two pieces of articulated slabs one piece of hinge are fixed on framework, one piece is connected with handle pipe, makes handle pipe can freely be turned to diverse location on framework, and the push-and-pull to be respectively used to water pump is moved and packed and transported.Meanwhile, hinge arranges alignment pin and is connected with the fixing of hinge to realize handle pipe, make hands being connected to when push-and-pull is moved and can be relatively fixed between framework, take out alignment pin when needs upturned position, can relatively rotate again;So, make the handle pipe on water pump installing rack use as handle when water pump is moved in push-and-pull, can use as shipping beams when water pump packed and transported again.Alignment pin metallic bond is hung on hinge, it is simple to take at any time, it is prevented that lose;And the spacing steel ball with spring is set on alignment pin the connection of alignment pin can be made fixing more firm.
Accompanying drawing explanation
Fig. 1 is this utility model structural representation.
Fig. 2 is this utility model side view.
Fig. 3 is hinge top view.
Fig. 4 is hinge side view.
Fig. 5 is hinge schematic diagram.
Fig. 6 is hinge schematic diagram during with alignment pin.
Element numbers illustrates: handgrip pipe body 1, hinge 2, connecting rod 3, alignment pin 4, metallic bond 5, spacing steel ball 6, Left-side support 7, Right side support bar 8, Backside support the 9, second body the 101, first body the 102, first articulated slab the 201, second articulated slab 202, jointed shaft 203.
Detailed description of the invention
By particular specific embodiment, embodiment of the present utility model being described below, those skilled in the art the content disclosed by this specification can understand other advantages of the present utility model and effect easily.
Below in conjunction with drawings and Examples, the utility model is described in further detail:
As it is shown in figure 1, the handle pipe on a kind of water pump installing rack, including handgrip pipe body 1 and frame body (as shown in phantom in Figure 1 part);Frame body includes Backside support 9, Left-side support bar 7 and Right side support bar 8, and wherein, the upper end of left and right side support bar is lower than the upper end of Backside support 9, and the upper/lower terminal of left and right side support bar is connected with Backside support 9 each through connecting rod 3.Handgrip pipe body 1 takes the shape of the letter U, two terminations of handgrip pipe body 1 are hinged on the upper end of left and right side support bar respectively through hinge 2, when sliding frame support body makes water pump move, the bending segment of handgrip pipe body 1 is in the front along left and right side support bar and stretches out the state of frame body, during transport water pump, align with the upper end of left and right side support bar in two terminations of handgrip pipe body 1, and the bending segment of handgrip pipe body 1 is shelved on the upper end of Backside support 9.As shown in Figure 2, when handgrip pipe body 1 is turned to horizontal level to the left around hinge 2, can use as the handle that sliding is employed, as shown in phantom in Figure 2, when handgrip pipe body 1 is turned to the right when horizontal level contacts with Backside support 9 top of frame body can use as shipping beams around hinge 2.
Further, as shown in Fig. 35, the hinge 2 between above-mentioned handgrip pipe body 1 and Left-side support bar 7 and Right side support bar 8 includes the first articulated slab the 201, second articulated slab 202 and jointed shaft 203, and jointed shaft 203 specifically can make the version of pin.First articulated slab 201 is hinged by jointed shaft 203 and the second articulated slab 202;Wherein, the bottom surface of the first articulated slab 201 is fixed on the upper end of left and right side support bar, the upper surface of the first articulated slab 201 has groove, second articulated slab 202 is positioned at this groove and hinged by jointed shaft 203 and the first articulated slab 201, and the second articulated slab 202 is fixed in the two ends of described handgrip pipe body 1.
Further, as shown in Figure 6, first articulated slab 201 and the second articulated slab 202 are provided with mutually corresponding pin-and-hole, when handgrip pipe body 1 is in and stretches out state, alignment pin 4 it is inserted with in described pin-and-hole, by alignment pin 4, handgrip pipe body 1 is carried out spacing, by fixing for handgrip pipe body 1 dead, it is prevented that handgrip pipe body 1 rotates.
Further, as shown in Figure 6, the plunger end of alignment pin 4 is provided with the spacing steel ball 6 being positioned at outside the first articulated slab 201, and spacing steel ball 6 carries out resiliency supported by the spring arranged in plunger end, and spacing steel ball 6 can ensure that described alignment pin does not skid off from pin-and-hole when being extruded in described alignment pin.For preventing spacing steel ball 6 from dropping, the part of the cylindrical outer surface of the maximum extended alignment pin 4 of spacing steel ball 6 less than self 1/2nd volume size, in order to avoid small ball 6 rolls out from alignment pin 4.
Further, as shown in Figure 6, the pin tail end at alignment pin 4 is provided with connection ring, and described connection ring is connected with jointed shaft 203 by metallic bond 5.When using as push and pull bar, alignment pin 4 can being inserted pin-and-hole, when needs use as shipping beams, then be extracted by alignment pin 4, the alignment pin 4 after extracting just is suspended on jointed shaft 203, is available for taking at any time next time.
Further, as it is shown in figure 1, handgrip pipe body 1 includes the first body 102 and the second body 101;First and second body all takes the shape of the letter U, the A/F of the second body 101 is less than the A/F of the first body 102, second body 101 two termination is fixed on the horizontal edge of the first body 102, and the first body 102 two termination is respectively hinged at the upper end of left and right side support bar.
Handgrip pipe body 1 is not limited to the version of above-mentioned U-shaped steel pipe, any realize the grip structure that push-and-pull moves and all can use, a kind of mode that above-mentioned U-tube structure simply wherein can realize.
Above-described embodiment only illustrative principle of the present utility model and effect thereof, not for restriction this utility model.Above-described embodiment all under spirit of the present utility model and category, can be modified or change by any those skilled in the art.Therefore, art has all equivalence modification or changes that usually intellectual completes under the spirit disclosed without departing from this utility model with technological thought such as, must be contained by claim of the present utility model.

Claims (6)

1. the handle pipe on water pump installing rack, including handgrip pipe body and frame body;It is characterized in that: frame body includes Backside support, Left-side support bar and Right side support bar, wherein, left, the upper end of Right side support bar is lower than the upper end of Backside support, left, Right side support bar upper, lower two ends are connected with Backside support each through connecting rod, handgrip pipe body takes the shape of the letter U, two terminations of handgrip pipe body respectively through hinge on a left side, the upper end of Right side support bar, when sliding frame support body makes water pump move, the bending segment of handgrip pipe body is in along left, the state of frame body is stretched out in the front of Right side support bar, during transport water pump, two terminations of handgrip pipe body are with left, the upper end alignment of Right side support bar, and the bending segment of handgrip pipe body is shelved on the upper end of Backside support.
2. the handle pipe on water pump installing rack as claimed in claim 1, it is characterised in that: described hinge includes the first articulated slab, the second articulated slab and jointed shaft;The bottom surface of described first articulated slab is fixed on the upper end of described left and right side support bar, the upper surface of the first articulated slab has groove, described second articulated slab is positioned at groove and hinged by jointed shaft and the first articulated slab, and described second articulated slab is fixed in the two ends of described handgrip pipe body.
3. the handle pipe on water pump installing rack as claimed in claim 2, it is characterized in that: described first articulated slab and the second articulated slab are provided with mutually corresponding pin-and-hole, when handgrip pipe body is in and stretches out state, in described pin-and-hole, it is inserted with alignment pin, by alignment pin, handgrip pipe body is carried out spacing.
4. the handle pipe on water pump installing rack as claimed in claim 3, it is characterised in that: the plunger end of described alignment pin is provided with the spacing steel ball being positioned at outside the first articulated slab, and spacing steel ball carries out resiliency supported by the spring of setting in plunger end.
5. the handle pipe on water pump installing rack as claimed in claim 4, it is characterised in that: the pin tail end at alignment pin is provided with connection ring, and described connection ring is connected with jointed shaft by metallic bond.
6. the handle pipe on the water pump installing rack as described in claim 1,2,3,4 or 5, it is characterised in that: described handgrip pipe body includes the first body and the second body;First and second body all takes the shape of the letter U, and the A/F of the second body is less than the A/F of the first body, and two terminations of the second body are fixed on the horizontal edge of the first body, and two terminations of the first body are respectively hinged at the upper end of left and right side support bar.
CN201620164671.6U 2016-03-03 2016-03-03 Hand (hold) pipe on water pump mounting bracket Withdrawn - After Issue CN205401090U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620164671.6U CN205401090U (en) 2016-03-03 2016-03-03 Hand (hold) pipe on water pump mounting bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620164671.6U CN205401090U (en) 2016-03-03 2016-03-03 Hand (hold) pipe on water pump mounting bracket

Publications (1)

Publication Number Publication Date
CN205401090U true CN205401090U (en) 2016-07-27

Family

ID=56443573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620164671.6U Withdrawn - After Issue CN205401090U (en) 2016-03-03 2016-03-03 Hand (hold) pipe on water pump mounting bracket

Country Status (1)

Country Link
CN (1) CN205401090U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105587657A (en) * 2016-03-03 2016-05-18 隆鑫通用动力股份有限公司 Handlebar pipe of water pump installation frame

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105587657A (en) * 2016-03-03 2016-05-18 隆鑫通用动力股份有限公司 Handlebar pipe of water pump installation frame
CN105587657B (en) * 2016-03-03 2018-02-06 隆鑫通用动力股份有限公司 A kind of handle pipe on water pump mounting bracket

Similar Documents

Publication Publication Date Title
CN205401090U (en) Hand (hold) pipe on water pump mounting bracket
CN104997269A (en) Luggage rack
CN105587657B (en) A kind of handle pipe on water pump mounting bracket
CN203582026U (en) Oil tank material pouring-out device
CN207890495U (en) A kind of quantitative bowl type lifter
CN202776056U (en) Infant bathe device and support thereof
CN204580687U (en) Foldable flower holder
CN201411573Y (en) Clothes hanger
CN204734028U (en) Folding travelling basket
CN204523039U (en) A kind of clinical laboratory test tube case
CN204580686U (en) A kind of foldable flower holder
CN202636514U (en) Novel clothes hanger
CN210324752U (en) Word amalgamation device is used in english teaching
CN207712695U (en) A kind of cloth stacking mechanism
CN201445208U (en) Mosquito curtain with post fixing device
CN205338175U (en) Portable supporter
CN202925340U (en) Automatic drying rack
CN204586930U (en) A kind of shopping cart
CN204472976U (en) A kind of Foldable basket of bicycle
CN204210674U (en) Motor cycle combination suspension
CN205457128U (en) Foldable bookrack
CN202671914U (en) Combined folding clothes hanger
CN202051226U (en) Extensible wardrobe
CN202069385U (en) Telescopic clothes hanger
CN202312716U (en) Spiral stereo clothes rack

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20160727