CN205400810U CN201620175370.3U CN201620175370U CN205400810U CN 205400810 U CN205400810 U CN 205400810U CN 201620175370 U CN201620175370 U CN 201620175370U CN 205400810 U CN205400810 U CN 205400810U
Authority
CN
China
Prior art keywords
reinforcing bar
stones
laying bricks
bar ladder
sealing wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620175370.3U
Other languages
Chinese (zh)
Inventor
郭春生
谷成锡
吕鸿明
郑鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangquan Kehui Gas Detection Technology Co Ltd
Original Assignee
Yangquan Kehui Gas Detection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangquan Kehui Gas Detection Technology Co Ltd filed Critical Yangquan Kehui Gas Detection Technology Co Ltd
Priority to CN201620175370.3U priority Critical patent/CN205400810U/en
Application granted granted Critical
Publication of CN205400810U publication Critical patent/CN205400810U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a mine sealing wall, and parallel arrangement's the same including two structures reinforcing bar net, there are a plurality of reinforcing bar ladder roof beams in the outside of every reinforcing bar net along its width direction parallel arrangement in proper order, and two online reinforcing bar ladder roof beams of reinforcing bar correspond in proper order, and many to drawing the stock to be parallel to each other and to be all perpendicular rather than the two reinforcing bar ladder roof beams that correspond to drawing the stock all to be connected with many on the two reinforcing bar ladder roof beams that correspond each other, and it has the filling bag who builds the material by laying bricks or stones to build inside packing by laying bricks or stones according to the preface between two reinforcing bars net. The utility model discloses has improved the structure of traditional fire dam and the form of building by laying bricks or stones, has effectually improved the fire dam security performance and resisted the explosion wave performance, and use manpower sparingly, material resources, the engineering time is short, construction cost is low.

Description

A kind of mine sealing wall
Technical field
This utility model relates to coal mining field, is specifically related to a kind of mine sealing wall.
Background technology
The coal production complicated condition of China, geological conditions is various, and a large amount of coal minings are all carry out under extremely complex structural environment.Along with China's rapid economic development, energy shortage problem highlights, and promotes coal mining industry to develop rapidly, puts into production one after another in the underground coal mine of many large-scale high-yield and high-efficiencies, and the problem efficiently produced that therefore ensures safety is also following.In progress of coal mining, often it is subject to the threat of the disasters such as fire, water, coal dust, roof fall, gas.Production safety is affected, it is often necessary to set up fire dam in order to prevent spontaneous combustion of coal seam, harmful gases diffusion or gas explosion.
Fire dam building, in the UNICOM tunnel with enclosed area, the shaft production district, is used to cut off the air stream in UNICOM tunnel, prevents the isolation structures that personnel enter simultaneously.
Conventional containment wall is that brick mix structure, cement or yellow mud are wiped one's face, and its advantage is that cost is low, comprcssive strength is big.But it also has irresistible shortcoming, as: under dynamic pressure effect, very easily cracking leaks out, and construction is mainly by craft, when drift section is 5~6m2If building 6~7m2Fire dam, the time needs 4~5h the soonest;When drift section is 10m2Above, if building 12~13m2Fire dam, the time needs 8~10h the soonest, forms the material weight of fire dam simultaneously and quantity is all very big, the mine deep up to hundreds of rice for being in underground, transport extremely difficult, cause that utilization and recycle rate is unsatisfactory.And the airtight effect that substantially cannot resist gas explosion shock wave of lightweight.Therefore conventional containment wall arranges unreasonable because of it, causes needing to expend substantial amounts of human and material resources, and the engineering time is oversize, it is impossible to meet instructions for use.
Utility model content
In order to solve above-mentioned technical problem, this utility model provides a kind of mine sealing wall, and this fire dam safety is good, and resistance explosion wave performance is good, and saves human and material resources, and the engineering time is short, and construction cost is low.
The purpose of this utility model implements by the following technical programs:
A kind of mine sealing wall, bar-mat reinforcement that is identical including two structures and that be arranged in parallel, the outside of every bar-mat reinforcement is arranged with multiple reinforcing bar ladder beam in parallel successively along its width, reinforcing bar ladder beam on two bar-mat reinforcements is corresponding in turn to, two mutually corresponding reinforcing bar ladder beams are respectively connected with many Counter-pulled bolts, many Counter-pulled bolts are parallel to each other and two all corresponding reinforcing bar ladder beams are vertical, sequentially build inside by laying bricks or stones and be filled with the filling bag of building materials between two bar-mat reinforcements.
Further, the distance between two Counter-pulled bolts adjacent on two mutually corresponding reinforcing bar ladder beams is identical.
Further, described Counter-pulled bolts two ends are outwards provided with extension.
This utility model one mine sealing wall, this fire dam includes two bar-mat reinforcements, bar-mat reinforcement arranges multiple reinforcing bar ladder beam, corresponding reinforcing bar ladder beam is connected to Counter-pulled bolts, adopts the form of the internal filling bag being filled with building materials to build by laying bricks or stones simultaneously, improve the structure of conventional containment wall and build form by laying bricks or stones, effectively raise fire dam security performance and resist explosion wave performance, and saving human and material resources, the engineering time is short, and construction cost is low.
Accompanying drawing explanation
Below according to drawings and Examples, this utility model is described in further detail.
Fig. 1 is the structural representation of a kind of mine sealing wall of this utility model;
Fig. 2 is the right view of Fig. 1.
In figure: 1-bar-mat reinforcement;2-reinforcing bar ladder beam;3-Counter-pulled bolts;4-filling bag;5-building materials.
Detailed description of the invention
As shown in Figure 1-2, a kind of mine sealing wall described in this utility model embodiment, bar-mat reinforcement 1 that is identical including two structures and that be arranged in parallel, the outside of every bar-mat reinforcement 1 is arranged with multiple reinforcing bar ladder beam 2 in parallel successively along its width, reinforcing bar ladder beam 2 on two bar-mat reinforcements 1 is corresponding in turn to, two mutually corresponding reinforcing bar ladder beams 2 are respectively connected with many Counter-pulled bolts 3, many Counter-pulled bolts 3 are parallel to each other and two all corresponding reinforcing bar ladder beams 2 are vertical, sequentially build inside by laying bricks or stones and be filled with the filling bag 4 of building materials 5 between two bar-mat reinforcements 1.
This utility model is in use, according to the demand thickness of fire dam, closing place section etc., bar-mat reinforcement 1, reinforcing bar ladder beam 2 are installed, make correspondingly sized filling bag 4, be filled with building materials in the inside of filling bag 4, build by laying bricks or stones between two bar-mat reinforcements 1, and do drawing firm with Counter-pulled bolts 3, which improve the structure of conventional containment wall and build form by laying bricks or stones, effectively raise fire dam security performance and resist explosion wave performance, and saving human and material resources, engineering time is short, and construction cost is low.
Preferred embodiment, the distance between two Counter-pulled bolts 3 adjacent on two mutually corresponding reinforcing bar ladder beams 2 is identical for one, it is possible to the effective stability improving fire dam.
Simultaneously, Counter-pulled bolts 3 two ends are outwards provided with extension, Counter-pulled bolts 3 lever strength is higher than airtight body of wall, it is made up of the bidirectional fastening body of rod, the extension at its two ends can form friction (or bonding) resistance with Rock And Soil close contact, it is positioned at the extension outside body of wall and can form the Radial resistant force to body of wall, form actively pretension.
In order to save manpower further, material resources, save engineering time and construction cost, when Specific construction, can first according to the demand thickness of fire dam, close place section and bar-mat reinforcement 1 is installed, reinforcing bar ladder beam 2, make correspondingly sized filling bag 4, build by laying bricks or stones between two bar-mat reinforcements 1, and do drawing firm with Counter-pulled bolts 3, then building materials is selected further according to user demand, it is mixed the building materials being formed uniformly liquid, and the building materials of liquid is pumped in filling bag 4 by filling, complete to build by laying bricks or stones after material solidification, filling bag 4 can be made difformity and model according to tunnel specification and construct requirement to adapt to tunnel.
This utility model one mine sealing wall, for the isolation between mine, exploiting field, the main air entering and returning of coal-face or the closing to exploiting field and flame range, this fire dam safety is good, resist explosion wave performance good, and saving human and material resources, engineering time is short, and construction cost is low, it is easy to promote the use of.
Last it is noted that the foregoing is only preferred embodiment of the present utility model; it is not limited to this utility model; for a person skilled in the art; technical scheme described in foregoing embodiments still can be adjusted by it; or wherein portion of techniques feature is carried out equivalent replacement; all within spirit of the present utility model and principle, any amendment of making, equivalent replacement, improvement etc., should be included within protection domain of the present utility model.

Claims (3)

1. a mine sealing wall, it is characterized in that: include the bar-mat reinforcement that two structures are identical and be arranged in parallel, the outside of every bar-mat reinforcement is arranged with multiple reinforcing bar ladder beam in parallel successively along its width, reinforcing bar ladder beam on two bar-mat reinforcements is corresponding in turn to, two mutually corresponding reinforcing bar ladder beams are respectively connected with many Counter-pulled bolts, many Counter-pulled bolts are parallel to each other and two all corresponding reinforcing bar ladder beams are vertical, sequentially build inside by laying bricks or stones and be filled with the filling bag of building materials between two bar-mat reinforcements.
2. a kind of mine sealing wall according to claim 1, it is characterised in that: the distance between two Counter-pulled bolts adjacent on two mutually corresponding reinforcing bar ladder beams is identical.
3. a kind of mine sealing wall according to claim 1 and 2, it is characterised in that: described Counter-pulled bolts two ends are outwards provided with extension.
CN201620175370.3U 2016-03-09 2016-03-09 Mine sealing wall Active CN205400810U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620175370.3U CN205400810U (en) 2016-03-09 2016-03-09 Mine sealing wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620175370.3U CN205400810U (en) 2016-03-09 2016-03-09 Mine sealing wall

Publications (1)

Publication Number Publication Date
CN205400810U true CN205400810U (en) 2016-07-27

Family

ID=56441894

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620175370.3U Active CN205400810U (en) 2016-03-09 2016-03-09 Mine sealing wall

Country Status (1)

Country Link
CN (1) CN205400810U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106837420A (en) * 2017-04-01 2017-06-13 河南理工大学 Apparatus and method based on the closed coal mine gob of roadway surrounding rock fissured structure
CN109184789A (en) * 2018-11-15 2019-01-11 徐州和盛矿业科技有限公司 A kind of quick vertical mold device of fire dam and construction method
CN111594267A (en) * 2020-05-07 2020-08-28 兖州煤业股份有限公司南屯煤矿 Light water horse module splicing-based airtight wall and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106837420A (en) * 2017-04-01 2017-06-13 河南理工大学 Apparatus and method based on the closed coal mine gob of roadway surrounding rock fissured structure
CN106837420B (en) * 2017-04-01 2019-08-09 河南理工大学 Device and method based on the closed coal mine gob of roadway surrounding rock fissured structure
CN109184789A (en) * 2018-11-15 2019-01-11 徐州和盛矿业科技有限公司 A kind of quick vertical mold device of fire dam and construction method
CN111594267A (en) * 2020-05-07 2020-08-28 兖州煤业股份有限公司南屯煤矿 Light water horse module splicing-based airtight wall and construction method thereof

Similar Documents

Publication Publication Date Title
AU2017405652B2 (en) Method for stepwise construction of preferential gas migration pathway at stope in coal seam
Meng et al. Support technology for mine roadways in extreme weakly cemented strata and its application
CN205400810U (en) Mine sealing wall
CN103939144B (en) A kind of consecutive intervals cushion wall for closed large scale mined area
CN106150545B (en) A kind of method that the filling of goaf part is carried out according to roof caving feature
CN104790952B (en) The other unilateral up second mining of part filling of a kind of post pedals the method in sky coal seam
CN104074534B (en) A kind of combining adopts/the gob-side entry retaining method of fully mechanized coal face
Liu et al. A safe mining approach for deep outburst coal seam groups with hard‐thick sandstone roof: Stepwise risk control based on gas diversion and extraction
Yao et al. Key technique study of stability control of surrounding rock in deep chamber with large cross-section: A case study of the Zhangji Coal Mine in China
CN207813629U (en) A kind of strong dynamic load anti-impact supporting new structure in tunnel
Ma et al. Wongawilli roadway backfilling coal mining method-a case study in Wangtaipu coal mine
CN105669238A (en) Environmentally friendly building heat-insulation material, heat insulation board, seam covering plate and environmentally friendly heat-insulation wall
CN202673299U (en) Double-layer mold constructing composite lining supporting structure of weak surrounding rock tunnel
CN211342952U (en) Asymmetric supporting construction in stratiform soft rock tunnel
Zhang et al. Patterns and security technologies for co-extraction of coal and gas in deep mines without entry pillars
CN207620820U (en) A kind of breaking surrounding rock and soft-rock tunnel U-shaped steel cover canopy supporting construction
Lin Study of soft rock roadway support technique
CN203488188U (en) Mining area roadway arrangement structure of ultra-thick coal seams
XUE et al. Surrounding rock pressure of deep roadway and influences on advance support
Li et al. Raw Gangue Filling Mining under Construction—A Case Study in China
CN105332460A (en) Environment-friendly seismic-isolation building block
Guo et al. Instability Mechanism and Control Technology for Deep-Buried Large-Span Complex Roof Coal Roadway for the Prevention of Coal Pollution.
CN207620819U (en) A kind of tunnel U-shaped steel set canopy supporting construction
Stormont Preliminary seal design evaluation for the Waste Isolation Pilot Plant
CN208152668U (en) A kind of Novel underground tunnel partial seismic isolation structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
DD01 Delivery of document by public notice

Addressee: Gu Chengxi