CN205377440U - Stable dual -path electricity supply device - Google Patents

Stable dual -path electricity supply device Download PDF

Info

Publication number
CN205377440U
CN205377440U CN201521107060.XU CN201521107060U CN205377440U CN 205377440 U CN205377440 U CN 205377440U CN 201521107060 U CN201521107060 U CN 201521107060U CN 205377440 U CN205377440 U CN 205377440U
Authority
CN
China
Prior art keywords
circuit breaker
module
ups
ats
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201521107060.XU
Other languages
Chinese (zh)
Inventor
蔡桂华
王志刚
韩涛
王婧羽
宋夏桐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Baoding Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Baoding Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd, Baoding Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201521107060.XU priority Critical patent/CN205377440U/en
Application granted granted Critical
Publication of CN205377440U publication Critical patent/CN205377440U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Stand-By Power Supply Arrangements (AREA)

Abstract

The utility model relates to a stable dual -path electricity supply device, be equipped with way module, first circuit breaker QF1, second circuit breaker QF2, third circuit breaker QF3, fourth circuit breaker QF4, the 5th circuit breaker QF5, the 6th circuit breaker QF6, the first module of ATS, ATS the second module, a PDU, the 2nd PDU, first load and second load including UPS main road module, UPS, the utility model discloses the activestandby of having optimized the UPS input has relatively only ensured input reliability of power supply with UPS main road module with setting up, and instantaneous overload can the reinforce. Relatively only adopt to be equipped with module parallel machine use in way with UPS main road module with UPS, work is convenient, low cost, and configuration optimization, it is loose relatively to set up the requirement to the parameter, and scalability is strong.

Description

A kind of stable device that supplies power with double circuit
Technical field
This utility model relates to a kind of stable device that supplies power with double circuit, and relates to electric power machine room load supplying field.
Background technology
In power system, especially the stability that apparatus of load is powered is most important, stable operation in order to ensure apparatus of load, the UPS that apparatus of load will be powered every year patrols and examines, pay bigger man power and material, how providing a kind of failure rate is low, power supply is stable, and the equipment convenient electric supply installation with autgmentability of connection becomes urgent need and solves the technical problem that.
Utility model content
It is reliable and stable that technical problem to be solved in the utility model is to provide a kind of power supply, it is achieved switching free of discontinuities, and equipment connects the convenient stable device that supplies power with double circuit with autgmentability.
For solving the problems referred to above, technical solution adopted in the utility model is:
This utility model it include UPS main road module, UPS for road module, the first circuit breaker Q F1, the second circuit breaker Q F2, the 3rd circuit breaker Q F3, the 4th circuit breaker Q F4, the 5th circuit breaker Q F5, the 6th circuit breaker Q F6, ATS the first module, ATS the second module, a PDU, the 2nd PDU, the first load and the second load;
UPS main road module passes sequentially through the first circuit breaker Q F1 and the three circuit breaker Q F3 and accesses ATS the first module;
UPS main road module passes sequentially through the first circuit breaker Q F1 and the four circuit breaker Q F4 and accesses ATS the second module;
UPS passes sequentially through the second circuit breaker Q F2 and the five circuit breaker Q F5 for road module and accesses ATS the first module;
UPS passes sequentially through the second circuit breaker Q F2 and the six circuit breaker Q F6 for road module and accesses ATS the second module;
ATS the first module, a PDU connect and the first load is sequentially connected with;
ATS the second module, the 2nd PDU connect and the second load is sequentially connected with.
Further, the first circuit breaker Q F1 and the second circuit breaker Q F2 is three grades of choppers, and the 3rd circuit breaker Q F3, the 4th circuit breaker Q F4, the 5th circuit breaker Q F5, the 6th circuit breaker Q F6 are two grades of choppers.
Further, the model of the first circuit breaker Q F1 and the second circuit breaker Q F2 is NSE100N-3P-100A, the model of the 3rd circuit breaker Q F3 and the four circuit breaker Q F4 is C65N-2P-C16A+OF, and the model of the 5th circuit breaker Q F5 and the six circuit breaker Q F6 is S251S-2P-C16A+OF.
Further, UPS main road module is 40KVA, UPS is 80KVA for road module.
Further, UPS main road module includes UPS host module and battery module, and UPS includes UPS host module and battery module for road module.
Further, ATS the first module and ATS the second module are rack ATS.
Further, UPS main road module is independent of one another for road module with UPS.
A kind of stable device that supplies power with double circuit according to claim 6, PDU and the two PDU is rack PDU.
Adopt and have the beneficial effects that produced by technique scheme:
This utility model optimizes the standby usage of UPS input and arranges, and has relatively only ensured the reliability of supplying power for input end by UPS main road module, and momentary overload capacity is strong.Relatively using for road module machine with UPS only with by UPS main road module, work is convenient, with low cost, and parameter is arranged and requires relative loose by structure optimization, and extensibility is strong.
This utility model realizes the end-to-end power supply truly from building civil power to feeder ear by the working method in conjunction with UPS double-bus.
This utility model can according to the actual loading of each road and UPS equipment loading condition, switching ATS module for power supply mode free of discontinuities, it is ensured that UPS load stability is powered.
This utility model can the multiple-way supply of proof load by ATS.
This utility model reduces cost, reduces construction volume, maintenance period.
This utility model powers to supporting single supply load equipment by rack ATS, flexibly and easily so that 2 UPS are really separate, without any association, eliminates the failure problems caused in traditional double bus schemes a little, and electric power system stability is greatly improved.
Accompanying drawing explanation
Fig. 1 is modular structure block diagram of the present utility model.
Wherein: 1, UPS main road module;2, UPS is for road module;First circuit breaker Q F1, the second circuit breaker Q F2, the 3rd circuit breaker Q F3, the 4th circuit breaker Q F4, the 5th circuit breaker Q F5, the 6th circuit breaker Q F6;3, ATS the first module;4, ATS the second module;5, a PDU;6, the 2nd PDU;7, the first load;8 second loads.
Detailed description of the invention
As it is shown in figure 1, this utility model it include UPS main road module 1, UPS for road module the 2, first circuit breaker Q F1, the second circuit breaker Q F2, the 3rd circuit breaker Q F3, the 4th circuit breaker Q F4, the 5th circuit breaker Q F5, the 6th circuit breaker Q F6, ATS the first module 3, ATS the second module the 4, the oneth PDU5, the 2nd PDU6, the first load 7 and the second load 8;Wherein UPS (English full name UninterruptiblePowerSystem/UninterruptiblePowerSupply, be translated as uninterrupted power source) module, PDU (English full name PowerDistributionUnit, it is translated as power distribution unit) ATS (English full name Automatictransferswitchingequipment, be translated as automatic change-over) module.
UPS main road module 1 passes sequentially through the first circuit breaker Q F1 and the three circuit breaker Q F3 and accesses ATS the first module 3;UPS main road module 1 passes sequentially through the first circuit breaker Q F1 and the four circuit breaker Q F4 and accesses ATS the second module 4;UPS passes sequentially through the second circuit breaker Q F2 and the five circuit breaker Q F5 for road module 2 and accesses ATS the first module 3;UPS passes sequentially through the second circuit breaker Q F2 and the six circuit breaker Q F6 for road module 2 and accesses ATS the second module 4;ATS the first module the 3, the oneth PDU5 connects and the first load 7 is sequentially connected with;ATS the second module the 4, the 2nd PDU6 connects and the second load 8 is sequentially connected with.
Wherein, the first circuit breaker Q F1 and the second circuit breaker Q F2 is three grades of choppers, and the 3rd circuit breaker Q F3, the 4th circuit breaker Q F4, the 5th circuit breaker Q F5, the 6th circuit breaker Q F6 are two grades of choppers.Adopt hierarchical multi-layer that chopper, science rational in infrastructure are set.
As preferably, the equal NSE100N-3P-100A of model of the first circuit breaker Q F1 and the second circuit breaker Q F2, the model of the 3rd circuit breaker Q F3 and the four circuit breaker Q F4 is C65N-2P-C16A+OF, and the model of the 5th circuit breaker Q F5 and the six circuit breaker Q F6 is S251S-2P-C16A+OF.
Wherein, UPS main road module 1 is 40KVA, UPS is 80KVA for road module 2.
Wherein, UPS main road module 1 includes UPS host module and battery module, and UPS includes UPS host module and battery module for road module 2.
Wherein, UPS main road module 1 is independent of one another for road module 2 with UPS.
Further, ATS the first module 3 and ATS the second module 4 are rack ATS, it is possible to be arranged in giant-screen cabinet-type air conditioner.
Further, PDU5 and the two PDU6 is rack PDU.As those skilled in the art, it is possible on utility model basis, only with a PDU5 mono-kind, or adopt a multiple PDU5 or the 2nd PDU6 to be incorporated in device, be apparent from.
This utility model optimizes the standby usage of UPS input and arranges, and has relatively only ensured the reliability of supplying power for input end by UPS main road module 1, and momentary overload capacity is strong.Relatively using for road module 2 machine with UPS only with by UPS main road module 1, work is convenient, with low cost, and parameter is arranged and requires relative loose by structure optimization, and extensibility is strong.
This utility model realizes the end-to-end power supply truly from building civil power to feeder ear by the working method in conjunction with UPS double-bus.
This utility model can according to the actual loading of each road and UPS equipment loading condition, switching ATS module for power supply mode free of discontinuities, it is ensured that UPS load stability is powered.
This utility model can the multiple-way supply of proof load by ATS.
This utility model reduces cost, reduces construction volume, maintenance period.
This utility model powers to supporting single supply load equipment by rack ATS, flexibly and easily so that 2 UPS are really separate, without any association, eliminates the failure problems caused in traditional double bus schemes a little, and electric power system stability is greatly improved.
Concrete mounting means of the present utility model:
For achieving the above object, certain scheduling hall dispatching desk employing technical solution of the present utility model is:
1. ATS switching device 2, front operating board 1, rear operating board 1 are installed.
2. being with the first load 7 cutover to other power supplys front operating board the oneth PDU5, before closing, higher level's sky of operating board the oneth PDU5 is opened.
3. the former power line (main road) being connected to front operating board the oneth PDU5 is connected to front operating board ATS the first module 3.
4. 2 road power supplys (standby road) the wherein road attracted from ups power room is connected to ATS the first module 3.
5. a road output of ATS the first module 3 is connected on an original PDU5.
6. check that whether all modes of connection are correct, confirm errorless rear to ATS the first module 3, debugging.
7. do dual system ups power system switch test after having debugged, facilities for observation load whether normal power supply.
8. confirm load will not power down when, former the first load 7 being connected to front operating board the oneth PDU5 is directed on a PDU5.
9. other ATS mode of connection is described above.
Last it is noted that above example is only in order to illustrate the technical solution of the utility model, it is not intended to limit;Although this utility model being described in detail with reference to previous embodiment, it will be understood by those within the art that: the technical scheme described in previous embodiment still can be modified by it, or wherein portion of techniques feature is carried out equivalent replacement;It is combined being apparent to multiple technical schemes of the present utility model as those skilled in the art.And these amendments or replacement, do not make the essence of appropriate technical solution depart from the spirit and scope of this utility model embodiment technical scheme.

Claims (8)

1. the device that supplies power with double circuit a kind stable, it is characterised in that: it includes UPS main road module (1), UPS for road module (2), the first circuit breaker Q F1, the second circuit breaker Q F2, the 3rd circuit breaker Q F3, the 4th circuit breaker Q F4, the 5th circuit breaker Q F5, the 6th circuit breaker Q F6, ATS the first module (3), ATS the second module (4), a PDU (5), the 2nd PDU (6), the first load (7) and the second load (8);
UPS main road module (1) passes sequentially through the first circuit breaker Q F1 and the three circuit breaker Q F3 and accesses ATS the first module (3);
UPS main road module (1) passes sequentially through the first circuit breaker Q F1 and the four circuit breaker Q F4 and accesses ATS the second module (4);
UPS passes sequentially through the second circuit breaker Q F2 and the five circuit breaker Q F5 for road module (2) and accesses ATS the first module (3);
UPS passes sequentially through the second circuit breaker Q F2 and the six circuit breaker Q F6 for road module (2) and accesses ATS the second module (4);
ATS the first module (3), a PDU (5) connect and the first load (7) is sequentially connected with;
ATS the second module (4), the 2nd PDU (6) connect and the second load (8) is sequentially connected with.
2. a kind of stable device that supplies power with double circuit according to claim 1, it is characterized in that: the first circuit breaker Q F1 and the second circuit breaker Q F2 is three grades of choppers, and the 3rd circuit breaker Q F3, the 4th circuit breaker Q F4, the 5th circuit breaker Q F5, the 6th circuit breaker Q F6 are two grades of choppers.
3. a kind of stable device that supplies power with double circuit according to claim 2, it is characterized in that: the model of the first circuit breaker Q F1 and the second circuit breaker Q F2 is NSE100N-3P-100A, the model of the 3rd circuit breaker Q F3 and the four circuit breaker Q F4 is C65N-2P-C16A+OF, and the model of the 5th circuit breaker Q F5 and the six circuit breaker Q F6 is S251S-2P-C16A+OF.
4. a kind of stable device that supplies power with double circuit according to claim 3, it is characterised in that: UPS main road module (1) is 80KVA for 40KVA, UPS for road module (2).
5. a kind of stable device that supplies power with double circuit according to claim 4, it is characterised in that: UPS main road module (1) includes UPS host module and battery module, and UPS includes UPS host module and battery module for road module (2).
6. a kind of stable device that supplies power with double circuit according to claim 5, it is characterised in that: UPS main road module (1) and UPS is independent of one another for road module (2).
7. a kind of stable device that supplies power with double circuit according to claim 6, it is characterised in that: ATS the first module (3) and ATS the second module (4) is rack ATS.
8. a kind of stable device that supplies power with double circuit according to claim 7, it is characterised in that: a PDU (5) and the 2nd PDU (6) is rack PDU.
CN201521107060.XU 2015-12-27 2015-12-27 Stable dual -path electricity supply device Expired - Fee Related CN205377440U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521107060.XU CN205377440U (en) 2015-12-27 2015-12-27 Stable dual -path electricity supply device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521107060.XU CN205377440U (en) 2015-12-27 2015-12-27 Stable dual -path electricity supply device

Publications (1)

Publication Number Publication Date
CN205377440U true CN205377440U (en) 2016-07-06

Family

ID=56257591

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521107060.XU Expired - Fee Related CN205377440U (en) 2015-12-27 2015-12-27 Stable dual -path electricity supply device

Country Status (1)

Country Link
CN (1) CN205377440U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108988479A (en) * 2018-08-17 2018-12-11 华为技术有限公司 A kind of data center and its control method
CN109038793A (en) * 2018-07-11 2018-12-18 佛山市众盈电子有限公司 A kind of open-ended modularity uninterruptible power supply
CN110492595A (en) * 2019-08-01 2019-11-22 神华(福建)能源有限责任公司 A kind of DC power supply automatic switching control equipment and system
WO2020253433A1 (en) * 2019-06-19 2020-12-24 深圳光峰科技股份有限公司 Power source switching circuit and power source apparatus

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109038793A (en) * 2018-07-11 2018-12-18 佛山市众盈电子有限公司 A kind of open-ended modularity uninterruptible power supply
CN108988479A (en) * 2018-08-17 2018-12-11 华为技术有限公司 A kind of data center and its control method
WO2020253433A1 (en) * 2019-06-19 2020-12-24 深圳光峰科技股份有限公司 Power source switching circuit and power source apparatus
CN110492595A (en) * 2019-08-01 2019-11-22 神华(福建)能源有限责任公司 A kind of DC power supply automatic switching control equipment and system

Similar Documents

Publication Publication Date Title
CN205377440U (en) Stable dual -path electricity supply device
KR20220115623A (en) Charging systems for swapping stations or for energy storage stations
CN104242438A (en) Power supply system based on modularization UPS
CN102355045A (en) Power supply method, power supply controller and power supply system
CN207652128U (en) A kind of dual power supply uninterruptible power system
CN203014488U (en) Distributed intelligent power distribution terminal
CN203071637U (en) DC power supply connection control apparatus
CN107611794A (en) Fire-fighting power distribution cabinet based on bas and fas monitoring systems
CN204065322U (en) For the failure diagnosis apparatus of ring main unit distribution terminal
CN103178599A (en) Shore-based power supply operation and support system of seafloor observation network
CN104065156B (en) A kind of input wires device that intersects in parallel of 2N power-supply system
CN110943476A (en) Multi-stage UPS parallel distributed control system and wiring circuit thereof
CN202817874U (en) Uninterruptible power supply (UPS) redundant system
CN105553089A (en) Machine room illumination power supply and distribution system and power supply method
CN203800696U (en) Parallel intersection input wiring apparatus for 2N power supply system
CN211127297U (en) AC/DC screen power supply circuit
CN203326904U (en) Intelligent high-frequency switching power supply system
CN208608963U (en) Two-way photovoltaic energy storage one invertor operation state display device
CN201601529U (en) Power supply system for electric power communication computer room
CN208285069U (en) A kind of transformer substation communication power supply monitoring system
CN106527610A (en) Whole cabinet server and power module thereof
CN203352281U (en) Automatic measuring and controlling device for electricity distribution network
CN201854047U (en) Uninterrupted power supply (UPS) connecting device
CN206364577U (en) A kind of distributed electricity system of looped network case
CN206211655U (en) A kind of domestic power supply auto-parallel device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160706

Termination date: 20161227

CF01 Termination of patent right due to non-payment of annual fee