CN205368276U - Gasifier cross prevents that stifled ash sweeps device - Google Patents

Gasifier cross prevents that stifled ash sweeps device Download PDF

Info

Publication number
CN205368276U
CN205368276U CN201620084658.XU CN201620084658U CN205368276U CN 205368276 U CN205368276 U CN 205368276U CN 201620084658 U CN201620084658 U CN 201620084658U CN 205368276 U CN205368276 U CN 205368276U
Authority
CN
China
Prior art keywords
cross
tee
gasification furnace
nitrogen
soot blowing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620084658.XU
Other languages
Chinese (zh)
Inventor
李社洲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Chao Shun Of Boiler Group Boiler Plant Manufacturing Co Ltd
Original Assignee
Wuhan Chao Shun Of Boiler Group Boiler Plant Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Chao Shun Of Boiler Group Boiler Plant Manufacturing Co Ltd filed Critical Wuhan Chao Shun Of Boiler Group Boiler Plant Manufacturing Co Ltd
Priority to CN201620084658.XU priority Critical patent/CN205368276U/en
Application granted granted Critical
Publication of CN205368276U publication Critical patent/CN205368276U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

The utility model relates to a gasifier cross prevents that stifled ash sweeps device, comprises a housin, the cross that the level that is equipped with in the casing set up, the casing outside is equipped with nitrogen gas provides the device, nitrogen gas provides the device and passes through the connecting pipe connection three -way pipe in the casing, the three -way pipe blows grey spout device through the pipe connection to a plurality of, blow grey spout device with the cross corresponds the setting, blow grey spout unit bit in the top of cross, each it includes a spray tube and one spouts the core to blow grey spout device, the spray tube is just right the cross sets up. On from spray tube spun nitrogen gas direct injection to the cross to clear away the dust on the cross, solved the stifled grey coking phenomenon of cross, this operation need not stop the gasifier operation to gasifier cycle of operation has been prolonged.

Description

Gasification furnace cross anti-blocking ash blow device
Technical field
This utility model relates to a kind of gasification furnace cross anti-blocking ash blow device, for gasification furnace.
Background technology
Because of cross place dust stratification after existing gasifier operation a period of time, and affect gasifier operation, ultimately result in blowing out, when carrying out clearing up, not only waste time and energy, and expense is high.Each blowing out, blow-on direct cost are no less than 1,000,000 yuan.
It is therefore desirable to design a kind of gasification furnace cross anti-blocking ash blow device, to overcome the problems referred to above.
Utility model content
The purpose of this utility model is in that to overcome the defect of existing structure, it is provided that one can extend the gasifier operation cycle, solves the gasification furnace cross anti-blocking ash blow device of cross stifled ash coking phenomenon.
This utility model is achieved in that
This utility model provides a kind of gasification furnace cross anti-blocking ash blow device, including a housing, horizontally disposed cross tee it is provided with in described housing, described hull outside is provided with nitrogen and provides device, described nitrogen provides device to connect the tee T in described housing by connecting tube, described tee T is connected to multiple soot blowing spout device by pipeline, described soot blowing spout device and described cross tee are correspondingly arranged, described soot blowing spout device is positioned at the top of described cross tee, each described soot blowing spout device includes a jet pipe and a spray core, described cross tee is just arranged by described jet pipe.
Further, described nitrogen provides the position that device is connected with described housing to be provided with sleeve pipe.
Further, described nitrogen provides the pipeline that device is connected with described housing to be provided with nitrogen adjustment valve.
Further, the quantity of described tee T is two, and each tee T is connected to two soot blowing spout devices.
Further, the inwall of described housing is provided with water-cooling wall.
Further, described cross tee includes four steel pipes, and four steel pipes are that cross is arranged.
This utility model has the advantages that
Described soot blowing spout device is positioned at the top of described cross tee, and each described soot blowing spout device includes a jet pipe and a spray core, and described cross tee is just arranged by described jet pipe.It is directly injected to cross tee from the nitrogen of jet pipe ejection, thus the dust removed on cross tee, solves cross stifled ash coking phenomenon;This operation need not stop gasification furnace operation, thus extending the gasifier operation cycle.
Accompanying drawing explanation
In order to be illustrated more clearly that this utility model embodiment or technical scheme of the prior art, the accompanying drawing used required in embodiment or description of the prior art will be briefly described below, apparently, accompanying drawing in the following describes is only embodiments more of the present utility model, for those of ordinary skill in the art, under the premise not paying creative work, it is also possible to obtain other accompanying drawing according to these accompanying drawings.
The front view of the gasification furnace cross anti-blocking ash blow device that Fig. 1 provides for this utility model embodiment;
The top view of the gasification furnace cross anti-blocking ash blow device that Fig. 2 provides for this utility model embodiment.
Detailed description of the invention
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is clearly and completely described, it is clear that described embodiment is only a part of embodiment of this utility model, rather than whole embodiments.Based on the embodiment in this utility model, all other embodiments that those of ordinary skill in the art obtain under the premise not making creative work, broadly fall into the scope of this utility model protection.
Such as Fig. 1 and Fig. 2, this utility model embodiment provides a kind of gasification furnace cross anti-blocking ash blow device, including a housing 1, is provided with horizontally disposed cross tee 2 in described housing 1, being provided with nitrogen outside described housing 1 and provide device (not shown), nitrogen provides device to be gasification furnace nitrogen header.In this preferred embodiment, the inwall of described housing 1 is provided with water-cooling wall 8.
Such as Fig. 1 and Fig. 2, described nitrogen provides device to connect the tee T 6 in described housing 1 by connecting tube 5, and described nitrogen provides the position that device is connected with described housing 1 to be provided with sleeve pipe 4.Described nitrogen provides the pipeline that device is connected with described housing 1 to be provided with nitrogen adjustment valve 3, for regulating the flow of provided nitrogen.In this preferred embodiment, the quantity of described nitrogen adjustment valve 3 is two, and namely described nitrogen provides device to connect the inside of described housing 1 by two pipelines.
Such as Fig. 1 and Fig. 2, described tee T 6 is connected to multiple soot blowing spout device 7 by pipeline, and described soot blowing spout device 7 is correspondingly arranged with described cross tee 2, and described cross tee 2 includes four steel pipes, four steel pipes are that cross is arranged, and a soot blowing spout device 7 and a steel pipe are correspondingly arranged.Described soot blowing spout device 7 is positioned at the top of described cross tee 2, each described soot blowing spout device 7 includes a jet pipe (i.e. nozzle) and a spray core (controlling the part of internal gas flow), described cross tee 2 is just arranged by described jet pipe, for by nitrogen jet to cross tee 2, thus the dust on cross tee 2 is purged, solve cross stifled ash coking phenomenon.
Such as Fig. 1 and Fig. 2, in this preferred embodiment, the quantity of described tee T 6 is two, and each tee T 6 is connected to two soot blowing spout devices 7.The nitrogen that one opening of described tee T 6 connects outside by connecting tube 5 provides device, and Open Side Down arranges for two other, and is connected to two soot blowing spout devices 7 respectively through pipeline.
In concrete application, nitrogen provides the nitrogen pressure that device provides to be 0.6MP, after installing soot blowing spout device 7 additional, can reach 1.8MP from the nitrogen pressure of jet pipe ejection, it is possible to cross tee 2 tube wall is purged, reaches the purpose of not dust stratification noncoking.
In sum, described gasification furnace cross anti-blocking ash blow device is directly injected on cross tee by the nitrogen sprayed from jet pipe, thus the dust removed on cross tee, solves cross stifled ash coking phenomenon;This operation need not stop gasification furnace operation, thus extending the gasifier operation cycle.
The foregoing is only preferred embodiment of the present utility model; not in order to limit this utility model; all within spirit of the present utility model and principle, any amendment of making, equivalent replacement, improvement etc., should be included within protection domain of the present utility model.

Claims (6)

1. a gasification furnace cross anti-blocking ash blow device, including a housing, horizontally disposed cross tee it is provided with in described housing, it is characterized in that, described hull outside is provided with nitrogen and provides device, described nitrogen provides device to connect the tee T in described housing by connecting tube, described tee T is connected to multiple soot blowing spout device by pipeline, described soot blowing spout device and described cross tee are correspondingly arranged, described soot blowing spout device is positioned at the top of described cross tee, each described soot blowing spout device includes a jet pipe and a spray core, described cross tee is just arranged by described jet pipe.
2. gasification furnace cross as claimed in claim 1 anti-blocking ash blow device, it is characterised in that: described nitrogen provides the position that device is connected with described housing to be provided with sleeve pipe.
3. gasification furnace cross as claimed in claim 1 anti-blocking ash blow device, it is characterised in that: described nitrogen provides the pipeline that device is connected with described housing to be provided with nitrogen adjustment valve.
4. gasification furnace cross as claimed in claim 1 anti-blocking ash blow device, it is characterised in that: the quantity of described tee T is two, and each tee T is connected to two soot blowing spout devices.
5. gasification furnace cross as claimed in claim 1 anti-blocking ash blow device, it is characterised in that: the inwall of described housing is provided with water-cooling wall.
6. gasification furnace cross as claimed in claim 1 anti-blocking ash blow device, it is characterised in that: described cross tee includes four steel pipes, and four steel pipes are that cross is arranged.
CN201620084658.XU 2016-01-28 2016-01-28 Gasifier cross prevents that stifled ash sweeps device Expired - Fee Related CN205368276U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620084658.XU CN205368276U (en) 2016-01-28 2016-01-28 Gasifier cross prevents that stifled ash sweeps device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620084658.XU CN205368276U (en) 2016-01-28 2016-01-28 Gasifier cross prevents that stifled ash sweeps device

Publications (1)

Publication Number Publication Date
CN205368276U true CN205368276U (en) 2016-07-06

Family

ID=56270423

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620084658.XU Expired - Fee Related CN205368276U (en) 2016-01-28 2016-01-28 Gasifier cross prevents that stifled ash sweeps device

Country Status (1)

Country Link
CN (1) CN205368276U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112032748A (en) * 2020-07-29 2020-12-04 华电电力科学研究院有限公司 Circular lower spray pipe type nozzle of coal-fired boiler pneumatic soot blowing system and soot blowing method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112032748A (en) * 2020-07-29 2020-12-04 华电电力科学研究院有限公司 Circular lower spray pipe type nozzle of coal-fired boiler pneumatic soot blowing system and soot blowing method

Similar Documents

Publication Publication Date Title
CN201880706U (en) Cleaning machine
CN205368276U (en) Gasifier cross prevents that stifled ash sweeps device
CN204201367U (en) A kind of small-bore pipeline on-line production send blocking device
CN202612770U (en) Connecting pipe for opening ball valve with double blow off mouths
CN201739627U (en) Dredging and anti-sticking device for gas pipe valve
CN205067134U (en) Buggy pipe sample sealing joint
CN203768385U (en) Nitrogen gas purging device for blast furnace coal gas pipeline
CN201532145U (en) Spray cooling rotator of cooling tower
CN202356171U (en) Water injection device of vertical mill
CN206897994U (en) Carbon distribution cleaning device inside a kind of burner noz(zle)
CN203175599U (en) Wind-water linkage spraying dust settling device
CN208431762U (en) A kind of gas fired-boiler low NO
CN102380450B (en) Water spraying device for vertical mill
CN206924711U (en) Blender back purge system
CN219681526U (en) Device for preventing blockage of flame arrester of gas pipeline
CN207715175U (en) A kind of tunnel dedusting, air feed, water supply installation
CN204878872U (en) A U type equipment for water seal
CN204373431U (en) Water-stop intercepts flue gas mechanism
CN203862108U (en) High-temperature-resistant desulfurization tower
CN203877928U (en) Urea pyrolysis furnace and spray gun transition connecting device thereof
CN201933100U (en) Blast furnace belly pipe with double guns
CN204958836U (en) Gasification nozzle cooling line device
CN204251640U (en) Air-casing is utilized to prevent the fire door flue of slagging scorification
CN205559191U (en) Gasifier water installations
CN205796793U (en) A kind of sack cleaner pulse gas bag air feeder structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160706

Termination date: 20200128