CN205316357U - Steel ball deashing lock gas seal device - Google Patents

Steel ball deashing lock gas seal device Download PDF

Info

Publication number
CN205316357U
CN205316357U CN201521032022.2U CN201521032022U CN205316357U CN 205316357 U CN205316357 U CN 205316357U CN 201521032022 U CN201521032022 U CN 201521032022U CN 205316357 U CN205316357 U CN 205316357U
Authority
CN
China
Prior art keywords
steel ball
storehouse
ball storehouse
boiler
deashing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201521032022.2U
Other languages
Chinese (zh)
Inventor
刘海永
赵尚武
王瑞军
刘光耀
马剑博
王学术
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ruixing Low Carbon Technology Jiangsu Co ltd
Original Assignee
Beijing Redun Energy Saving Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Redun Energy Saving Technology Co Ltd filed Critical Beijing Redun Energy Saving Technology Co Ltd
Priority to CN201521032022.2U priority Critical patent/CN205316357U/en
Application granted granted Critical
Publication of CN205316357U publication Critical patent/CN205316357U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

The utility model discloses a steel ball deashing lock gas seal device, its aim at provide one kind and carry out the deashing to exhaust -heat boiler, guarantee boiler heat exchange efficiency and life and realize the sealed of boiler system through sealing air -look device, avoid the air that leaks in, guarantee the steel ball deashing lock gas seal device of the safe operation of boiler, the device is including setting up in the second steel ball storehouse and the third steel ball storehouse of boiler upstream and downstream, third steel ball storehouse below is provided with the shale shaker, shale shaker below is equipped with ashes storage silo, and the side is equipped with fourth steel ball storehouse, fourth steel ball storehouse is passed through steel ball direction chute and is communicate to steel ball feeding trolley, steel ball feeding trolley sets up on the feeding trolley track, feeding trolley guide rail top is equipped with the feeding trolley guided way, the feeding trolley guided way is located to correspond and is provided with first steel ball storehouse, first steel ball storehouse below corresponds second steel ball storehouse, steel ball feeding trolley passes through the rope and connects the automatic control hoist engine.

Description

Steel ball deashing sealing device
Technical field
This utility model relates to metallurgical technical field of dust removal equipment, particularly relates to a kind of steel ball deashing sealing device.
Background technology
Metallurgy industry pyrometallurgical smelting process smelting process produces a large amount of containing dust high-temperature flue gas, some technique toxic gas, needs recycling. As steelmaking converter smelting process produces the high-temperature flue gas containing CO, reclaim qualified flue gas and use as coal gas of converter.
Due in flue gas containing higher concentration dust, adopt common waste heat boiler that boiler internal boiler tube gap can be caused to block, thus causing that boiler lost efficacy. This kind of flue gas of process is generally adopted Venturi tube and realizes dedusting and cooling at present, but can produce a large amount of mud, Treatment of Sludge long flow path, contaminated environment; Or adopt conventional dust removal device dedusting after being mixed into large quantity of air cooling, but the flue gas containing fuel gas can not be mixed into air, otherwise can set off an explosion impact safety in production.
Summary of the invention
The technical problems to be solved in the utility model is to provide one and waste heat boiler is carried out deashing, ensure boiler heat exchange efficiency and service life and realized the sealing of steam generator system by dense block device of air, avoid leaking-in air, it is ensured that the steel ball deashing sealing device of the safe operation of boiler.
For reaching above-mentioned purpose, this utility model one steel ball deashing sealing device, described device includes the second steel ball storehouse and the 3rd steel ball storehouse that are arranged at boiler upstream and downstream, described 3rd steel ball storehouse is arranged below vibrosieve, described vibrosieve is connected with ash-storing bin, side is provided with the 4th steel ball storehouse, described 4th steel ball storehouse is communicated to steel ball feeding cart by steel ball guide chutes, described steel ball feeding cart is arranged on feeding cart track, described feeding cart guide rail top is provided with feeding cart guided way, described feeding cart guided way place is correspondingly arranged on the first steel ball storehouse, corresponding described second steel ball storehouse below described first steel ball storehouse, described steel ball feeding cart automatically controls hoist engine by rope connection.
Wherein said first steel ball storehouse, the second steel ball storehouse, the 3rd steel ball storehouse and the 4th steel ball storehouse are respectively arranged with steel ball storehouse clock valve and hydraulic mandril, and hydraulic mandril realizes the switch in steel ball storehouse for controlling either on or off steel ball storehouse clock valve.
Wherein said feeding cart guided way is arranged over assembly pulley, and described rope end is walked around and automatically controlled hoist engine described in the connection of described assembly pulley.
Wherein said boiler is connected with lower portion thereof ash-storing bin, and described lower portion thereof ash-storing bin is arranged below described 3rd steel ball storehouse.
Wherein said 3rd steel ball storehouse is provided with boiler unloading valve, and described boiler unloading valve connects a hydraulic mandril, and described boiler unloading valve is provided with the pilot seal storehouse of a described lower portion thereof ash-storing bin of connection.
Wherein said pilot seal storehouse adopts steel chain guiding transmission.
Wherein said rope is steel wire rope.
This utility model steel ball deashing sealing device difference from prior art is in that this utility model achieves following technique effect:
1, this utility model device is alternately opened by hoist engine and steel ball storehouse, waste heat boiler top and the bottom and clock valve, realize the circulation of steel ball, steel ball mutually collides the dust collision removing and vibration removing that will accumulate on boiler tube in waste heat boiler with boiler tube in dropping process simultaneously, it is achieved removing ash of boiler;
2, this utility model device replaces opening and closing by steel ball storehouse and the steel ball storehouse clock valve of boiler top and the bottom, it is achieved the sealing of waste heat boiler.
3, this utility model by adopting steel chain guiding transmission to pilot seal storehouse, by hydraulic mandril, controls bell type valve, it is prevented that high-temperature smoke and the impact of steel ball, equipment is high temperature resistant, wearability. Sealing strictly definitely up to standard to preventing leaking into of outside air, isolation boiler is total closed type structure with ball dust cabin, it is ensured that boiler smoke is smooth and easy, and heating surface area deashing is clean, and heat exchange is stable, steam reliable.
Below in conjunction with accompanying drawing, the utility model is described in further detail.
Accompanying drawing explanation
Fig. 1 is the structural representation of this utility model steel ball deashing sealing device.
Description of reference numerals: 1-ash-storing bin; 2-the 4th steel ball storehouse clock valve; 3-vibrosieve; 4-the 3rd steel ball storehouse clock valve; 5,11,13,21,23-hydraulic mandril; 6-pilot seal storehouse; 7-lower portion thereof ash-storing bin; 8-boiler; 9-the second steel ball storehouse clock valve; 10-the second steel ball storehouse; 12-the first steel ball storehouse clock valve; 14-steel ball feeding cart; 15-assembly pulley; 16-feeding cart guided way; 17-the first steel ball storehouse; 18-steel wire rope; 19-feeding cart track; 20-boiler unloading valve; 22-the 3rd steel ball storehouse; 24-the 4th steel ball storehouse; 25-steel ball guide chutes; 26-automatically controls hoist engine.
Detailed description of the invention
Below in conjunction with drawings and Examples, to this utility model, above-mentioned and other technical characteristic and advantage are described in more detail.
As shown in Figure 1, this utility model one steel ball deashing sealing device, described device includes the second steel ball storehouse 10 being arranged at boiler 8 upstream, boiler 8 is connected with lower portion thereof ash-storing bin 7, lower portion thereof ash-storing bin 7 is connected with the 3rd steel ball storehouse 22, and the 3rd steel ball storehouse 22 is provided with boiler unloading valve 20, and boiler unloading valve 20 connects a hydraulic mandril 5, boiler unloading valve 20 is provided with the pilot seal storehouse 6 of a connection lower portion thereof ash-storing bin 7, and pilot seal storehouse 6 adopts steel chain guiding transmission, 3rd steel ball storehouse 22 is arranged below vibrosieve 3, vibrosieve 3 is connected with ash-storing bin 1, vibrosieve 3 side is provided with the 4th steel ball storehouse 24, 4th steel ball storehouse 24 is communicated to steel ball feeding cart 14 by steel ball guide chutes 25, steel ball feeding cart 14 is arranged on feeding cart track 19, feeding cart guide rail 19 top is provided with feeding cart guided way 16, feeding cart guided way 16 place is correspondingly arranged on the first steel ball storehouse 17, corresponding second steel ball storehouse 10 below first steel ball storehouse 17, feeding cart guided way 16 is arranged over assembly pulley 15, after steel ball feeding cart 14 walks around assembly pulley 15 by steel wire rope 18, connection automatically controls hoist engine 26,
Wherein the first steel ball storehouse 22, the 17, second steel ball storehouse the 10, the 3rd, steel ball storehouse and the 4th steel ball storehouse 24 are respectively arranged with first steel ball storehouse clock valve the 12, second steel ball storehouse clock valve the 9, the 3rd steel ball storehouse clock valve 4 and the 4th steel ball storehouse clock valve 2 and hydraulic mandril 13,11,21 and 23, and hydraulic mandril realizes the switch in steel ball storehouse for controlling either on or off steel ball storehouse clock valve.
Work process:
Open the 4th steel ball storehouse clock valve 2 by hydraulic mandril 23 and steel ball is put into steel ball feeding cart 14, automatically control hoist engine 26 steel wire rope 18 and steel ball feeding cart 14 is promoted to boiler top, realizing steel ball feeding cart 14 by feeding cart guided way 16 to overturn steel ball loads the first steel ball storehouse 17, steel ball feeding cart 14 returns to bottom and continues steel loading ball; Controlled to open the first steel ball storehouse clock valve 12 by hydraulic mandril 13, steel ball is loaded in the second steel ball storehouse 10, hydraulic mandril 13 promotes the first steel ball storehouse clock valve 12 and closes, and seals in the second steel ball storehouse 10, repeats above-mentioned charging action to the second steel ball storehouse 10 and reaches to set steel loading ball amount;
Controlled the second steel ball storehouse clock valve 9 by hydraulic mandril 11 to open, 10 steel balls in the second steel ball storehouse are put into boiler and carries out deashing, after steel ball drains, close the second steel ball storehouse clock valve 9, it is ensured that boiler seal;
In boiler, steel ball falls together with the dust removed, and major part is taken away by flue gas, and little part dust and steel ball drop temporarily store to lower portion thereof ash-storing bin 7;
Hydraulic mandril 5 controls boiler unloading valve 20 and opens, and the steel ball of lower portion thereof ash-storing bin 7 and dust are put into the 3rd steel ball storehouse 22, puts into the 3rd steel ball storehouse 22 when the weight of dust and steel ball reaches setting value, closes boiler unloading valve 20, it is ensured that boiler seal state;
Opening the 3rd steel ball storehouse clock valve 4 by hydraulic mandril 21, the steel ball in the 3rd steel ball storehouse 22 and dust discharged, Vibration on Start-up sieve 3 realizes separating of steel ball and dust simultaneously, and after separation, steel ball loads the 4th steel ball storehouse 24, and dust puts into ash-storing bin 1, regularly transports;
Lower portion thereof ash-storing bin 7 outlet arranges pilot seal storehouse 6, it is ensured that boiler unloading valve 20 opening and closing controlled by hydraulic mandril 5 is not leaked out.
Said process circulation carries out, it is achieved boiler dust is removed, it is ensured that boiler safety, trouble-free operation.
Embodiment described above is only that preferred implementation of the present utility model is described; not scope of the present utility model is defined; under the premise designing spirit without departing from this utility model; various deformation that the technical solution of the utility model is made by those of ordinary skill in the art and improvement, all should fall in the protection domain that this utility model claims are determined.

Claims (7)

1. a steel ball deashing sealing device, it is characterized in that: described device includes being arranged at the second steel ball storehouse and the 3rd steel ball storehouse of boiler upstream and downstream, described 3rd steel ball storehouse is arranged below vibrosieve, described vibrosieve is connected with ash-storing bin, side is provided with the 4th steel ball storehouse, described 4th steel ball storehouse is communicated to steel ball feeding cart by steel ball guide chutes, described steel ball feeding cart is arranged on feeding cart track, described feeding cart guide rail top is provided with feeding cart guided way, described feeding cart guided way place is correspondingly arranged on the first steel ball storehouse, corresponding described second steel ball storehouse below described first steel ball storehouse, described steel ball feeding cart automatically controls hoist engine by rope connection.
2. steel ball deashing sealing device according to claim 1, it is characterized in that: described first steel ball storehouse, the second steel ball storehouse, the 3rd steel ball storehouse and the 4th steel ball storehouse are respectively arranged with steel ball storehouse clock valve and hydraulic mandril, hydraulic mandril realizes the switch in steel ball storehouse for controlling either on or off steel ball storehouse clock valve.
3. steel ball deashing sealing device according to claim 1, it is characterised in that: described feeding cart guided way is arranged over assembly pulley, and described rope end is walked around and automatically controlled hoist engine described in the connection of described assembly pulley.
4. steel ball deashing sealing device according to claim 1, it is characterised in that: described boiler is connected with lower portion thereof ash-storing bin, and described lower portion thereof ash-storing bin is arranged below described 3rd steel ball storehouse.
5. steel ball deashing sealing device according to claim 4, it is characterized in that: described 3rd steel ball storehouse is provided with boiler unloading valve, described boiler unloading valve connects a hydraulic mandril, and described boiler unloading valve is provided with the pilot seal storehouse of a described lower portion thereof ash-storing bin of connection.
6. steel ball deashing sealing device according to claim 5, it is characterised in that: described pilot seal storehouse adopts steel chain guiding transmission.
7. steel ball deashing sealing device according to claim 1, it is characterised in that: described rope is steel wire rope.
CN201521032022.2U 2015-12-14 2015-12-14 Steel ball deashing lock gas seal device Active CN205316357U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521032022.2U CN205316357U (en) 2015-12-14 2015-12-14 Steel ball deashing lock gas seal device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521032022.2U CN205316357U (en) 2015-12-14 2015-12-14 Steel ball deashing lock gas seal device

Publications (1)

Publication Number Publication Date
CN205316357U true CN205316357U (en) 2016-06-15

Family

ID=56184903

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521032022.2U Active CN205316357U (en) 2015-12-14 2015-12-14 Steel ball deashing lock gas seal device

Country Status (1)

Country Link
CN (1) CN205316357U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110597217A (en) * 2019-10-17 2019-12-20 江苏利港电力有限公司 Intelligent automatic ash loading system and automatic ash loading method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110597217A (en) * 2019-10-17 2019-12-20 江苏利港电力有限公司 Intelligent automatic ash loading system and automatic ash loading method thereof

Similar Documents

Publication Publication Date Title
CN102952908B (en) Equipment and method for steel slag air quenching and waste heat recycling
CN106395824A (en) Continuous carbon disulfide production process and device adopting coke method
CN202575416U (en) Pneumatic transmission and blast furnace injection device for coke oven fly ash
CN205316357U (en) Steel ball deashing lock gas seal device
CN203428534U (en) Blast furnace dry dedusting dense phase pneumatic conveying system
CN211035805U (en) Top-mounted coke oven coal-charging smoke treatment system
CN2786449Y (en) Ash and slag remover of CFB refuse incinerator
CN105217631B (en) The method and its system of clean environment firendly semicoke formula continuous production carbon disulfide
CN111112287A (en) Hazardous waste recycling comprehensive treatment system adopting electric arc furnace and treatment method thereof
CN209763052U (en) Circulating fluidized bed boiler return ash conveying structure
CN205926545U (en) Used smoke and dust device that removes of carbon disulfide production line
CN209782653U (en) System for preventing pyrolysis furnace heat from flowing back during solid waste feeding
CN105838444B (en) A kind of fluidized gasification bottom slag cooling conveying system
CN107128708A (en) Ash silo ash-discharging device
CN110746994A (en) Coupling system and process for coal-charging smoke treatment and coke oven flue gas purification of top-loading coke oven
CN206958953U (en) One kind fire prevention defeated coal device of Wind-Pressure Resistance
CN206751860U (en) The simple third dedusting system of converter based on a tank
CN106216342B (en) Dust-removing device used in carbon disulphide production line and the smoke abatement system constituted
CN106978518B (en) Simple three-time dedusting system and method for converter based on one-pot system
CN211035810U (en) Coupling system for coal-charging smoke treatment and coke oven flue gas purification of top-loading coke oven
KR100752126B1 (en) System for detecting and controling initial trouble in the cooling chamber for coke dry quencher
CN205974575U (en) Unloading pipe nitrogen air valve device
CN212451313U (en) Full-automatic dustless no-leakage coal feeding set equipment of coal gas making equipment
CN218511299U (en) High-temperature metal dust cooling device
CN205710608U (en) A kind of fluidized gasification bottom slag cooling conveying system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170414

Address after: 014000 East District, the Inner Mongolia Autonomous Region, Baotou East Street, No. 88, building No. two, No. 7

Patentee after: Ma Jianbo

Address before: 102627 Beijing Xinghua Street (No. two), building 3, building 21, floor 1, 2511

Patentee before: BEIJING REDUN ENERGY SAVING TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190522

Address after: 014030 Software Park Building C508, Rare Earth High-tech Zone, Baotou City, Inner Mongolia Autonomous Region

Patentee after: Inner Mongolia heat shield energy saving Technology Co.,Ltd.

Address before: 014000 No. 88, Building 7, East 2, Tongshun Street, Donghe District, Baotou City, Inner Mongolia Autonomous Region

Patentee before: Ma Jianbo

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200826

Address after: Room 503-2, block a, national innovation and entrepreneurship demonstration base, Baotou Rare Earth Development Zone, Inner Mongolia Autonomous Region 026000

Patentee after: Inner Mongolia Yuanqi Technology Co.,Ltd.

Address before: 014030 C508 Software Park, rare-earth high tech Zone, Baotou, the Inner Mongolia Autonomous Region

Patentee before: Inner Mongolia heat shield energy saving Technology Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221018

Address after: 014000 Room 409, Office Building, No. 102, Bayantala West Street, Donghe District, Baotou, Inner Mongolia Autonomous Region

Patentee after: Inner Mongolia heat shield energy saving Technology Co.,Ltd.

Address before: Room 503-2, block a, national innovation and entrepreneurship demonstration base, Rare Earth Development Zone, Baotou City, Inner Mongolia Autonomous Region 026000

Patentee before: Inner Mongolia Yuanqi Technology Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230302

Address after: Room b027, Floor 3, Building 2, Wucheng Industrial Park, Zhenglu Town, Tianning District, Changzhou City, Jiangsu Province, 213000

Patentee after: Ruixing Low Carbon Technology (Jiangsu) Co.,Ltd.

Address before: 014000 Room 409, Office Building, No. 102, Bayantala West Street, Donghe District, Baotou, Inner Mongolia Autonomous Region

Patentee before: Inner Mongolia heat shield energy saving Technology Co.,Ltd.

TR01 Transfer of patent right