CN205298825U CN201620043416.6U CN201620043416U CN205298825U CN 205298825 U CN205298825 U CN 205298825U CN 201620043416 U CN201620043416 U CN 201620043416U CN 205298825 U CN205298825 U CN 205298825U
Authority
CN
China
Prior art keywords
pipe
concrete
pipe collar
vertical
foundation bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620043416.6U
Other languages
Chinese (zh)
Inventor
张正海
宋功业
鲁辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Institute of Architectural Technology
Jiangsu Jianzhu Institute
Original Assignee
Jiangsu Institute of Architectural Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Institute of Architectural Technology filed Critical Jiangsu Institute of Architectural Technology
Priority to CN201620043416.6U priority Critical patent/CN205298825U/en
Application granted granted Critical
Publication of CN205298825U publication Critical patent/CN205298825U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

Concrete conveying pipe corner support is concrete conveying pipe said during for the pump sending concrete reliable and stable design, belongs to building construction field, concrete conveying pipe corner support comprises horizontal stand and vertical support, the horizontally concrete conveying pipe way of the fixed corner of horizontal stand, the vertical concrete conveying pipe way of the fixed corner of vertical support, the horizontal stand comprises ferrule no. 1, rag bolt no. 1, buttress, a ferrule ring cover concreties with the buttress through rag bolt no. 1 in horizontal concrete conveying pipe's outside, vertical support comprises ferrule no. 2, rag bolt no. 2, ferrule second ring cover concreties with vertical support thing through rag bolt no. 2 in vertical concrete conveying pipe's outside, the beneficial effects of the utility model are that conveyer pipe in the time of can making the pump sending concrete is reliable in the corner transmission, guarantees the concrete pumping construction and can go on smoothly.

Description

Concrete delivery pipe corner support
Technical field
This utility model is concrete delivery pipe corner support, concrete conveying pipe reliable and stable when being for pump concrete and design, belong to the realm of building construction.
Background technology
During pumping concrete construction, the concrete needing pumping is applied high pressure by concrete pump, by concrete delivery pipe, is pumped into concreting place and builds; The essential condition of pump concrete is that concrete conveying pipe joint sealing is reliable, once concrete delivery pipe joint area imprecision, gas leak phenomenon occurs, and concrete will be unable to be pumped by concrete delivery pipe; During due to pumping concrete construction, the concrete needing pumping is applied high pressure by concrete pump, work progress often easily leaks gas in pipe joint place of rotation angle position, cause that concrete cannot pump, the concrete delivery pipe corner support that this utility model provides, it is possible to solve the corner imprecise problem of concrete conveyance pipe joint.
Utility model content
The specific practice of this programme is:
As shown in Figures 1 to 5, fixed at concrete delivery pipe rotation angle position, so that it may so that corner concrete delivery pipe jointing reliably seals, air tight; Concrete delivery pipe corner support is made up of horizontal stand 1 and vertical supports 2; Horizontal stand 1 fixes the concrete conveying pipe of the level of corner, and vertical supports 2 fixes the vertical concrete conveying pipe of corner, and horizontal stand 1 is made up of pipe collar 1, foundation bolt 1, buttress 13; Pipe collar 1 ring set carries the outside of pipe 3 at Horizontal concrete, is consolidated by foundation bolt 1 and buttress 13; Vertical supports 2 is made up of pipe collar 2 21, foundation bolt 2 22; Pipe collar 2 21 ring set, in the outside of vertical concrete delivery pipe 3, is consolidated by foundation bolt 2 22 and vertical support 4;
Horizontal stand 1 and a dot center of vertical supports 2, be respectively positioned on straight tube position, distance straight tube and union elbow place 200-500 millimeter; Under external force, the buttress 13 of horizontal stand 1 is connected reliably with ground, is not subjected to displacement; Vertical supports 2 is connected reliably with vertical support 4, is not subjected to displacement.
Pipe collar 1 and pipe collar 2 21 are arc strip-shaped members, and the steel plate that preferential recommendation adopts thickness to be 6-12 millimeters thick makes; Pipe collar 1 and pipe collar 2 21 all include arc section, vertical section and horizontal segment three part (see figure 4); The radian at restrained position is identical with the pipeline of concrete delivery pipe 3 respectively with the radian of pipe collar 2 21 arc section for pipe collar 1, and pipe collar 1 is identical with the overall diameter of the diameter of pipe collar 2 21 arc section Yu concrete delivery pipe 3; Pipe collar 1 is connected with arc section with in the vertical section of pipe collar 2 21, under be connected with horizontal segment, be highly 30-50 millimeter; Pipe collar 1 is connected with the bottom of vertical section with horizontal segment one end of pipe collar 2 21, and the length of horizontal segment is 80-100 millimeter; Having bolt hole in the horizontal segment middle part of pipe collar 1 with pipe collar 2 21, the diameter of bolt hole is the big 0-2 millimeter than with the diameter dimension of foundation bolt 1 and foundation bolt 2 22 screw rod respectively.
Foundation bolt 1 and foundation bolt 2 22 are the rod-like members with double nut Yu pad, and preferential recommendation adopts the reinforcement fabrication of diameter 12-20 millimeter; The length of foundation bolt 1 is 100-200 millimeter, and reach is 40-60 millimeter, and pitch is 2-2.5 millimeter, it does not have the lower half of screw thread is embedded in buttress 13, length of embedment 60-140 millimeter; The first half of foundation bolt 1 exposes the foundation bolt outside buttress 13; Foundation bolt 2 22 is length is 100-200 millimeter, and reach is 40-60 millimeter, and pitch is 2-2.5 millimeter, and kink external diameter is the expansion bolt of 24-40, is arranged on by its lower semisection in vertical support 4 during work, and upper semisection is exposed at the surface of vertical support 4.
Buttress 13 is length is 500-600 millimeter, and width is 400-500 millimeter, is highly the block parts of the concrete of 300-400 millimeter or masonry class; The centre distance of buttress 13 is 2-5 rice, and the length direction of buttress 13 is consistent with the centerline direction of concrete delivery pipe 3, is fixed thereon by concrete delivery pipe 3 by foundation bolt 1 during with work; The centrage of buttress 13 keeps consistent with the centrage of concrete delivery pipe 3.
Conveying pipe when the beneficial effects of the utility model are to make pump concrete on the corner transmits reliably, it is ensured that Concrete Pumping Construction can be smoothed out.
Accompanying drawing explanation
Fig. 1 concrete delivery pipe corner support schematic diagram;
Fig. 2 concrete delivery pipe horizontal stand schematic diagram;
Fig. 3 concrete delivery pipe vertical supports schematic diagram;
The vertical concrete conveyance pipe holder schematic diagram of Fig. 4;
Fig. 5 Horizontal concrete conveying pipe holder schematic diagram;
In figure: 1-horizontal stand; 11-pipe collar one; 12-foundation bolt one; 13-buttress; 2-vertical supports; 21-pipe collar two; 22-foundation bolt two; 3-concrete delivery pipe; The vertical support of 4-.
Detailed description of the invention
Embodiment
Certain engineering adopts concrete delivery pipe horizontal stand as shown in Figures 1 to 5 that the concrete delivery pipe of corner is fixed, and makes corner concrete delivery pipe jointing reliably seal, air tight;
Concrete delivery pipe corner support is made up of horizontal stand 1 and vertical supports 2; Horizontal stand 1 fixes the concrete conveying pipe of the level of corner, and vertical supports 2 fixes the vertical concrete conveying pipe of corner, and horizontal stand 1 is made up of pipe collar 1, foundation bolt 1, buttress 13; Pipe collar 1 ring set carries the outside of pipe 3, the diameter of concrete delivery pipe 3 120 millimeters at Horizontal concrete, is consolidated by foundation bolt 1 and buttress 13;Vertical supports 2 is made up of pipe collar 2 21, foundation bolt 2 22; Pipe collar 2 21 ring set, in the outside of vertical concrete delivery pipe 3, is consolidated by foundation bolt 2 22 and vertical support 4;
Horizontal stand 1 and a dot center of vertical supports 2, be respectively positioned on straight tube position, distance straight tube and 300 millimeters of union elbow place; Under external force, the buttress 13 of horizontal stand 1 is connected reliably with ground, is not subjected to displacement; Vertical supports 2 is connected reliably with vertical support 4, is not subjected to displacement.
Pipe collar 1 and pipe collar 2 21 are arc strip-shaped members, and the steel plate adopting thickness to be 6 millimeters thick makes; Pipe collar 1 and pipe collar 2 21 all include arc section, vertical section and horizontal segment three part (see figure 4); The radian at restrained position is identical with the pipeline of concrete delivery pipe 3 respectively with the radian of pipe collar 2 21 arc section for pipe collar 1, the diameter 120 millimeters of pipe collar 1 and pipe collar 2 21 arc section; Pipe collar 1 is connected with arc section with in the vertical section of pipe collar 2 21, under be connected with horizontal segment, be highly 30 millimeters; Pipe collar 1 is connected with the bottom of vertical section with horizontal segment one end of pipe collar 2 21, and the length of horizontal segment is 80 millimeters; Having bolt hole in the horizontal segment middle part of pipe collar 1 with pipe collar 2 21, the diameter of bolt hole is respectively than big 2 millimeters of the diameter dimension with foundation bolt 1 with foundation bolt 2 22 screw rod.
Foundation bolt 1 and foundation bolt 2 22 are the rod-like members with double nut Yu pad, adopt the reinforcement fabrication of diameter 16 millimeters; The length of foundation bolt 1 is 150 millimeters, and reach is 50 millimeters, and pitch is 2.5 millimeters, it does not have the lower half of screw thread is embedded in buttress 13, length of embedment 90 millimeters; The first half of foundation bolt 1 exposes the foundation bolt outside buttress 13; Foundation bolt 2 22 is length is 150 millimeters, and reach is 50 millimeters, and pitch is 2.5 millimeters, and kink external diameter is the expansion bolt of 30, is arranged on by its lower semisection in vertical support 4 during work, and upper semisection is exposed at the surface of vertical support 4.
Buttress 13 is length is 500 millimeters, and width is 400 millimeters, is highly the block parts of the concrete of 350 millimeters or masonry class; The centre distance of buttress 13 is 4 meters, and the length direction of buttress 13 is consistent with the centerline direction of concrete delivery pipe 3, is fixed thereon by concrete delivery pipe 3 by foundation bolt 1 during with work; The centrage of buttress 13 keeps consistent with the centrage of concrete delivery pipe 3.

Claims (5)

1. concrete delivery pipe corner support, is characterized in that, described support is made up of horizontal stand (1) and vertical supports (2); The concrete conveying pipe of the level of the fixing corner of horizontal stand (1), the vertical concrete conveying pipe of the fixing corner of vertical supports (2), horizontal stand (1) is made up of pipe collar one (11), foundation bolt one (12), buttress (13); Pipe collar one (11) ring set is in the outside of Horizontal concrete conveying pipe (3), by foundation bolt one (12) and buttress (13) consolidation; Vertical supports (2) is made up of pipe collar two (21), foundation bolt two (22); Pipe collar two (21) ring set is in the outside of vertical concrete delivery pipe (3), by foundation bolt two (22) and vertical support (4) consolidation.
2. concrete delivery pipe corner according to claim 1 support, is characterized in that, described horizontal stand (1) props up dot center with vertical supports (2), is respectively positioned on straight tube position.
3. concrete delivery pipe corner according to claim 1 support, it is characterized in that, described pipe collar one (11) is arc strip-shaped members with pipe collar two (21), and pipe collar one (11) and pipe collar two (21) all include arc section, vertical section and horizontal segment three part;Pipe collar one (11) is identical with the radian at the restrained position of pipeline of concrete delivery pipe (3) respectively with the radian of pipe collar two (21) arc section, and pipe collar one (11) is identical with the overall diameter of the diameter of pipe collar two (21) arc section Yu concrete delivery pipe (3); Pipe collar one (11) is connected with arc section with in the vertical section of pipe collar two (21), under be connected with horizontal segment; Pipe collar one (11) is connected with the bottom of vertical section with horizontal segment one end of pipe collar two (21); Bolt hole is had in the horizontal segment middle part of pipe collar one (11) with pipe collar two (21).
4. concrete delivery pipe corner according to claim 1 support, it is characterized in that, described foundation bolt one (12) is the rod-like members with double nut Yu pad with foundation bolt two (22), it is inner that foundation bolt one (12) is that lower half is embedded in buttress (13), and the first half exposes the foundation bolt of buttress (13) outside; Foundation bolt two (22) is expansion bolt, its lower semisection is arranged on vertical support (4) inner during work, and upper semisection is exposed at the surface of vertical support (4).
5. concrete delivery pipe corner according to claim 1 support, is characterized in that, described buttress (13) is concrete or the block parts of masonry class, is fixed thereon by concrete delivery pipe (3) by foundation bolt one (12) during work.
CN201620043416.6U 2016-01-18 2016-01-18 Concrete conveying pipe corner support Expired - Fee Related CN205298825U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620043416.6U CN205298825U (en) 2016-01-18 2016-01-18 Concrete conveying pipe corner support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620043416.6U CN205298825U (en) 2016-01-18 2016-01-18 Concrete conveying pipe corner support

Publications (1)

Publication Number Publication Date
CN205298825U true CN205298825U (en) 2016-06-08

Family

ID=56429309

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620043416.6U Expired - Fee Related CN205298825U (en) 2016-01-18 2016-01-18 Concrete conveying pipe corner support

Country Status (1)

Country Link
CN (1) CN205298825U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031426A (en) * 2020-09-09 2020-12-04 上海宝冶集团有限公司 High-strength concrete pouring system for super high-rise building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031426A (en) * 2020-09-09 2020-12-04 上海宝冶集团有限公司 High-strength concrete pouring system for super high-rise building

Similar Documents

Publication Publication Date Title
CN103556644A (en) Basement bottom plate dewatering well mouth plugging casing and construction method
CN105822330A (en) GFRP tube concrete support for underground engineering supporting and construction technology thereof
CN107217851A (en) Concrete filled steel tubular column concrete lift-up device for casting and its construction technology
CN203514333U (en) Basement soleplate precipitation well mouth blocking sleeve
CN205298825U (en) Concrete conveying pipe corner support
CN107387922A (en) A kind of seal for pipe joints connector
CN207620126U (en) Beam slab leaks drainage device
CN104895329B (en) Silo sliding formwork storehouse wall concrete with liter conveying, pour device
CN204385727U (en) Spiral grouting preformed pile
JP2015105569A (en) Pump
CN204082057U (en) Bored pile faces fills with front gaslift hole cleaning device
CN205875188U (en) Pressure -bearing precipitation well plugging device
CN105386451A (en) Grouting device for preventing secondary sinking of open caisson
CN202274222U (en) Pipeline connecting device for large-expansion-amount pipelines
CN204781608U (en) Take finish rolling screw -thread steel anchor backing plate of slip casting coupling
CN104234217B (en) Light-duty pressure grouting device for overall and grout construction method thereof
CN207003602U (en) Urban discharging pipeline anti-leakage structure
CN205618128U (en) Directional plugging device of deep well wall of a well
CN206110124U (en) Bored concrete pile stake end post grouting device
CN215519999U (en) Grouting device for grouting sleeve of prefabricated vertical component
CN214574450U (en) Basement pipeline connecting structure under large-difference settlement
CN210092836U (en) Prefabricated steel cylinder concrete circular power pipe gallery with pipe seat
CN209227571U (en) Plugging dewatering well tool during a kind of dewatering construction
CN204691791U (en) The waterproof construction of rectangular top pipe
CN207144496U (en) Concrete filled steel tubular column concrete lift-up device for casting

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160608

Termination date: 20170118

CF01 Termination of patent right due to non-payment of annual fee