CN205296975U CN201620014390.2U CN201620014390U CN205296975U CN 205296975 U CN205296975 U CN 205296975U CN 201620014390 U CN201620014390 U CN 201620014390U CN 205296975 U CN205296975 U CN 205296975U
Authority
CN
China
Prior art keywords
rod
mark
wire pole
sign
total length
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620014390.2U
Other languages
Chinese (zh)
Inventor
尚钰真
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Zhongli Tower Co Ltd
Original Assignee
Henan Zhongli Tower Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Zhongli Tower Co Ltd filed Critical Henan Zhongli Tower Co Ltd
Priority to CN201620014390.2U priority Critical patent/CN205296975U/en
Application granted granted Critical
Publication of CN205296975U publication Critical patent/CN205296975U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a cement standard wire pole, comprises a pole body, the body of rod on be equipped with first sign and second sign, first sign setting in 16 departments that are body of rod total length apart from body of rod bottom, the second sign set up in 15 departments that are body of rod total length apart from body of rod bottom, the body of rod in set up the ground connection reinforcing bar, ground connection reinforcing bar top set up the lightning rod fixing base, the body of rod of second sign top on set up reflection of light strip, generally, the utility model has the advantages of whether the laying depth of wire pole that looks over that can convenient and fast meets the requirements, can select laying depth according to the geology condition, make things convenient for the construction operation personnel to climb the operation from top to bottom, effectively avoids the earth connection stolen, guarantees effective reliable connection of earth connection, makes the position that the people can very easy discovery wire pole, in time dodges, has high practical value.

Description

A kind of concrete wire pole
Technical field
This utility model belongs to electric power facility field, relates to a kind of concrete wire pole.
Background technology
Concrete wire pole widely uses in transmission of electricity and the communications field, and for ensureing the safe operation of circuit, electric pole all must assure that 1/5 or 1/6 that enough depth of buryings, the general depth of burying are electric pole total length.
First, the concrete wire pole currently used, its surface does not have any mark, make the workmen can not the depth of burying of accurate assurance electric pole, if workmen's irresponsibility is arbitrarily dug a shallow hole and is just buried electric pole underground, quality monitoring personnel also cannot accurately measure the depth of burying of concrete wire pole, and cannot discover. In this case, run into after the construction of line that conductor tension is big or when wind-force is bigger, electric pole all easily tilts, time serious, then electric pole is toppled over, electric wire breaks, power failure and line contacts ground, greatly threaten neighbouring people, animals life composition, it is easy to cause major accident.
Secondly, existing lightning protection line is all exposed on electric pole surface, and climbing electric pole is inconvenient, affect the working performance of upkeep operation personnel, be prone to be stolen by lawless person simultaneously, cause supply line's supply voltage unstable, damage electrical appliance, burn transformator, initiation fire.
Finally, when dark, do not know road conditions often due to observe, the electric pole on road or roadside can be knocked, cause injury to personnel, even knock electric pole down and cause a serious accident.
Summary of the invention
The purpose of this utility model is in that to provide a kind of concrete wire pole, can conveniently check whether burying underground of electric pole meets the requirements, ensureing electric pole stablizing in use, it is ensured that the safe operation of circuit, convenient construction operating personnel climbs operation up and down, it is prevented effectively from the problem that earth lead is stolen, make concrete wire pole become to be very easy to discovery at night, reduce the risk knocking concrete wire pole, simple in construction, easy to make, there is high practical value.
The purpose of this utility model is achieved in that a kind of concrete wire pole, including the body of rod, the described body of rod is provided with the first mark and the second mark, the first described mark is arranged on 1/6 place that distance post is body of rod total length, the second described mark is arranged on 1/5 place that distance post is body of rod total length, arranging ground rebar in the described body of rod, described ground rebar top arranges the fixing seat of discharging rod, and the body of rod of the second described mark top arranges reflecting strips.
Described first mark and the second mark are arranged around body of rod circumference one week.
Described the first mark and second is designated the projection with body of rod integral production or groove.
Described ground rebar is connected with the structure reinforcing bars of the body of rod.
Described ground rebar lower end is stretched out in the body of rod and is connected with grounding device.
Described reflecting strips height is two meters.
This utility model produces to provide the benefit that: simple in construction, can conveniently observe the depth of burying of concrete wire pole, the depth of burying that different choice according to geology is different, ensure that burying underground of electric pole meets the requirements, the unified height arranged makes trolley wire distance ground level identical, ensure stablizing of electric pole, the fixing seat of the discharging rod at body of rod top is convenient installs discharging rod at the top of electric pole, built-in ground rebar is prevented effectively from the stolen situation of earth lead to be occurred, ensure the reliability service of lightning arrester, ensure that circuit is at thunder and lightning weather reliability service, reflecting strips enables pedestrian to find the position of electric pole easily, avoid knocking electric pole, there is high practical value.
Accompanying drawing explanation
Fig. 1 is perspective view of the present utility model.
In figure: 1, the body of rod 2, first identifies the 3, second mark 4, ground rebar 5, discharging rod fixing seat 6, reflecting strips.
Detailed description of the invention
Below in conjunction with accompanying drawing to embodiment further instruction of the present utility model.
Embodiment 1
As shown in Figure 1, a kind of concrete wire pole, including the body of rod 1, the described body of rod 1 is provided with the first mark 2 and the second mark 3, the first described mark 2 is arranged on 1/6 place bottom the distance body of rod 1 for the body of rod 1 total length, and the second described mark 3 is arranged on 1/5 place bottom the distance body of rod 1 for the body of rod 1 total length, arranges ground rebar 4 in the described body of rod 1, described ground rebar 4 top arranges the fixing seat 5 of discharging rod, and the described body of rod 1 above the second mark 3 arranges reflecting strips 6.
Described first mark 2 and the second mark 3 setting were around the body of rod 1 circumference one week.
The first described mark 2 and the second mark 3 are the projection with the body of rod 1 integral production.
This utility model is in use: a kind of concrete wire pole, including the body of rod, the body of rod is provided with the first mark and the second mark, the body of rod is carried out labelling, first mark and the second mark arrange around body of rod circumference one week, the convenient all directions at the body of rod are checked, first mark and second is designated the projection with body of rod integral production, integral production ensures the Stability Analysis of Structures of the body of rod, projection is more convenient checks, first mark is arranged on 1/6 place that distance post is body of rod total length, bury underground electric pole place geology excellent time the depth of burying be the 1/6 of body of rod total length, first mark is in ground place, second mark is arranged on 1/5 place that distance post is body of rod total length, bury underground electric pole place geology bad time the depth of burying be the 1/5 of body of rod total length, second mark is in ground place, ground rebar is set in the body of rod, ground rebar is avoided to be stolen by lawless person, ensure grounding device effective grounding, ground rebar top arranges the fixing seat of discharging rod, facilitate the installation of discharging rod, the body of rod of the second mark top arranges reflecting strips, dodging in the position of electric pole to enable pedestrian very easily to find.
Generally, this utility model has can conveniently check whether the depth of burying of electric pole meets the requirements, the depth of burying can be selected according to geological conditions, convenient construction operating personnel climbs operation up and down, it is prevented effectively from earth lead stolen, it is ensured that being effectively reliably connected of earth lead, enables a person to find easily the position of electric pole, dodge in time, the advantage with high practical value.
Embodiment 2
As shown in Figure 1, a kind of concrete wire pole, including the body of rod 1, the described body of rod 1 is provided with the first mark 2 and the second mark 3, the first described mark 2 is arranged on 1/6 place bottom the distance body of rod 1 for the body of rod 1 total length, and the second described mark 3 is arranged on 1/5 place bottom the distance body of rod 1 for the body of rod 1 total length, arranges ground rebar 4 in the described body of rod 1, described ground rebar 4 top arranges the fixing seat 5 of discharging rod, and the described body of rod 1 above the second mark 3 arranges reflecting strips 6.
Described first mark 2 and the second mark 3 setting were around the body of rod 1 circumference one week.
The first described mark 2 and the second mark 3 are the groove with the body of rod 1 integral production.
Described ground rebar 4 is connected with the structure reinforcing bars of the body of rod 1.
Described ground rebar 4 lower end is stretched out in the body of rod 1 and is connected with grounding device.
Described reflecting strips 6 is highly two meters.
This utility model is in use: a kind of concrete wire pole, including the body of rod, the body of rod is provided with the first mark and the second mark, the body of rod is carried out labelling, first mark and the second mark arrange around body of rod circumference one week, the convenient all directions at the body of rod are checked, first mark and second is designated the groove with body of rod integral production, integral production ensures the Stability Analysis of Structures of the body of rod, groove is more convenient to be checked, first mark is arranged on 1/6 place that distance post is body of rod total length, bury underground electric pole place geology excellent time the depth of burying be the 1/6 of body of rod total length, first mark is in ground place, second mark is arranged on 1/5 place that distance post is body of rod total length, bury underground electric pole place geology bad time the depth of burying be the 1/5 of body of rod total length, second mark is in ground place, ground rebar is set in the body of rod, ground rebar lower end is stretched out in the body of rod and is connected with grounding device, ground rebar is avoided to be stolen by lawless person, ensure grounding device effective grounding, ground rebar top arranges the fixing seat of discharging rod, facilitate the installation of discharging rod, the body of rod of the second mark top arranges reflecting strips, the height of reflecting strips is two meters, reflecting strips is made conveniently to observe looking squarely in visual line of sight of people, dodging in the position of electric pole to enable pedestrian very easily to find, it is prevented effectively from waste resource simultaneously.
Generally, this utility model has can conveniently check whether the depth of burying of electric pole meets the requirements, the depth of burying can be selected according to geological conditions, convenient construction operating personnel climbs operation up and down, it is prevented effectively from earth lead stolen, it is ensured that being effectively reliably connected of earth lead, enables a person to find easily the position of electric pole, dodge in time, the advantage with high practical value.

Claims (6)

1. a concrete wire pole, including the body of rod, it is characterized in that: the described body of rod is provided with the first mark and the second mark, the first described mark is arranged on 1/6 place that distance post is body of rod total length, the second described mark is arranged on 1/5 place that distance post is body of rod total length, arranging ground rebar in the described body of rod, described ground rebar top arranges the fixing seat of discharging rod, and the body of rod of the second described mark top arranges reflecting strips.
2. a kind of concrete wire pole according to claim 1, it is characterised in that: the first described mark and the second mark are arranged around body of rod circumference one week.
3. a kind of concrete wire pole according to claim 1, it is characterised in that: described the first mark and second is designated the projection with body of rod integral production or groove.
4. a kind of concrete wire pole according to claim 1, it is characterised in that: described ground rebar is connected with the structure reinforcing bars of the body of rod.
5. a kind of concrete wire pole according to claim 1, it is characterised in that: described ground rebar lower end is stretched out in the body of rod and is connected with grounding device.
6. a kind of concrete wire pole according to claim 1, it is characterised in that: described reflecting strips height is two meters.
CN201620014390.2U 2016-01-08 2016-01-08 Cement standard wire pole Expired - Fee Related CN205296975U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620014390.2U CN205296975U (en) 2016-01-08 2016-01-08 Cement standard wire pole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620014390.2U CN205296975U (en) 2016-01-08 2016-01-08 Cement standard wire pole

Publications (1)

Publication Number Publication Date
CN205296975U true CN205296975U (en) 2016-06-08

Family

ID=56485637

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620014390.2U Expired - Fee Related CN205296975U (en) 2016-01-08 2016-01-08 Cement standard wire pole

Country Status (1)

Country Link
CN (1) CN205296975U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106150175A (en) * 2016-08-23 2016-11-23 胡广生 A kind of power distribution rod with anticollision device, collision-prevention device
CN108756415A (en) * 2018-04-26 2018-11-06 合肥海银杆塔有限公司 A kind of electric force pole tower with reflective prompting function
CN114016804A (en) * 2021-11-25 2022-02-08 广东电网有限责任公司 Cement telegraph pole and manufacturing method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106150175A (en) * 2016-08-23 2016-11-23 胡广生 A kind of power distribution rod with anticollision device, collision-prevention device
CN108756415A (en) * 2018-04-26 2018-11-06 合肥海银杆塔有限公司 A kind of electric force pole tower with reflective prompting function
CN114016804A (en) * 2021-11-25 2022-02-08 广东电网有限责任公司 Cement telegraph pole and manufacturing method thereof

Similar Documents

Publication Publication Date Title
CN205296975U (en) Cement standard wire pole
CN212694553U (en) External-breakage-preventing early warning and warning pile for underground pipeline
CN205777803U (en) A kind of multifunction power electric pole
CN210137091U (en) Lightning protection device for traction power supply
JP2010054440A (en) Method for inspecting on-site surge current discharge experiment to equipotential connection and basic pile grounded plate, discharge testing device, and discharge monitoring method
CN210460139U (en) Be applied to monitoring facilities's closed wiring formula pole setting
CN102495323A (en) Lightning flashover indicator
CN114033239A (en) Pull wire connector with external force damage prevention function
CN212810858U (en) Block terminal with lightning-arrest function
CN204144930U (en) A kind of microprocessor relay and protection system of transmission line
CN208416441U (en) A kind of Cadge ladder for construction of deep base pit
CN208986572U (en) A kind of protection component of family electricity box house lead in steel pipe
CN111236674A (en) Civil engineering construction safety warning rail guard
CN206753178U (en) A kind of electric pole with illumination functions and the alarm that can have a power failure
CN219158618U (en) Residential building lightning rod fence with warning function
CN206250741U (en) A kind of cable branch box of glass steel material
CN203133231U (en) Solar lightning flashover indicator
CN216121795U (en) Lightning overvoltage protection device for multifunctional intelligent rod
CN203643654U (en) All-weather combined optical cable direction indicating apparatus
CN205389010U (en) Pole, table case earthing device
CN219368869U (en) Subway flood prevention device based on internet of things
CN210050588U (en) Oil gas pipeline warning mechanism
CN216648623U (en) Grounding device for electrical instrument
CN212716128U (en) Novel pulse electronic fence with anti-shearing touch net type
CN217581522U (en) Pull wire connector with external force damage prevention function

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160608