CN205226745U - Ware is repaired to clamp formula pipeline - Google Patents
Ware is repaired to clamp formula pipeline Download PDFInfo
- Publication number
- CN205226745U CN205226745U CN201521136082.9U CN201521136082U CN205226745U CN 205226745 U CN205226745 U CN 205226745U CN 201521136082 U CN201521136082 U CN 201521136082U CN 205226745 U CN205226745 U CN 205226745U
- Authority
- CN
- China
- Prior art keywords
- steel band
- dunnage
- hook
- type pipeline
- box hat
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a ware is repaired to clamp formula pipeline when the pipeline takes place to reveal, can repair the device that the pipeline was revealed fast. And be not subject to impaired length of pipeline and pipeline pipe diameter. This device is including the fixed box hat (1) of repairing, bolt (2), nut (3), gasket (4), rubber seal board (5), couple steel band (6), adjustable steel band (7), deflector (8), first backup pad (9), second backup pad (10) and buckle (11), rubber seal board (5) have the groove shape structure of extension at the axial tip of repairing the ware, can carry out the axial extension according to the length of pipeline leak, and high flexibility and high convenience are obtained, the repair the when pipeline is revealed has been shortened greatly.
Description
Technical field
The utility model relates to fluid line Rapid-Repair field, particularly relates to a kind of clamp band type pipeline patching device.
Background technique
When pipeline occurs to reveal, when using existing repairing device product to repair, be often limited by the restriction of caliber and leakage place size, length.Many times need, according to the pipe diameter size revealing pipeline, to customize the model of the repairing device of suitable repairing device or stock buildup.Both delayed the repairing time, and affected the speed of pipe first-aid, increase cost again.
Model utility content
The purpose of this utility model is to provide a kind of clamp band type pipeline patching device, and not by the caliber repairing pipeline, the length of leakage place, the restrictions such as width, according to repairing the length revealed, can be repaired pipe diameter, regulating freely.Therefore, will time and the efficiency of pipe first-aid be greatly improved, also greatly reduce inventory cost.
For achieving the above object, the utility model provides following scheme:
A kind of clamp band type pipeline patching device, it is characterized in that: comprise retained prosthesis makes box hat 1, bolt 2, nut 3, rubber gasket sheet 5, hook steel band 6, adjustable steel band 7, guide plate 8, first dunnage 9, second dunnage 10 and buckle 11, described retained prosthesis makes box hat 1 is arcuate structure, the first dunnage 9 described in a slice is welded on the both sides of described retained prosthesis makes box hat 1 respectively, described first dunnage 9 is welded with guiding device described in three groups respectively, often organize described guiding device and comprise two panels guide plate 8, described retained prosthesis makes box hat 1 side is provided with described hook steel band 6, described retained prosthesis makes box hat 1 opposite side is provided with described adjustable steel band 7, described buckle 11 is buckled on dunnage and guide plate 8, and use bolt 2 nut 3 and pad 4 to fix described buckle 11.
Hook steel band 6 does not have the one side of one end and described second dunnage 10 linked up with to weld together, the another side of described second dunnage 10 is together with described bolt 2 bottom welding, adjustable steel band 7 does not have the one side of one end of adjustment hole and described second dunnage 10 to weld together, and the another side of described second dunnage 10 is together with described bolt 2 bottom welding.
The adjustment hole of described adjustable steel band 7 is slotted hole.
Described buckle 11 has three pilot holes, described pilot hole is used for construction bolt 2.
Described rubber gasket sheet 5 is stained with inside described retained prosthesis makes box hat 1.
Described rubber gasket sheet 5 has the groove shape structure of prolongation at the axial end portion of repairing device, and described rubber gasket sheet 5 internal surface has tiny grid.
There is multiple adjustment hole described adjustable steel band 7 one end, and described adjustable steel band 7 the other end and a slice second dunnage weld together.There is hook described hook steel band 6 one end, and the hook of described hook steel band 6 can hook the adjustment hole of described adjustable steel band 7, and described hook steel band 6 the other end and a slice second dunnage weld together.
Described buckle 11 both sides have a flanging respectively, and a flanging of described buckle 11 is arranged between the gap between described retained prosthesis makes box hat 1 and the first dunnage 9.
The adjustment hole quantity of described adjustable steel band is 6-10.
Can multiple described clip repairing device with the use of.
According to the specific embodiment that the utility model provides, the utility model discloses following technique effect:
The utility model, not by the caliber repairing pipeline, the length of leakage place, the restrictions such as width, adjustable steel band there is 6-10 adjustment hole, can according to being repaired pipe diameter, regulate freely, so model can contain the caliber scope of a conventional repair device 3-5 model in the past, sealed rubber plate has the groove shape structure of prolongation at the axial end portion of repairing device, can overlap with the rubber plate of adjacent repairing device, thus can according to repairing the length revealed, unrestricted choice uses one or more repairing device.Therefore, do not need the repairing device model customizing repairing device or stock buildup, highly shortened the time of repairing, accelerate the speed of repairing, again reduce cost.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technological scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment below, apparently, accompanying drawing in the following describes is only an embodiment of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the structural drawing of the clamp band type pipeline patching device of the utility model embodiment one;
Fig. 2 is the structural drawing of second dunnage of the utility model embodiment two;
Fig. 3 is the structural drawing of the adjustable steel band of the utility model embodiment two.
In figure: 1. retained prosthesis makes box hat, 2. bolt, 3. nut, 4. pad, 5. sealed rubber plate, 6. link up with steel band, 7. adjustable steel band, 8. guide plate, 9. the first dunnage, 10. the second dunnage 11. buckle
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, be clearly and completely described the technological scheme in the utility model embodiment, obviously, described embodiment is only the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all belong to the scope of the utility model protection.
The purpose of this utility model is to provide a kind of clamp band type pipeline patching device.
Example one: Fig. 1 is an embodiment of the present utility model.As shown in Figure 1, a kind of clamp band type pipeline patching device, it is characterized in that: comprise retained prosthesis makes box hat 1, bolt 2, nut 3, rubber gasket sheet 5, hook steel band 6, adjustable steel band 7, guide plate 8, first dunnage 9, second dunnage 10 and buckle 11, described retained prosthesis makes box hat 1 is arcuate structure, the first dunnage 9 described in a slice is welded on the both sides of described retained prosthesis makes box hat 1 respectively, described first dunnage 9 is welded with guiding device described in three groups respectively, often organize described guiding device and comprise two panels guide plate 8, described retained prosthesis makes box hat 1 side is provided with described hook steel band 6, described retained prosthesis makes box hat 1 opposite side is provided with described adjustable steel band 7, described buckle 11 is buckled on dunnage and guide plate 8, and use bolt 2 nut 3 and pad 4 to fix described buckle 11.
Hook steel band 6 does not have the one side of one end and described second dunnage 10 linked up with to weld together, the another side of described second dunnage 10 is together with described bolt 2 bottom welding, adjustable steel band 7 does not have the one side of one end of adjustment hole and described second dunnage 10 to weld together, and the another side of described second dunnage 10 is together with described bolt 2 bottom welding.
The adjustment hole of described adjustable steel band 7 is slotted hole.
Described buckle 11 has three pilot holes, described pilot hole is used for construction bolt 2.
Described rubber gasket sheet 5 is stained with inside described retained prosthesis makes box hat 1.
Described rubber gasket sheet 5 has the groove shape structure of prolongation at the axial end portion of repairing device, and described rubber gasket sheet 5 internal surface has tiny grid.
There is multiple adjustment hole described adjustable steel band 7 one end, and described adjustable steel band 7 the other end and a slice second dunnage weld together.
There is hook described hook steel band 6 one end, and the hook of described hook steel band 6 can hook the adjustment hole of described adjustable steel band 7, and described hook steel band 6 the other end and a slice second dunnage weld together.
Described buckle 11 both sides have a flanging respectively, and a flanging of described buckle 11 is arranged between the gap between described retained prosthesis makes box hat 1 and the first dunnage 9.
The adjustment hole quantity of described adjustable steel band is 6-10.
Can multiple described clip repairing device with the use of.
Example two:
Fig. 2 is the structural drawing of second dunnage of the utility model embodiment two.Fig. 3 is the structural drawing of the adjustable steel band of the utility model embodiment two.
Consider that the clip repairing device of the application is stressed larger in use, adjustable steel band and hook steel band are the sheet metal part that thin plate makes, reuse in process and may occur damaging, a hook is welded in described second dunnage 10 bottom, increase a slotted hole in the one end of adjustment hole that do not have of described hook steel band 6, the hook of described second dunnage 10 bottom welding can insert in the slotted hole of described hook steel band 6 increase.
When repairing pipeline, retained prosthesis makes box hat 1 is placed on leakage place of repaired pipeline, and guarantee that leakage place can cover by rubber gasket sheet 5 completely, after treating that leakage place is completely coated, at the adjustment hole that adjustable steel band 7 chosen distance is suitable, the hook of hook steel band 6 is linked in adjustment hole selected on adjustable steel band 7, after adjustable steel band 7 is connected with hook steel band 6, insert being welded on adjustable steel band 7 respectively in the pilot hole corresponding with guide plate 11 with the bolt 2 on hook steel band 6, by buckle 11 by bolt 2, be buckled on the first dunnage 9 and guide plate 8, the flanging of buckle 11 side is placed between the gap between retained prosthesis makes box hat 1 and the first dunnage 9, nut 3 and pad 4 are fastened on bolt 2, regulate this repairing device to the pressure of pipeline by tightening or unscrewing nut 3, the axial two ends of rubber gasket sheet 5 are with slope O-shaped structure, overlap joint can be carried out according to the length of leakage place and extend repairing length.
Apply specific case herein to set forth principle of the present utility model and mode of execution, the explanation of above embodiment just understands method of the present utility model and core concept thereof for helping; Meanwhile, for one of ordinary skill in the art, according to thought of the present utility model, all will change in specific embodiments and applications.In sum, this description should not be construed as restriction of the present utility model.
Claims (10)
1. a clamp band type pipeline patching device, it is characterized in that: comprise retained prosthesis makes box hat (1), bolt (2), nut (3), rubber gasket sheet (5), hook steel band (6), adjustable steel band (7), guide plate (8), first dunnage (9), second dunnage (10) and buckle (11), described retained prosthesis makes box hat (1) is arcuate structure, the first dunnage (9) described in a slice is welded on the both sides of described retained prosthesis makes box hat (1) respectively, described first dunnage (9) is welded with guiding device described in three groups respectively, often organize described guiding device and comprise two panels guide plate (8), described retained prosthesis makes box hat (1) side is provided with described hook steel band (6), described retained prosthesis makes box hat (1) opposite side is provided with described adjustable steel band (7), described buckle (11) is buckled on dunnage and guide plate (8), and use bolt (2) nut (3) and the fixing described buckle (11) of pad (4).
2. clamp band type pipeline patching device described in claim 1, it is characterized in that: hook steel band (6) does not have the one side of one end and described second dunnage (10) linked up with to weld together, the another side of described second dunnage (10) is together with described bolt (2) bottom welding, adjustable steel band (7) does not have the one side of one end of adjustment hole and described second dunnage (10) to weld together, and the another side of described second dunnage (10) is together with described bolt (2) bottom welding.
3. clamp band type pipeline patching device described in claim 1, is characterized in that: the adjustment hole of described adjustable steel band (7) is slotted hole.
4. clamp band type pipeline patching device described in claim 1, is characterized in that: described buckle (11) has three pilot holes, and described pilot hole is used for construction bolt (2).
5. clamp band type pipeline patching device described in claim 1, is characterized in that: described retained prosthesis makes box hat (1) inner side is stained with described rubber gasket sheet (5).
6. clamp band type pipeline patching device described in claim 1, is characterized in that: described rubber gasket sheet (5) has the groove shape structure of prolongation at the axial end portion of repairing device, and described rubber gasket sheet (5) internal surface has tiny grid.
7. clamp band type pipeline patching device described in claim 1, is characterized in that: there is multiple adjustment hole described adjustable steel band (7) one end, and described adjustable steel band (7) the other end and a slice second dunnage weld together.
8. clamp band type pipeline patching device described in claim 1, it is characterized in that: there is hook described hook steel band (6) one end, the hook of described hook steel band (6) can hook the adjustment hole of described adjustable steel band (7), and described hook steel band (6) the other end and a slice second dunnage weld together.
9. clamp band type pipeline patching device described in claim 1, it is characterized in that: described buckle (11) both sides have a flanging respectively, a flanging of described buckle (11) is arranged between the gap between described retained prosthesis makes box hat (1) and the first dunnage (9).
10. clamp band type pipeline patching device described in claim 2, is characterized in that: the adjustment hole quantity of described adjustable steel band is 6-10.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201521136082.9U CN205226745U (en) | 2015-12-18 | 2015-12-18 | Ware is repaired to clamp formula pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201521136082.9U CN205226745U (en) | 2015-12-18 | 2015-12-18 | Ware is repaired to clamp formula pipeline |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205226745U true CN205226745U (en) | 2016-05-11 |
Family
ID=55901811
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201521136082.9U Expired - Fee Related CN205226745U (en) | 2015-12-18 | 2015-12-18 | Ware is repaired to clamp formula pipeline |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205226745U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105423062A (en) * | 2015-12-18 | 2016-03-23 | 郭文星 | Clamp-type pipeline repair device |
-
2015
- 2015-12-18 CN CN201521136082.9U patent/CN205226745U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105423062A (en) * | 2015-12-18 | 2016-03-23 | 郭文星 | Clamp-type pipeline repair device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206001191U (en) | Sucralose produces pipeline equipment valve Pressurized plugging clamp | |
CN205226745U (en) | Ware is repaired to clamp formula pipeline | |
CN203907113U (en) | Leakage stoppage device for pipe leakage hole | |
CN204004894U (en) | A kind of Novel pure metal sealing joint structure | |
CN105423062A (en) | Clamp-type pipeline repair device | |
CN203836486U (en) | Flexible under-pressure leaking stoppage set | |
CN208670430U (en) | A kind of gas pipeline leakage repairing clamp | |
CN204512736U (en) | A kind of two flange limit expansion joint | |
CN204477390U (en) | A kind of multiplex pipeline band bypass composite joint assembly | |
CN207935626U (en) | A kind of gas pipeline leak source sealing device | |
CN201093141Y (en) | Pipe U-shaped leak stopping card | |
CN106931255A (en) | Pipeline connects head device | |
CN108386629A (en) | The method of pipe jointer secondary seal | |
CN205226744U (en) | Emergent plugging device of pipeline | |
CN204493988U (en) | A kind of high-pressure leakage pipeline flexible prefastening compensates blocking clamper | |
CN203147156U (en) | Fast leakage stopping fixture for pipeline perforation | |
CN203258240U (en) | Tooth-shaped flange sealing gasket | |
CN204493986U (en) | A kind of high pressure pipe line blocking clamper | |
CN201103770Y (en) | Clamp apparatus for blocking under pressure | |
CN203836491U (en) | Splicing type pipe sleeve | |
CN103883839A (en) | Emergency leakage stopping box of stainless steel pipeline and method for installing emergency leakage stopping box | |
CN204035726U (en) | Special buckle internal thread machining blade | |
CN204805840U (en) | Hourglass instrument of controlling is pressed in filled type area | |
CN103481267A (en) | Petroleum pipeline cutting line tool | |
CN203686469U (en) | Pressure pipeline nausea board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20190124 Address after: 116000 Qingshan Village, Youngzheng Street, Jinzhou District, Dalian City, Liaoning Province Patentee after: Dalian Chuhong Machinery Co., Ltd. Address before: 116000 Xinghuali No.4 1-3-1, Dalian Economic and Technological Development Zone, Liaoning Province Patentee before: Guo Wenxing |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160511 Termination date: 20191218 |
|
CF01 | Termination of patent right due to non-payment of annual fee |