CN205188795U - Keep natural large -span belt conveyor landing stage that overflows form of coombe - Google Patents
Keep natural large -span belt conveyor landing stage that overflows form of coombe Download PDFInfo
- Publication number
- CN205188795U CN205188795U CN201520950408.5U CN201520950408U CN205188795U CN 205188795 U CN205188795 U CN 205188795U CN 201520950408 U CN201520950408 U CN 201520950408U CN 205188795 U CN205188795 U CN 205188795U
- Authority
- CN
- China
- Prior art keywords
- coombe
- girder truss
- strainer
- wire rope
- basis
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a keep natural large -span belt conveyor landing stage that overflows form of coombe, the trussed girder spanes the coombe, and the trussed girder both ends are articulated with the pylon basis of both sides respectively, be provided with rubber belt conveyor in the trussed girder, trussed girder length is 50 -70m, the trussed girder height is 2 -2.5m. Pylon basis and strainer basis are organized through the stock and are fixed on the ground, be provided with the pylon on the pylon basis, be provided with the strainer on the anchor beam, the anchor beam is connected with a plurality of wire rope's one end through the strainer, wire rope's the other end pulley through the pylon top turns to the piggy -back connector frame of back between saving with the trussed girder standard and is connected, the utility model discloses a mode that adopts wire rope to draw the trussed girder to one side reduces trussed girder section height by a wide margin, its section height satisfy the technology headroom require can, need not because of span size, the big or small increase deck -molding of atress. Also reduce simultaneously the volume of using the steel of trussed girder web member, diagonal bracing and montant by a wide margin, had good economic nature.
Description
Technical field
The utility model relates to construction of hydropower plant, refers to the large span adhesive tape conveyor trestle keeping the natural overcurrent form of coombe especially.
Background technology
Nearly ten years, China's hydroelectric project major part concentrates on deep mountain valleys area, southwest, and general sandstone stock ground, dam main raw material(s) supply place or Preservation for Aggregate Production System position are comparatively far away apart from dam construction district, need build special long distance adhesive tape conveyor sand transportation building stones.Adhesive tape conveyor paddy gully along the line is grown thickly, and adhesive tape conveyor needs frequent leap mountain valley coombe.It is steep that southwest narrow valley region coombe generally has ditch depth slope, and the large even association mud-rock flow secondary disaster of run-off in rainy season occurs, and dry season with the feature that larger crosscut wind produces, has a negative impact to the safe operation of adhesive tape conveyor again.Phase of the executing Preservation for Aggregate Production System in the black East Germany power station of my institute's design, all there is above-mentioned geographic and geomorphic conditions in the adhesive tape conveyor participating in the sand transportation building stones of the Pubugou Hydropower Station, imperial opening power station etc. of the Jinping Hydroelectric Power Station of sandstone system, Xiangjiabahydropower project, Xi Luo Du reservoir, power station, white crane beach and Da Gang Mountain power station and the design of other unit.Guarantee that adhesive tape conveyor is safe and reliable, the span structure of adhesive tape conveyor as far as possible directly should cross over coombe, therefore the selection across groove structure form is very important, and on the selection of transporter overall plan, it determines that impact is comparatively large, be the controlling project of adhesive tape conveyor design.
According to statistics in above-mentioned engineering, sealing-tape machine supply line circuit longest distance is 39Km, and the shortest is 4.5Km, needs the span scope crossing over coombe on the way between 30 ~ 60m, the coombe degree of depth 20 ~ 90m.Wherein the coombe span of 60m is far beyond the conventional adhesive tape conveyor structural span of current domestic water electrical engineering.And existing adhesive tape conveyor girder truss span is generally within 24m, 30m is comparatively rare with upper span.
And the large span sealing-tape machine of conventional art generally needs to arrange the structure such as column, buttress sub-truss beam in coombe.Support the flow section area that structure not only reduce coombe, also can form stop to advancing of mud-rock flow, and then the safe operation of adhesive tape conveyor is had a negative impact.
Utility model content
The purpose of this utility model is to overcome that the deadweight of existing large span trestle is excessive, high cost and the large span adhesive tape conveyor trestle of the natural overcurrent form of maintenance coombe that provides.
The utility model realizes by following technical scheme:
Keep the large span adhesive tape conveyor trestle of the natural overcurrent form of coombe, comprise the tower foundation and girder truss be located in coombe both sides; Described tower foundation is fixed on ground by inner side anchor pole group; Described tower foundation arranged outside has strainer basis; Described strainer basis is fixed on ground by outside anchor pole group;
Described girder truss two ends are hinged with the described tower foundation of both sides respectively, and described girder truss is across coombe; Rubber conveyer is provided with in described girder truss; Described girder truss length is 50-70m;
Described tower foundation is provided with pylon; Described pylon top is provided with pulley; Described strainer basis is provided with strainer, and described strainer basis is connected with one end of some wire rope by described strainer; Described wire rope and described pulley are slidably matched; Described girder truss is made up of some sections of girder truss standard knots, and adjacent described girder truss standard knot is connected by connection segment frame; Described connection segment frame is provided with wire rope hole; The other end of described wire rope is connected with described wire rope hole.
Described girder truss height is 2-2.5m.
Maintenance channel is provided with in described girder truss.
Preferably, described girder truss length is 50-70m.
The utility model utilizes the pylon being fixed on coombe two sides, adopts wire rope inclined-pulling girder truss.To the large-span truss beam of coombe two sides be supported in, by the oblique pull of several wire rope be connected with beam, for span structure provides multiple fulcrum, single beam be become continuous beam on many supports.Wire rope is fixed on the anchor beam on bank by strainer after then being altered course by the pylon being arranged in coombe two sides.
The utility model proposes and use adhesive tape conveyor to transport leap large span coombe sand material, the adhesive tape conveyor trestle adopted is by the mode of wire rope inclined-pulling girder truss, namely wire rope one end is connected with girder truss, and the other end is fixed on the ground of two sides after being altered course by the pylon being arranged at coombe two sides.Without the need to arranging the structure of any lattice beam in coombe, keeping the natural overcurrent mode of coombe, being specially adapted to southwestern narrow valley region coombe.It is steep that southwest narrow valley region coombe generally has ditch depth slope, the feature that the large even association mud-rock flow secondary disaster of run-off in rainy season occurs.
Trestle truss depth of beam is comprehensively determined according to span size, stressed size and technological requirement etc.The rise-span ratio of general simple truss beam gets 1/12 ~ 1/15.For 60m span, truss deck-molding h=5 ~ 4m.Adopting the mode of wire rope inclined-pulling girder truss across coombe adhesive tape conveyor trestle, is 2m by the height reduction of girder truss, corresponding rise-span ratio 1/30.The girder truss cross dimensions of design meets technique Clearance requirement, without the need to because of span size, stressed size and increase deck-molding.Meanwhile, girder truss height is reduced to 2m by 5 ~ 4m, greatly reduces the steel using amount of web member, diagonal web member and montant, has good economy.
Girder truss profile height is little, is made up of multiple standard knot.Structure and component simple, light, easily transport, be convenient to oblique pull method assembled, be easy to install, reinforce and reconstruction.Not by landform and the impact in season.The junction of wire rope and each standard knot of girder truss arranges connection segment frame, can arrange stiffener easily in steel pipe, to ensure the Strength Safety of junction.Wire rope permissible stress is very high, and connecting structure between girder truss is succinct, convenient, to girder construction without any weakening.Wire rope and girder truss supporting the use on the adhesive tape conveyor trestle crossing over coombe, accomplish to make the best use of everything very easily.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Fig. 2 is coombe bank end structure schematic diagram.
In figure: tower foundation 1; Inner side anchor pole group 21; Outside anchor pole group 22; Anchor beam 3; Strainer 4; Pylon 5; Pulley 6; Wire rope 7; Girder truss 8; Rubber conveyer 9; Connection segment frame 10.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is described in further detail, but this embodiment should not be construed restriction of the present utility model, only for example, simultaneously by illustrating that advantage of the present utility model will become clearly and easy understand.
As shown in drawings, keep the large span adhesive tape conveyor trestle of the natural overcurrent form of coombe: comprise the tower foundation 1 and girder truss 8 be located in coombe both sides; Tower foundation 1 is fixed on ground by inner side anchor pole group 21; Tower foundation 1 arranged outside has strainer basis 3; Strainer basis 3 is fixed on ground by outside anchor pole group 22;
Girder truss 8 two ends are hinged with the tower foundation 1 of both sides respectively, and girder truss 8 is across coombe; Rubber conveyer 9 is provided with in girder truss 8; Girder truss 8 length is 50-70m;
Tower foundation 1 is provided with pylon 5; Pylon 5 top is provided with pulley 6; Strainer basis 3 is provided with strainer 4, strainer basis 3 is connected with one end of some wire rope 7 by strainer 4; Wire rope 7 and pulley 6 are slidably matched; Girder truss 8 is made up of some sections of girder truss standard knots, and adjacent truss beam standard knot is connected by connection segment frame 10; Connection segment frame 10 is provided with wire rope hole; The other end of wire rope 7 is connected with wire rope hole.
Girder truss 8 is highly 2-2.5m.
Maintenance channel is provided with in girder truss 8.
Girder truss 8 length is 50-70m.
It should be noted that: to those of ordinary skill in the art, can also make some changes or distortion to the utility model under the prerequisite not changing the utility model principle, this belongs to protection domain of the present utility model equally.
Claims (4)
1. keep the large span adhesive tape conveyor trestle of the natural overcurrent form of coombe, it is characterized in that: comprise the tower foundation (1) and girder truss (8) be located in coombe both sides; Described tower foundation (1) is fixed on ground by inner side anchor pole group (21); Described tower foundation (1) arranged outside has strainer basis (3); Described strainer basis (3) is fixed on ground by outside anchor pole group (22);
Described girder truss (8) two ends are hinged with the described tower foundation (1) of both sides respectively, and described girder truss (8) is across coombe; Rubber conveyer (9) is provided with in described girder truss (8); Described girder truss (8) length is 50-70m;
Described tower foundation (1) is provided with pylon (5); Described pylon (5) top is provided with pulley (6); Described strainer basis (3) is provided with strainer (4), and described strainer basis (3) is connected with one end of some wire rope (7) by described strainer (4); Described wire rope (7) and described pulley (6) are slidably matched; Described girder truss (8) is made up of some sections of girder truss standard knots, and adjacent described girder truss standard knot is connected by connection segment frame (10); Described connection segment frame (10) is provided with wire rope hole; The other end of described wire rope (7) is connected with described wire rope hole.
2. the large span adhesive tape conveyor trestle of the natural overcurrent form of maintenance coombe according to claim 1, is characterized in that: described girder truss (8) is highly 2-2.5m.
3. the large span adhesive tape conveyor trestle of the natural overcurrent form of maintenance coombe according to claim 1, is characterized in that: described girder truss is provided with maintenance channel in (8).
4. the large span adhesive tape conveyor trestle of the natural overcurrent form of maintenance coombe according to claim 1, is characterized in that: described girder truss (8) length is 50-70m.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520950408.5U CN205188795U (en) | 2015-11-25 | 2015-11-25 | Keep natural large -span belt conveyor landing stage that overflows form of coombe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520950408.5U CN205188795U (en) | 2015-11-25 | 2015-11-25 | Keep natural large -span belt conveyor landing stage that overflows form of coombe |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205188795U true CN205188795U (en) | 2016-04-27 |
Family
ID=55781798
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520950408.5U Active CN205188795U (en) | 2015-11-25 | 2015-11-25 | Keep natural large -span belt conveyor landing stage that overflows form of coombe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205188795U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107313355A (en) * | 2017-08-18 | 2017-11-03 | 中国十七冶集团有限公司 | A kind of steel trestle construction method waterborne |
CN109928139A (en) * | 2019-04-24 | 2019-06-25 | 焦作科瑞森重装股份有限公司 | Large span suspension bridge circular pipe belt type conveyer |
CN113512949A (en) * | 2021-05-10 | 2021-10-19 | 中国电建集团贵阳勘测设计研究院有限公司 | Rapid installation method of long-span temporary steel structure bridge |
-
2015
- 2015-11-25 CN CN201520950408.5U patent/CN205188795U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107313355A (en) * | 2017-08-18 | 2017-11-03 | 中国十七冶集团有限公司 | A kind of steel trestle construction method waterborne |
CN107313355B (en) * | 2017-08-18 | 2019-03-12 | 中国十七冶集团有限公司 | A kind of steel trestle construction method waterborne |
CN109928139A (en) * | 2019-04-24 | 2019-06-25 | 焦作科瑞森重装股份有限公司 | Large span suspension bridge circular pipe belt type conveyer |
CN113512949A (en) * | 2021-05-10 | 2021-10-19 | 中国电建集团贵阳勘测设计研究院有限公司 | Rapid installation method of long-span temporary steel structure bridge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10280575B2 (en) | Cable-stayed suspension bridge structure suitable for super long spans | |
CN205188795U (en) | Keep natural large -span belt conveyor landing stage that overflows form of coombe | |
CN203923882U (en) | One-sided dorsal funciculus steel work cable stayed bridge | |
CN207079458U (en) | The truss-like beam-arch composite bridge of double deck full steel structure | |
CN103821075B (en) | Long span oblique pull assembly type steel bridge on highway | |
CN204781326U (en) | Novel prestressing force industry stock ground cover shed structure | |
CN204551891U (en) | A kind of Spatial beam string structure and truss combining structure | |
CN103774543B (en) | A kind of deck type rope arch combination bridge | |
CN206753138U (en) | New wide span dry coal shed structure | |
CN209081290U (en) | Bailey truss pylon and distributing earth anchor CABLEWAY ERECTION SYSTEM that can be traversing | |
CN203716044U (en) | Low bearing or middle bearing cable arch combined structural bridge | |
CN206196499U (en) | A kind of photovoltaic agricultural greenhouse support | |
CN206719483U (en) | A kind of anchor for being used to adjust photovoltaic floating body waterborne | |
CN204024430U (en) | Adopt the bamboo ladder stand of contiguous block overlapping | |
CN207904868U (en) | A kind of illiciumverum Chained slope protection building block | |
CN203546601U (en) | Steel truss assembling support | |
CN205115988U (en) | Part earth anchor height tower cable -stay bridge structure | |
CN204024443U (en) | Adopt the bamboo ladder stand of connector overlapping | |
CN209011637U (en) | A kind of plane view ladder structure | |
CN203716045U (en) | Deck type cable-arch combined structure bridge | |
CN206052664U (en) | Large-scale powerhouse structure of run-of-river power plant | |
CN202730633U (en) | Self-anchored suspension bridge for main cables in parallel spaces of one-column tower | |
CN104499438A (en) | Arched T-beam hangar tunnel structure | |
CN204356707U (en) | A kind of arch T beam shed hole structure | |
CN208918327U (en) | A kind of assembly place high-altitude safeguard procedures structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |