CN205148172U - Transmission line iron tower screw fastening instrument - Google Patents
Transmission line iron tower screw fastening instrument Download PDFInfo
- Publication number
- CN205148172U CN205148172U CN201520778981.2U CN201520778981U CN205148172U CN 205148172 U CN205148172 U CN 205148172U CN 201520778981 U CN201520778981 U CN 201520778981U CN 205148172 U CN205148172 U CN 205148172U
- Authority
- CN
- China
- Prior art keywords
- wrench
- transmission line
- connecting plate
- screw fastening
- locking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Details Of Spanners, Wrenches, And Screw Drivers And Accessories (AREA)
Abstract
本实用新型公开了一种输电线路铁塔螺丝紧固工具,其特征在于它包括止转扳手(1),止转扳手(1)通过连接杆(5)连接连接板(4),连接板(4)上嵌套有锁紧扳手(2),锁紧扳手(2)通过连接板(4)上部的卡槽(8)嵌套在连接板(4)内,锁紧扳手(2)连接棘轮扳手(3),止转扳手(1)和锁紧扳手(2)均采用梅花套筒扳手,本实用新型灵活性好、操作简单,缩短螺丝紧固的时间,提高杆塔组立的效率,提高高空作业的安全性,节省作业人员的体力,减少作业人员携带工具的数量。
The utility model discloses a screw fastening tool for an iron tower of a power transmission line, which is characterized in that it comprises a stop wrench (1), the stop wrench (1) is connected to a connecting plate (4) through a connecting rod (5), and the connecting plate (4 ) is nested with a locking wrench (2), the locking wrench (2) is nested in the connecting plate (4) through the slot (8) on the upper part of the connecting plate (4), and the locking wrench (2) is connected to the ratchet wrench (3), both the anti-rotation wrench (1) and the locking wrench (2) use a ring wrench. The utility model has good flexibility, simple operation, shortens the time for screw tightening, improves the efficiency of pole and tower assembly, and improves the height of the tower. The safety of the operation saves the physical strength of the operators and reduces the number of tools carried by the operators.
Description
技术领域: Technical field:
本实用新型涉及一种输电线路铁塔螺丝紧固工具,属于电力系统输电线路检修领域。 The utility model relates to a screw fastening tool for an iron tower of a power transmission line, which belongs to the field of power system transmission line maintenance.
背景技术: Background technique:
在输电线路铁塔组立和检修的过程中,需要大量重复性的螺丝紧固工作。在螺丝紧固的过程中经常出现螺栓随螺帽转动的情况,需要对螺栓头部进行固定方可继续紧固。目前,普遍采用的是分别用扳手固定螺栓头部和螺帽的方法,使用工具多,而且需要双手操作。同时,由于塔上作业空间有限,对工作造成严重不便,降低工作效率,增加了作业人员的危险系数。孔洞相对于塔材的位置可能出现阻碍扳手操作的现象,使扳手无法固定螺栓头部。 In the process of assembling and overhauling transmission line iron towers, a lot of repetitive screw fastening work is required. In the process of screw fastening, it often occurs that the bolt rotates with the nut, and the head of the bolt needs to be fixed before continuing to tighten. At present, it is generally adopted to fix the head of the bolt and the nut with a wrench respectively, which uses many tools and requires both hands to operate. At the same time, due to the limited working space on the tower, it causes serious inconvenience to the work, reduces work efficiency, and increases the risk factor of operators. The position of the hole relative to the tower material may hinder the operation of the wrench, so that the wrench cannot fix the bolt head.
实用新型内容: Utility model content:
本实用新型的目的在于克服上述已有技术的不足而提供一种灵活性好、操作简单,缩短螺丝紧固的时间,提高杆塔组立的效率,提高高空作业的安全性,节省作业人员的体力,减少作业人员携带工具的数量的输电线路铁塔螺丝紧固工具。 The purpose of the utility model is to overcome the deficiencies of the above-mentioned prior art and provide a flexible, simple operation, shorten the time of screw fastening, improve the efficiency of pole tower assembly, improve the safety of high-altitude operations, and save the physical strength of operators. , A power transmission line iron tower screw fastening tool that reduces the number of tools carried by operators.
本实用新型的目的可以通过如下措施来达到:一种输电线路铁塔螺丝紧固工具,其特征在于它包括止转扳手,止转扳手通过连接杆连接连接板,连接板上嵌套有锁紧扳手,锁紧扳手通过连接板上部的卡槽嵌套在连接板内,锁紧扳手连接棘轮扳手,止转扳手和锁紧扳手均采用梅花套筒扳手。 The purpose of this utility model can be achieved through the following measures: a power transmission line iron tower screw fastening tool, which is characterized in that it includes a stop wrench, the stop wrench is connected to the connecting plate through a connecting rod, and a locking wrench is nested on the connecting plate , the locking wrench is nested in the connecting plate through the slot on the upper part of the connecting plate, the locking wrench is connected with the ratchet wrench, and both the anti-rotation wrench and the locking wrench use a ring wrench.
为了进一步实现本实用新型的目的,所述的止转扳手与卡槽之间的距离为100mm。 In order to further realize the purpose of the utility model, the distance between the anti-rotation wrench and the clamping groove is 100mm.
本实用新型同已有技术相比可产生如下积极效果:本实用新型可以提高螺丝紧固的便捷性,缩短螺丝紧固的时间,进而缩短杆塔组立和检修的时间,提高杆塔组立的效率。本实用新型只使用一个工具实现了螺丝的紧固,减少作业人员攀登杆塔作业需要携带的工具数量,简化作业人员高空作业的操作步骤,一定程度上降低作业人员的高空作业风险,同时,在螺丝紧固的过程中使作业人员保持舒适的工作姿态,提高高空作业的安全性,节省作业人员的体力。本实用新型与使用两个扳手实现螺丝紧固相比,具有灵活性好、操作简单的特点。 Compared with the prior art, the utility model can produce the following positive effects: the utility model can improve the convenience of screw fastening, shorten the time of screw fastening, further shorten the time of tower erection and maintenance, and improve the efficiency of pole tower erection . The utility model only uses one tool to realize the fastening of screws, reduces the number of tools that operators need to carry when climbing poles and towers, simplifies the operation steps of operators for high-altitude operations, and reduces the risk of operators for high-altitude operations to a certain extent. During the fastening process, the operator maintains a comfortable working posture, improves the safety of high-altitude operations, and saves the physical strength of the operator. Compared with the realization of screw fastening by using two spanners, the utility model has the characteristics of good flexibility and simple operation.
本实用新型的应用,为提高输电线路杆塔组立和检修的工作效率起到了极大的推动作用,缩短了杆塔组立和检修的时间,使工程工期和停电时间大大减少,提高了供电的可靠性。本实用新型使一颗螺丝紧固的平均时间由90秒缩短到50秒,按照一基铁塔1000颗螺丝计算,一基铁塔在螺丝紧固工作中节省的时间为: The application of the utility model greatly promotes the work efficiency of tower erection and maintenance of transmission lines, shortens the time of tower erection and maintenance, greatly reduces the construction period and power failure time, and improves the reliability of power supply sex. The utility model shortens the average time of fastening a screw from 90 seconds to 50 seconds. According to the calculation of 1000 screws in a base iron tower, the time saved in the screw fastening work of a base iron tower is:
1000颗*(90秒-65秒)=25000秒≈6.94小时 1000pcs * (90 seconds - 65 seconds) = 25000 seconds ≈ 6.94 hours
以一条输电线路50基铁塔计算,一条输电线路的建设工期将缩短: Calculated on the basis of 50 towers for a transmission line, the construction period of a transmission line will be shortened:
6.94小时*50基÷24小时/天≈14.46天 6.94 hours * 50 basis ÷ 24 hours/day ≈ 14.46 days
因此,结构合理、操作方便、节省体力的新型输电线路铁塔螺丝紧固工具具有较强的实用性、客观的安全效益及经济效益,适合在输电线路杆塔组立和检修工作中大规模的使用。同时,能够推广到在需要螺丝紧固面临同样问题的其他领域。 Therefore, the novel transmission line iron tower screw fastening tool with reasonable structure, convenient operation and energy saving has strong practicability, objective safety benefits and economic benefits, and is suitable for large-scale use in the erection and maintenance of transmission line poles and towers. At the same time, it can be extended to other fields that require screw fastening and face the same problem.
附图说明: Description of drawings:
图1为本实用新型的结构示意图; Fig. 1 is the structural representation of the utility model;
图2为图1的A位置的侧视图。 FIG. 2 is a side view of position A in FIG. 1 .
具体实施方式:下面结合附图对实用新型的具体实施方式做详细说明: The specific embodiment: the specific embodiment of the utility model is described in detail below in conjunction with accompanying drawing:
实施例:一种输电线路铁塔螺丝紧固工具(参见图1、图2),它包括止转扳手1,防止在紧固螺丝时螺栓转动。止转扳手1通过连接杆5与连接板4连接在一起,止转扳手1与连接杆5之间通过螺栓6锁紧;连接杆5与连接板4之间可在第一连接部位7通过铆钉铆合固定。连接板4上部嵌套有锁紧扳手2,锁紧扳手2通过连接板4上部的卡槽8嵌套在连接板4内,锁紧扳手2可以旋转和左右移动,达到可随意调节止转扳手1与锁紧扳手2间距离和螺丝紧固的目的。止转扳手1与卡槽8之间的距离为100mm,即锁紧扳手2移动的距离可达100mm,大于所有杆塔螺栓的螺杆长度。锁紧扳手2连接棘轮扳手3,锁紧扳手2与棘轮扳手3之间通过第三连接部位9焊接固定,棘轮扳手3可以通过调节实现正转和反转。止转扳手1和锁紧扳手2都采用梅花套筒扳手参见图2,能够保证从各个角度都能紧扣在六角螺栓或六角螺帽上,从而轻松地将工具卡在螺杆上,通过调节锁紧扳手2的位置,使止转扳手1贴合在螺栓头部的同时,锁紧扳手2紧密贴合在螺帽上,转动棘轮扳手3,锁紧扳手2带动螺帽在螺杆上不停移动,螺丝紧固时向止转扳手1方向移动,松动时向卡槽8方向移动,最终完成螺丝紧固和松动工作。 Embodiment: A power transmission line iron tower screw fastening tool (see Fig. 1, Fig. 2), which includes a stop wrench 1 to prevent the bolt from rotating when the screw is fastened. The anti-rotation wrench 1 is connected with the connecting plate 4 through the connecting rod 5, and the bolt 6 is used to lock the anti-rotating wrench 1 and the connecting rod 5; Riveted to secure. The upper part of the connecting plate 4 is nested with a locking wrench 2, and the locking wrench 2 is nested in the connecting plate 4 through the slot 8 on the upper part of the connecting plate 4. The locking wrench 2 can rotate and move left and right, so that the stop wrench can be adjusted at will. 1. The distance between the locking wrench and 2. The purpose of screw tightening. The distance between the anti-rotation wrench 1 and the slot 8 is 100mm, that is, the moving distance of the locking wrench 2 can reach 100mm, which is greater than the screw length of all tower bolts. The locking wrench 2 is connected to the ratchet wrench 3, and the locking wrench 2 and the ratchet wrench 3 are welded and fixed by the third connection part 9, and the ratchet wrench 3 can be adjusted to realize forward rotation and reverse rotation. Both the anti-rotation wrench 1 and the lock wrench 2 use a torx socket wrench, as shown in Figure 2, which can ensure that they can be tightly fastened on the hexagonal bolt or hexagonal nut from all angles, so that the tool can be easily clamped on the screw rod. By adjusting the lock Tighten the position of the wrench 2 so that the anti-rotation wrench 1 fits on the head of the bolt, and the locking wrench 2 fits closely on the nut. Turn the ratchet wrench 3, and the locking wrench 2 drives the nut to move continuously on the screw rod. , when the screw is tightened, move to the direction of the anti-rotation wrench 1, and when it is loose, move to the direction of the card slot 8, and finally complete the screw tightening and loosening work.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520778981.2U CN205148172U (en) | 2015-10-10 | 2015-10-10 | Transmission line iron tower screw fastening instrument |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520778981.2U CN205148172U (en) | 2015-10-10 | 2015-10-10 | Transmission line iron tower screw fastening instrument |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN205148172U true CN205148172U (en) | 2016-04-13 |
Family
ID=55683911
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520778981.2U Expired - Fee Related CN205148172U (en) | 2015-10-10 | 2015-10-10 | Transmission line iron tower screw fastening instrument |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN205148172U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105269498A (en) * | 2015-10-10 | 2016-01-27 | 国网山东省电力公司烟台供电公司 | Screw fastening tool of power transmission line iron tower |
| CN109571337A (en) * | 2018-12-17 | 2019-04-05 | 包头钢铁(集团)有限责任公司 | A kind of narrow operation area pipe flange fastening method |
-
2015
- 2015-10-10 CN CN201520778981.2U patent/CN205148172U/en not_active Expired - Fee Related
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105269498A (en) * | 2015-10-10 | 2016-01-27 | 国网山东省电力公司烟台供电公司 | Screw fastening tool of power transmission line iron tower |
| CN109571337A (en) * | 2018-12-17 | 2019-04-05 | 包头钢铁(集团)有限责任公司 | A kind of narrow operation area pipe flange fastening method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105269498A (en) | Screw fastening tool of power transmission line iron tower | |
| CN205148172U (en) | Transmission line iron tower screw fastening instrument | |
| CN105972021B (en) | For steel structure connection can unilateral operation attachment device and electronic installation tool | |
| CN105171665B (en) | A kind of transmission tower fastened by screw aid | |
| CN105952738B (en) | It is a kind of for steel structure connection can unilateral operation attachment device and installation tool | |
| CN201118146Y (en) | Clamp type hot-line work fixture | |
| CN206273516U (en) | Livewire work rocking arm spanner | |
| CN204935511U (en) | A kind of transmission tower fastened by screw aid | |
| CN203380823U (en) | Telescopic rod of socket wrench | |
| CN217292133U (en) | Double-end pointed tail ratchet wrench | |
| CN205823820U (en) | A kind of for steel structure connection can the attachment means of unilateral operation and installation tool | |
| CN207534714U (en) | A kind of high-strength double end bolt group applies the sleeve crossover device of torque operation | |
| CN202344473U (en) | Torsion reacting force device of hexagon bolt spanner | |
| CN103358260A (en) | Method and tool for screwing wind turbine generator system gear case stud in base body rapidly | |
| CN106392969B (en) | Livewire work rocking arm spanner | |
| CN201877732U (en) | Live line tool for fastening insulator nuts | |
| CN223164844U (en) | A square mounting nut for quick positioning and tightening | |
| CN202377962U (en) | Wrench for fast installing bolts | |
| CN201960497U (en) | Special tool for installing coiling machine roller way motor bolt | |
| CN205497315U (en) | Spanner auxiliary device | |
| CN223431552U (en) | A movable wrench that can be operated in a confined space | |
| CN203804910U (en) | Long bolt fastening nut device | |
| CN212653351U (en) | Duckbilled adjustable portable wrench | |
| CN218137517U (en) | Clamp for building beam | |
| CN102570344B (en) | Charged tool for tightening screw cap of insulator |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160413 Termination date: 20161010 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |