CN205138413U - Three probe timesharing detect moderate -low speed magnetic levitation train gap measuring apparatus - Google Patents

Three probe timesharing detect moderate -low speed magnetic levitation train gap measuring apparatus Download PDF

Info

Publication number
CN205138413U
CN205138413U CN201520869732.4U CN201520869732U CN205138413U CN 205138413 U CN205138413 U CN 205138413U CN 201520869732 U CN201520869732 U CN 201520869732U CN 205138413 U CN205138413 U CN 205138413U
Authority
CN
China
Prior art keywords
probe
coil
switch
measuring apparatus
controlled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520869732.4U
Other languages
Chinese (zh)
Inventor
靖永志
张昆仑
王滢
董金文
刘国清
郭小舟
何飞
廖海军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
Original Assignee
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University filed Critical Southwest Jiaotong University
Priority to CN201520869732.4U priority Critical patent/CN205138413U/en
Application granted granted Critical
Publication of CN205138413U publication Critical patent/CN205138413U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a three probe timesharing detect moderate -low speed magnetic levitation train gap measuring apparatus, include with the automobile body on the controllable high frequency switch that links to each other of high frequency signal source, the probe coil that links to each other with controllable high frequency switch, the signal detection circuit who is connected with the coil of popping one's head in. Measuring device comprises three probe the same completely, every probe contains a detecting coil, three probe center point -blank, the distance all be D between the arbitrary two adjacent hub of a spools, and the size of every coil and winding to the same, every detecting coil input is connected to three controllable high frequency switch (K1, K2 and K3) respectively, three high frequency switch is associative with high frequency signal source (S1, S2 and S3) respectively, the output of every detecting coil links to each other with mutually independent signal detection circuit (PS1, PS2 and PS3) respectively, controllable high frequency switch and signal detection circuit still link to each other with time schedule controller (T) simultaneously. No frequency signal disturbs between the three probe of this measuring device, mutual independence between three signal detection circuit's the output signal, the frequency of three signal source can be the same also may not with, any operating condition of monitoring channel does not all the way influence the testing result of other passageways.

Description

A kind of three probe timesharing detect medium-and low-speed maglev train gap measuring apparatus
Technical field
The utility model relates to a kind of magnetic floating train suspending gap non-contact measurement apparatus.
Background technology
Magnetic-levitation train safe operation needs to detect levitation gap between train electromagnet and track in real time non-contactly, and the track of medium-and low-speed maglev train is " F type " track, and under various line condition, adjacent orbit junction remains with the gap of 1 ~ 4cm.Magnetic float car commonly use gap measuring apparatus be mostly based on eddy current principle realize measure, when current vortex levitation gap measurement mechanism moves in parallel in F rail detection faces, when magnetic test coil moves to track seam crossing, its output valve is by significant change, produce the measuring error of vertical gap width, therefore general magnetic-levitation train gap measurement at least needs two two magnetic test coils keeping certain distance, and when a coil is affected by seam, another coil still can detect correct gap width.Simultaneously for ensureing the reliable and security performance of the height of magnetic-levitation train, even if when adopting three cover probes to make one to pop one's head in lose efficacy, suspension controller still can be made to obtain correct gap width.
Existing medium-and low-speed maglev train levitation gap measures many employings No-contact Displacement Measurement device (gap measuring apparatus), need three probe coils to work simultaneously, although keep certain intervals distance between coil, but the space magnetic field interference between coil still exists, therefore the testing result of any one probe is all by the impact of another two coil working states, and its accuracy of detection and accuracy are all affected.
The main deficiency of present technology is exactly that three coils are when normally working, there is electromagnetic interference (EMI) each other, and when a certain map duty sudden change, the testing result of other two-way also can be affected, therefore its measuring accuracy is low, poor reliability, cannot meet magnetic and float car and operationally carry out controlling to guarantee the requirement that levitation gap high precision is adjustable in real time accurately.
Utility model content
The purpose of this utility model is to provide a kind of three probe timesharing and detects medium-and low-speed maglev train gap measuring apparatus, this measurement mechanism accurately can detect train levitation gap value, without space magnetic field interference between triple coil, any one probe coil does not affect by other two probe coil working conditions.
The utility model is for realizing its utility model object, and the technical scheme adopted is:
A kind of three probe timesharing detect medium-and low-speed maglev train gap measuring apparatus, comprise the controlled HF switch be connected with high-frequency signal source on car body, the probe coil be connected with controlled HF switch, the signal deteching circuit be connected with probe coil; It is characterized in that, measurement mechanism is made up of three duplicate probes; Each probe comprises a magnetic test coil, and point-blank, the spacing of arbitrary neighborhood two hub of a spool is all D to three center probes, and the size of each coil with around to identical; Each magnetic test coil input end is connected respectively to three controlled HF switch (K1, K2 and K3); Three HF switch are connected with high-frequency signal source (S1, S2 and S3) respectively; The output terminal of each magnetic test coil is connected with separate signal deteching circuit (PS1, PS2 and PS3) respectively; Controlled HF switch and signal deteching circuit also make the time schedule controller (T) of three time-sharing works of popping one's head in be connected with generation simultaneously.
Each high-frequency signal source is connected with corresponding magnetic test coil through corresponding controlled HF switch, and three high-frequency signal sources (S1, S2 and S3) are separate, and its frequency can be the same or different.Each magnetic test coil size is identical, around to identical, point-blank, staggered without space overlap between coil, any two adjacent windings central points are all D apart to the mid point of three coils mutually.Three gate-controlled switches (K1, K2 and K3) are controlled by time schedule controller (T), only have a switch to close in random time section.Three signal deteching circuits (PS1, PS2 and PS3) are also by being controlled by time schedule controller (T), only when respective switch closes, signal deteching circuit just detects corresponding signal, and the timesharing of three probes detects three independently gap widths.Any one probe coil does not affect by other two probe coil working conditions, independent mutually between the output of three signal deteching circuits (PS1, PS2 and PS3).
Like this, the duty of three magnetic test coils is subject to the control of three controlled HF switch, three coil time-sharing works can be made to the logic level that time schedule controller sends excessively, when time schedule controller (T) sends logic level, make to visit K switch 1 and close the t time, and at this moment between when K2 and K3 disconnects in section, magnetic test coil L1 is by the excitation of high-frequency signal source S1, normal work, the logic level that its information detection is also subject to time schedule controller controls normal work, thus this road signal exports current detection value.And now due to K switch 2 and K3 not closed, therefore magnetic test coil L2 and L3 opens a way, working coil L1 cannot produce induction current in L2 and the L3 coil of open circuit, therefore L2 and L3 coil can not affect the space distribution in L1 coil working magnetic field, L2 and L3 coil also can not produce magnetic interference to the external space when opening a way and not working simultaneously.Now passage 2 and passage 3 exported the detected value in a upper cycle.In like manner, when K2 closes K1 with K3 disconnect and K3 close and K1 with K2 disconnect time each coil duty similar.Therefore three probe timesharing detector gap values, export independently glitch-free three road gap widths mutually.
Because the frequency of operation of eddy current measurement device can be arranged on more than 2MHz, and the frequency of operation of suspension controller is no more than 20KHz, the frequency of operation of driving source is more than 100 times of final required effective clearance signal as can be seen here, therefore the turn-on cycle of HF switch is suitably set, three tunnel testing results can be made all to meet the Signal Regulation requirement of suspension controller.
Compared with prior art, the beneficial effects of the utility model are:
Do not have magnetic Field Coupling to disturb between the magnetic test coil of one, each road clearance measurement, improve the accuracy of detection of gap signal;
Independent between the output of two, each signal deteching circuit, the testing result on any road does not affect by the duty of other two-way, even if when catastrophic failure appears in a certain road, other two-way still can normally work, and improves the reliability of measurement mechanism;
Three, owing to there is no magnetic interference between each probe, only need to consider adjacent F rail gap width index when designing the spacing of adjacent probes, do not consider the magnetic Field Coupling interference between adjacent windings, therefore can reduce the distance between adjacent probes, measurement mechanism volume and weight is optimized.
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
Accompanying drawing explanation
Fig. 1 is the arrangement of each magnetic test coil of the utility model embodiment and the schematic diagram of electric principle thereof.
Fig. 2 is the electrical principle structural representation of the utility model embodiment.
Fig. 3 is the steering logic schematic diagram that the time schedule controller of the utility model embodiment exports.
Embodiment
Fig. 1 and Fig. 2 illustrates, a kind of embodiment of the present utility model is: a kind of three probe timesharing detect medium-and low-speed maglev train gap measuring apparatus, comprise the controlled HF switch be connected with high-frequency signal source on car body, the probe coil be connected with controlled HF switch, the signal deteching circuit be connected with probe coil; It is characterized in that, measurement mechanism is made up of three duplicate probes; Each probe comprises a magnetic test coil, and point-blank, the spacing of arbitrary neighborhood two hub of a spool is all D to three center probes, and the size of each coil with around to identical; Each magnetic test coil input end is connected respectively to three controlled HF switch (K1, K2 and K3); Three HF switch are connected with high-frequency signal source (S1, S2 and S3) respectively; The output terminal of each magnetic test coil is connected with separate signal deteching circuit (PS1, PS2 and PS3) respectively; Controlled HF switch and signal deteching circuit are also connected with time schedule controller (T) simultaneously.
Fig. 3 illustrates, time schedule controller of the present utility model controls three controlled HF switch (K1, K2 and K3) simultaneously, three switches close successively, phase 120 degree, synchronization is a closed switch only, namely synchronization only has a magnetic test coil job, and three coil timesharing detect and export independently gap width.
Each high-frequency signal source is connected with corresponding magnetic test coil through corresponding controlled HF switch, and three high-frequency signal sources (S1, S2 and S3) are separate, and its frequency can be the same or different.Each magnetic test coil size is identical, around to identical, point-blank, staggered without space overlap between coil, any two adjacent windings central points are all D apart to the mid point of three coils mutually.Three gate-controlled switches (K1, K2 and K3) are controlled by time schedule controller (T), only have a switch to close in random time section.Three signal deteching circuits (PS1, PS2 and PS3) are also by being controlled by time schedule controller (T), only when respective switch closes, signal deteching circuit just detects corresponding signal, and the timesharing of three probes detects three independently gap widths.Any one probe coil does not affect by other two probe coil working conditions, independent mutually between the output of three signal deteching circuits (PS1, PS2 and PS3).

Claims (6)

1. three probe timesharing detect a medium-and low-speed maglev train gap measuring apparatus, comprise the controlled HF switch be connected with high-frequency signal source on car body, the probe coil be connected with controlled HF switch, the signal deteching circuit be connected with probe coil; It is characterized in that, measurement mechanism is made up of three duplicate probes; Each probe comprises a magnetic test coil, and point-blank, the spacing of arbitrary neighborhood two hub of a spool is all D to three center probes, and the size of each coil with around to identical; Each magnetic test coil input end is connected respectively to three controlled HF switch (K1, K2 and K3); Three HF switch are connected with high-frequency signal source (S1, S2 and S3) respectively; The output terminal of each magnetic test coil is connected with separate signal deteching circuit (PS1, PS2 and PS3) respectively; Controlled HF switch and signal deteching circuit also make the time schedule controller (T) of three time-sharing works of popping one's head in be connected with generation simultaneously.
2. a kind of three probe timesharing according to claim 1 detect medium-and low-speed maglev train gap measuring apparatus, it is characterized in that: the separate setting of described three high-frequency signal sources (S1, S2 and S3), its frequency can be the same or different.
3. a kind of three probe timesharing according to claim 1 detect medium-and low-speed maglev train gap measuring apparatus, it is characterized in that: described probe coil arrangement concrete structure is: each magnetic test coil size is identical, around to identical, the mid point of three coils point-blank, staggered without space overlap between coil, any two adjacent windings central points are at a distance of being all D mutually.
4. a kind of three probe timesharing according to claim 1 detect medium-and low-speed maglev train gap measuring apparatus, it is characterized in that: described gate-controlled switch (K1, K2 and K3) is controlled by time schedule controller (T) in random time section, only having a switch to close.
5. a kind of three probe timesharing according to claim 1 detect medium-and low-speed maglev train gap measuring apparatus, it is characterized in that: described signal deteching circuit (PS1, PS2 and PS3) is by being controlled by time schedule controller (T), only when respective switch closes, signal deteching circuit just detects corresponding signal, and the timesharing of three probes detects three independently gap widths.
6. a kind of three probe timesharing according to claim 1 detect medium-and low-speed maglev train gap measuring apparatus, it is characterized in that: independent mutually between the output of described three signal deteching circuits (PS1, PS2 and PS3).
CN201520869732.4U 2015-11-03 2015-11-03 Three probe timesharing detect moderate -low speed magnetic levitation train gap measuring apparatus Expired - Fee Related CN205138413U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520869732.4U CN205138413U (en) 2015-11-03 2015-11-03 Three probe timesharing detect moderate -low speed magnetic levitation train gap measuring apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520869732.4U CN205138413U (en) 2015-11-03 2015-11-03 Three probe timesharing detect moderate -low speed magnetic levitation train gap measuring apparatus

Publications (1)

Publication Number Publication Date
CN205138413U true CN205138413U (en) 2016-04-06

Family

ID=55624199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520869732.4U Expired - Fee Related CN205138413U (en) 2015-11-03 2015-11-03 Three probe timesharing detect moderate -low speed magnetic levitation train gap measuring apparatus

Country Status (1)

Country Link
CN (1) CN205138413U (en)

Similar Documents

Publication Publication Date Title
EP3321125A1 (en) Intelligent electric phase splitting device for alternating-current electrified railway
CN105333810B (en) The probe timesharing detection medium-and low-speed maglev train gap sensor of one kind three
CN101734172B (en) Magnetic suspension train suspension spacing sensor capable of compensating slot effect
CN105914801A (en) Segmented-switching wireless electric energy transmission system primary side power supply device and switching method thereof
CN104251659A (en) Fault detection of four wire variable differential transformer sensors
CN102650573B (en) A kind of electric locomotive automatic passing over of neutral section function detection device
CN104276186B (en) The monitoring method of a kind of point tongue and the closely connected spacing of base rail
CN102253308A (en) Method for determining asymmetric short circuit fault of long stator according to negative sequence voltage
CN205245985U (en) Twin coil self -diagnosis maglev train that singly pops one's head in suspension air gap measuring device
CN109774489B (en) Two-by-two-out-of-two redundant maglev train suspension sensor and control method
CN205138413U (en) Three probe timesharing detect moderate -low speed magnetic levitation train gap measuring apparatus
CN100494877C (en) Device for measuring distance between moving object and its railway
CN103424627B (en) The method of double-end measurement parallel grid line zero-sequence impedance
CN105352424A (en) Single-probe three-coil maglev train gap sensor with fault location function
CN205138414U (en) Three coil maglev train gap measuring apparatus singly pop one's head in with fault locating function
CN110481387A (en) A kind of train operation state detection method and device in neutral-section passing system
CN103552581B (en) Wheel sensor
CN203511692U (en) Wheel sensor
CN105818838B (en) A kind of axle count sensor and meter shaft detection method
CN105445526B (en) The measurement structure of single cable insulation leakage current under a kind of service condition
CN201589599U (en) Levitation space measuring apparatus of maglev train capable of compensating cogging effect
CN205365606U (en) On -vehicle induction receive device of auto -passing phase separation system based on magnesensor
EA027383B1 (en) Method for registration of train wage wheels passage and device for implementation thereof
CN102253309B (en) Method for determining multipoint earth faults of long stator according to line voltage
CN103575959A (en) Novel non-contact three-phase current measuring method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160406

Termination date: 20181103

CF01 Termination of patent right due to non-payment of annual fee