CN205118450U CN201520789503.1U CN201520789503U CN205118450U CN 205118450 U CN205118450 U CN 205118450U CN 201520789503 U CN201520789503 U CN 201520789503U CN 205118450 U CN205118450 U CN 205118450U
Authority
CN
China
Prior art keywords
concrete
pump pipe
fixing device
fixed
concrete pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520789503.1U
Other languages
Chinese (zh)
Inventor
于海申
裴鸿斌
柯子平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201520789503.1U priority Critical patent/CN205118450U/en
Application granted granted Critical
Publication of CN205118450U publication Critical patent/CN205118450U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides a concrete pump pipe fixing device, include: concrete pier, concrete pier is last to have seted up a plurality of through -holes, the connecting rod, the connecting rod passes through -hole and floor, the connecting rod will concrete pier is together fixed with the floor, the bearing piece, bearing piece rigid coupling in last and the bearing concrete pump pipe of concrete pier, and mounting, the mounting rigid coupling in on the bearing piece, concrete pump pipe is fixed in the mounting with between the bearing piece. The utility model discloses a set up the through -hole on concrete pier, pass with the connecting rod the through -hole is fixed concrete pier on the floor, rigid coupling bearing piece on concrete pier, be connected with the mounting on the bearing piece, fix concrete pump pipe between mounting and bearing piece. Characteristic more than synthesizing makes the utility model relates to a concrete pump pipe fixing device has that simple structure, steadiness are good, repeatedly usable's characteristics.

Description

Concrete pump pipe fixing device
Technical field
The utility model relates to a kind of construction of super highrise building field, is specifically related to a kind of concrete pump pipe fixing device.
Background technique
Along with the rise of domestic and international skyscraper, concrete pumping usually selects ultrahigh pressure pumping mode, this fixedly having higher requirement to pump line.In present stage construction, the scaffold that adopts is fixed more, or uses concrete directly to be fixed by pump line.The mode that the former is fixed with scaffold is very unstable exists potential safety hazard, and the latter uses concrete directly fixedly to make engineering work load large and extremely unfavorable to green construction.
Therefore, a kind of concrete pump pipe fixing device that can overcome the above problems is needed.
Model utility content
In view of the foregoing, existing the utility model provides a kind of concrete pump pipe fixing device, and it has the advantages such as structure is simple, steadiness good, reusable.
For achieving the above object, the technological scheme that the utility model is taked is:
A kind of concrete pump pipe fixing device, comprising: concrete pier, described concrete pier offers multiple through hole; Connecting rod, described connecting rod is through described through hole and floor, and described concrete pier and floor are fixed together by described connecting rod; Supporting parts, described supporting parts to be fixed on described concrete pier and support concrete pump pipe; And fixed block, described fixed block is fixed in described supporting parts to be fixed on described supporting parts by described concrete pump pipe.
The beneficial effects of the utility model are, by offering through hole on concrete pier, through described through hole, concrete pier is fixed on floor with connecting rod, affixed supporting parts on concrete pier, described supporting parts is connected with fixed block, concrete pump pipe is fixed between fixed block and supporting parts.Comprehensive above feature, a kind of concrete pump pipe fixing device of the utility model is had, and structure is simple, steadiness good, reusable feature.
The further improvement of the utility model concrete pump pipe fixing device is, described connecting rod is split bolt, the diameter 3mm to 5mm less of the diameter of described through hole of described split bolt.
The further improvement of the utility model concrete pump pipe fixing device is, described split bolt comprises screw rod and nut, described screw rod is arranged in through hole and the floor of described concrete pier, and described concrete pier and floor link together by the two ends that described nut is fixed on described screw rod.
The further improvement of the utility model concrete pump pipe fixing device is, described supporting parts comprises I-steel, and the bottom of described I-steel is also welded with firm muscle, and described firm muscle is embedded in described concrete pier.
The further improvement of the utility model concrete pump pipe fixing device is, described fixed block is U-shaped steel, described U-shaped steel forms the first joint and the second joint along the two ends of bearing of trend, described first joint and described second joint are provided with screw thread and are arranged in the top of described supporting parts, and described first joint and the second joint are fixed on described supporting parts by nut.
The further improvement of the utility model concrete pump pipe fixing device is, described concrete pier is also provided with the multiple lifting member being convenient to concrete pier movement.
The further improvement of the utility model concrete pump pipe fixing device is, described lifting member is suspension ring.
Accompanying drawing explanation
Fig. 1 is the utility model concrete pump pipe fixing device structure front view.
Fig. 2 is the utility model concrete pump pipe fixing device structure side view.
Embodiment
For the benefit of to the understanding of structure of the present utility model, be described below in conjunction with drawings and Examples.
Please refer to Fig. 1, Fig. 2, Fig. 1 is the structure front view of the utility model concrete pump pipe fixing device, and Fig. 2 is the structure side view of the utility model concrete pump pipe fixing device.
As depicted in figs. 1 and 2, the utility model provides a kind of concrete pump pipe fixing device, comprising: concrete pier 1, and described concrete pier 1 vertically offers multiple through hole; Connecting rod 2, described concrete pier 1 is fixed together with floor 4 through described through hole and floor 4 by described connecting rod 2; Supporting parts 3, described supporting parts 3 to be fixed on described concrete pier 1 and support concrete pump pipe 5; And fixed block 6, described fixed block 6 is fixed in described supporting parts 3 so that concrete pump pipe 5 is fixed on described supporting parts 3.
Below said modules is described in detail:
As shown in Figure 1 and Figure 2, connecting rod 2 passes through hole and the floor 4 of concrete pier 1, and the two ends fastening nuts of connecting rod 2, makes concrete pier 1 and floor 4 be fixed together.In order to achieve the above object better, preferred version is: connecting rod 2 adopts split bolt, floor 4 is offered fixed hole on the position corresponding with the through hole of concrete pier 1, and the diameter of fixed hole is identical with the diameter of through hole, and all large than the diameter of split bolt 3mm to 5mm.Split bolt comprises screw rod and nut, and by screw rod through after through hole and fixed hole, the two ends fastening nuts of screw rod, makes concrete pier 1 and floor 4 be fixed together.
Connecting rod 2 can be also stud bolt, and the two ends of stud bolt are provided with screw thread and are connected with nut, after stud bolt passes the fixed hole on concrete through hole and floor, and two ends nut screwing clamping, thus concrete pier and floor are fixed together.
The effect of supporting parts 3 is that support lives concrete pump pipe 5, preferably, supporting parts 3 comprises I-steel, the top of I-steel and bottom are respectively a rectangular steel plates, the bottom of I-steel is also vertically welded with firm muscle 33, firm muscle 33 is embedded in concrete pier 1 (can be welded with the reinforcing bar of a transverse direction in the bottom of firm muscle 33 to strengthen the steadiness of firm muscle 33), makes more stable being fixed on concrete pier 1 of whole supporting parts 3.
The effect of fixed block 6 is fixed on supporting parts 3 by concrete pump pipe 5, and preferably, fixed block 6 is U-shaped steel, the width of U-shaped steel internal diameter and the diameter of concrete pump pipe 5 suitable.U-shaped steel forms the first joint 61 and the second joint 62 along the two ends of bearing of trend, first joint 61 and the second joint 62 are equipped with screw thread, and the first joint 61 and the second joint 62 are arranged in the top of supporting parts 3 respectively and are fixed on supporting parts 3 with nut, fixed block 6 and supporting parts 3 are linked together.
In view of the weight of concrete pier 1, the conveniently movement of concrete pier 1 and installation, concrete pier 1 is also provided with multiple lifting member 7, lifting member 7 is suspension ring, suspension ring comprise an arched ribs and are connected to two long straight muscle at arched ribs two ends, and two long straight muscle are vertically embedded in concrete pier, in order to strengthen the stationarity of long straight muscle in concrete pier, preferably, horizontal reinforcing bar is welded with in the bottom of long straight muscle.
The as installed of the utility model concrete pump pipe fixing device be operating as:
The utility model concrete pump pipe fixing device is placed in pump line fixed position, floor is offered and concrete pier lead to the hole site fixed hole one to one; By split bolt through through hole and fixed hole, concrete pier and floor are linked together; Concrete pump pipe is placed on supporting parts, with fixed block, concrete pump pipe is fixed on supporting parts; After having constructed, dismantle fixed block and concrete pump pipe, withdrawn the utility model by lifting member with mobile device.
Below embodiment has been described in detail the utility model by reference to the accompanying drawings, and those skilled in the art can make multiple change to the utility model according to the above description.Thus, under the prerequisite not violating claim aim of the present utility model, some details in embodiment should not formed restriction of the present utility model, the utility model by the scope that defines using appended claims as protection domain.

Claims (7)

1. a concrete pump pipe fixing device, is characterized in that comprising:
Concrete pier, described concrete pier offers multiple through hole;
Connecting rod, described connecting rod is through described through hole and floor, and described concrete pier and floor are fixed together by described connecting rod;
Supporting parts, described supporting parts to be fixed on described concrete pier and support concrete pump pipe; And
Fixed block, described fixed block is fixed in described supporting parts to be fixed on described supporting parts by described concrete pump pipe.
2. concrete pump pipe fixing device according to claim 1, is characterized in that: described connecting rod is split bolt, the diameter 3mm to 5mm less of the diameter of described through hole of described split bolt.
3. concrete pump pipe fixing device according to claim 2, it is characterized in that: described split bolt comprises screw rod and nut, described screw rod is arranged in through hole and the floor of described concrete pier, and described concrete pier and floor link together by the two ends that described nut is fixed on described screw rod.
4. concrete pump pipe fixing device according to claim 1, is characterized in that: described supporting parts comprises I-steel, and the bottom of described I-steel is also welded with firm muscle, and described firm muscle is embedded in described concrete pier.
5. concrete pump pipe fixing device according to claim 4, it is characterized in that: described fixed block is U-shaped steel, described U-shaped steel forms the first joint and the second joint along the two ends of bearing of trend, described first joint and described second joint are provided with screw thread and are arranged in the top of described supporting parts, and described first joint and the second joint are fixed on described supporting parts by nut.
6. concrete pump pipe fixing device according to claim 1, is characterized in that: described concrete pier is also provided with the multiple lifting member being convenient to concrete pier movement.
7. concrete pump pipe fixing device according to claim 6, is characterized in that: described lifting member is suspension ring.
CN201520789503.1U 2015-10-12 2015-10-12 Concrete pump pipe fixing device Expired - Fee Related CN205118450U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520789503.1U CN205118450U (en) 2015-10-12 2015-10-12 Concrete pump pipe fixing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520789503.1U CN205118450U (en) 2015-10-12 2015-10-12 Concrete pump pipe fixing device

Publications (1)

Publication Number Publication Date
CN205118450U true CN205118450U (en) 2016-03-30

Family

ID=55574064

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520789503.1U Expired - Fee Related CN205118450U (en) 2015-10-12 2015-10-12 Concrete pump pipe fixing device

Country Status (1)

Country Link
CN (1) CN205118450U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385982A (en) * 2018-03-15 2018-08-10 广厦建设集团有限责任公司 A kind of Super High concrete pumping pipe and its installation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385982A (en) * 2018-03-15 2018-08-10 广厦建设集团有限责任公司 A kind of Super High concrete pumping pipe and its installation method

Similar Documents

Publication Publication Date Title
CN203150936U (en) Power distribution cabinet pedestal
CN201490637U (en) Fixing frame for mounting cable bridge on wall body
CN203834915U (en) Adjustable steel beam suspension operation platform
CN206134422U (en) Multi -functional transformer mounting bracket
CN204717144U (en) A kind of concrete pump pipe setting tool cribbing
CN205118450U (en) Concrete pump pipe fixing device
CN203860787U (en) Novel connection support foot
CN105042196A (en) Spring damping vibration attenuation pipeline support with adjustable prestress
CN215484886U (en) Adjustable strutting arrangement for building
CN205116736U (en) Superelevation compressive concrete pump line fixing device
CN205857006U (en) Novel Bailey bracket
CN205444889U (en) Support arrangement for horizontal prefabricated component
CN204057560U (en) Be attached to attached wall connection structure in the jacking system of section
CN211647537U (en) Communication tower reinforcing apparatus
CN204663027U (en) For the bracing or strutting arrangement that rack is installed
CN204062152U (en) High-pressure service pump pipe fixing device
CN209398928U (en) A kind of fixed bracket of pump line attached wall
CN203373661U (en) Movable operation platform device below cantilever arm of steel-structure bridge
CN105257966A (en) Rack of power transmission and distribution equipment
CN204901080U (en) Spring damping damping pipeline bracket with adjustable prestressing force
CN204645590U (en) A kind of tool-type builder's jack diagonal supporting member
CN205476444U (en) Light -duty support post based on low level jacking die carrier system
CN206203725U (en) Small-sized sustaining wall
CN205172036U (en) Formwork support equipment for building engineering
CN214942404U (en) T beam formwork

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160330

Termination date: 20201012

CF01 Termination of patent right due to non-payment of annual fee