CN205088917U CN201520802050.1U CN201520802050U CN205088917U CN 205088917 U CN205088917 U CN 205088917U CN 201520802050 U CN201520802050 U CN 201520802050U CN 205088917 U CN205088917 U CN 205088917U
Authority
CN
China
Prior art keywords
layer
anchor pole
anchor
draw
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520802050.1U
Other languages
Chinese (zh)
Inventor
黄华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHENZHEN NAIMOTE GRADE LEVEL TECHNOLOGY Co Ltd
Original Assignee
SHENZHEN NAIMOTE GRADE LEVEL TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN NAIMOTE GRADE LEVEL TECHNOLOGY Co Ltd filed Critical SHENZHEN NAIMOTE GRADE LEVEL TECHNOLOGY Co Ltd
Priority to CN201520802050.1U priority Critical patent/CN205088917U/en
Application granted granted Critical
Publication of CN205088917U publication Critical patent/CN205088917U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a draw anchor air defense drum ground structure, technological purpose provides a disappearance hollowing when implementing, reduces delamination simultaneously, and then improves the life's on ground draw anchor air defense drum ground structure. Water the layer under including and water the layer on and, under water the layer and water on and be equipped with the stock between the layer. The utility model discloses used and used prefabricated stock to draw the structure of anchor very reliable, impelled whole terrace structure to become a whole, improved the life on ground. Use in being applicable to the terrace technique.

Description

Draw the anti-hollowing earth construction of anchor
Technical field
The utility model relates to a kind of earth construction, in particular, relates to a kind of ground concrete structure be applied in building.
Background technology
In the prior art, the structure of ground concrete is generally divided into when building carries out for 2 times, i.e. the building of structural slab, and the building of facing concrete.Operation is: after structural slab layer of concrete is built, and in order to top layer carries out looking for slope, and repair planeness, can carry out building of surface layer pea gravel concreten, this layer concrete thickness generally only has 5-8 centimetre.Because surface layer pea gravel concreten is too thin, and poor with structural slab concrete bonding power, often there is " hollowing ", " delamination " phenomenon.In actual use, the damage on ground is very easily caused, greatly reduction of service life.
Summary of the invention
Technical purpose of the present utility model overcomes the structure of ground concrete in prior art to build the rear phenomenon easily occurring hollowing and delamination, there is provided a kind of and do not occur hollowing when implementing, reduce delamination simultaneously, so improve ground application life draw the anti-hollowing earth construction of anchor.
For realizing above technical purpose, the technical solution of the utility model is:
Draw the anti-hollowing earth construction of anchor, include down water layer and on water layer, water under described layer and on water between layer and be provided with anchor pole.
Further, described anchor pole is T-shaped anchor pole.
Further, described anchor pole is I-shaped anchor pole.
Further, described anchor pole periphery is provided with external screw thread.
Further, described anchor pole is upper and lower two umbrella shape anchor pole.
Advantageous Effects of the present utility model is: employ and carry out drawing the structure of anchor very reliable with prefabricated anchor pole, this structure facilitates understandable when applying, operate without the need to professional, but effectively can control the problem of two layer concrete delaminations well, impel whole floor structure to become as a whole, improve the application life on ground.Anchor pole periphery is provided with external screw thread and more improves bonding force between anchor pole and concrete.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model embodiment.
Detailed description of the invention
Composition graphs 1, describes detailed description of the invention of the present utility model in detail, but is not limited in any way claim.Of the present utility modelly draw the anti-hollowing earth construction of anchor, include down water layer 100 and on water layer 101, water under described layer 100 and on water between layer 101 and be provided with anchor pole 102.When implementing, described anchor pole 102 is T-shaped anchor pole.For realizing better fastening effect, anchor pole 102 be oblique cutting structure, namely anchor pole 102 under water layer 100 and on to water between layer 101 be incline structure.Described anchor pole 102 is I-shaped anchor pole.Described anchor pole 102 periphery is provided with external screw thread.When implementing, can under water layer 100 non-bone dry time insert letter anchor pole 102, and regulate the height of anchor pole 102, under water layer 100 dry time, anchor pole 102 is fixed, then waters the cast of layer 101 on carrying out.In force, further, described anchor pole is upper and lower two umbrella shape anchor pole, bonding more firmly near.
The utility model employs and carries out drawing the structure of anchor very reliable with prefabricated anchor pole 102, this structure facilitates understandable when applying, anchor pole 102 periphery is provided with external screw thread and more improves bonding force between anchor pole 102 and concrete, not hollowing, is the not only practical but also novel technological improvement in one, this area.

Claims (5)

1. draw the anti-hollowing earth construction of anchor, it is characterized in that: include down water layer and on water layer, water under described layer and on water between layer and be provided with anchor pole.
2. according to claim 1ly draw the anti-hollowing earth construction of anchor, it is characterized in that: described anchor pole is T-shaped anchor pole.
3. according to claim 1ly draw the anti-hollowing earth construction of anchor, it is characterized in that: described anchor pole is I-shaped anchor pole.
4. according to claim 1 or 2 or 3, draw the anti-hollowing earth construction of anchor, it is characterized in that: described anchor pole periphery is provided with external screw thread.
5. according to claim 1ly draw the anti-hollowing earth construction of anchor, it is characterized in that: described anchor pole is two umbrella shape anchor pole up and down.
CN201520802050.1U 2015-10-19 2015-10-19 Draw anchor air defense drum ground structure Expired - Fee Related CN205088917U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520802050.1U CN205088917U (en) 2015-10-19 2015-10-19 Draw anchor air defense drum ground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520802050.1U CN205088917U (en) 2015-10-19 2015-10-19 Draw anchor air defense drum ground structure

Publications (1)

Publication Number Publication Date
CN205088917U true CN205088917U (en) 2016-03-16

Family

ID=55479618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520802050.1U Expired - Fee Related CN205088917U (en) 2015-10-19 2015-10-19 Draw anchor air defense drum ground structure

Country Status (1)

Country Link
CN (1) CN205088917U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109760903A (en) * 2018-10-27 2019-05-17 张荐 The production method for preventing hollow body from deforming
CN112663899A (en) * 2021-01-22 2021-04-16 郭智霖 Manufacturing method of self-leveling mortar terrace

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109760903A (en) * 2018-10-27 2019-05-17 张荐 The production method for preventing hollow body from deforming
CN109760903B (en) * 2018-10-27 2020-12-22 张荐 Method for preventing hollow body from deforming
CN112663899A (en) * 2021-01-22 2021-04-16 郭智霖 Manufacturing method of self-leveling mortar terrace

Similar Documents

Publication Publication Date Title
CN201826511U (en) Elevation control system for pouring construction of concrete floors
CN202595739U (en) Anchor rod suitable for soft soil layer
CN205088917U (en) Draw anchor air defense drum ground structure
CN204081445U (en) To encorbelment i iron anchor device
CN206245157U (en) A kind of pavior brick
CN203452209U (en) Bathroom waterproof structure
CN110439353A (en) A kind of erection construction method of concrete wire pole overturning-preventing
CN104420408A (en) Water-retention water-permeable tile
CN202989727U (en) Cement square brick
CN206220114U (en) A kind of eight High-Rise Pile Cap Foundations
CN104790578A (en) Manufacturing device of preformed hole in building floor concrete construction and construction method thereof
CN102371622A (en) Process method for combining prefabricated member by paving ceramic tiles in advance
CN204960251U (en) Paint layer gauge control device
CN103171021A (en) Method for enhancing concrete strength, improving volume stability and reducing cracking
CN204023582U (en) A kind of slope retaining structure
CN202925518U (en) Geomembrane with anchoring nails
CN207714352U (en) A kind of miniature clump of piles formula bored concrete pile
CN202482897U (en) Concrete structure
CN206359878U (en) A kind of pile foundation of light section steel structure bridge
CN203129458U (en) Cantilevered stairway for rammed earth wall
CN105544533A (en) Slab-pile wall digging pile retaining wall flitch plate
CN205136295U (en) Self -tapping screw that wall body and steel joist are connected
CN105317216A (en) Wall body reversed construction method and wall body and concrete framework casting structure
CN203583751U (en) Brick
CN202323756U (en) Hollow grouting anchor rod used in bridge construction process

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160316

Termination date: 20161019

CF01 Termination of patent right due to non-payment of annual fee