CN205079222U - Novel living beings boiler - Google Patents

Novel living beings boiler Download PDF

Info

Publication number
CN205079222U
CN205079222U CN201520702855.9U CN201520702855U CN205079222U CN 205079222 U CN205079222 U CN 205079222U CN 201520702855 U CN201520702855 U CN 201520702855U CN 205079222 U CN205079222 U CN 205079222U
Authority
CN
China
Prior art keywords
fume collecting
collecting chamber
box
smoke
heating furnace
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520702855.9U
Other languages
Chinese (zh)
Inventor
蔡军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Linyi Taihe Environmental Protection And Energy Saving Technology Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201520702855.9U priority Critical patent/CN205079222U/en
Application granted granted Critical
Publication of CN205079222U publication Critical patent/CN205079222U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Air Supply (AREA)

Abstract

The utility model discloses a novel living beings boiler, including base, bunker, fan, tuber pipe, fuel way, auger, tobacco pipe, heating furnace and preheater, wherein the heating furnace includes combustion chamber, grey grit chamber and hot water cavity, wherein heating furnace and preheater set up on base upper portion side by side, bunker and fan setting are in heating furnace one side, just wherein the bunker passes through fuel way and combustion chamber intercommunication, the fan is linked together through air duct and grey grit chamber and fuel way, the preheater includes first album of smoke -box, second collection smoke -box and third collection smoke -box, and wherein first smoke -box and the third of collecting collects the smoke -box and set up the position department of being close to the top in the preheater, the second collects the smoke -box and sets up in the preheater and to be close to bottom position department, just first album of smoke -box and combustion chamber, first album of smoke -box and second collection smoke -box, second collection smoke -box and third collection smoke -box be respectively through the flue intercommunication, this utility model reasonable in design, and convenient to use can improve the fuel availability effectively.

Description

A kind of novel biomass hot-water boiler
Technical field
The utility model belongs to boiler plant technical field, particularly a kind of novel biomass hot-water boiler.
Background technology
Boiler is a kind of capital equipment for supplying hot water in productive life, the boiler of current use is generally Steam Heating, coal burning heating or electrical heating, biologic grain boiler is as a kind of environment-protection boiler utilizing renewable resource, extensively promoted the use of, often there is feed problems in traditional biological particle boiler, and the problems such as capacity usage ratio is low, current biologic grain boiler is all generally that the dust produced after the high-temperature flue gas be not fully used and the non-Thorough combustion of this biologic grain burning produced directly is discharged in air, very large thermal loss can be caused also to pollute the environment simultaneously, do not meet the theory of sustainable development.
Utility model content
Technical assignment of the present utility model provides a kind of novel biomass hot-water boiler for above prior art deficiency.
It is a kind of novel biomass hot-water boiler that the utility model solves the technical scheme that its technical problem adopts, and comprises base, Bunker, blower fan, airduct, fuel channel, auger, smoke pipe, water inlet, delivery port, sewage draining exit, exhaust outlet, heating furnace and preheating furnace, wherein said heating furnace comprises combustion chamber, cinder chamber and hot-water cavity, wherein said heating furnace and preheating furnace are disposed in parallel in base top and hot-water cavity and preheating furnace pass through pipeline communication, described Bunker and blower fan are arranged on heating furnace side, and wherein said Bunker is by fuel channel and combustion chamber, described blower fan is connected with fuel channel with cinder chamber by wireway, and described preheating furnace comprises the first fume collecting chamber, second fume collecting chamber and the 3rd fume collecting chamber, wherein the first fume collecting chamber and the 3rd fume collecting chamber are arranged at the position near top in preheating furnace, and described second fume collecting chamber is arranged near bottom position place in preheating furnace, and described first fume collecting chamber and combustion chamber, first fume collecting chamber and the second fume collecting chamber, second fume collecting chamber is communicated with respectively by smoke pipe with the 3rd fume collecting chamber.
Further, described first fume collecting chamber is ring-type, and described 3rd fume collecting chamber is cylindric, and the internal diameter of the first fume collecting chamber is greater than the external diameter of the 3rd fume collecting chamber.
Further, described first fume collecting chamber, the second fume collecting chamber and the 3rd fume collecting chamber all have dust removal port.
Further, described fuel channel be connected with heating furnace one end downward bending, be horizontally disposed with away from one end of heating furnace.
Originally being the beneficial effect of utility model is: fuel channel designs entering advantageously in fuel by bending, the supply that moving air in the general mood of fuel channel introducing simultaneously accelerates fuel makes this boiler oil supply be protected, the design of preheating furnace Zhong Yan road effectively adds fuel availability, also greatly reduces the content of dust in tail gas simultaneously.
Accompanying drawing explanation
Fig. 1 is the utility model tangent plane structural representation.
Detailed description of the invention
With reference to Figure of description, workflow of the present utility model is described below:
As shown in Figure 1, a kind of novel biomass hot-water boiler, comprises base, Bunker 10, blower fan 12, airduct, fuel channel 11, auger, smoke pipe 6, water inlet, delivery port, sewage draining exit, exhaust outlet, heating furnace 1 and preheating furnace 2, wherein said heating furnace 1 comprises combustion chamber 3, cinder chamber 5 and hot-water cavity 4, wherein said heating furnace 1 and preheating furnace 2 are disposed in parallel in base top and hot-water cavity 4 and preheating furnace 2 pass through pipeline communication, described Bunker 10 and blower fan 12 are arranged on heating furnace 1 side, and wherein said Bunker 10 is communicated with combustion chamber 3 by fuel channel 11, described blower fan 12 is connected with fuel channel 11 with cinder chamber 5 by wireway, and described preheating furnace 2 comprises the first fume collecting chamber 8, second fume collecting chamber 7 and the 3rd fume collecting chamber 9, wherein the first fume collecting chamber 8 and the 3rd fume collecting chamber 9 are arranged at the position near top in preheating furnace 2, and described second fume collecting chamber 7 is arranged near bottom position place in preheating furnace 2, and described first fume collecting chamber 8 and combustion chamber 3, first fume collecting chamber 8 and the second fume collecting chamber 7, second fume collecting chamber 7 is communicated with respectively by smoke pipe 6 with the 3rd fume collecting chamber 9.
Further, described first fume collecting chamber 8 is ring-type, and described 3rd fume collecting chamber 9 is cylindric, and the internal diameter of the first fume collecting chamber 8 is greater than the external diameter of the 3rd fume collecting chamber 9.
Further, described first fume collecting chamber 7 of fume collecting chamber 8, second and the 3rd fume collecting chamber 9 all have dust removal port.
Further, described fuel channel 11 be connected with heating furnace 1 one end downward bending, be horizontally disposed with away from one end of heating furnace 1.

Claims (4)

1. a novel biomass hot-water boiler, comprises base, Bunker (10), blower fan (12), airduct, fuel channel (11), auger, smoke pipe (6), water inlet, delivery port, sewage draining exit, exhaust outlet, heating furnace (1) and preheating furnace (2), wherein said heating furnace (1) comprises combustion chamber (3), cinder chamber (5) and hot-water cavity (4), wherein said heating furnace (1) and preheating furnace (2) are disposed in parallel in base top and hot-water cavity (4) and preheating furnace (2) pass through pipeline communication, described Bunker (10) and blower fan (12) are arranged on heating furnace (1) side, and wherein said Bunker (10) is communicated with combustion chamber (3) by fuel channel (11), described blower fan (12) is connected with fuel channel (11) with cinder chamber (5) by wireway, it is characterized in that: described preheating furnace (2) comprises the first fume collecting chamber (8), second fume collecting chamber (7) and the 3rd fume collecting chamber (9), wherein the first fume collecting chamber (8) and the 3rd fume collecting chamber (9) are arranged at the position near top in preheating furnace (2), described second fume collecting chamber (7) is arranged near bottom position place in preheating furnace (2), and described first fume collecting chamber (8) and combustion chamber (3), first fume collecting chamber (8) and the second fume collecting chamber (7), second fume collecting chamber (7) is communicated with respectively by smoke pipe (6) with the 3rd fume collecting chamber (9).
2. a kind of novel biomass hot-water boiler according to claim 1, it is characterized in that: described first fume collecting chamber (8) is ring-type, described 3rd fume collecting chamber (9) is for cylindric, and the internal diameter of the first fume collecting chamber (8) is greater than the external diameter of the 3rd fume collecting chamber (9).
3. a kind of novel biomass hot-water boiler according to claim 1, is characterized in that: described first fume collecting chamber (8), the second fume collecting chamber (7) and the 3rd fume collecting chamber (9) all have dust removal port.
4. a kind of novel biomass hot-water boiler according to claim 1, is characterized in that: one end downward bending that described fuel channel (11) is connected with heating furnace (1), be horizontally disposed with away from one end of heating furnace (1).
CN201520702855.9U 2015-09-12 2015-09-12 Novel living beings boiler Expired - Fee Related CN205079222U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520702855.9U CN205079222U (en) 2015-09-12 2015-09-12 Novel living beings boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520702855.9U CN205079222U (en) 2015-09-12 2015-09-12 Novel living beings boiler

Publications (1)

Publication Number Publication Date
CN205079222U true CN205079222U (en) 2016-03-09

Family

ID=55431630

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520702855.9U Expired - Fee Related CN205079222U (en) 2015-09-12 2015-09-12 Novel living beings boiler

Country Status (1)

Country Link
CN (1) CN205079222U (en)

Similar Documents

Publication Publication Date Title
CN204285422U (en) Biological particles steam oven
CN205079222U (en) Novel living beings boiler
CN103497776B (en) Thermal barrier self-circulation heating-type agriculture and forestry organic waste material pyrolysis liquefying systems
CN204730243U (en) The heating gas system of positive-pressure type biomass powder powder fluidized airflow bed gasification furnace
CN104236081A (en) Tubular heating furnace device
CN203963954U (en) Utilize tail gas from incinerator to add the heat recovery device of hot-air
CN203836998U (en) Novel heat pipe type waste heat recovery device
CN208042119U (en) Parallel-connection type coal-burning powder heat medium heater
CN204829834U (en) A utilize device that is arranged in methanol production from coal steam and tail gas
CN202485187U (en) Natural circulating hot water boiler structure
CN201715533U (en) Powder feeding device of pulverized coal boiler at power station
CN201190990Y (en) Improved coal-fired boiler
CN203972266U (en) Fire coal and the dual-purpose heater of fuel oil of drying tunnel for a kind of application
CN205119027U (en) Biomass furnace of environmental protection
CN203757999U (en) Normal-pressure horizontal energy-saving and environment-friendly boiler
CN204064001U (en) Energy-efficient UTILIZATION OF VESIDUAL HEAT IN hot bellows
CN203947056U (en) A kind of black reactor gas-fired treatment unit
CN205174429U (en) Biomass briquette fuel flue -cured tobacco stove level four air inlet system
CN204285783U (en) Biomass hot air interchanger
CN203162927U (en) Coal-fired boiler
CN204923431U (en) Hot air system heater
CN202747610U (en) Biomass fuel organic heat carrier furnace with chain grate
CN205084550U (en) Gaseous energy -conserving converter of boiler exhaust
CN209688804U (en) A kind of efficient energy-saving and emission-reducing biomass boiler
CN204202156U (en) A kind of boiler of the biologic grain that burns

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180502

Address after: 276013 Zhou Jing Pu village, Yitang Town, Lanshan District, Linyi, Shandong

Patentee after: Linyi Taihe environmental protection and energy saving Technology Co.,Ltd.

Address before: 276000 No. 157, Jiang Jia village, Fei Town, Feixian County, Linyi, Shandong

Patentee before: Cai Jun

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160309