CN205039429U - Cold main pump of current conversion station valve overhauls moisturizing operation car on line - Google Patents

Cold main pump of current conversion station valve overhauls moisturizing operation car on line Download PDF

Info

Publication number
CN205039429U
CN205039429U CN201520654496.4U CN201520654496U CN205039429U CN 205039429 U CN205039429 U CN 205039429U CN 201520654496 U CN201520654496 U CN 201520654496U CN 205039429 U CN205039429 U CN 205039429U
Authority
CN
China
Prior art keywords
valve
moisturizing
water tank
main pump
branch road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201520654496.4U
Other languages
Chinese (zh)
Inventor
王小岭
常开忠
杨涛
陈图腾
柳坤
马向南
夏云礼
张家兴
叶健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunming Bureau of Extra High Voltage Power Transmission Co
Original Assignee
Kunming Bureau of Extra High Voltage Power Transmission Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunming Bureau of Extra High Voltage Power Transmission Co filed Critical Kunming Bureau of Extra High Voltage Power Transmission Co
Priority to CN201520654496.4U priority Critical patent/CN205039429U/en
Application granted granted Critical
Publication of CN205039429U publication Critical patent/CN205039429U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Cold main pump of current conversion station valve overhauls moisturizing operation car on line relates to not interruption maintenance's special moisturizing equipment of a specially adapted for current conversion station change of current valve cooling system main pump, and characterized by includes the moving platform car and fix the water storage tank on the moving platform car and soften the branch road, inhale water injection branch road, external moisturizing branch road certainly with the self -loopa that the water storage tank is connected respectively that this cold main pump of current conversion station valve overhauls moisturizing operation car on line's beneficial effect is: it is convenient portable, but the manpower pulls to any operation place carries out the operation, accomplish operation, easy operation through simple control circuit, the device can be independent the completion pure water soften with moisturizing operation, errorless operational risk.

Description

Converter Station Valve cold main pump on-bne repair moisturizing Operation Van
Technical field
The utility model belongs to Converter Station Valve cold main pump on-bne repair special equipment field.
Background technology
Along with the continuous maturation of high voltage dc transmission technology, nationwide large area builds current conversion station, and the requisite a set of important auxiliary equipment of current conversion station is exactly valve cooling system, it can ensure that current conversion station core component converter valve operating temperature remains in confidence band, but the core component main circulation pump of valve cooling system (hereinafter referred to as: main pump) as long-term high-speed rotating equipment, its failure rate is very high, when there is main pump fault needed direct current to stop transport to overhaul, this certainly will affect sending of electricity in the past.
Valve cooling system main pump is generally a fortune one and configures for redundant, namely an other operation can be switched to when a main pump breaks down, but if do not keeped in repair in time fault water pump, system will lose redundancy, during an other main pump fault, the locking of valve group will be caused, affect electricity net safety stable, so the on-bne repair of main pump becomes trend of the times, and the technological difficulties key of main pump on-bne repair is the benefit draining to main pump place pipeline, current most current conversion station does not possess main pump on-bne repair condition, minority current conversion station is (as Chuxiong current conversion station, Pu'er current conversion station) through can meet the on-bne repair condition of main pump to the appropriate reconstruction on system superintendent road, but risk factor is high, easily cause the direct current locking because human factor causes, subject matter is as follows:
1, overhaul main pump moisturizing process by touch panel starter gate valve self small pump cold, by the external interface of small pump, the pure water in water supply tank is supplemented to emptying section, there is operation touch-screen mistiming operational risk in this, causes the locking of valve group;
2, the pure water in water supply tank or the current conversion station stock pure water general storage time very long, the pure water conductivity of long-term storage can sharply rise violently, if directly the pure water in water supply tank is supplemented to main water route, whole water-cooling generator conductivity can be caused higher, even exceed conductivity high trip value (0.7 μ s/cm) and trip after 3 seconds.
Comprehensive above analysis, if think the safe and reliable on-bne repair completing the cold main pump of valve, risk is dropped to minimum, then need a set of special water replanishing device, this device should be able to complete independently to the moisturizing of maintenance main pump pipeline, and supplementary electrical conductivity of water ensures in trip value (0.7 μ s/cm) below at least, and it is reported that current all current conversion stations still do not possess such device.
Summary of the invention
The object of this Converter Station Valve cold main pump on-bne repair moisturizing Operation Van, just in order to overcome the deficiency of the cold main pump on-bne repair of above-mentioned valve, realizes the safe and reliable on-bne repair of the cold main pump of valve.
This Converter Station Valve cold main pump on-bne repair moisturizing Operation Van is achieved by the following technical solution.
Converter Station Valve cold main pump on-bne repair moisturizing Operation Van, relate to a kind of special water supplement apparatus being specially adapted for current conversion station converter valve cooling system main pump service without power-off, feature is, the water tank comprising sliding platform and be fixed on sliding platform and soften branch road, imbibition waterflooding branch road, external moisturizing branch road with the self-loopa that water tank is connected respectively, sliding platform is also provided with operation control box; (sliding platform is used for all parts of bogey, can be dragged to any operating location easily; ) 100L pure water can be stored; Wherein self-loopa is softened branch road and is comprised and to draw from water tank and to get back to the loop of water tank: namely valve V01, self-circulating pump, valve, ion-exchanger, accurate filter and valve sequentially connect and compose; Its function is softened by self-loopa to make the pure water conductivity in water tank remain on lower value (0.7 μ s/cm) below; Imbibition waterflooding branch road adopts self priming pump, by valve, outside pure water is drawn to water tank; Route valve is propped up in external moisturizing, small pump, valve sequentially connect and compose, for carrying out supplementary pure water to pipeline during site examining and repairing; The on off control switch to self-circulating pump, small pump and self priming pump is assembled with in operation control box case, water tank is provided with conductivity transmitter, conductivity transmitter display floater is installed on operation control box, carries out real-time conductivity supervision to the pure water in water tank.The utilization of Operation Van can realize reliable moisturizing during Converter Station Valve cold main pump on-bne repair.
This Converter Station Valve cold main pump on-bne repair moisturizing Operation Van water tank adopts stainless steel, and ion-exchanger adopts stainless steel, and all connecting lines adopt stainless steel.
Current most valve cooling system cannot carry out safe and reliable on-bne repair, but the cold main pump of valve is as the core component of valve cooling system, it is again high-speed rotating equipment, its failure rate is very high, realize the on-bne repair of main pump, and ensure the fail safe of operation process, effectively can reduce direct current temporary interruption number of times, sending of effective guarantee electricity.
The design studies of Converter Station Valve cold main pump on-bne repair moisturizing Operation Van, solve the moisturizing difficult problem in on-bne repair process, and may cause think that misoperation factor is thoroughly got rid of, make main pump on-bne repair except necessary safety measure, all the other operations all complete outside system, for raising operating efficiency, safeguard work fail safe is significant.Therefore if realize the safe and reliable on-bne repair of main pump, a large blank of valve cooling system main pump on-bne repair certainly will be filled up.
The beneficial effect of this Converter Station Valve cold main pump on-bne repair moisturizing Operation Van is: convenient removable, can be dragged to any operating location and carry out operation by manpower; By simple control circuit complete operation, simple to operate; Device independently can complete pure water correction and moisturizing operation, errorless operational risk.
The utility model content is set forth further below in conjunction with Figure of description and embodiment.
Accompanying drawing explanation
Fig. 1 is this apparatus structure schematic diagram;
Fig. 2 is operation control circuit logic diagram;
Fig. 3 is this device three-dimensional effect diagram;
Fig. 4 is this device planar configuration figure front view;
Fig. 5 is this device planar configuration figure vertical view;
Fig. 6 is this device planar configuration figure end view.
Embodiment
See Fig. 1, Fig. 2, Converter Station Valve cold main pump on-bne repair moisturizing Operation Van, relate to a kind of special water supplement apparatus being specially adapted for current conversion station converter valve cooling system main pump service without power-off, the utility model feature is, the water tank C01 comprising sliding platform and be fixed on sliding platform and soften branch road, imbibition waterflooding branch road, external moisturizing branch road with the self-loopa that water tank C01 is connected respectively, sliding platform is also provided with operation control box; Sliding platform is used for all parts of bogey, can be dragged to any operating location easily; 100L pure water can be stored; Wherein self-loopa is softened branch road and is comprised and to draw from water tank C01 and to get back to the loop of water tank C01: namely valve V01, self-circulating pump B01, valve V02, ion-exchanger R01, accurate filter G01 and valve V03 sequentially connect and compose; Its function is softened by self-loopa to make the pure water conductivity in water tank remain on lower value 0.7 below μ s/cm; Imbibition waterflooding branch road adopts self priming pump B03, by valve V06, outside pure water is drawn to water tank C01; Route valve V04, small pump B02 are propped up in external moisturizing, valve V05 sequentially connects and composes, for carrying out supplementary pure water to pipeline during site examining and repairing; The on off control switch to self-circulating pump B01, small pump B02 and self priming pump B03 is assembled with in operation control box case, water tank C01 is provided with conductivity transmitter, conductivity transmitter display floater is installed on operation control box, carries out real-time conductivity supervision to the pure water in water tank.The utilization of Operation Van can realize reliable moisturizing during Converter Station Valve cold main pump on-bne repair.
This Converter Station Valve cold main pump on-bne repair moisturizing Operation Van water tank adopts stainless steel, and ion-exchanger adopts stainless steel, and all connecting lines adopt stainless steel.
The a set of external 220V AC power of whole moisturizing car design, power supply causes control operation case, is tapped into the A.C. contactor of circulating pump, small pump and self priming pump.In control box, AC-DC conversion module is installed, 220V alternating current can be converted to 24V direct current, for control loop and conductivity transmitter.
The utility model using method:
One, water tank C01 carries out water-filling:
1, switch on power;
2, V06 valve is opened;
3, V06 valve rear hose end is immersed water bucket;
4, open self priming pump B03, water-filling is carried out to water tank.
5, treat that water tank liquid level reaches about 90%, stop moisturizing.
Two, the self-loopa of moisturizing car is softened:
1, switch on power;
2, V01, V02, V03 valve is opened;
3, ON cycle pump B01, makes pure water in water tank through ion-exchanger R01 and accurate filter G01, softens;
4, observe the supervision value of conductivity transmitter on control operation case, until conductivity is reduced to 0.7 below μ s/cm, preparation completes.
Three, main pump on-bne repair moisturizing:
1, switch on power;
2, the external interface after V05 is connected with needing the inner cold water pipe valve of moisturizing;
3, V004 and V005 valve is opened;
4, open small pump B02 and carry out moisturizing to needing water pipe;
5, moisturizing completes, and closes V004 and V005 valve, prevents the water in storage tank from flowing out;
6, deenergization.
The system requirement that the utility model realizes the cold main pump on-bne repair of valve is: as the on-bne repair for realizing valve cooling system, first the redundant configuration of the cold main pump of valve is met, general main circulation pump turnover water end (W.E.) all has valve to cut off Inlet and outlet water, also non-return valve is designed with below main pump flowing water Valve, bottom the pump housing or pipeline low spot also can design emptying valve, the above is the essential structure of single main pump unit, the on-bne repair of main pump is realized as wanted, the two problems that must solve is exactly draining and moisturizing, if only by emptying valve, under siphonage, water is difficult to outflow lines, so vent valve must be installed additional below non-return valve, siphonic effect is destroyed by vent valve, realize fast completing of draining and moisturizing.

Claims (2)

1. Converter Station Valve cold main pump on-bne repair moisturizing Operation Van, it is characterized in that, the water tank (C01) comprising sliding platform and be fixed on sliding platform and soften branch road, imbibition waterflooding branch road, external moisturizing branch road with the self-loopa that water tank (C01) is connected respectively, sliding platform is also provided with operation control box; Wherein self-loopa is softened branch road and is comprised and to draw from water tank (C01) and to get back to the loop of water tank (C01): namely valve V01, self-circulating pump (B01), valve V02, ion-exchanger (R01), accurate filter (G01) and valve V03 sequentially connect and compose; Imbibition waterflooding branch road adopts self priming pump (B03), by valve V06, outside pure water is drawn to water tank (C01); Route valve V04 is propped up in external moisturizing, small pump (B02), valve V05 sequentially connect and compose, for carrying out supplementary pure water to water tank (C01) during site examining and repairing; The on off control switch to self-circulating pump (B01), small pump (B02) and self priming pump (B03) is assembled with in operation control box case; Water tank (C01) is provided with conductivity transmitter, and conductivity transmitter display floater is installed on operation control box, carries out real-time conductivity supervision to the pure water in water tank.
2. Converter Station Valve according to claim 1 cold main pump on-bne repair moisturizing Operation Van, is characterized in that, water tank adopts stainless steel, and ion-exchanger adopts stainless steel, and all connecting lines adopt stainless steel.
CN201520654496.4U 2015-08-27 2015-08-27 Cold main pump of current conversion station valve overhauls moisturizing operation car on line Withdrawn - After Issue CN205039429U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520654496.4U CN205039429U (en) 2015-08-27 2015-08-27 Cold main pump of current conversion station valve overhauls moisturizing operation car on line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520654496.4U CN205039429U (en) 2015-08-27 2015-08-27 Cold main pump of current conversion station valve overhauls moisturizing operation car on line

Publications (1)

Publication Number Publication Date
CN205039429U true CN205039429U (en) 2016-02-17

Family

ID=55298300

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520654496.4U Withdrawn - After Issue CN205039429U (en) 2015-08-27 2015-08-27 Cold main pump of current conversion station valve overhauls moisturizing operation car on line

Country Status (1)

Country Link
CN (1) CN205039429U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105071261A (en) * 2015-08-27 2015-11-18 中国南方电网有限责任公司超高压输电公司昆明局 Converter station valve cooling main pump online maintenance water replenishing work vehicle
CN106006841A (en) * 2016-06-22 2016-10-12 国家电网公司 Automatic deionized water supply device for cooling system of SFC (static frequency converter)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105071261A (en) * 2015-08-27 2015-11-18 中国南方电网有限责任公司超高压输电公司昆明局 Converter station valve cooling main pump online maintenance water replenishing work vehicle
CN105071261B (en) * 2015-08-27 2017-03-22 中国南方电网有限责任公司超高压输电公司昆明局 Converter station valve cooling main pump online maintenance water replenishing work vehicle
CN106006841A (en) * 2016-06-22 2016-10-12 国家电网公司 Automatic deionized water supply device for cooling system of SFC (static frequency converter)
CN106006841B (en) * 2016-06-22 2019-06-14 国家电网公司 A kind of SFC cooling system deionized water automatically supplying apparatus

Similar Documents

Publication Publication Date Title
CN205039429U (en) Cold main pump of current conversion station valve overhauls moisturizing operation car on line
CN204303363U (en) A kind of Spent Fuel Pool emergency monitoring and water charging system
CN204010702U (en) A kind of steam generator emergency feedwater supply system
CN201902279U (en) Dual-pump control device for generator oil supply system
CN203701190U (en) Rainwater utilization system capable of realizing automatic control by water level
CN202853091U (en) External auxiliary electric heating system of water heater
CN105071261A (en) Converter station valve cooling main pump online maintenance water replenishing work vehicle
CN206947122U (en) Oil immersed type station local coordinate frame repairing dolly
CN204215254U (en) Tap water secondary water-supply remote supervision system for boosting pump stations
CN105971836A (en) System for lifting water through solar photovoltaic and making redundant electricity get on grid
CN205453283U (en) Incessant UPS power supply unit
CN105068476A (en) Converter valve cooling control system
CN207988015U (en) Remote auto control secondary water supply system
CN202850121U (en) Combination water supply system
CN204806758U (en) Circulative cooling water supply system outside hydroelectric power plant
CN201985607U (en) Standby power throw-in device
CN106816197B (en) One kind being used for nuclear power plant's Spent Radioactive gas processing system dehumidifying cooling device
CN104948913A (en) Zero-leakage safe alkali discharging device and method thereof
CN104214823A (en) Unattended centralized heating monitor station operating stably
CN209104975U (en) A kind of Generator Stator Cooling water system anti-siphon means
CN103363513B (en) A kind of water supply system of sintering waste heat generating boiler
CN206467723U (en) Non-negative pressure method of water supply control system
CN205986321U (en) Haul oneself willingly into protection logic and verify device
CN208513254U (en) A kind of flushing pipe network system
CN206226110U (en) A kind of denitrating system of generating set

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20160217

Effective date of abandoning: 20170322

C25 Abandonment of patent right or utility model to avoid double patenting