CN205035045U - A hanging flower basket guider for applying paint two curve type cooling tower inner walls - Google Patents

A hanging flower basket guider for applying paint two curve type cooling tower inner walls Download PDF

Info

Publication number
CN205035045U
CN205035045U CN201520822594.4U CN201520822594U CN205035045U CN 205035045 U CN205035045 U CN 205035045U CN 201520822594 U CN201520822594 U CN 201520822594U CN 205035045 U CN205035045 U CN 205035045U
Authority
CN
China
Prior art keywords
cooling tower
rope
guide rail
hanging basket
joist
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520822594.4U
Other languages
Chinese (zh)
Inventor
黄向阳
蔡高龙
陈勇
朱天云
李�杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUAFENG CONSTRUCTION CO Ltd
Zhejiang Electric Power Construction Co Ltd
Original Assignee
HUAFENG CONSTRUCTION CO Ltd
Zhejiang Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUAFENG CONSTRUCTION CO Ltd, Zhejiang Electric Power Construction Co Ltd filed Critical HUAFENG CONSTRUCTION CO Ltd
Priority to CN201520822594.4U priority Critical patent/CN205035045U/en
Application granted granted Critical
Publication of CN205035045U publication Critical patent/CN205035045U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a hanging flower basket guider for applying paint two curve type cooling tower inner walls, it includes hanging flower basket (1), bearing rope (2), shaped steel support (3) and direction subassembly, and shaped steel support (3) are fixed on the collar tie beam that bears down on one (4) at cooling tower (13) top, and bearing rope (2) both ends are connected with shaped steel support (3) and hanging flower basket (1) respectively, every direction subassembly includes a guide rail rope (5), a hand -drive block, a plurality of even joist (7) and a plurality of internal thread sleeve pipes (8), a plurality of internal thread sleeve pipe (8) are the pre -buried inner wall in cooling tower (13) of perpendicular column pitch, every links joist (7) and closes soon in internal thread sleeve pipe (8) that correspond, guide rail rope (5) embolias each even joist (7) cover intra -annular, head end and bear down on one collar tie beam (4) of guide rail rope (5) are fixed, guide rail rope (5) is terminal through hand -drive block and cooling tower (13) bottom tensioning. The device makes and applies paint with a brush fast, convenient, laborsaving and practice thrift the consumptive material.

Description

For the hanging basket guide piece of brushing Hyperbolic cooling tower inwall
Technical field
The utility model relates to the anticorrosive construction technical field of the Hyperbolic cooling tower of power plant, is specifically a kind of hanging basket guide piece for the inwall brushing anti fouling composition at Hyperbolic cooling tower.
Background technology
Along with the development of construction of fire and electricity, the construction of towering (generally more than 150 meters) cooling tower structure in hyperbolic-type is also more and more extensive.Behind the concrete construction knot top of Hyperbolic cooling tower, also need the inwall brushing one deck anti fouling composition at cooling tower.
The brushing method of prior art is on cooling tower bears down on one collar tie beam, fix a shape steel bracket, and with a head-rope connecting-type steel bracket and hanging basket, people is in hanging basket, and decline hanging basket, brushes cooling tower inwall from top to bottom.But, cooling tower is hyperbolic configuration, upper and lower two head breadths and central waist is narrow, hanging basket from tower top vertically hang time can only drop to the waist location of cooling tower, and the hanging basket of height below the waist of cooling tower cannot reach, so also need the steel tube fastener scaffold setting up floor type from the bottom up, then worker stands is brushed the inwall below cooling tower waist on scaffold.And setting up of scaffold is long in time limit, labor content is large, speed is slow and the consumptive material of steel pipe and fastener is large.
Utility model content
The technical problems to be solved in the utility model is, provides a kind of and painting process can be made quick, convenient, laborsaving and the hanging basket guide piece for brushing Hyperbolic cooling tower inwall of saving consumptive material.
Technical solution of the present utility model is, a kind of hanging basket guide piece for brushing Hyperbolic cooling tower inwall is provided, it comprises hanging basket, head-rope and shape steel bracket, what shape steel bracket was fixed on cooling tower top bears down on one on collar tie beam, the upper end of head-rope is connected with shape steel bracket, and head-rope lower end is connected with hanging basket;
This hanging basket guide piece also comprises guidance set, each guidance set comprise a Guide rail rope, bottle gouard moved by hands, multiple connect joist and with connect joist multiple negative thread sleeve pipe one to one, multiple negative thread sleeve pipe is embedded in the inwall of cooling tower in perpendicular row interval, each the inner connecting joist screws in the negative thread sleeve pipe of correspondence, and each joist outer end that connects is provided with the notched collar; Guide rail rope is inserted in each collar through breach, the head end of Guide rail rope and the collar tie beam that bears down on one of cooling tower are fixed, the hook of Guide rail rope end and bottle gouard moved by hands is fixed, and bottom the lower hook cooling tower of the hoisting chain lower end of bottle gouard moved by hands, bottle gouard moved by hands is by Guide rail rope lower end and cooling tower bottom tension.
Utilize the method that this hanging basket guide piece is brushed Hyperbolic cooling tower inwall, its step comprises:
A, when building cooling tower cement concrete, multiple negative thread sleeve pipe is embedded in cement concrete, and makes the opening of each negative thread sleeve pipe be exposed to the inwall of cooling tower;
Behind b, tower to be cooled knot top, shape steel bracket is fixed on bearing down on one on collar tie beam of cooling tower top, and connects hanging basket and shape steel bracket with head-rope;
C, the head end of Guide rail rope is fixed on and bears down on one on collar tie beam, then Guide rail rope all the other section of throwing is pressed down top beam, Guide rail rope end and bottle gouard moved by hands hook are fixed, the lower suspension hook hook on the hoisting chain of bottle gouard moved by hands is fixed on bottom cooling tower;
D, forward stretch-draw bottle gouard moved by hands pull chain, the hook of bottle gouard moved by hands is declined, with preliminary tensioning Guide rail rope;
E, worker stands are in hanging basket, and a hand-held pull bar, the outer end of pull bar is provided with a rope sling, and rope sling is linked in Guide rail rope;
F, decline hanging basket, and pull bar synchronously can decline along with hanging basket, when dropping to the height of top negative thread sleeve pipe, workman pulls pull bar, make hanging basket close to cooling tower inwall, then screw in connecting joist in the negative thread sleeve pipe of this height, and Guide rail rope is inserted in the collar of company's joist of this height, then releasing lever, makes head-rope recover vertically;
G, continuation decline hanging basket, until drop to the height of the negative thread sleeve pipe of lower one deck, pull pull bar, make hanging basket near cooling tower inwall, screw in company's joist of this height, and Guide rail rope is inserted in the collar of company's joist of this height, then releasing lever, makes hanging basket recover vertically;
H, repeat step g, the joist of each height from top to bottom has all been screwed in corresponding negative thread sleeve pipe, and Guide rail rope is also inserted in each from top to bottom and is connected in the collar of joist;
I, again forward stretch-draw bottle gouard moved by hands pull chain, make the downward stretch-draw Guide rail rope of the hook of bottle gouard moved by hands, cause the complete tensioning of Guide rail rope, hanging basket is drawn high go back to cooling tower top;
J, two workmans enter in hanging basket, vertical decline hanging basket, and to cooling tower inwall brushing anti fouling composition from top to bottom, in painting process, a workman hooks Guide rail rope and shank of pulling back with a shank, makes hanging basket near cooling tower inwall, another workman seizes the opportunity brushing, after having brushed the inwall in one section of height, unclamp shank, be convenient to hanging basket and continue vertically to decline.
The utility model is used for the hanging basket guide piece of brushing Hyperbolic cooling tower inwall compared with prior art, has the following advantages and effect:
First, this technical scheme without the need to setting up the steel tube fastener scaffold of floor type as prior art, therefore eliminate a large amount of steel pipes and fastener, considerably reduce material consumption, and the program only needs the company's of screwing joist from top to bottom and Guide rail rope is inserted in the collar connecting joist, then tensioning, it is convenient to operation, significantly shortens man-hour; Secondly; in the process of dismounting Guide rail rope, be also dismantle in hanging basket from top to bottom, workman relies on shank to hold Guide rail rope; the company's of dismantling joist one by one again; and the Guide rail rope now strained completely connects joist this of short duration process just in time to dismounting to provide interim safety guard-safeguard, all connect after joist dismantles, come loose bottle gouard moved by hands; and then the Guide rail rope that comes loose; dismounting can be completed, and the device such as bottle gouard moved by hands, Guide rail rope after dismounting all can circulate and recycles, good economy performance.
As improvement, the herringbone column bottom cooling tower is banded with horizontal anchoring rope; The lower suspension hook of the hoisting chain lower end of bottle gouard moved by hands is hooked on anchoring rope, like this, the good anchoring rope of bottom extremity place colligation of two batter posts of special construction bottom cooling tower i.e. herringbone column can be used, and herringbone column's two batter posts more upwards spacing is larger, just in time prevent anchoring rope to be pulled up slip, guarantee that Guide rail rope is tightened up, and its structure is also simple, easy to operate, good to the stretch-draw effect of Guide rail rope, firmness is high.
Accompanying drawing explanation
Fig. 1 is the positive sectional structure schematic diagram of the utility model for the hanging basket guide piece of brushing Hyperbolic cooling tower inwall.
Fig. 2 is the close-up schematic view of the utility model for the Guide rail rope end anchors fixing structure of the hanging basket guide piece of brushing Hyperbolic cooling tower inwall.
What Fig. 3 was the utility model for the hanging basket guide piece of brushing Hyperbolic cooling tower inwall overlooks partial enlargement structural representation.
Shown in figure 1, hanging basket, 2, head-rope, 3, shape steel bracket, 4, bear down on one collar tie beam, 5, Guide rail rope, 6, bottle gouard moved by hands, 7, connect joist, 8, negative thread sleeve pipe, 9, the collar, 10, hoisting chain, 11, hook, 12, lower suspension hook, 13, cooling tower, 14, herringbone column, 15, anchoring rope.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
As shown in Figure 1, Figure 2, Figure 3 shows, the utility model is used for the hanging basket guide piece of brushing Hyperbolic cooling tower inwall, and it comprises hanging basket 1, head-rope 2 and shape steel bracket 3.What shape steel bracket 3 was fixed on cooling tower 13 top bears down on one on collar tie beam 4, specifically, the collar tie beam 4 that bears down on one can establish anchor hole, and the part of shape steel bracket 3 is erected shaped steel and inserted anchor hole and inject cement wash and tamp.The upper end of head-rope 2 is connected with shape steel bracket 3, and namely shape steel bracket 3 is provided with winch, and head-rope 2 head end is connected with winch, and shape steel bracket 3 is provided with a fixed pulley, and it is sagging that fixed pulley walked around by head-rope 2.Head-rope 2 lower end is connected as colligation is fixed with hanging basket 1.Drive winch, just can Lifting basket 1.
This hanging basket guide piece also comprises guidance set, each guidance set comprise a Guide rail rope 5, bottle gouard moved by hands 6, multiple connect joist 7 and with connect joist 7 multiple negative thread sleeve pipe 8 one to one.Multiple negative thread sleeve pipe 8 is embedded in the inwall of cooling tower 13 in perpendicular row interval, a negative thread sleeve pipe 8 as pre-buried in spacing 9 meters.Connecting joist 7 inner segment is external thread section, and each the inner connecting joist 7 screws in the negative thread sleeve pipe 8 of correspondence, and each joist 7 outer end that connects is provided with the notched collar 9.Guide rail rope 5 is inserted in each collar 9 through breach.The head end of Guide rail rope 5 is fixed through the collar tie beam 4 that bears down on one of shape steel bracket 3 with cooling tower 13, and namely Guide rail rope 5 head end is fixed on shape steel bracket 3, certainly, also Guide rail rope 5 directly can be fixed on and bear down on one on collar tie beam 4.The hook 11 of Guide rail rope 5 end and bottle gouard moved by hands 6 is fixed, and the lower suspension hook 12 of hoisting chain 10 lower end of bottle gouard moved by hands 6 hooks bottom cooling tower 13, and two batter posts of the herringbone column 14 namely bottom cooling tower 13 are banded with horizontal anchoring rope 15; The lower suspension hook 12 of hoisting chain 10 lower end of bottle gouard moved by hands 6 is hooked on anchoring rope 15.Bottle gouard moved by hands 6 is by Guide rail rope 5 lower end and cooling tower 13 bottom tension.
As shown in Figure 1, Figure 2, Figure 3 shows, utilize the method that the utility model hanging basket guide piece is brushed Hyperbolic cooling tower inwall, its step is as follows.
A, when building cooling tower 13 cement concrete, multiple negative thread sleeve pipe 8 is embedded in cement concrete, and makes the opening of each negative thread sleeve pipe 8 be exposed to the inwall of cooling tower 13.
Behind b, tower to be cooled 13 knot top, shape steel bracket 3 is fixed on bearing down on one on collar tie beam 4 of cooling tower 13 top, and connects hanging basket 1 and shape steel bracket 3 with head-rope 2.
C, the head end of Guide rail rope 5 is fixed on and bears down on one on the shape steel bracket 3 of collar tie beam 4, then Guide rail rope 5 all the other section of throwing is pressed down top beam 4, Guide rail rope 5 end and bottle gouard moved by hands 6 hook 11 are fixed, lower suspension hook 12 hook on the hoisting chain 10 of bottle gouard moved by hands 6 is fixed on bottom cooling tower 13.
D, forward stretch-draw bottle gouard moved by hands 6 pull chain, the hook 11 of bottle gouard moved by hands 6 is declined, with preliminary tensioning Guide rail rope 5, make Guide rail rope 5 be fitted in cooling tower 13 inwall formed with inwall radian coincide curve.
E, worker stands are in hanging basket 1, and a hand-held hard pull bar, the outer end of pull bar is provided with a rope sling, and rope sling is linked in Guide rail rope 5.
F, decline hanging basket 1, and pull bar synchronously can decline along with hanging basket 1, when dropping to the height of top negative thread sleeve pipe 8, workman pulls pull bar, makes hanging basket 1 close to cooling tower 13 inwall, then screws in the negative thread sleeve pipe 8 of this height by connecting joist 7, and Guide rail rope 5 is inserted in the collar 9 of company's joist 7 of this height, be be inserted in from the breach of the collar 9 specifically, then releasing lever, makes head-rope 2 recover vertical; This head-rope 2 is under vertical state, and also wanting inside than the narrowest place of cooling tower 13 waist, is for guaranteeing that hanging basket 1 can descend through the narrowest place of cooling tower 13 waist smoothly like this.
G, continuation decline hanging basket 1, until drop to the height of the negative thread sleeve pipe 8 of lower one deck, pull pull bar, make hanging basket 1 near cooling tower 13 inwall, screw in company's joist 7 of this height, and Guide rail rope 5 being inserted in the collar 9 of company's joist 7 of this height, then releasing lever, makes hanging basket 1 recover vertical.
H, repetition step g, the joist 7 of each height from top to bottom has all been screwed in corresponding negative thread sleeve pipe 8, and Guide rail rope 5 is also inserted in each collar 9 connecting joist 7 from top to bottom.
I, again forward stretch-draw bottle gouard moved by hands 6 pull chain, and the hook 11 of bottle gouard moved by hands 6 is declined further, to a greater degree downward stretch-draw Guide rail rope 5, cause Guide rail rope 5 tensioning completely, hanging basket 1 are drawn high go back to cooling tower 13 top.
J, two workmans enter in hanging basket 1, vertical decline hanging basket 1, and to cooling tower 13 inwall brushing anti fouling composition from top to bottom, in painting process, a workman hooks Guide rail rope 5 and shank of pulling back with a shank, shank just refers to a stiff rod being provided with hook, make hanging basket 1 near cooling tower 13 inwall, another workman seizes the opportunity brushing, after having brushed the inwall in one section of height, unclamp shank, be convenient to hanging basket 1 and continue vertical decline.
After brushing, then Guide rail rope 5 extracted out from connecting the collar 9 of joist 7 from top to bottom, and remove each and connect joist 7, and inwardly insert epoxy mortar in threaded sleeve 8, finally come loose bottle gouard moved by hands 6 reclaim Guide rail rope 5.

Claims (2)

1. the hanging basket guide piece for brushing Hyperbolic cooling tower inwall, it comprises hanging basket (1), head-rope (2) and shape steel bracket (3), shape steel bracket (3) is fixed on the collar tie beam that bears down on one (4) at cooling tower (13) top, the upper end of head-rope (2) is connected with shape steel bracket (3), and head-rope (2) lower end is connected with hanging basket (1); It is characterized in that:
This hanging basket guide piece also comprises guidance set, each guidance set comprise a Guide rail rope (5), bottle gouard moved by hands (6), multiple connect joist (7) and with connect joist (7) multiple negative thread sleeve pipe (8) one to one, multiple negative thread sleeve pipe (8) is embedded in the inwall of cooling tower (13) in perpendicular row interval, each the inner connecting joist (7) screws in the negative thread sleeve pipe (8) of correspondence, and each joist (7) outer end that connects is provided with the notched collar (9); Guide rail rope (5) is inserted in each collar (9) through breach, the head end of Guide rail rope (5) and the collar tie beam that bears down on one (4) of cooling tower (13) are fixed, the hook (11) of Guide rail rope (5) end and bottle gouard moved by hands (6) is fixed, the lower suspension hook (12) of hoisting chain (10) lower end of bottle gouard moved by hands (6) hooks cooling tower (13) bottom, and bottle gouard moved by hands (6) is by Guide rail rope (5) lower end and cooling tower (13) bottom tension.
2. the hanging basket guide piece for brushing Hyperbolic cooling tower inwall according to claim 1, is characterized in that: the herringbone column (14) of cooling tower (13) bottom is banded with horizontal anchoring rope (15); The lower suspension hook (12) of hoisting chain (10) lower end of bottle gouard moved by hands (6) is hooked on anchoring rope (15).
CN201520822594.4U 2015-10-22 2015-10-22 A hanging flower basket guider for applying paint two curve type cooling tower inner walls Expired - Fee Related CN205035045U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520822594.4U CN205035045U (en) 2015-10-22 2015-10-22 A hanging flower basket guider for applying paint two curve type cooling tower inner walls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520822594.4U CN205035045U (en) 2015-10-22 2015-10-22 A hanging flower basket guider for applying paint two curve type cooling tower inner walls

Publications (1)

Publication Number Publication Date
CN205035045U true CN205035045U (en) 2016-02-17

Family

ID=55293960

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520822594.4U Expired - Fee Related CN205035045U (en) 2015-10-22 2015-10-22 A hanging flower basket guider for applying paint two curve type cooling tower inner walls

Country Status (1)

Country Link
CN (1) CN205035045U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105236318A (en) * 2015-10-22 2016-01-13 浙江省电力建设有限公司 Hanging basket guiding device used for painting inner wall of hyperbolic-type cooling tower and painting method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105236318A (en) * 2015-10-22 2016-01-13 浙江省电力建设有限公司 Hanging basket guiding device used for painting inner wall of hyperbolic-type cooling tower and painting method

Similar Documents

Publication Publication Date Title
CN104153587B (en) A kind of built with ribbed bricks body of wall assembly construction method
CN103334378B (en) The few circulation classification stretch-draw construction method of Self-Anchored Concrete Suspension hoist cable
CN205035045U (en) A hanging flower basket guider for applying paint two curve type cooling tower inner walls
CN206158204U (en) Construction equipment of chimney shaft
CN105236318B (en) Hanging basket guider and brushing method for brushing Hyperbolic cooling tower inwall
CN205348724U (en) Detachable wire rope rings anchor structure of external scaffolding of encorbelmenting
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
CN107476443A (en) Cast-in-place concrete floor hanging built-in fitting and technique
CN204001980U (en) The steel structure enclosure wall that a kind of building site is special
CN110748173A (en) Portable autoclaved aerated concrete strip installation device
CN203200719U (en) Hanging type slope pouring template device
CN207063177U (en) Cast-in-place concrete floor hanging built-in fitting
CN205134546U (en) But quick detachable I -steel built -in fitting of encorbelmenting of cyclic utilization
CN216276900U (en) Expansion joint steel formwork capable of being constructed on same floor
CN214834994U (en) Safety rope upright post for H-shaped steel
CN211945954U (en) Detachable hanging ring structure
CN212141204U (en) Anti-falling system for aerial work
CN201447862U (en) Instrumental operating platform used for elevator shaft shear wall shuttering erection
CN211447786U (en) Turnover pull ring used on shear wall
CN109025246B (en) Scaffold frame for building engineering convenient to installation
CN206448519U (en) Constructional column side form bracing means
CN204079226U (en) A kind of movable beam string hanging apparatus that can increase rigidity when tubular truss lifts
CN204068045U (en) Transmission line wire conductor spacer maintenance aid
CN202187602U (en) Heat insulation brooder for water inlet passage of PX pump house
CN208702170U (en) A kind of tool for the installation of prestressed stretch-draw intermediate plate

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant