CN204940224U CN201520677513.6U CN201520677513U CN204940224U CN 204940224 U CN204940224 U CN 204940224U CN 201520677513 U CN201520677513 U CN 201520677513U CN 204940224 U CN204940224 U CN 204940224U
Authority
CN
China
Prior art keywords
steel slab
embedded steel
wooden form
wooden
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520677513.6U
Other languages
Chinese (zh)
Inventor
段伟
黎雄飞
龙起煌
熊忠明
余扬
张风强
田业军
童文辉
李业盛
周洲
张秋华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201520677513.6U priority Critical patent/CN204940224U/en
Application granted granted Critical
Publication of CN204940224U publication Critical patent/CN204940224U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/50Manufacturing or production processes characterised by the final manufactured product

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model provides a kind of pre-embedded steel slab being applicable to wooden model, comprises wooden form, pre-embedded steel slab, lacing wire, bolt, the lumps of wood, nut; Described wooden form and pre-embedded steel slab surface are close to, and wooden form and pre-embedded steel slab are fixed through wooden form and pre-embedded steel slab attaching nut by bolt.The utility model adopts bolt between pre-embedded steel slab and wooden form, apply a pressure, pre-embedded steel slab and wooden form surface can be tightly affixed, and between nut and wooden form, add billet, the lumps of wood to make it uniform force, avoid pre-embedded steel slab concreting vibrate work progress produce displacement; Further, avoid because of pre-embedded steel slab fix loosely can not be close to template surface produce the artificial chisel that needs remove the operation of pre-embedded steel slab surface concrete; Further, artificial chisel is except after pre-embedded steel slab surface concrete, and pre-embedded steel slab surface will be inconsistent with concrete surface planeness, cause difficulty to later stage welding for steel structure, will avoid the generation of this problem after adopting the utility model.

Description

A kind of pre-embedded steel slab being applicable to wooden model
Technical field
The utility model relates to a kind of pre-embedded steel slab being applicable to wooden model, belongs to hydroelectric project technical field.
Background technology
In the buildings such as hydroelectric project power plant building, dam, water inlet, usually need the pre-embedded steel slab when concrete structure pouring, as the pad of the steel work such as later stage cable testing bridge, railing, gate slot.Traditional way is after structure reinforcing bars colligation, is connected by the pre-embedded steel slab with lacing wire, then formwork erection, then concreting with structure reinforcing bars spot welding.Because formwork erection carries out after pre-embedded steel slab location, usually because inaccurate, the fixing reason loosely in pre-embedded steel slab location, pre-embedded steel slab surface is difficult to be adjacent to template, after causing the complete form removal of concreting, pre-embedded steel slab can not expose the problem of concrete surface, artificial chisel must be adopted to remove concrete, to make pre-embedded steel slab exposure in concrete surface, waste time and energy.And after pre-embedded steel slab surface concrete cuts, there is the discrepancy in elevation in concrete surface and pre-embedded steel slab surface, causes difficulty to weld job between steel work and pre-embedded steel slab.
Utility model content
For solving the problems of the technologies described above, the utility model provides a kind of pre-embedded steel slab being applicable to wooden model, this pre-embedded steel slab being applicable to wooden model is fastened by bolts power makes pre-embedded steel slab firmly locate accurately on wooden form the mode that pre-embedded steel slab surface and wooden model surface are close to, and ensure that pre-embedded steel slab can expose structural concrete surface, eliminate the operation of artificial chisel except pre-embedded steel slab surface concrete, and reduce the difficulty of steel work and pre-embedded steel slab weld job.
The utility model is achieved by the following technical programs.
A kind of pre-embedded steel slab being applicable to wooden model that the utility model provides, comprises wooden form, pre-embedded steel slab, lacing wire, bolt, the lumps of wood, nut; Described wooden form and pre-embedded steel slab surface are close to, and wooden form and pre-embedded steel slab are fixed through wooden form and pre-embedded steel slab attaching nut by bolt; Described lacing wire welding edges pre-embedded steel slab relative to wooden form another on the surface; The quantity of described lacing wire is more than two; Described wooden form is also fixed with the lumps of wood on the surface, between wooden form and nut relative to another of pre-embedded steel slab.
Also comprise billet, billet is fixed between nut and the lumps of wood; On the contact surface of billet and the lumps of wood, billet covers the lumps of wood completely.
Described lumps of wood length is more than or equal to the width of wooden form.
The diameter of described bolt is 20mm, and length is 20cm, and model is M16.
Described pre-embedded steel slab is Q235 steel plate, thickness 20mm.
The length of described lacing wire is greater than 50cm, and material is screw-thread steel, and diameter is 20mm.
Described wooden form is wood plywood material, and thickness is 1cm.
The beneficial effects of the utility model are: adopt bolt between pre-embedded steel slab and wooden form, apply a pressure, pre-embedded steel slab and wooden form surface can be tightly affixed, and between nut and wooden form, add billet, the lumps of wood to make it uniform force, avoid pre-embedded steel slab concreting vibrate work progress produce displacement; Further, avoid because of pre-embedded steel slab fix loosely can not be close to template surface produce the artificial chisel that needs remove the operation of pre-embedded steel slab surface concrete; Further, artificial chisel is except after pre-embedded steel slab surface concrete, and pre-embedded steel slab surface will be inconsistent with concrete surface planeness, cause difficulty to later stage welding for steel structure, will avoid the generation of this problem after adopting the utility model.
Accompanying drawing explanation
Fig. 1 is cross-sectional structural representation of the present utility model, i.e. A-A face sectional view in Fig. 2;
Fig. 2 is vertical profile structural representation of the present utility model, i.e. B-B face sectional view in Fig. 1;
Fig. 3 is the utility model is applicable to the pre-embedded steel slab surface of wooden model elevation perpendicular to wood, i.e. C-C face sectional view in Fig. 1 and Fig. 2.
In figure: 1-wooden form, 2-pre-embedded steel slab, 3-lacing wire, 4-bolt, the 5-lumps of wood, 6-billet, 7-nut, 8-structural concrete.
Detailed description of the invention
Further describe the technical solution of the utility model below, but described in claimed scope is not limited to.
A kind of pre-embedded steel slab being applicable to wooden model as shown in Figure 1 to Figure 3, comprises wooden form 1, pre-embedded steel slab 2, lacing wire 3, bolt 4, the lumps of wood 5, nut 7; Described wooden form 1 and pre-embedded steel slab 2 surface are close to, and wooden form 1 and pre-embedded steel slab 2 are fixed through wooden form 1 and pre-embedded steel slab 2 attaching nut 7 by bolt 4; Described lacing wire 3 welding edges pre-embedded steel slab 2 relative to wooden form 1 another on the surface; The quantity of described lacing wire 3 is more than two; Described wooden form 1 is also fixed with the lumps of wood 5 on the surface, between wooden form 1 and nut 7 relative to another of pre-embedded steel slab 2.
Also comprise billet 6, billet 6 is fixed between nut 7 and the lumps of wood 5; On the contact surface of billet 6 and the lumps of wood 5, billet 6 covers the lumps of wood 5 completely.
The described lumps of wood 5 length is more than or equal to the width of wooden form 1.
The diameter of described bolt 4 is 20mm, and length is 20cm, and model is M16.
Described pre-embedded steel slab 2 is Q235 steel plate, thickness 20mm.
The length of described lacing wire 3 is greater than 50cm, and material is screw-thread steel, and diameter is 20mm.
Described wooden form 1 is wood plywood material, and thickness is 1cm, combines lateral force when bearing pouring structure concrete eight with the lumps of wood 5.
The object of the setting of billet 6 is that the pressure uniform in order to make nut 7 produce is distributed in the lumps of wood 5 surface, prevent stressed concentrating below nut 7 from causing the lumps of wood 5 surface indentation to destroy, and then affect the fastening force of bolt 4 generation, cause pre-embedded steel slab 2 can not be close to wooden form 1.
The object that the lumps of wood 5 is arranged is the active area of fastening force on wooden form 1 produced to expand bolt 4, in order to avoid local pressure crosses havoc wooden form 1 structure.
The utility model is installed in the following way:
1st step: lacing wire 3 is welded with pre-embedded steel slab 2.
2nd step: binding structure steel mesh reinforcement, according to roughly locating, that the thin galvanized wire of pre-embedded steel slab 2 is temporarily fixed on structure reinforcing bars is online.
3rd step: standing tree template 1, and according to project organization size, measurement and positioning is carried out and fixing wooden form 1 to wooden form 1.
4th step: surveying and locating pre-embedded steel slab 2 is located, and hole in the relevant position of wooden form 1.
5th step: pre-embedded steel slab 2, bolt 4, the lumps of wood 5, billet 6 are arranged on wooden form 1 both sides respectively, remove the thin galvanized wire of temporary fixed pre-embedded steel slab 2, remeasures location pre-embedded steel slab and upper jack panel 7.
6th step: pouring structure concrete eight.
7th step: after structural concrete 8 reaches design strength, removes wooden form 1, is cleaned out by pre-embedded steel slab 2 surface and oil contaminant.
8th step: steel work (cable testing bridge, railing, gate slot etc.) is connected by welding on pre-embedded steel slab 2.

Claims (7)

1. one kind is applicable to the pre-embedded steel slab of wooden model, comprise wooden form (1), pre-embedded steel slab (2), lacing wire (3), bolt (4), the lumps of wood (5), nut (7), it is characterized in that: described wooden form (1) and pre-embedded steel slab (2) surface are close to, wooden form (1) and pre-embedded steel slab (2) are fixed through wooden form (1) and pre-embedded steel slab (2) attaching nut (7) by bolt (4); Described lacing wire (3) welding edges pre-embedded steel slab (2) relative to wooden form (1) another on the surface; The quantity of described lacing wire (3) is more than two; Described wooden form (1) is also fixed with the lumps of wood (5) on the surface, between wooden form (1) and nut (7) relative to another of pre-embedded steel slab (2).
2. be applicable to the pre-embedded steel slab of wooden model as claimed in claim 1, it is characterized in that: also comprise billet (6), billet (6) is fixed between nut (7) and the lumps of wood (5); On the contact surface of billet (6) and the lumps of wood (5), billet (6) covers the lumps of wood (5) completely.
3. be applicable to the pre-embedded steel slab of wooden model as claimed in claim 1, it is characterized in that: the described lumps of wood (5) length is more than or equal to the width of wooden form (1).
4. be applicable to the pre-embedded steel slab of wooden model as claimed in claim 2, it is characterized in that: the diameter of described bolt (4) is 20mm, and length is 20cm, and model is M16.
5. be applicable to the pre-embedded steel slab of wooden model as claimed in claim 2, it is characterized in that: described pre-embedded steel slab (2) is Q235 steel plate, thickness 20mm.
6. be applicable to the pre-embedded steel slab of wooden model as claimed in claim 1, it is characterized in that: the length of described lacing wire (3) is greater than 50cm, material is screw-thread steel, and diameter is 20mm.
7. be applicable to the pre-embedded steel slab of wooden model as claimed in claim 1, it is characterized in that: described wooden form (1) is wood plywood material, and thickness is 1cm.
CN201520677513.6U 2015-09-01 2015-09-01 A kind of pre-embedded steel slab being applicable to wooden model Active CN204940224U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520677513.6U CN204940224U (en) 2015-09-01 2015-09-01 A kind of pre-embedded steel slab being applicable to wooden model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520677513.6U CN204940224U (en) 2015-09-01 2015-09-01 A kind of pre-embedded steel slab being applicable to wooden model

Publications (1)

Publication Number Publication Date
CN204940224U true CN204940224U (en) 2016-01-06

Family

ID=55007666

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520677513.6U Active CN204940224U (en) 2015-09-01 2015-09-01 A kind of pre-embedded steel slab being applicable to wooden model

Country Status (1)

Country Link
CN (1) CN204940224U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105133556A (en) * 2015-09-01 2015-12-09 中国电建集团贵阳勘测设计研究院有限公司 Pre-embedded steel plate applicable to wood formwork

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105133556A (en) * 2015-09-01 2015-12-09 中国电建集团贵阳勘测设计研究院有限公司 Pre-embedded steel plate applicable to wood formwork

Similar Documents

Publication Publication Date Title
CN104790569A (en) Formwork-free shear wall and construction method thereof
CN104005556A (en) Shaped and fabricated formwork construction process used for shear wall at expansion and contraction joint
CN103437493A (en) Connecting node of prefabricated reinforced concrete beam and construction method of connecting node
CN204940224U (en) A kind of pre-embedded steel slab being applicable to wooden model
CN105133556A (en) Pre-embedded steel plate applicable to wood formwork
CN101694127B (en) Formwork support system for steel frame structure cast-in-place concrete floorslabs
CN206091355U (en) Post structure is taken out to concrete plant's pillars of a house
CN103225396B (en) Beam frame type construction template system
KR100865133B1 (en) A fixing device, a pre-fabricating forms for concrete-structure and the construction method thereof
CN202596148U (en) Reusable cantilever scaffold anchoring compression ring
CN204940219U (en) A kind of magnetic pre-embedded steel slab fixed structure
CN205171999U (en) Narrow expansion joint of shear force wall template
CN111411643A (en) Construction method of construction elevator foundation supported on basement top plate
CN103290966A (en) Floor slab component
CN105275198B (en) A kind of shear-wall strengthening formwork structure and its construction method
CN105735666A (en) Method for reinforcing concrete column rapidly
CN201826526U (en) Device for supporting template of steel frame structure cast-in-situ concrete floor slab
CN204940825U (en) A kind of foundation structure of builder's jack
CN104790353A (en) Sluice pier construction method for small and medium size sluices
CN201695676U (en) Strengthening tool of cast-in-place concrete beam side formwork of house building
CN203531380U (en) Size-adjustable formwork system with local supports arranged bellow beam and no support arranged below plate
CN210563380U (en) Combined template at deformation joint of building construction
CN201679227U (en) Template-supporting device of cast-in-place concrete floor slab of box-shaped beam with steel frame structure
KR100695491B1 (en) A fixing device, a pre-fabricating forms for concrete-structure and the construction method thereof
CN210621946U (en) Novel U type of concrete frame and concrete wallboard be connected device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant