CN204850482U
CN204850482U CN201520547289.9U CN201520547289U CN204850482U CN 204850482 U CN204850482 U CN 204850482U CN 201520547289 U CN201520547289 U CN 201520547289U CN 204850482 U CN204850482 U CN 204850482U
Authority
CN
China
Prior art keywords
jack
stretch
balance beam
draw
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520547289.9U
Other languages
Chinese (zh)
Inventor
张传令
殷倩倩
文璐
张华和
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CR10BG CONSTRUCTION ENGINEERING Co Ltd
Construction Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Original Assignee
CR10BG CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CR10BG CONSTRUCTION ENGINEERING Co Ltd filed Critical CR10BG CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201520547289.9U priority Critical patent/CN204850482U/en
Application granted granted Critical
Publication of CN204850482U publication Critical patent/CN204850482U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an anti - stretch -draw pre -compaction instrument of jack, including cushion cap and support to and balance beam, finish rolling screw -thread steel, jack and steel shotcrete, balance beam sets up on the support, it is one pre -buried in the cushion cap that gasket no. 1, nut are passed through to the lower part of finish rolling screw -thread steel, and balance beam is passed on upper portion, and the steel shotcrete penetrates the finish rolling screw -thread steel through gasket no. 2 and puts on balance beam, and the jack is arranged in through gasket no. 3 and three anchors on the nut on the steel shotcrete. The utility model discloses lay balance beam on the support of setting up, finish rolling screw -thread steel pre -buried on the cushion cap passes balance beam, utilizes the anti - stretch -draw finish rolling screw -thread steel of jack to realize the pre -compaction effect. The utility model discloses utilizing the anti - stretch -draw pre -compaction of jack, controlling stretch -draw stress with the reading of oil meter, the pre -compaction precision is high, has convenience, swift characteristics, can improve work efficiency, shortens construction period, practices thrift the cost.

Description

A kind of jack anti-sheet draws prepressing means
Technical field
The utility model relates to a kind of jack anti-sheet and draws prepressing means, belongs to technical field of building construction.
Background technology
Pre-pressing bracket is one important procedure of Construction of continuous beam.Current, pre-pressing bracket majority uses sand pocket prepressing means, expends more manpower and materials and adds construction cost, also having a certain impact to construction period.
Summary of the invention
Technical problem to be solved in the utility model is the defect existed for prior art, provides a kind of jack anti-sheet reducing construction cost to draw prepressing means.
For solving this technical problem, the utility model provides a kind of jack anti-sheet and draws prepressing means, comprise cushion cap and support, and shoulder pole girder, fining twisted steel, jack and bracing members, described shoulder pole girder is set up on support, and the bottom of described fining twisted steel is pre-buried in cushion cap by pad one, nut one, and top is through shoulder pole girder, bracing members penetrates fining twisted steel by pad two and is placed on shoulder pole girder, and jack is placed on bracing members by pad three and nut three anchoring.
Described jack is hydraulic jack.
Beneficial effect: the utility model lays shoulder pole girder on the support set up, fining twisted steel pre-buried on cushion cap, through shoulder pole girder, utilizes jack anti-sheet to draw fining twisted steel to realize pre-compressed effect.The utility model utilizes jack anti-sheet to draw precompressed, controls tension stress with the reading of oil meter, and precompressed precision is high, has feature easily and efficiently, can increase work efficiency, and shortens the construction period, cost-saving.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
In figure: 1 cushion cap, 2 supports, 3 shoulder pole girders, 4 fining twisted steels, 5 pad one, 6 nut one, 7 jack, 8 bracing members, 9 pad two, 10 nut two, 11 pad three, 12 nuts three.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is specifically described.
Figure 1 shows that structural representation of the present utility model.
The utility model comprises cushion cap 1 and support 2, and shoulder pole girder 3, fining twisted steel 4, jack 7 and bracing members 8.
Described shoulder pole girder 3 is set up on support 2.
The bottom of described fining twisted steel 4 is pre-buried in cushion cap 1 by pad 1, nut 1, and top is through shoulder pole girder 3.
Described bracing members 8 penetrates fining twisted steel 4 by pad 29 and is placed on shoulder pole girder 3.
Described jack 7 is placed on bracing members 8 by pad 3 11 and nut 3 12 anchoring.
Described jack 7 is hydraulic jack.
Utility model works principle and pressing step:
Described jack 7 utilizes oil meter reading to control tension stress: tighten the nut 3 12 above jack 7 before every grade of precompressed, stretch-draw is embedded in cushion cap 1 li of fining twisted steel 4; Bracing members 8 inner nut 2 10 is tightened after fining twisted steel 4 stretch-draw; Continue all the other fining twisted steels 4 of precompressed; After the equal precompressed of all fining twisted steels 4, proceed all the other rank precompressed according to same steps.
The utility model lays shoulder pole girder on the support set up, and fining twisted steel pre-buried on cushion cap, through shoulder pole girder, utilizes jack anti-sheet to draw fining twisted steel to realize pre-compressed effect.The utility model utilizes jack anti-sheet to draw precompressed, controls tension stress with the reading of oil meter, and precompressed precision is high, has feature easily and efficiently, can increase work efficiency, and shortens the construction period, cost-saving.
The above-mentioned embodiment of the utility model, just illustrates, is not only, and all changes within the scope of the utility model or in equivalent scope of the present utility model are all surrounded by the utility model.

Claims (2)

1. a jack anti-sheet draws prepressing means, comprise cushion cap (1) and support (2), it is characterized in that: also comprise shoulder pole girder (3), fining twisted steel (4), jack (7) and bracing members (8), described shoulder pole girder (3) is set up on support (2), the bottom of described fining twisted steel (4) is by pad one (5), nut one (6) is pre-buried in cushion cap 1, top is through shoulder pole girder (3), bracing members (8) penetrates fining twisted steel (4) by pad two (9) and is placed on shoulder pole girder (3), jack (7) is placed on bracing members (8) by pad three (11) and nut three (12) anchoring.
2. jack anti-sheet according to claim 1 draws prepressing means, it is characterized in that: described jack (7) is hydraulic jack.
CN201520547289.9U 2015-07-24 2015-07-24 Anti - stretch -draw pre -compaction instrument of jack Active CN204850482U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520547289.9U CN204850482U (en) 2015-07-24 2015-07-24 Anti - stretch -draw pre -compaction instrument of jack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520547289.9U CN204850482U (en) 2015-07-24 2015-07-24 Anti - stretch -draw pre -compaction instrument of jack

Publications (1)

Publication Number Publication Date
CN204850482U true CN204850482U (en) 2015-12-09

Family

ID=54741047

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520547289.9U Active CN204850482U (en) 2015-07-24 2015-07-24 Anti - stretch -draw pre -compaction instrument of jack

Country Status (1)

Country Link
CN (1) CN204850482U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576223A (en) * 2020-05-12 2020-08-25 陕西中立检测鉴定有限公司 Main tower lower cross beam support pre-pressing device and pre-pressing method thereof
CN113737653A (en) * 2021-08-11 2021-12-03 广东水电二局股份有限公司 Prepressing device of bearing support and using method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576223A (en) * 2020-05-12 2020-08-25 陕西中立检测鉴定有限公司 Main tower lower cross beam support pre-pressing device and pre-pressing method thereof
CN113737653A (en) * 2021-08-11 2021-12-03 广东水电二局股份有限公司 Prepressing device of bearing support and using method thereof

Similar Documents

Publication Publication Date Title
CN203129026U (en) Reinforced concrete arch bridge reinforced structure
CN104020056B (en) The loading method of concrete creep test under the effect of a kind of curved scissors pressure compound stress
CN205223871U (en) Suspension bridge bridge tower overarm brace pre -compaction device
CN204850482U (en) Anti - stretch -draw pre -compaction instrument of jack
CN203546717U (en) Recycled prestress anchor rod
CN202787099U (en) Reinforced concrete cap beam external prestressing structure
CN103306495B (en) Wooden construction truncated cylinder reinforced construction method
CN202100021U (en) Transverse crack reinforcing device for reinforced concrete electric pole with circular section
CN201738246U (en) Ground loading and pressing device for continuous beam suspended bracket
CN204827499U (en) Novel slip casting stock of taking scale is by clamping ring
CN202466651U (en) Loading device for axial force test of prestressed pipe pile
CN204492851U (en) Metro built by mining method transverse passage-way temporary support component
CN101281119B (en) Sustained load loader for FRP cloth reinforcement experiment as well as method thereof
CN203260257U (en) Prestress construction teaching model
CN203174892U (en) Pre-stressed tendon single pole multi-thread connector for field processing
CN204475872U (en) Pre-stressed carbon fiber plate tensioning equipment
CN202194073U (en) Large-volume long-cantilever capping beam construction device
CN205223842U (en) Cable -stay bridge structure system prevents that negative reaction structure from appearing in girder
CN105569371A (en) Site strengthening method for enhancing structural load carrying capacity of existing steel beam and steel structure composite beam
CN204349332U (en) A kind of suspension clamp for electric line fastened tools with moment Presentation Function
CN204418535U (en) Strengthening beam steel cushion block
CN203613469U (en) Bridge bonding steel plate reinforcing device
CN203430131U (en) Inhaul cable single-pipe tower resistant to deformation
CN110387829A (en) Large-scale transverse beam bracket carries out the system and operating method of precompressed by multi-point-anchoring stretching method
CN209456907U (en) The steel horizontal-associate structure of transversely strengthening between concrete prefabricated T beam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant