CN204850368U - Modularization riser system - Google Patents
Modularization riser system Download PDFInfo
- Publication number
- CN204850368U CN204850368U CN201520537578.0U CN201520537578U CN204850368U CN 204850368 U CN204850368 U CN 204850368U CN 201520537578 U CN201520537578 U CN 201520537578U CN 204850368 U CN204850368 U CN 204850368U
- Authority
- CN
- China
- Prior art keywords
- riser
- riser systems
- standpipe
- modularization
- floor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a modularization riser system, including at least a set of riser system module, every group riser system module includes pipeline bracket and fixes pipeline bracket a plurality of last risers, every riser is unanimous with interval between the adjacent riser, and riser length is corresponding with the floor height, riser system module place tubular well is the one -piece casting with the floor of floor, and position one -to -one between upper and lower two sets of riser system module's the riser, forms stable tubular well structure. The utility model discloses a riser system module one by one, fortune to job site integral erection are makeed at the interplant according to the high merogenesis of floor together with pipeline bracket in advance by the riser for the construction progress reduces intensity of labour, compares single installation, the welding of the construction of conventional tubular well riser, and modularization riser system has reduced danger along with the structure construction effectively.
Description
Technical field
The utility model belongs to building dynamo-electric installation of modular field, specifically a kind of installation system of standpipe.
Background technology
Along with the progress in epoch, management expectancys such as reducing high-rise working reduction security risk to greatest extent, ensure installation quality, the reduction of erection time makes investment be recompensed early, all queries to traditional construction method of installation.
In these small spaces of main pipe well of highrise building, need the standpipe arranging the various medium of conveying, comprise living water supply pipe, fire water supply pipe, sewage drainage pipe, ventilating pipe, hot-water line, return pipe and intermediate water pipeline etc.How improving installation rate and the efficiency of pipe well standpipe, reduce the security risk of tube well construction, ensure the installation quality etc. of riser systems, is an emphasis difficult problem for building electromechanical installation all the time, the tube well construction process of especially high-rise super highrise building.
Traditional standpipe integral installation method, transport, installation all need to drop into a large amount of manpower, financial resources, and construction is slow, labour intensity is large, and safety can not be guaranteed, and needs improve, to meet current building operations requirement.
Summary of the invention
Goal of the invention: the utility model object is for the deficiencies in the prior art, provides one to be convenient to processing, transport, the modularization riser systems that installation effectiveness is high, and the modularization realized in dynamo-electric work progress is installed.
Technical scheme: modularization riser systems described in the utility model, for the pipe well Pipe installing that many floors are built, comprise at least one group of riser systems module, often organize described riser systems module to comprise support of pipelines and be fixed on some standpipes on described support of pipelines, spacing between adjacent two standpipes is consistent, riser length and story height suitable; The floor of described riser systems module place pipe well and floor is monobloc cast, and position one_to_one corresponding between the standpipe of upper and lower two groups of riser systems modules, form stable pipe well structure.
Principle of the present utility model is: form a riser systems module with pipeline all or part of in pipe well, in prefabricated processing factory, standpipe is processed into the stable tube coupling corresponding with story height, and forms total system by support of pipelines.When major structure of construction constructs respective storey, utilize on-site hoisting equipment by riser systems module hoisting in pipe well, in place and fixing, connect, the laggard line pipe well of riser systems module installation and concrete floor slab placement, pipe well and floor are connected as a single entity.
The utility model further preferably technical scheme is, described riser systems module also comprises the location pipe clamp consistent with described standpipe quantity, and described standpipe is fastened by described positioning pipe and is erected on described support of pipelines.Linked by positioning pipe and connect standpipe and support of pipelines, guarantee both stable connections.
Further, every root standpipe of described riser systems module and support of pipelines are provided with unique radio frequency identification to identify.For marking the uniqueness of each module, thus making between standpipe and pipe support, between pipe support and pipe support, forming a metastable integral module between standpipe and standpipe, being convenient to installation and maintenance.
Preferably, the height of described standpipe is 2 ~ 3 floor layer heights.
Preferably, described in every root, the error in length of standpipe is ± 5mm, and section error is ± 0.8-2.5mm; Described support of pipelines scale error is ± 3mm.
Beneficial effect: (1) standpipe of the present utility model is according to story height merogenesis, in factory, riser systems module is one by one made in advance together with support of pipelines, be transported to job site integral installation, accelerating construction progress, reduce labour intensity, compare the single installation of conventional pipe well standpipe construction, welding, modularization riser systems, with structure construction, significantly reduces danger;
(2) every root standpipe of riser systems module of the present utility model and support of pipelines are provided with unique RFID tag, by RFID radio-frequency recognition system, to often organizing riser systems module, even often root standpipe and support of pipelines identify, make between standpipe and pipe support, between pipe support and pipe support, form a metastable integral module between standpipe and standpipe, achieve the standardization of products, digitize and informationize, convenient installation and maintenance;
(3) machining accuracy of the present utility model is high, and on-the-spot interface is few, and workmanship can greatly be ensured; The laggard line pipe well of standpipe installation and concrete floor slab placement simultaneously, pipe well and floor are connected as a single entity, and have stopped potential safety hazard.
(4) modularization riser systems of the present utility model is a kind of novel mounting process breaking through traditional highrise building pipe well interior conduit mounting method, structure is simple, and easy to operate, installation effectiveness is high, strong adaptability, has good market prospects in high level, the dynamo-electric installation process of super highrise building.
Accompanying drawing explanation
Fig. 1 is the structural representation of modularization riser systems described in the utility model.
Detailed description of the invention
Below by accompanying drawing, technical solutions of the utility model are described in detail, but protection domain of the present utility model is not limited to described embodiment.
embodiment 1:a kind of modularization riser systems, for the pipe well Pipe installing that many floors are built, comprises at least one group of riser systems module, as shown in Figure 1:
Often organize riser systems module and comprise support of pipelines 2, and be fixed on some standpipes 1 on support of pipelines 2 by location pipe clamp 3, every root standpipe 1 of this riser systems module and support of pipelines 2 are provided with unique RFID radio frequency identification identify, spacing between adjacent two standpipes 1 is consistent, standpipe 1 length is consistent with 2 ~ 3 layers of story height to be onstructed, the error in length of every root standpipe is ± 5mm, and section error is ± 0.8-2.5mm; Support of pipelines 2 scale error is ± 3mm;
The pipe well at each group of riser systems module place and the floor monobloc cast of floor, and position one_to_one corresponding between the standpipe 1 of upper and lower two groups of riser systems modules, form stable pipe well structure.
As mentioned above, although represented with reference to specific preferred embodiment and described the utility model, it shall not be construed as the restriction to the utility model self.Under the spirit and scope prerequisite of the present utility model not departing from claims definition, various change can be made in the form and details to it.
Claims (5)
1. a modularization riser systems, for the pipe well Pipe installing that many floors are built, it is characterized in that, comprise at least one group of riser systems module, often organize described riser systems module to comprise support of pipelines and be fixed on some standpipes on described support of pipelines, spacing between adjacent two standpipes is consistent, riser length and story height suitable; The floor of described riser systems module place pipe well and floor is monobloc cast, and position one_to_one corresponding between the standpipe of upper and lower two groups of riser systems modules, form stable pipe well structure.
2. modularization riser systems according to claim 1, is characterized in that, described riser systems module also comprises the location pipe clamp consistent with described standpipe quantity, and described standpipe is fastened by described positioning pipe and is erected on described support of pipelines.
3. modularization riser systems according to claim 1, is characterized in that, every root standpipe of described riser systems module and support of pipelines is provided with unique radio frequency identification and identifies.
4. modularization riser systems according to claim 1, is characterized in that, the height of described standpipe is 2 ~ 3 floor layer heights.
5. modularization riser systems according to claim 1, is characterized in that, described in every root, the error in length of standpipe is ± 5mm, and section error is ± 0.8-2.5mm; Described support of pipelines scale error is ± 3mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520537578.0U CN204850368U (en) | 2015-07-22 | 2015-07-22 | Modularization riser system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520537578.0U CN204850368U (en) | 2015-07-22 | 2015-07-22 | Modularization riser system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204850368U true CN204850368U (en) | 2015-12-09 |
Family
ID=54740933
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520537578.0U Active CN204850368U (en) | 2015-07-22 | 2015-07-22 | Modularization riser system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204850368U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700399A (en) * | 2018-11-22 | 2020-01-17 | 中铁工程装备集团钢结构有限公司 | Modular pipeline system for assembled integrated house and installation method |
CN113530151A (en) * | 2021-06-29 | 2021-10-22 | 大荣建设集团有限公司 | Construction method for vertical pipeline of segmented and assembled high-rise building pipe well |
-
2015
- 2015-07-22 CN CN201520537578.0U patent/CN204850368U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700399A (en) * | 2018-11-22 | 2020-01-17 | 中铁工程装备集团钢结构有限公司 | Modular pipeline system for assembled integrated house and installation method |
CN110700399B (en) * | 2018-11-22 | 2021-06-01 | 中铁钢结构有限公司 | Modular pipeline system for assembled integrated house and installation method |
CN113530151A (en) * | 2021-06-29 | 2021-10-22 | 大荣建设集团有限公司 | Construction method for vertical pipeline of segmented and assembled high-rise building pipe well |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104806822A (en) | Combined type stand pipe and modularized installation method thereof | |
CN203961276U (en) | High-building construction steel form and handling frame Integral lifting stage apparatus | |
CN204850368U (en) | Modularization riser system | |
CN110107972A (en) | Cabin-type refrigerating plant room and its construction method | |
CN103290918A (en) | Underground prefabricated pump station | |
CN203820287U (en) | Composite steel carrying pole for hoisting roof tiles of steel structure workshops | |
CN102352690B (en) | Construction method of anti-floating locating system of cast-in-place concrete hollow floorslab steel tube | |
CN102733614B (en) | A kind of construction method of room module of nuclear power plant | |
CN202865996U (en) | Room modular structure for nuclear power plant | |
CN108086523B (en) | Light steel concrete block composite wall and construction method thereof | |
CN204959890U (en) | Prefabricated mounting structure of indoor U -PVC soil stack of high -rise building | |
CN103276840B (en) | Nuclear power plant composite floor slab module and construction method thereof | |
CN204815493U (en) | Big space furred ceiling blowing system of modularization | |
CN114382295A (en) | Indoor assembled drainage pipeline modular construction method | |
CN203454182U (en) | Central gas supply system of boiler | |
CN203067936U (en) | High-altitude pipeline installation safe lifting bracket | |
CN207960151U (en) | A kind of protective fence of construction | |
CN211257431U (en) | Assembled wall body | |
CN106451169A (en) | Box module combined transformer substation and installation method thereof | |
CN203850627U (en) | Overall framework type modularization secondary device applied to substation construction | |
CN202055496U (en) | Easy-to-adjust moving operation platform | |
CN102251679A (en) | Construction method | |
CN111395744A (en) | Construction method of aluminum template in horizontal flowing section process of villa | |
CN111321878A (en) | Conversion construction method for double-layer breathing type curtain wall frame body system | |
CN203924748U (en) | Kitchen and toilet air flue horizontal protector |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 210046 Yaojia Road, Qixia District, Nanjing, Jiangsu Province Patentee after: China Construction Installation Group Co., Ltd. Address before: 210046 Yaojia Road, Qixia District, Nanjing, Jiangsu Province Patentee before: China Construction Industrial Equipment Installation Co., Ltd. |
|
CP01 | Change in the name or title of a patent holder |