CN204789647U - Two split conductor on -line monitoring device install fixture - Google Patents

Two split conductor on -line monitoring device install fixture Download PDF

Info

Publication number
CN204789647U
CN204789647U CN201520492388.1U CN201520492388U CN204789647U CN 204789647 U CN204789647 U CN 204789647U CN 201520492388 U CN201520492388 U CN 201520492388U CN 204789647 U CN204789647 U CN 204789647U
Authority
CN
China
Prior art keywords
anchor clamps
wire
sheath
box
coil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201520492388.1U
Other languages
Chinese (zh)
Inventor
张亚博
黄桥林
李玉伟
王磊
张红梅
朱国营
李燕妮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Puyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Puyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Puyang Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201520492388.1U priority Critical patent/CN204789647U/en
Application granted granted Critical
Publication of CN204789647U publication Critical patent/CN204789647U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model provides a two split conductor on -line monitoring device install fixture, its mounting means is fairly simple, reliable. The installation fixture include coil anchor clamps and coil, and the coil anchor clamps include that the cross section is semicircular and goes up anchor clamps and anchor clamps down, go up anchor clamps and anchor clamps one end down through the pivot link to each other, in addition one end pass through the connecting piece and connect, lower anchor clamps link to each other with the connecting plate of sheath tip, lower anchor clamps link to each other with the box, box top with lid, the circuit board setting in the box, the sheath cross section be with wire complex arc, the hank knotting winding is on sheath and wire in advance. The utility model discloses the can be swiftly reliable fixes the installation of circuit monitoring facilities at the mounting point, and the atress is even behind the equipment fixing, can not cause the damage to the wire, can guarantee that mounting point equipment can not take place to slide in the wire direction, and the radial direction of wire can not take place rotatoryly, ensures that equipment is fixed reliable and stable, and can get the influence electricity from two high -pressure wires simultaneously.

Description

Double bundle conductor on-Line Monitor Device installs jig
Technical field
The utility model relates to the jig on a kind of double bundle conductor, is specifically related to a kind of installation jig can powered to pick-up unit.
Background technology
The on-line monitoring equipment that transmission line of electricity is installed and high-voltage conducting wires be fixedly the difficult problem all the time faced, irrational fixed form, can following problems be brought:
1. when double bundle conductor installs the monitoring device based on induction power taking, solid conductor electric current is only 1/2 of line current, the circuit that portion of electrical current is less, only installs induction electricity getting device and can not meet monitoring device power requirement, need all install induced electricity device additional on two wires on solid conductor.
2. install the difficulty of operation: due to the special operation condition of high-tension line erecting equipment, irrational sectional fixture can cause installing operating difficulties, and the set-up time is long.
3. it is fastening unreliable to install; The user that ultra-high-tension power transmission line relates to is numerous, and accidental power failure tripping operation can cause heavy losses, and conductive line surfaces is aluminum material, and irrational fixture can cause wire impaired, conventional fastened by screw mode, the circuit waved very easily produces and loosens, there is potential safety hazard.
Utility model content
The purpose of this utility model is for above-mentioned the deficiencies in the prior art, provides a kind of double bundle conductor on-Line Monitor Device to install jig, can be fixed on double bundle conductor very easily, for pick-up unit provides power supply, its mounting means is fairly simple, reliable.
The technical solution of the utility model is achieved in that
A kind of double bundle conductor on-Line Monitor Device installs jig, comprise coil clamp and coil, it is semicircular upper fixture and lower clamp that coil clamp comprises xsect, upper fixture is connected by rotating shaft with lower clamp one end, other one end is connected by web member, and lower clamp is connected with the web joint of sheath ends, and lower clamp is connected with box, lid is provided with above box, wiring board is arranged in box, and sheath xsect is the arc coordinated with wire, and preformed armor rods is wrapped on sheath and wire.
Described sheath is provided with spacing preiection.
Described box is connected with flange and column up and down respectively, and flange is connected with monitoring device, and column is connected with bridge.
Path monitoring equipment can be fixed on mounting points by the utility model fast reliably, equipment installs rear uniform force, damage can not be caused to wire, can ensure that mounting points equipment can not slide in wire direction, wire radial direction can not rotate, guarantee that equipment fixing-stable is reliable, and induced electricity can be got from two high-voltage conducting wires simultaneously.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is only embodiments more of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is schematic perspective view of the present utility model (not showing sheath).
Fig. 2 is structural representation of the present utility model.
Fig. 3 is the structural representation of coil clamp.
Fig. 4 is the winding arrangement schematic diagram of preformed armor rods.
Wherein: 1. coil clamp, the upper fixture of 1-1., 1-2. lower clamp, 2. sheath, 3. web joint, 4. box, 5. lid, 6. wire, 7. preformed armor rods, 8. flange, 9. column, 10. spacing preiection, 11. pick-up units, 12. bridges.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, be clearly and completely described the technical scheme in the utility model embodiment, obviously, described embodiment is only the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not paying the every other embodiment obtained under creative work prerequisite, all belong to the scope of the utility model protection.
As shown in figures 1-4, a kind of double bundle conductor on-Line Monitor Device installs jig, comprise coil clamp 1 and coil, it is semicircular upper fixture 1-1 and lower clamp 1-2 that coil clamp 1 comprises xsect, upper fixture 1-1 is connected by axis of rotation with lower clamp 1-2 one end, other one end is connected by web member, lower clamp 1-2 is connected with the web joint 3 of sheath 2 end, lower clamp 1-2 is connected with box 4, lid 5 is provided with above box 4, wiring board is arranged in box 4, sheath 2 xsect is the arc coordinated with wire 6, and preformed armor rods 7 is wrapped on sheath 2 and wire 6.Connection between lid 5 and box 4 adopts waterproofing design, and cassette interior arranges wire and circuit board, and web joint 2 and lower clamp 1-2 can be that bolt is connected, and also can be welding.
Preferably, described sheath 2 is provided with spacing preiection 10.When winding preformed armor rods, spacing preiection 10 can play anticreep effect, can prevent preformed armor rods, sheath 2 departs from.
The utility model is installed on high-tension line: the first step: be wound to corresponding monitoring equipment mounting points by middle for preformed armor rods 7 one section, second step: path monitoring equipment the latter half is held up, first one end sheath 2 is rested on the preformed armor rods 7 of partial fixing on high-voltage conducting wires, end preformed armor rods is lashed on high-voltage conducting wires, other one end sheath 2 also uses preformed armor rods to be wrapped on high-voltage conducting wires with same method by the 3rd step, note guaranteeing that preformed armor rods enwinds sheath when two ends preformed armor rods is wound around, and preformed armor rods is in spacing preiection 10 scope, guarantee that preformed armor rods is in place, guarantee that the winding of preformed armor rods is consistent with high-voltage conducting wires twisted wire groove, the fastening firm of installation can be ensured.
When in use, described box about 4 is connected with flange 8 and column 9 respectively, and flange 8 is connected with monitoring device 11 or other power devices, and column 9 is connected with bridge 12.
Installation jig described in the utility model, install in the following manner:
(1) by one ends wound in the middle of preformed armor rods on the wire 6 of monitoring equipment mounting points;
(2) box 4 is held up, sheath 2 is placed on partial fixing and, on the preformed armor rods of wire, utilizes preformed armor rods sheath 2 and wire to be intertwined;
(3) be connected with lower clamp 1-2 after upper fixture 1-1 being walked around wire.Connection between upper fixture 1-1 and lower clamp 1-2 can be realized by the various forms such as hasp, bolt and nut.
The utility model is arranged on high voltage electricity transmission conductive wire, after installation, coil winding is in wire outer ring, on high voltage electricity transmission conductive wire, process is alternating current, coil all generation currents under coupling on two wires, the conversion of the Voltage stabilizing module again in circuit board etc., may be used for powering directly to pick-up unit, and electric current is enough to the use of supply pick-up unit.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (3)

1. a double bundle conductor on-Line Monitor Device installs jig, comprise coil clamp (1) and coil, it is characterized in that: it is semicircular upper fixture (1-1) and lower clamp (1-2) that coil clamp (1) comprises xsect, upper fixture (1-1) is connected by rotating shaft with lower clamp (1-2) one end, one end is connected by web member in addition, lower clamp (1-2) is connected with the web joint (3) of sheath (2) end, lower clamp (1-2) is connected with box (4), box (4) top is provided with lid (5), wiring board is arranged in box (4), sheath (2) xsect is the arc coordinated with wire (6), preformed armor rods (7) is wrapped on sheath (2) and wire (6).
2. double bundle conductor on-Line Monitor Device according to claim 1 installs jig, it is characterized in that: described sheath (2) is provided with spacing preiection (10).
3. double bundle conductor on-Line Monitor Device according to claim 2 installs jig, it is characterized in that: described box (4) is connected with flange (8) and column (9) up and down respectively, flange (8) is connected with monitoring device (11), and column (9) is connected with bridge (12).
CN201520492388.1U 2015-07-09 2015-07-09 Two split conductor on -line monitoring device install fixture Withdrawn - After Issue CN204789647U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520492388.1U CN204789647U (en) 2015-07-09 2015-07-09 Two split conductor on -line monitoring device install fixture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520492388.1U CN204789647U (en) 2015-07-09 2015-07-09 Two split conductor on -line monitoring device install fixture

Publications (1)

Publication Number Publication Date
CN204789647U true CN204789647U (en) 2015-11-18

Family

ID=54529664

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520492388.1U Withdrawn - After Issue CN204789647U (en) 2015-07-09 2015-07-09 Two split conductor on -line monitoring device install fixture

Country Status (1)

Country Link
CN (1) CN204789647U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105044395A (en) * 2015-07-09 2015-11-11 国网河南省电力公司濮阳供电公司 Double-split wire on-line monitoring device installation fixture and installation method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105044395A (en) * 2015-07-09 2015-11-11 国网河南省电力公司濮阳供电公司 Double-split wire on-line monitoring device installation fixture and installation method
CN105044395B (en) * 2015-07-09 2017-10-10 国网河南省电力公司濮阳供电公司 Double bundle conductor on-Line Monitor Device installs fixture and installation method

Similar Documents

Publication Publication Date Title
US20170338633A1 (en) Quick connect and disconnect cable junction box
CN204789647U (en) Two split conductor on -line monitoring device install fixture
JP2010268595A (en) Wind power generator and power cable laying method to wind-power generator
CN105846195A (en) Wiring device with grounding connector for electrical distribution box
RU181891U1 (en) ISOLATED ADAPTER
CN110676607A (en) Parallel groove lapping device capable of live working and operation method thereof
CN105044395A (en) Double-split wire on-line monitoring device installation fixture and installation method
CN103022734A (en) Copper-aluminum wire lap-joint device and method
CN203705487U (en) Cable head insulating and branching device for three-core cables
CN204575689U (en) High-voltage conducting wires condition monitoring device preformed armor rods installs jig
CN202034330U (en) Bypass fuse
CN205385160U (en) Portable electrification of ground wire alarm device that connects
CN201413956Y (en) Guard ring allowing live line connection and disconnection
CN106848638A (en) Water conservancy diversion supports gold utensil and fixed conductor and cantilever conductor attachment structure
CN203218823U (en) Cable terminal grounding fixing device
CN203277670U (en) Wire connecting clamp
CN104810119A (en) Insulator
CN205790502U (en) The electric distribution box termination with grounding connector
CN207502567U (en) Electric energy quality monitoring switching device
CN204516511U (en) A kind of insulator
CN110895323A (en) Portable mutual inductor test rod
CN201956292U (en) Wire connecting terminal for high-voltage alternating-current demarcation circuit breaker
CN106299759A (en) The double T-shaped wire clamp of downlead of a kind of single conductor
CN204065238U (en) A kind of stress_responsive genes instrument
CN205583338U (en) Multifunctional cable clamp

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20151118

Effective date of abandoning: 20171010

AV01 Patent right actively abandoned