CN204787192U - Water heating machine - Google Patents
Water heating machine Download PDFInfo
- Publication number
- CN204787192U CN204787192U CN201520435725.3U CN201520435725U CN204787192U CN 204787192 U CN204787192 U CN 204787192U CN 201520435725 U CN201520435725 U CN 201520435725U CN 204787192 U CN204787192 U CN 204787192U
- Authority
- CN
- China
- Prior art keywords
- water
- water tank
- heating unit
- delivery port
- tank
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 457
- 238000010438 heat treatment Methods 0.000 title claims abstract description 79
- 230000003020 moisturizing effect Effects 0.000 claims abstract description 19
- 238000012544 monitoring process Methods 0.000 claims description 41
- 230000003247 decreasing effect Effects 0.000 claims description 10
- 238000003860 storage Methods 0.000 claims description 3
- 230000000694 effects Effects 0.000 description 3
- 238000009413 insulation Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 239000000203 mixture Substances 0.000 description 3
- 230000001186 cumulative effect Effects 0.000 description 2
- 238000010304 firing Methods 0.000 description 2
- 239000003507 refrigerant Substances 0.000 description 2
- 239000008400 supply water Substances 0.000 description 2
- 238000010521 absorption reaction Methods 0.000 description 1
- 238000003915 air pollution Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 239000000567 combustion gas Substances 0.000 description 1
- 238000002485 combustion reaction Methods 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000446 fuel Substances 0.000 description 1
- JEGUKCSWCFPDGT-UHFFFAOYSA-N h2o hydrate Chemical compound O.O JEGUKCSWCFPDGT-UHFFFAOYSA-N 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 231100000572 poisoning Toxicity 0.000 description 1
- 230000000607 poisoning effect Effects 0.000 description 1
- 239000002912 waste gas Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Heat-Pump Type And Storage Water Heaters (AREA)
Abstract
The utility model discloses a water heating machine, including first water tank, the second water tank, the heating unit, the water inlet that the delivery port of first water tank and second water tank passes through pipeline and heating unit links to each other, the delivery port that the water inlet of first water tank and second water tank passes through pipeline and heating unit links to each other, set up first solenoid valve between the delivery port of first water tank and the water inlet of heating unit, set up the second solenoid valve between the delivery port of second water tank and the water inlet of heating unit, set up the third solenoid valve between the water inlet of first water tank and the delivery port of heating unit, set up the fourth solenoid valve between the water inlet of second water tank and the delivery port of heating unit, water heating machine still includes first moisturizing pipe and second moisturizing pipe, sets up the 5th solenoid valve on first moisturizing is managed, sets up the 6th solenoid valve on the second moisturizing pipe. The utility model discloses a this water heating machine can not go into to lead to the temperature because of the benefit of running water and descend, can not lead to hot water supply untimely because of the moisturizing is untimely to water heating machine's practicality has been improved.
Description
Technical field
The utility model relates to a kind of hot water machine.
Background technology
Existing hot water machine is all made up of main frame and water tank, is heated by the water inside water tank by main frame, then for user, when the water level decreasing in water tank to a certain extent time, the past water tank of needs starts moisturizing, then is heated by main frame.Now, if user needs continuation water, the running water covered and original hot water are mixed with, water temperature inherently declines, higher when just having occurred that water temperature is brought into use thus, then reduce gradually, the temperature of the water finally flowed out by hot water machine moves closer to the water temperature of running water, so, the user demand of user has been badly influenced.
Utility model content
Main purpose of the present utility model, for providing a kind of hot water machine, is intended to solve existing hot water machine when moisturizing, covers the running water come and mixes with original hot water and result in water temperature drop, have influence on the problem of user's use.
For achieving the above object, the utility model provides a kind of hot water machine, described hot water machine comprises the first water tank for water storage and the second water tank, and heating unit, described heating unit has water inlet and delivery port, described first water tank is connected by the water inlet of pipeline with described heating unit with the delivery port of the second water tank, described first water tank is connected by the delivery port of pipeline with described heating unit with the water inlet of the second water tank, the first magnetic valve is provided with between the delivery port of described first water tank and the water inlet of described heating unit, the second magnetic valve is provided with between the delivery port of described second water tank and the water inlet of described heating unit, the 3rd magnetic valve is provided with between the water inlet of described first water tank and the delivery port of described heating unit, the 4th magnetic valve is provided with between the water inlet of described second water tank and the delivery port of described heating unit, described hot water machine also comprises for the first filling pipe to the first water tank moisturizing, described first filling pipe is provided with the 5th magnetic valve, described hot water machine also comprises for the second filling pipe to the second water tank moisturizing, described second filling pipe is provided with the 6th magnetic valve.
Preferably, described first water tank has one for water being discharged the first row water pipe for user, described first row water pipe is provided with one for monitoring the first monitoring meter of the first water tank water flow and volume; Described first filling pipe is provided with first-class gauge, and described first-class gauge is used for controlling according to the monitoring information of described first monitoring meter flow and the volume that running water flows into described first water tank.
Preferably, described second water tank has one for water being discharged the second row water pipe for user, described second row water pipe is provided with one for monitoring the second monitoring meter of the second water tank water flow and volume; Described second filling pipe is provided with second gauge, and described second gauge is used for controlling according to the monitoring information of described second monitoring meter flow and the volume that running water flows into described second water tank.
Preferably, the first flow velocity device comprised for measuring flow rate of water flow is counted in described first monitoring, and for measuring the first timer of current flowing time; The the second flow velocity device comprised for measuring flow rate of water flow is counted in described second monitoring, and for measuring the second timer of current flowing time.
Preferably, be also provided with the first water-level gauge in described first water tank, described first water-level gauge is used for when the water level decreasing in described first water tank is to predeterminated position, and described first water tank stops supplying water turning and supplied water to user by described second water tank; Also be provided with the second water-level gauge in described second water tank, described second water-level gauge is used for when the water level decreasing in described second water tank is to predeterminated position, and described second water tank stops supplying water turning and supplied water to user by described first water tank.
Preferably, the water inlet of described first water tank is arranged at the upper end of described first water tank, and the water inlet of described second water tank is arranged at the upper end of described second water tank; The delivery port of described first water tank is arranged at the lower end of described first water tank, and the delivery port of the second water tank is arranged at the lower end of described second water tank.
Preferably, described heating unit is air-source water heater.
Preferably, the quantity of described heating unit is at least three groups, to meet the different demands of user to the water rate of heat addition.
Hot water machine of the present utility model is by arranging two water tanks, user is when using the hot water in one of them water tank, the running water newly filled into enters another water tank, heating unit is by opening the first magnetic valve and the 3rd magnetic valve, or by opening the second magnetic valve and the 4th magnetic valve to the water heating in another water tank, hot water in two water tanks is used alternatingly, and enables that user is continual uses hot water.This hot water machine can not cause water temperature drop because of filling into of running water, also can not cause hot water supply not in time not in time because of moisturizing, thus improves the practicality of hot water machine.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model hot water machine one embodiment;
The realization of the utility model object, functional characteristics and advantage will in conjunction with the embodiments, are described further with reference to accompanying drawing.
Detailed description of the invention
Should be appreciated that specific embodiment described herein only in order to explain the utility model, and be not used in restriction the utility model.
With reference to Fig. 1, described hot water machine comprises the first water tank 11 and the second water tank 12 for water storage, and heating unit 20, described heating unit 20 has water inlet and delivery port, described first water tank 11 is connected by the water inlet of pipeline with described heating unit 20 with the delivery port of the second water tank 12, described first water tank 11 is connected by the delivery port of pipeline with described heating unit 20 with the water inlet of the second water tank 12, the first magnetic valve 210 is provided with between the delivery port of described first water tank 11 and the water inlet of described heating unit 20, the second magnetic valve 220 is provided with between the delivery port of described second water tank 12 and the water inlet of described heating unit 20, the 3rd magnetic valve 230 is provided with between the water inlet of described first water tank 11 and the delivery port of described heating unit 20, the 4th magnetic valve 240 is provided with between the water inlet of described second water tank 12 and the delivery port of described heating unit 20, described hot water machine also comprises for the first filling pipe 41 to the first water tank 11 moisturizing, described first filling pipe 41 is provided with the 5th magnetic valve 410, described hot water machine also comprises for the second filling pipe 42 to the second water tank 12 moisturizing, and described second filling pipe 42 is provided with the 6th magnetic valve 420.
Particularly, can effectively control to heat unit 20 to the water heating in described first water tank 11 or the second water tank 12 by arranging of four magnetic valves.Concrete, when user uses the hot water in the first water tank 11, close the first magnetic valve 210 and the 3rd magnetic valve 230, open the second magnetic valve 220 and the 4th magnetic valve 240, so, described heating unit 20 is directly communicated with described second water tank 12, and the water in the second water tank 12 flows into heating unit 20, through importing the second water tank 12 by pipeline after heating unit 20 heats.After the hot water in the first water tank 11 uses, the water in the second water tank 12 continues to provide hot water to user; Now, the running water filled into enters the first water tank 11, second magnetic valve 220 and the 4th magnetic valve 240 cuts out, and the first magnetic valve 210 and the 3rd magnetic valve 230 are opened, and heating unit 20 gives the heating of the water in the first water tank 12.Certainly, in the process, when needs inject water to the first water tank 11, described 5th magnetic valve 410 is opened, otherwise closes.When needs are to the second water tank 12 water filling, described 6th magnetic valve 420 is opened, otherwise closes.
Hot water machine of the present utility model is by arranging two water tanks, user is when using the hot water in one of them water tank, the running water newly filled into enters another water tank, heating unit 20 is by opening the first magnetic valve 210 and the 3rd magnetic valve 230, or by opening the second magnetic valve 220 and the 4th magnetic valve 240 to the water heating in another water tank, hot water in two water tanks is used alternatingly, and enables that user is continual uses hot water.This hot water machine can not cause water temperature drop because of filling into of running water, also can not cause hot water supply not in time not in time because of moisturizing, thus improves the practicality of hot water machine.
Further, described first water tank 11 has one for water being discharged the first row water pipe 31 for user, described first row water pipe 31 is provided with one for monitoring the first monitoring meter 311 of the first water tank water flow and volume; Described first filling pipe 41 is provided with first-class gauge 411, and described first-class gauge 411 is for controlling according to the monitoring information of described first monitoring meter 311 flow and the volume that running water flows into described first water tank 11.
With reference to Fig. 1, when user uses the hot water in the first water tank 11, heating unit 20 gives the heating of the water in the second water tank 12, along with the hot water in the first water tank 11 can reduce gradually, until the hot water in the first water tank 11 runs out, continue as user in the second water tank 12 and hot water is provided; While second water tank 12 provides hot water to user, the running water filled into enters the first water tank 11, and heating unit 20 gives again the heating of the water in the first water tank 11; After hot water in second water tank 12 is finished, the first water tank 11 continues as again user and provides hot water, and the running water filled into enters the second water tank 12, and heating unit 20 is to the water heating in the second water tank 12.Circulation like this, this hot water machine provides continual hot water for user.In addition, when user uses the hot water in the first water tank 11, heating unit 20 is to the water heating in the second water tank 12, first monitoring meter 311 runs, after the water in the first water tank 11 uses, water heating in second water tank 12 is complete, change the second water tank 12 into by original first water tank 11 water supply to supply water, the flow of monitoring and volume information are passed to first-class gauge 411 by it by the first monitoring meter 311, such as water consumption 3 tons/hour, then control refill flow by first-class gauge 411, need the supply completing at most 3 tons of water in 1 hour.When moisturizing completes, heating unit 20 also completes the hot water heating work of the first water tank 11.
Further, described second water tank 12 has one for water being discharged the second row water pipe 32 for user, described second row water pipe 32 is provided with one for monitoring the second monitoring meter 321 of the second water tank 12 water flow and volume; Described second filling pipe 42 is provided with second gauge 421, and described second gauge 421 is for controlling according to the monitoring information of described second monitoring meter 321 flow and the volume that running water flows into described second water tank 12.
Particularly, when user uses the hot water in the second water tank 12, heating unit 20 is to the water heating in the first water tank 11, second monitoring meter 321 runs, after the water in the second water tank 12 uses, water heating in first water tank 11 is complete, change the first water tank 11 into by original second water tank 12 water supply to supply water, the flow of monitoring and volume information are passed to second gauge 421 by it by the second monitoring meter 321, such as water consumption 3 tons/hour, then control refill flow by second gauge 421, need the supply completing at most 3 tons of water in 1 hour.When moisturizing completes, heating unit 20 also completes the hot water heating work of the second water tank 12.It should be noted that, described first monitoring meter 311 comprises the first flow velocity device for measuring flow rate of water flow, and for measuring the first timer of current flowing time, described first monitoring meter 311 can draw the current cumulative volume through this first monitoring meter 311 by time and flow velocity, and first-class gauge 411 is according to the time of the first monitoring meter monitoring and cumulative volume regulation and control moisturizing speed.It is identical that described second monitoring meter 321 and first detects the function counted, and the second monitoring meter 321 can make the function of this hot water machine more perfect.
Further, be also provided with the first water-level gauge in described first water tank 11, described first water-level gauge is used for when the water level decreasing in described first water tank 11 is to predeterminated position, and described first water tank 11 stops supplying water turning and supplied water to user by described second water tank 12; Also be provided with the second water-level gauge in described second water tank 12, described second water-level gauge is used for when the water level decreasing in described second water tank 12 is to predeterminated position, and described second water tank 12 stops supplying water turning and supplied water to user by described first water tank 11.
Further, the water inlet of described first water tank 11 is arranged at the upper end of described first water tank 11, and the water inlet of described second water tank 12 is arranged at the upper end of described second water tank 12; The delivery port of described first water tank 11 is arranged at the lower end of described first water tank 11, and the delivery port of the second water tank 12 is arranged at the lower end of described second water tank 12.
Be described for the water inlet that the first water tank 11 is arranged and delivery port.Concrete, water inlet and delivery port can be arranged at the optional position of described first water tank 11, if but the position of water inlet and delivery port is relatively close, hot water after so being heated by heater 20 enters after in the first water tank 11 via water inlet, may also not come anxious mix just to be imported by delivery port with other moisture in the first water tank 11 heat in unit 20, so will cause the hot water in the first water tank 11 and cold water mix uneven, firing rate is slow, and effect is poor.If delivery port is arranged at the lower end of described first water tank 11, on the one hand, be subject to the effect of hydraulic pressure, current easily enter heating unit 20, after water heats by heating unit 20, water imports the first water tank 11 by water inlet, and water inlet is arranged at the upper end of the first water tank 11, like this, hot water just fully can mix with other moisture in the first water tank 11 in the first water tank 11, heat distribution is even, and firing rate is fast, and efficiency is high.Equally, the water inlet of the second water tank 12 is arranged at the upper end of the second water tank 12, the beneficial effect that the delivery port of the second water tank 12 is arranged at the lower end of described second water tank 12 with the first water tank 11 water inlet and delivery port to arrange effect identical, be not repeated herein.
Further, be also provided with the first water-level gauge in described first water tank 11, described first water-level gauge is used for when the water level decreasing in described first water tank 11 is to predeterminated position, and described first water tank 11 stops supplying water turning and supplied water to user by described second water tank 12; Also be provided with the second water-level gauge in described second water tank 12, described second water-level gauge is used for when the water level decreasing in described second water tank 12 is to predeterminated position, and described second water tank 12 stops supplying water turning and supplied water to user by described first water tank 11.
Further, described heating unit 20 is air-source water heater.
Concrete, air-source water heater is that then refrigerant produces high temperature heat after compressor compresses by refrigerant by the heat absorption in air, with this heating of feeding water.Air energy water controller has energy-efficient feature, manufacture identical hot water amount, the cost of air energy water controller consumption costs is only 1/4 of electric heater, 1/3 of combustion gas water controller, utilize efficiency high than electric assisted solar heater, moreover, air-source water heater also overcomes the shortcoming that solar heater dependence sunlight adopts heat and installation inconvenience.In addition, media for heat exchange is passed through in work due to air-source water heater, therefore it does not need electrical heating elements directly to contact with water, avoid the danger of electric heater electrical leakage, also prevent combustion heater likely to explode and poisoning danger, more effectively control the air pollution that fuel heater discharging waste gas causes.In view of above-mentioned advantage, the heater in the present embodiment is air-source water heater.
Further, the quantity of described heating unit 20 is at least three groups, to meet the different demands of user to the water rate of heat addition.
Concrete, suppose that the water in water tank (such as one hour) can be heated to user's design temperature from running water water temperature by separate unit heating unit at the appointed time, if user employed the water yield of cube at previous hour, waterline drops to b or more than b from a, then unit allocation intelligent discrimination can only open a heating unit; If water level decreasing is to below b, c or more than c, then intelligent discrimination opens two heating units; If waterline drops to below c, d or more than d, then intelligent discrimination opens three units, to guarantee that in water tank, water temperature reaches design temperature at the appointed time, is also unlikely to because opening too many heating unit waste electric energy.
Water tank heat preserving works: if user is in water utilizing process, there will be desultory water in several hours, water consumption is less, and meet the condition switching another one water tank not enough, within these hours, the heat of water tank may scatter and disappear; In several hours, the moisturizing of another water tank and heating work complete, and the heat of water tank also has lost possibility, and now need to open unit and carry out heating and thermal insulation to water tank, water tank temperature first being reached to insulation design temperature heats.Concrete mode is closeall water compensating valve, only open in requisition for heating and thermal insulation water tank entering water electromagnetic valve and go out water solenoid valve, another water tank is for user's water.
The foregoing is only preferred embodiment of the present utility model; not thereby the scope of the claims of the present utility model is limited; every utilize the utility model description and accompanying drawing content to do equivalent structure or equivalent flow process conversion; or be directly or indirectly used in other relevant technical fields, be all in like manner included in scope of patent protection of the present utility model.
Claims (8)
1. a hot water machine, it is characterized in that, described hot water machine comprises the first water tank for water storage and the second water tank, and heating unit, described heating unit has water inlet and delivery port, described first water tank is connected by the water inlet of pipeline with described heating unit with the delivery port of the second water tank, described first water tank is connected by the delivery port of pipeline with described heating unit with the water inlet of the second water tank, the first magnetic valve is provided with between the delivery port of described first water tank and the water inlet of described heating unit, the second magnetic valve is provided with between the delivery port of described second water tank and the water inlet of described heating unit, the 3rd magnetic valve is provided with between the water inlet of described first water tank and the delivery port of described heating unit, the 4th magnetic valve is provided with between the water inlet of described second water tank and the delivery port of described heating unit, described hot water machine also comprises for the first filling pipe to the first water tank moisturizing, described first filling pipe is provided with the 5th magnetic valve, described hot water machine also comprises for the second filling pipe to the second water tank moisturizing, described second filling pipe is provided with the 6th magnetic valve.
2. hot water machine as claimed in claim 1, is characterized in that, described first water tank has one for water being discharged the first row water pipe for user, described first row water pipe is provided with one for monitoring the first monitoring meter of the first water tank water flow and volume; Described first filling pipe is provided with first-class gauge, and described first-class gauge is used for controlling according to the monitoring information of described first monitoring meter flow and the volume that running water flows into described first water tank.
3. hot water machine as claimed in claim 2, is characterized in that, described second water tank has one for water being discharged the second row water pipe for user, described second row water pipe is provided with one for monitoring the second monitoring meter of the second water tank water flow and volume; Described second filling pipe is provided with second gauge, and described second gauge is used for controlling according to the monitoring information of described second monitoring meter flow and the volume that running water flows into described second water tank.
4. hot water machine as claimed in claim 3, is characterized in that, the first flow velocity device comprised for measuring flow rate of water flow is counted in described first monitoring, and for measuring the first timer of current flowing time; The the second flow velocity device comprised for measuring flow rate of water flow is counted in described second monitoring, and for measuring the second timer of current flowing time.
5. hot water machine as claimed in claim 1, it is characterized in that, also be provided with the first water-level gauge in described first water tank, described first water-level gauge is used for when the water level decreasing in described first water tank is to predeterminated position, and described first water tank stops supplying water turning and supplied water to user by described second water tank; Also be provided with the second water-level gauge in described second water tank, described second water-level gauge is used for when the water level decreasing in described second water tank is to predeterminated position, and described second water tank stops supplying water turning and supplied water to user by described first water tank.
6. hot water machine as claimed in claim 1, it is characterized in that, the water inlet of described first water tank is arranged at the upper end of described first water tank, and the water inlet of described second water tank is arranged at the upper end of described second water tank; The delivery port of described first water tank is arranged at the lower end of described first water tank, and the delivery port of the second water tank is arranged at the lower end of described second water tank.
7. hot water machine as claimed in claim 1, it is characterized in that, described heating unit is air-source water heater.
8. hot water machine as claimed in claim 1, it is characterized in that, the quantity of described heating unit is at least three groups.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520435725.3U CN204787192U (en) | 2015-06-23 | 2015-06-23 | Water heating machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520435725.3U CN204787192U (en) | 2015-06-23 | 2015-06-23 | Water heating machine |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204787192U true CN204787192U (en) | 2015-11-18 |
Family
ID=54527231
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520435725.3U Expired - Fee Related CN204787192U (en) | 2015-06-23 | 2015-06-23 | Water heating machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204787192U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105823203A (en) * | 2015-11-25 | 2016-08-03 | 广州帝胜智能科技有限公司 | Split type quick-heating multifunctional water heater |
CN106016438A (en) * | 2016-05-24 | 2016-10-12 | 郭毅义 | Branch-control household water system |
CN106996644A (en) * | 2017-04-17 | 2017-08-01 | 珠海格力电器股份有限公司 | Air energy water heater and control method thereof |
-
2015
- 2015-06-23 CN CN201520435725.3U patent/CN204787192U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105823203A (en) * | 2015-11-25 | 2016-08-03 | 广州帝胜智能科技有限公司 | Split type quick-heating multifunctional water heater |
CN106016438A (en) * | 2016-05-24 | 2016-10-12 | 郭毅义 | Branch-control household water system |
CN106016438B (en) * | 2016-05-24 | 2020-01-03 | 江苏理想空间装饰工程股份有限公司 | Household water system with separate control |
CN106996644A (en) * | 2017-04-17 | 2017-08-01 | 珠海格力电器股份有限公司 | Air energy water heater and control method thereof |
CN106996644B (en) * | 2017-04-17 | 2023-12-05 | 珠海格力电器股份有限公司 | Air energy water heater and control method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102109220B (en) | Instant-heating air source water heater and control method thereof | |
CN107039667A (en) | The whistle control system and control method of fuel cell pack electricity generation system | |
CN201811414U (en) | Energy-saving electric water heater | |
CN204787192U (en) | Water heating machine | |
CN205066178U (en) | Utilize combined system of solar energy collection system linking water resource heat pump heat recovery water supply | |
CN201706714U (en) | Hot water supply device for producing liquid cement grinding aid | |
CN208983651U (en) | A kind of solar energy heating water system | |
CN200982758Y (en) | Full-automatic intelligent heat-storage cabin of solar energy water heater | |
CN202303598U (en) | Solar energy heat pump floor heating device | |
CN202630225U (en) | Solar and heat-pump combined hot water system | |
CN201606964U (en) | Residual water water conservation control device in gas solar pipeline | |
CN203131931U (en) | Heating system combining solar energy and off-peak electricity | |
CN201289151Y (en) | Hot water heating apparatus by utilizing solar | |
CN211146923U (en) | Sustainable high-capacity water heater | |
CN209978160U (en) | Phase-change heat storage based floor heating and hot water supply system | |
CN208859705U (en) | A kind of integral type heating energy-storage system | |
CN206300360U (en) | A kind of domestic solar-energy water heater system | |
CN202350160U (en) | Bathroom centralized heating equipment | |
CN201522032U (en) | Solar hot water supply energy-saving thermostatic device | |
CN201476357U (en) | Integrated system composed of solar energy heater and electric heater and energy saving comprehensive valve | |
CN201637070U (en) | Electric control outlet water heater | |
CN205037566U (en) | Energy -saving air energy water heater | |
CN201764655U (en) | Self-controlled non-pressure water heater | |
CN204202225U (en) | The solar water heating system combined with Instant heating type air source heat pump | |
CN109654586A (en) | A kind of integral type heating energy-storage system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20151118 Termination date: 20170623 |
|
CF01 | Termination of patent right due to non-payment of annual fee |