CN204780996U - Genuine joint design of prefabricated pin -connected panel - Google Patents
Genuine joint design of prefabricated pin -connected panel Download PDFInfo
- Publication number
- CN204780996U CN204780996U CN201520448179.7U CN201520448179U CN204780996U CN 204780996 U CN204780996 U CN 204780996U CN 201520448179 U CN201520448179 U CN 201520448179U CN 204780996 U CN204780996 U CN 204780996U
- Authority
- CN
- China
- Prior art keywords
- joint
- prefabricated
- precast
- joint design
- wall unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 210000003205 muscle Anatomy 0.000 claims description 15
- 229910000831 Steel Inorganic materials 0.000 claims description 8
- 239000010959 steel Substances 0.000 claims description 8
- 230000003014 reinforcing effect Effects 0.000 claims description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 6
- 238000010276 construction Methods 0.000 description 11
- 230000005540 biological transmission Effects 0.000 description 5
- 230000000694 effects Effects 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000011065 in-situ storage Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
The utility model relates to a genuine joint design of prefabricated pin -connected panel belongs to municipal works technical field for it passes power and waterproof problem to solve the prefabricated hoop of assembling genuine structure. This genuine joint design of prefabricated pin -connected panel is the tenon structure, the genuine concatenation through joint design hoop in proper order by a plurality of prefabricated subassemblies forms, prefabricated subassembly is including prefabricated midboard unit, prefabricated side wall unit, prefabricated genuine roof structure and prefabricated genuine bottom plate structure, the joint design is including joint no. 1 and joint no. 2, through connecting a fixed connection between the adjacent prefabricated midboard unit, through connecting two fixed connection between the adjacent prefabricated side wall unit, the middle part of joint no. 2 is equipped with the stagnant water component.
Description
Technical field
The utility model belongs to municipal engineering technical field, particularly a kind of joint design of precast splice type tunnel.
Background technology
China's underpass adopts the construction method of integral cast-in-situ usually, and preceding method exists construction period longer, construction quality to be difficult to ensure, pollute a series of problems such as urban environment to a certain extent.In order to address these problems, underpass adopts the construction method of precast assembly imperative.But owing to being subject to the restriction of the factors such as transport, lifting, genuine precast assembly structure needs to arrange joint usually.Therefore, how providing a kind of easy construction, effectively can solve the joint design in the precast assembly tunnel of reasonable power transmission and waterproof, is the technical problem that those skilled in the art need solution badly.
Utility model content
The purpose of this utility model is the joint design providing a kind of precast splice type tunnel, the waterproof genuine with satisfied employing precast assembly method construction and force request.
For solving the problems of the technologies described above, the technical solution of the utility model is as follows:
A kind of joint design of precast splice type tunnel, described joint design is tenon structure, described tunnel is spliced by described joint design successively hoop by some precast segments, described precast segment comprises prefabricated middle wall unit, prefabricated side wall unit, Precast Underpass top board structure and Precast Underpass base arrangement, described joint design comprises joint one and joint two, be fixedly connected with by described joint one between adjacent described prefabricated middle wall unit, be fixedly connected with by described joint two between adjacent described prefabricated side wall unit, the middle part of described joint two is also provided with waterstop member.
Further, described tenon structure is made by steel concrete.
Further, be respectively equipped with groove in the middle part of the two ends of described joint one, the middle part of the butt end of corresponding described prefabricated middle wall unit is provided with the protuberance corresponding with described groove.
Further, described waterstop member is steel limit waterstop.
Further, the main muscle of the structure stress of described precast segment one and structure stress main muscle two interlaced arrangement.
Further, the main muscle one of the structure stress of described precast segment is provided with reinforcing bar connector.
Compared with prior art, the technique effect that the utility model is useful is: in the joint design in the precast splice type tunnel that the utility model embodiment provides, joint design is tenon structure, tunnel is spliced by joint design successively hoop by some precast segments, precast segment comprises prefabricated middle wall unit, prefabricated side wall unit, Precast Underpass top board structure and Precast Underpass base arrangement, joint design comprises joint one and joint two, be fixedly connected with by joint one between adjacent prefabricated middle wall unit, be fixedly connected with by joint two between adjacent prefabricated side wall unit, the middle part of joint two is provided with waterstop member.By arranging tenon structure as joint design, the shear resistance of adjacent precast segment interface can be strengthened, thus ensure the hoop power transmission requirement of precast assembly underpass.In addition, assembled when meeting the prefabricated side wall unit in native face, waterstop member is set at the middle part of its joint two, can prevents the gap of underground water between adjacent precast segment from infiltrating genuine, thus solve the waterproof problem of contiguous prefabricated assembly interface in precast assembly underpass.
Accompanying drawing explanation
Fig. 1 is the precast splice type underpass schematic cross-sectional view of the utility model one embodiment;
The partial enlarged drawing in A portion in Fig. 2 Fig. 1;
Fig. 3 is the partial enlarged drawing in B portion in Fig. 1;
Fig. 4 is the C-C sectional drawing of Fig. 2;
Fig. 5 is the D-D sectional drawing of Fig. 3.
In figure:
The prefabricated middle wall unit of 1-; The prefabricated side wall unit of 2-; 3-joint one; 4-joint two; 5-waterstop member; The main muscle one of 6-structure stress; The main muscle two of 7-structure stress; 8-reinforcing bar connector; 9-expansive concrete.
Detailed description of the invention
Be described in further detail below in conjunction with the joint design of the drawings and specific embodiments to the precast splice type tunnel that the utility model proposes.According to the following describes and claims, advantage of the present utility model and feature will be clearer.It should be noted that, accompanying drawing all adopts the form that simplifies very much and all uses non-ratio accurately, only in order to object that is convenient, aid illustration the utility model embodiment lucidly.For sake of convenience, hereinafter described " on ", D score is consistent with the upper and lower direction of accompanying drawing, but this can not become the restriction of technical solutions of the utility model.
The utility model provides a kind of joint design of precast assembly tunnel, for solving hoop power transmission and the waterproof problem of precast assembly underpass.
The joint design in precast splice type tunnel of the present utility model is described in detail below in conjunction with Fig. 1 to Fig. 5.
Embodiment one
As shown in Figures 1 to 5, the joint design in precast splice type tunnel, joint design is tenon structure, tunnel is spliced by joint design successively hoop by some precast segments, precast segment comprises prefabricated middle wall unit 1, prefabricated side wall unit 2, Precast Underpass top board structure and Precast Underpass base arrangement, joint design comprises joint 1 and joint 24, connected by joint 1 between adjacent prefabricated middle wall unit 1, connected by joint 24 between adjacent prefabricated side wall unit 2, the middle part of joint 24 is provided with waterstop member 5.In the construction of precast assembly tunnel, i.e. prefabricated middle wall unit 1 and the setting parallel to each other of prefabricated side wall unit 2, Precast Underpass top board structure and Precast Underpass base arrangement parallel to each other, Precast Underpass top board structure is arranged perpendicular to prefabricated middle wall unit 1 and prefabricated side wall unit 2 respectively, Precast Underpass top board structure, prefabricated middle wall unit 1, Precast Underpass base arrangement and prefabricated side wall unit 2 head and the tail are in turn connected to form rectangular frame structure, thus form described underpass.At the scene during assembling construction, between adjacent precast segment, all leave gap between namely adjacent prefabricated middle wall unit 1 or between adjacent prefabricated side wall unit 2, the size in this gap and the size of joint design match.This joint design is tenon structure.By arranging tenon structure as joint design, the shear resistance of adjacent precast segment interface can be strengthened, thus ensure the hoop power transmission requirement of precast assembly underpass.In addition, assembled when meeting the prefabricated side wall unit 2 in native face, waterstop member 5 is set at the middle part of its joint 24, can prevents the gap of underground water between adjacent precast segment from infiltrating genuine, thus solve the waterproof problem of contiguous prefabricated assembly interface in precast assembly underpass.
Specifically, when produce in factory precast segment and joint design, the making material of precast segment is identical with the making material of tenon structure, is made by steel concrete.Be respectively equipped with groove in the middle part of the two ends of joint 1, the middle part of the butt end of corresponding prefabricated middle wall unit 1 is provided with the protuberance corresponding with groove.The structure of joint 24 and the structure difference of joint 1 are: the middle part of joint 24 is provided with waterstop member 5.This is because the prefabricated side wall unit 2 connected by joint 24 is positioned at meets native side, and it requires higher to water proof anti-seepage.Certainly, consider cost and convenience for construction, water-stopping structure 5 can be steel limit waterstop.
Accordingly, joint 1 and prefabricated middle wall unit 1, joint 24 and prefabricated side wall unit 2 build respectively be integrated for subsequent use.
Continue with reference to figure 2 and Fig. 4, certainly, in order to make the stressed integrality at interface place between adjacent precast segment, give full play to the effect of effective transmitting force of joint design, the main muscle of structure stress 1 (end is containing reinforcing bar connector 8) and structure stress main muscle 27 interlaced arrangement of precast segment.
Please continue to refer to Fig. 1 to Fig. 5, describe the construction method of the genuine joint design of precast splice type of the present embodiment in detail.The construction method of precast splice type joint design, comprises the following steps:
S001: according to job specfication, assembledly in genuine foundation ditch completes precast segment planning to build;
S002: be fixedly installed joint 1 in the butt end of adjacent prefabricated middle wall unit 1 respectively, is fixedly installed joint 24 in the butt end of adjacent prefabricated side wall unit 2, and in the middle part of joint 24 is arranged buried steel limit waterstop 5;
S003: build expansive concrete 9 in the gap between adjacent precast segment, expansive concrete 9 wraps joint design, makes adjacent precast segment form integrative-structure.
Specifically, the joint design interface that can prevent underground water between adjacent precast segment by buried steel limit waterstop 5 in arranging in the joint 24 of prefabricated side wall unit 2 of meeting native face infiltrates in tunnel.Expansive concrete 9 is built on the joint design surface of the precast segment spliced, expansive concrete 9 is made to wrap joint design, fill up the gap between adjacent precast segment, ensure that combining closely between joint design and precast segment, adjacent precast segment is made to form integrative-structure, thus avoid the space that joint design shrinks formation, thus define complete stressed and water-proof system.
Specifically, the main muscle of structure stress 1 of the precast segment in step one and structure stress main muscle 27 interlaced arrangement.The i.e. main muscle one, two (6,7) of the structure stress of prefabricated middle wall unit 1 and prefabricated side wall unit 2 all interlaced arrangement, thus ensure that the effective force effect of joint design.Certainly, stagger the length requirement that mechanical connecting joint that length need meet code requirement staggers mutually in the termination of the main muscle of structure stress 1 and the main muscle 27 of structure stress.
In sum, in the joint design in the precast splice type tunnel that the utility model provides, by arranging tenon structure as joint design, the shear resistance of adjacent precast segment interface can be strengthened, thus ensure the hoop power transmission requirement of precast assembly underpass.In addition, assembled when meeting the prefabricated side wall unit in native face, waterstop member is set at the middle part of its joint two, can prevents the gap of underground water between adjacent precast segment from infiltrating genuine, thus solve the waterproof problem of contiguous prefabricated assembly interface in precast assembly underpass.And, expansive concrete is built on the joint design surface of the precast segment spliced, expansive concrete is made to wrap joint design, fill up the gap between adjacent precast segment, ensure that combining closely between joint design and precast segment, make adjacent precast segment form integrative-structure, thus avoid the space that joint design shrinks formation, thus define complete stressed and water-proof system.
Foregoing description is only the description to the utility model preferred embodiment; any restriction not to the utility model scope; any change that the those of ordinary skill in the utility model field does according to above-mentioned disclosure, modification, all belong to the protection domain of claims.
Claims (6)
1. the joint design in a precast splice type tunnel, it is characterized in that, described joint design is tenon structure, described tunnel is spliced by described joint design successively hoop by some precast segments, described precast segment comprises prefabricated middle wall unit, prefabricated side wall unit, Precast Underpass top board structure and Precast Underpass base arrangement, described joint design comprises joint one and joint two, be fixedly connected with by described joint one between adjacent described prefabricated middle wall unit, be fixedly connected with by described joint two between adjacent described prefabricated side wall unit, the middle part of described joint two is also provided with waterstop member.
2. the joint design in precast splice type tunnel as claimed in claim 1, it is characterized in that, described tenon structure is made by steel concrete.
3. the joint design in precast splice type tunnel as claimed in claim 1 or 2, is characterized in that, be respectively equipped with groove in the middle part of the two ends of described joint one, and the middle part of the butt end of corresponding described prefabricated middle wall unit is provided with the protuberance corresponding with described groove.
4. the joint design in precast splice type tunnel as claimed in claim 3, it is characterized in that, described waterstop member is steel limit waterstop.
5. the joint design in precast splice type tunnel as claimed in claim 4, is characterized in that, the main muscle of structure stress one of described precast segment and structure stress main muscle two interlaced arrangement.
6. the joint design in precast splice type tunnel as claimed in claim 5, it is characterized in that, the main muscle one of structure stress of described precast segment is provided with reinforcing bar connector.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520448179.7U CN204780996U (en) | 2015-06-26 | 2015-06-26 | Genuine joint design of prefabricated pin -connected panel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520448179.7U CN204780996U (en) | 2015-06-26 | 2015-06-26 | Genuine joint design of prefabricated pin -connected panel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204780996U true CN204780996U (en) | 2015-11-18 |
Family
ID=54521079
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520448179.7U Expired - Fee Related CN204780996U (en) | 2015-06-26 | 2015-06-26 | Genuine joint design of prefabricated pin -connected panel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204780996U (en) |
-
2015
- 2015-06-26 CN CN201520448179.7U patent/CN204780996U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105908862B (en) | A kind of production method of masonry shell in 3D printing reinforced masonry shear wall | |
CN105113535A (en) | Prefabricated assembled tunnel joint structure and construction method thereof | |
CN105256838B (en) | Pipe gallery prefabricated members and prefabricated comprehensive pipe gallery | |
CN205857448U (en) | A kind of assembly concrete shear wall structure | |
CN101672007A (en) | Constructing method of precast pier footing for bridge | |
CN205329526U (en) | Pier is assembled to precast concrete | |
CN104153493A (en) | Concrete shear wall structure based on 3D printing and construction method of concrete shear wall structure | |
CN103883482A (en) | Precast concrete shell ring, manufacturing method thereof and fan tower barrel | |
CN104047225A (en) | Segment prefabrication and assembly beam structure with steel sleeve elastic shear force tenons | |
CN203891211U (en) | Mortise grouting type connector of prefabricated structure | |
CN102304953A (en) | Sandwich heat insulation reinforced concrete shear wall and construction method thereof | |
CN203684458U (en) | Flexibly-connected concrete prefabricated panel structure | |
CN206157916U (en) | A style of calligraphy connection structure | |
CN203559411U (en) | H-shaped support pile connecting structure | |
CN203145249U (en) | Integrally assembled composite partition wall | |
CN103266692B (en) | Top and bottom mounting structure for composite partition | |
CN204626235U (en) | A kind of concatenation unit of frame bridge | |
CN204780996U (en) | Genuine joint design of prefabricated pin -connected panel | |
CN102587329B (en) | Arched combined faceplate for earth-rock dam and construction method thereof | |
CN105227107A (en) | Solar photovoltaic assembly bridging type splicing hermetically-sealed construction | |
CN203960729U (en) | A kind of precast segment spliced girder body structure that steel sleeve elasticity shear tenon is set | |
CN201099578Y (en) | Combination type counterweight body | |
CN104153460A (en) | Precast concrete structural member and method for building construction horizontal connection between structural members | |
CN205444565U (en) | Wallboard connected node | |
CN113152669A (en) | Assembly type reinforced concrete column and column splicing structure and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20151118 |