CN204690785U - Long span section core in open-cut - Google Patents

Long span section core in open-cut Download PDF

Info

Publication number
CN204690785U
CN204690785U CN201520322746.4U CN201520322746U CN204690785U CN 204690785 U CN204690785 U CN 204690785U CN 201520322746 U CN201520322746 U CN 201520322746U CN 204690785 U CN204690785 U CN 204690785U
Authority
CN
China
Prior art keywords
core
open
annulus
cut
long span
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520322746.4U
Other languages
Chinese (zh)
Inventor
夏映贤
金宝
王玉峰
郑继清
李树伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Urban Construction Group Co Ltd
Original Assignee
Jinan Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Urban Construction Group Co Ltd filed Critical Jinan Urban Construction Group Co Ltd
Priority to CN201520322746.4U priority Critical patent/CN204690785U/en
Application granted granted Critical
Publication of CN204690785U publication Critical patent/CN204690785U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model belongs to open-cut technical field, particularly Long span section core in a kind of open-cut.Long span section core in this open-cut, is characterized in that: comprise some parallel annulus, and described annulus connecting reinforcement connects, and annulus surrounding is evenly provided with bamboo plate, and bamboo plate outsourcing is provided with tin plate, two ends bamboo slab rubber 5 shutoff.The beneficial effects of the utility model are: not only cost comparatively aerated core and double-wall corrugated pipe core low, and conveniently can install fixing and ensure the intensity of core, work progress core mould is reliable and stable, ensure that the monolithic stability of constructing structure and on-the-spot safety.

Description

Long span section core in open-cut
(1) technical field
The utility model belongs to open-cut technical field, particularly Long span section core in a kind of open-cut.
(2) background technology
At present, known Long span concrete cross section, for reducing deadweight, ensures intensity, the safety and stability of structure, adopts core process in the structure.Because the open cut tunnel had belongs to box culvert structure, as adopted aerated core construction, after construction, core can not take out the increase causing construction cost.
(3) summary of the invention
The utility model, in order to make up the deficiencies in the prior art, provides Long span section core in the open-cut that a kind of cost is low, installation convenient fixing, intensity are high.
The utility model is achieved by the following technical solution:
Long span section core in a kind of open-cut, it is characterized in that: comprise some parallel annulus, described annulus connecting reinforcement connects, and annulus surrounding is evenly provided with bamboo plate, and bamboo plate outsourcing is provided with tin plate, two ends bamboo slab rubber shutoff.
The spacing of described annulus is 1m.
Described connecting reinforcement is 3, is evenly arranged at the surrounding of annulus.
The screw-thread steel of described annulus Ф 12 is made, and the screw-thread steel of connecting reinforcement Ф 10 is made.
The beneficial effects of the utility model are: not only cost comparatively aerated core and double-wall corrugated pipe core low, and conveniently can install fixing and ensure the intensity of core, work progress core mould is reliable and stable, ensure that the monolithic stability of constructing structure and on-the-spot safety.
(4) accompanying drawing explanation
Below in conjunction with accompanying drawing, the utility model is further described.
Accompanying drawing 1 is main TV structure schematic diagram of the present utility model;
Accompanying drawing 2 is plan structure schematic diagram of the present utility model;
In figure, 1 annulus, 2 connecting reinforcements, 3 bamboo plates, 4 tin plates, 5 bamboo slab rubber.
(5) detailed description of the invention
Accompanying drawing is a kind of specific embodiment of the present utility model.This embodiment comprises some parallel annulus 1, and annulus 1 connecting reinforcement 2 connects, and annulus 1 surrounding is evenly provided with bamboo plate 3, and bamboo plate 3 outsourcing is provided with tin plate 4, two ends bamboo slab rubber 5 shutoff.The spacing of annulus 1 is 1m.Connecting reinforcement 2 is 3, is evenly arranged at the surrounding of annulus 1.Annulus 1 screw-thread steel of Ф 12 is made, and connecting reinforcement 2 screw-thread steel of Ф 10 is made.
Adopt Long span section core in open-cut of the present utility model, first the screw-thread steel of Ф 12 is adopted to be made into the annulus 1 of required core size several, adopting the screw-thread steel of Ф 10 these annulus 1 to be coupled together composition afterwards, cylindrical (pitch arrangement of annulus 1 is 1m, the quantity of Ф 10 connecting reinforcement 2 is 3, a ring), cylindrical complete after again bamboo plate 3 is uniformly clouded in cylindrical surrounding, finally adopt tin plate 4 wrap up shaping.For ensureing core firm, not off normal in work progress, adopt the mode of reinforcement welding by core and main body reinforcing bar fixed.Fixation is: spacing 0.5 meter arranges that a reinforced steel bar ring is firm with main body reinforcement welding after locking core.In work progress, the concreting time-division four layers builds, and carries out observation to the high level of core and plan-position constantly and control.First floor concreting did not have 10cm at the bottom of core, after 1 ~ 1.5 hour after-pouring second layer concrete, second layer concreting thickness is 30cm, after 1 ~ 1.5 hour after-pouring third layer concrete, third layer concreting thickness is 30cm, after 1 ~ 1.5 hour after-pouring the 4th layer concrete, it was 30cm that the 4th layer concrete builds thickness.Face maintenance is received in press polish afterwards.Every layer concrete vibrates when building fully, and vibrating spear must not contact with core the breakage preventing core.
Adopt Long span section core in open-cut of the present utility model, cost obviously reduces: cost-per-meter valency is only 180 yuan, and to adopt double-wall corrugated pipe to do core cost-per-meter valency be 380 yuan, adopts aerated core price cost every meter to be 300 yuan.

Claims (4)

1. Long span section core in an open-cut, it is characterized in that: comprise some parallel annulus (1), described annulus (1) connecting reinforcement (2) connects, annulus (1) surrounding is evenly provided with bamboo plate (3), bamboo plate (3) outsourcing is provided with tin plate (4), two ends bamboo slab rubber (5) shutoff.
2. Long span section core in a kind of open-cut according to claim 1, is characterized in that: the spacing of described annulus (1) is 1m.
3. Long span section core in a kind of open-cut according to claim 1, is characterized in that: described connecting reinforcement (2) is 3, is evenly arranged at the surrounding of annulus (1).
4. Long span section core in a kind of open-cut according to claim 1, it is characterized in that: described annulus (1) is made with the screw-thread steel of Ф 12, connecting reinforcement (2) is made with the screw-thread steel of Ф 10.
CN201520322746.4U 2015-05-19 2015-05-19 Long span section core in open-cut Active CN204690785U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520322746.4U CN204690785U (en) 2015-05-19 2015-05-19 Long span section core in open-cut

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520322746.4U CN204690785U (en) 2015-05-19 2015-05-19 Long span section core in open-cut

Publications (1)

Publication Number Publication Date
CN204690785U true CN204690785U (en) 2015-10-07

Family

ID=54231094

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520322746.4U Active CN204690785U (en) 2015-05-19 2015-05-19 Long span section core in open-cut

Country Status (1)

Country Link
CN (1) CN204690785U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895109A (en) * 2015-05-19 2015-09-09 济南城建集团有限公司 Long-span section mandrel in open cut construction and treatment method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895109A (en) * 2015-05-19 2015-09-09 济南城建集团有限公司 Long-span section mandrel in open cut construction and treatment method thereof

Similar Documents

Publication Publication Date Title
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN202718022U (en) Fabricated type prestressed concrete pavement
CN105019573A (en) Prefabricated external wall template structure system with heat insulation function, and construction method thereof
CN204645664U (en) A kind of construction work reinforcing bar location adjustable distance telescopic type instrument
CN104060760A (en) Layered construction method for oversized concrete beam of structural transfer floor of high-rise building
CN204690785U (en) Long span section core in open-cut
CN204456159U (en) A kind of steel kind design concrete anchor location structure
CN204456428U (en) A kind of entirety being installed on composite wallboard is waftd window
CN204551172U (en) A kind of prefabricated road surface of assembled steel reinforced concrete hollow
CN202658765U (en) Keel framework concrete anti-crack filling wall
CN201176551Y (en) Precast slab for roads
CN210002280U (en) road and bridge crack reinforcing structure
CN201400959Y (en) Silo concrete protecting layer locating piece in slipform construction
CN202882227U (en) Pre-embedded zigzag concrete horse-shaped stool
CN105350718A (en) Reinforcement permanency beam formwork and manufacturing method for concrete structural member with shearing resistance
CN202299421U (en) Inner support for controlling width of concrete beam or wallboard template
CN104895109A (en) Long-span section mandrel in open cut construction and treatment method thereof
CN202689278U (en) Superimposed hollow slab
CN203924694U (en) Biogas charging and discharging pond die special for concrete
CN104908150B (en) A kind of piping shaft making template and the method based on factorial praluction piping shaft
CN203080429U (en) Pier stud splicing construction structure for jacking of bridge broken column
CN201762890U (en) Positioning strip for steel bar and template of reinforced concrete wall
CN202644563U (en) Installation device for embedded foundation bolt of small facility
CN207277367U (en) Reinforcement of retaining wall structure
CN206707086U (en) Truss plate cast-in-situ reinforced concrete hollow superimposed sheet

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant