CN204608825U - A kind of three-chip type stone bolt locating rack - Google Patents
A kind of three-chip type stone bolt locating rack Download PDFInfo
- Publication number
- CN204608825U CN204608825U CN201520313252.XU CN201520313252U CN204608825U CN 204608825 U CN204608825 U CN 204608825U CN 201520313252 U CN201520313252 U CN 201520313252U CN 204608825 U CN204608825 U CN 204608825U
- Authority
- CN
- China
- Prior art keywords
- positioning frame
- anchor bolt
- arc positioning
- bolt positioning
- piece
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本实用新型公开了一种三片式地脚螺栓定位架,属于地脚螺栓埋设技术领域。本实用新型的一种三片式地脚螺栓定位架,包括三片圆弧定位架,圆弧定位架两两连接组成圆环结构,圆弧定位架上设置有若干个螺栓定位孔,圆弧定位架设置有弦向支撑柱,圆弧定位架和弦向支撑柱之间设置有若干个连接杆。本实用新型能够方便快捷的将三片圆弧定位架组装成地脚螺栓定位架,单片式的圆弧定位架占比面积小,便于地脚螺栓定位架的安装和运输,降低施工成本的同时减少运输过程中的损坏,而且结构简单,使用方便,施工成本低;另一方面,本实用新型提出的同时也提供了一种使地脚螺栓定位架更稳定的固定方式。
The utility model discloses a three-piece anchor bolt positioning frame, which belongs to the technical field of anchor bolt embedding. A three-piece anchor bolt positioning frame of the utility model includes three circular arc positioning frames, and the circular arc positioning frames are connected in pairs to form a ring structure. Several bolt positioning holes are arranged on the circular arc positioning frame. The positioning frame is provided with a chord-direction support column, and several connecting rods are arranged between the arc positioning frame and the chord-direction support column. The utility model can conveniently and quickly assemble three arc positioning frames into an anchor bolt positioning frame. The single-piece arc positioning frame occupies a small area, which is convenient for installation and transportation of the anchor bolt positioning frame and reduces construction costs. At the same time, the damage during transportation is reduced, and the structure is simple, convenient to use, and the construction cost is low; on the other hand, the utility model also provides a fixing method for making the anchor bolt positioning frame more stable.
Description
技术领域technical field
本实用新型涉及地脚螺栓埋设技术领域,更具体地说,涉及一种三片式地脚螺栓定位架。The utility model relates to the technical field of anchor bolt embedding, in particular to a three-piece anchor bolt positioning frame.
背景技术Background technique
在工业建筑工程施工中,常常会遇到含有地脚螺栓的圆形设备基础,而地脚螺栓的形状、质量,决定了其定位支撑效果。在施工过程中,基础中的地脚螺栓在混凝土浇筑前首先要制作地脚螺栓定位架,然后利用地脚螺栓定位架安装固定好地脚螺栓,验收合格后才能浇筑混凝土,当圆基础尺寸较大时,其地脚螺栓定位架的尺寸就越大,此时,在施工中就存在以下问题:第一,由于地脚螺栓定位架尺寸大,不仅不利于运输,还会在运输过程中对地脚螺栓定位架造成损伤而导致地脚螺栓形变;第二,地脚螺栓定位架大而重,往往需要较多的人力或者吊车配合安装,这些都大大增加了施工成本,所以这就需要一种既能降低施工成本又能保证螺栓定位架质量且方便运输的地脚螺栓定位架。In the construction of industrial construction projects, circular equipment foundations with anchor bolts are often encountered, and the shape and quality of the anchor bolts determine their positioning and support effects. During the construction process, the anchor bolts in the foundation should first be made with anchor bolt positioning frames before concrete pouring, and then the anchor bolts should be installed and fixed by using the anchor bolt positioning frames. When it is large, the size of the anchor bolt positioning frame is larger. At this time, there are the following problems in construction: First, due to the large size of the anchor bolt positioning frame, it is not only unfavorable for transportation, but also damages the The anchor bolt positioning frame causes damage and causes the deformation of the anchor bolts; second, the anchor bolt positioning frame is large and heavy, and often requires more manpower or cranes to cooperate with the installation, which greatly increases the construction cost, so this requires a The invention provides an anchor bolt positioning frame which can not only reduce the construction cost but also ensure the quality of the bolt positioning frame and is convenient for transportation.
通过专利检索,现有技术中已有相关技术方案公开。如,申请号200720055272.7,申请日为2007年8月8日,发明名称为:一种地脚螺栓架,该申请案由至少两条地脚螺栓和铁板或箍筋组成,铁板或箍筋将地脚螺栓以一定形状组合固定,该申请案虽然可以起到固定地脚螺栓的作用,但是大面积的制作不便于运输,而且制作需要较多的施工材料,安装需要较多的人力,施工成本高。Through patent retrieval, relevant technical solutions have been disclosed in the prior art. For example, the application number 200720055272.7, the application date is August 8, 2007, the title of the invention is: an anchor bolt frame, the application is composed of at least two anchor bolts and iron plates or stirrups, the iron plates or stirrups will The anchor bolts are combined and fixed in a certain shape. Although this application can play the role of fixing the anchor bolts, it is not convenient to transport in large-scale production, and more construction materials are required for production, more manpower is required for installation, and the construction cost high.
实用新型内容Utility model content
1.实用新型要解决的技术问题1. The technical problems to be solved by the utility model
本实用新型的目的在于克服现有技术中的不足,提供了一种三片式地脚螺栓定位架,采用本实用新型的技术方案,能够方便快捷的将三片圆弧定位架组装成地脚螺栓定位架,单片式的圆弧定位架占比面积小,便于地脚螺栓定位架的安装和运输,降低施工成本的同时减少运输过程中的损坏,而且结构简单,使用方便,施工成本低;另一方面,本实用新型提出的同时也提供了一种使地脚螺栓定位架更稳定的固定方式。The purpose of the utility model is to overcome the deficiencies in the prior art and provide a three-piece anchor bolt positioning frame. By adopting the technical scheme of the utility model, the three-piece arc positioning frame can be assembled into an anchor conveniently and quickly. Bolt positioning frame, the single-piece arc positioning frame occupies a small area, which is convenient for installation and transportation of the anchor bolt positioning frame, reduces construction costs and reduces damage during transportation, and has a simple structure, convenient use, and low construction cost ; On the other hand, the utility model also provides a more stable fixing method to make the anchor bolt positioning frame more stable.
2.技术方案2. Technical solution
为达到上述目的,本实用新型提供的技术方案为:In order to achieve the above object, the technical solution provided by the utility model is:
本实用新型的一种三片式地脚螺栓定位架,包括三片圆弧定位架,所述的圆弧定位架两两连接组成圆环结构,圆弧定位架上设置有若干个螺栓定位孔,圆弧定位架上设置有弦向支撑柱,圆弧定位架和弦向支撑柱之间设置有若干个连接杆。A three-piece anchor bolt positioning frame of the utility model includes three circular arc positioning frames, the circular arc positioning frames are connected in pairs to form a ring structure, and several bolt positioning holes are arranged on the circular arc positioning frames , the arc positioning frame is provided with a chord-direction supporting column, and several connecting rods are arranged between the arc positioning frame and the chord-direction supporting column.
作为本实用新型的更进一步改进,所述的圆弧定位架的两端外侧均设置有连接角钢,连接角钢的一端设置有螺栓孔,另一端固连于圆弧定位架的端部外侧。As a further improvement of the present utility model, connecting angle steels are provided on both ends of the arc positioning frame, one end of the connecting angle steel is provided with a bolt hole, and the other end is fixedly connected to the outside of the end of the arc positioning frame.
作为本实用新型的更进一步改进,所述的圆弧定位架两两之间通过螺栓穿过连接角钢端部的螺栓孔进行连接。As a further improvement of the utility model, the two arc positioning frames are connected by bolts passing through the bolt holes connecting the ends of the angle steel.
作为本实用新型的更进一步改进,所述的螺栓定位孔均匀对称的分布在圆弧定位架上。As a further improvement of the utility model, the bolt positioning holes are evenly and symmetrically distributed on the arc positioning frame.
作为本实用新型的更进一步改进,所述的弦向支撑柱两两之间设置有连接支撑柱,连接支撑柱和弦向支撑柱之间采用旋转扣件连接。As a further improvement of the present utility model, connecting support columns are arranged between two of the chordwise supporting columns, and the connecting supporting columns and the chordwise supporting columns are connected by rotating fasteners.
作为本实用新型的更进一步改进,所述的圆弧定位架的轴线位置设有样冲眼。As a further improvement of the utility model, the axial position of the circular arc positioning frame is provided with sample punching holes.
作为本实用新型的更进一步改进,所述的弦向支撑柱为脚手架钢管。As a further improvement of the utility model, the chordwise support column is a scaffold steel pipe.
作为本实用新型的更进一步改进,所述的连接杆为角钢或者钢管或者圆钢。As a further improvement of the utility model, the connecting rod is an angle steel or a steel pipe or a round steel.
3.有益效果3. Beneficial effect
采用本实用新型提供的技术方案,与现有技术相比,具有如下显著效果:Compared with the prior art, the technical solution provided by the utility model has the following remarkable effects:
(1)本实用新型的一种三片式地脚螺栓定位架,利用三片圆弧定位架组成圆环式地脚螺栓定位架,单片式圆弧定位架占地面积小,而且便于圆弧定位架的运输及地脚螺栓定位架的安装,在减少劳动力的同时大大降低了施工成本。(1) A three-piece anchor bolt positioning frame of the present utility model uses three circular arc positioning frames to form a ring type anchor bolt positioning frame. The single-piece arc positioning frame occupies a small area and is convenient for circular The transportation of the arc positioning frame and the installation of the anchor bolt positioning frame greatly reduce the construction cost while reducing the labor force.
(2)本实用新型的一种三片式地脚螺栓定位架,圆弧定位架上的弦向支撑柱和连接杆的设置,保证了圆弧定位架的稳固性,从而保证地脚螺栓定位架整体的稳定性。(2) A three-piece anchor bolt positioning frame of the present utility model, the setting of the chord-direction support columns and the connecting rods on the arc positioning frame ensures the stability of the arc positioning frame, thereby ensuring the positioning of the anchor bolts overall stability of the frame.
(3)本实用新型的一种三片式地脚螺栓定位架,弦向支撑柱两两之间设置有连接支撑柱,连接支撑柱在地脚螺栓定位架内组成了三角形,不仅保证了圆弧定位架拼接成整体后的刚度,减轻圆弧定位架的支撑重量,而且大大保证了地脚螺栓定位架的稳定性。(3) A three-piece anchor bolt positioning frame of the present utility model, connecting support columns are arranged between two of the chordwise supporting columns, and the connecting supporting columns form a triangle in the anchor bolt positioning frame, which not only ensures the circular The rigidity of the arc positioning frame spliced into a whole reduces the support weight of the arc positioning frame and greatly ensures the stability of the anchor bolt positioning frame.
(4)本实用新型的一种三片式地脚螺栓定位架,圆弧定位架的轴线处设置有样冲眼,便于地脚螺栓定位架对准圆形基础轴线进行安装找正。(4) A three-piece anchor bolt positioning frame of the present utility model, the axis of the circular arc positioning frame is provided with a sample punching hole, which is convenient for the anchor bolt positioning frame to align with the circular foundation axis for installation and alignment.
(5)本实用新型的一种三片式地脚螺栓定位架,弦向支撑柱采用脚手架钢管,便于地脚螺栓定位架与圆形基础处的脚手架进行连接固定,而且脚手架钢管可重复利用。(5) A three-piece anchor bolt positioning frame of the present utility model, the chordwise support column adopts scaffolding steel pipes, which facilitates the connection and fixing of the anchor bolt positioning frame and the scaffold at the circular foundation, and the scaffolding steel pipes can be reused.
(6)本实用新型的一种三片式地脚螺栓定位架,结构简单,使用方便,施工成本低。(6) A three-piece anchor bolt positioning frame of the present utility model has the advantages of simple structure, convenient use and low construction cost.
附图说明Description of drawings
图1为本实用新型的一种三片式地脚螺栓定位架的俯视图;Fig. 1 is the plan view of a kind of three-piece anchor bolt positioning frame of the present utility model;
图2为本实用新型的一种三片式地脚螺栓定位架的圆弧定位架的结构示意图;Fig. 2 is the structural representation of the circular arc positioning frame of a kind of three-piece anchor bolt positioning frame of the present utility model;
图3为本实用新型的一种三片式地脚螺栓定位架的两片圆弧定位架之间连接部位的结构示意图。Fig. 3 is a structural schematic diagram of the joint between two circular arc positioning frames of a three-piece anchor bolt positioning frame of the present invention.
示意图中的标号说明:Explanation of the labels in the schematic diagram:
1、圆弧定位架;2、螺栓定位孔;3、弦向支撑柱;4、连接杆;5、连接角钢;6、螺栓;7、连接支撑柱;8、样冲眼。1. Arc positioning frame; 2. Bolt positioning hole; 3. Chordal support column; 4. Connecting rod; 5. Connecting angle steel; 6. Bolt; 7. Connecting support column; 8. Sample punch.
具体实施方式Detailed ways
为进一步了解本实用新型的内容,结合附图及实施例对本实用新型作详细描述。In order to further understand the content of the utility model, the utility model is described in detail in conjunction with the accompanying drawings and embodiments.
实施例1Example 1
如图1所示,本实施例中的一种三片式螺栓定位架,包括三片圆弧定位架1,单片式圆弧定位架1占地面积小,而且便于圆弧定位架1的运输及地脚螺栓定位架的安装,在减少劳动力的同时大大降低了施工成本,所述的圆弧定位架1两两连接组成圆环结构,圆弧定位架1上设置有若干个螺栓定位孔2,螺栓定位孔2呈均匀对称分布,圆弧定位架1设置有弦向支撑柱3,弦向支撑柱3为脚手架钢管,便于地脚螺栓定位架与圆形基础处的脚手架进行连接固定,而且脚手架钢管可重复利用,圆弧定位架1和弦向支撑柱3之间设置有若干个连接杆4,连接杆4为角钢或者钢管或者圆钢,本实施例中,单片圆弧定位架1上的连接杆4的个数为3个,弦向支撑柱3和连接杆4的设置,保证了圆弧定位架1的稳固性,从而保证地脚螺栓定位架整体的稳定性,圆弧定位架1的两端外侧均设置有连接角钢5,连接角钢5的一端设置有螺栓孔,另一端固连于圆弧定位架1的端部外侧,圆弧定位架1两两之间通过螺栓6穿过连接角钢5端部的螺栓孔进行连接,圆弧定位架1的轴线位置设有样冲眼8,便于地脚螺栓定位架对准圆形基础轴线进行安装找正。As shown in Figure 1, a kind of three-piece bolt positioning frame in the present embodiment includes three arc positioning frames 1, and the single-piece arc positioning frame 1 occupies a small area, and is convenient for the arc positioning frame 1 The transportation and the installation of the anchor bolt positioning frame greatly reduce the construction cost while reducing the labor force. The circular arc positioning frame 1 is connected in pairs to form a ring structure, and the circular arc positioning frame 1 is provided with several bolt positioning holes. 2. The bolt positioning holes 2 are distributed evenly and symmetrically. The arc positioning frame 1 is provided with a chord support column 3. The chord support column 3 is a scaffold steel pipe, which is convenient for the connection and fixation of the anchor bolt positioning frame and the scaffold at the circular foundation. And the steel pipe of the scaffold can be reused. Several connecting rods 4 are arranged between the arc positioning frame 1 and the chord support column 3. The connecting rods 4 are angle steel or steel pipes or round steel. In the present embodiment, the single-piece arc positioning frame 1 The number of connecting rods 4 on the top is 3, and the setting of the chordwise support column 3 and the connecting rods 4 ensures the stability of the arc positioning frame 1, thereby ensuring the overall stability of the anchor bolt positioning frame, and the circular arc positioning Both ends of the frame 1 are provided with connecting angle steel 5, and one end of the connecting angle steel 5 is provided with a bolt hole, and the other end is fixedly connected to the outer side of the end of the arc positioning frame 1, and the arc positioning frame 1 is passed between two pairs of bolts 6. Pass through the bolt holes at the ends of the connecting angle steel 5 to connect, and the axial position of the arc positioning frame 1 is provided with a sample punching hole 8, which is convenient for the anchor bolt positioning frame to align with the circular foundation axis for installation and alignment.
所述的弦向支撑柱3两两之间设置有连接支撑柱7,连接支撑柱7在地脚螺栓定位架内组成了三角形,不仅保证了圆弧定位架1拼接成整体后的刚度,减轻圆弧定位架1的支撑重量,而且大大保证了地脚螺栓定位架的稳定性,连接支撑柱7和弦向支撑柱3之间采用旋转扣件连接。The chordwise support columns 3 are provided with connection support columns 7 in pairs, and the connection support columns 7 form a triangle in the anchor bolt positioning frame, which not only ensures the rigidity of the arc positioning frame 1 after splicing into a whole, but also reduces the The supporting weight of the circular arc positioning frame 1 also greatly ensures the stability of the anchor bolt positioning frame, and the connecting support column 7 and the chordwise support column 3 are connected by rotating fasteners.
根据图纸尺寸按1:1比例在钢平台上放出实样,根据放样尺寸做成圆环钢板,并将弦向支撑柱3和连接杆4焊接固定在圆环钢板上,形成一个整体,然后将圆环钢板分割成三等分的圆弧定位架1,并将带有螺栓孔的连接角钢5固定焊接到圆弧定位架1的端部,根据安装要求在三片圆弧定位架1上画出螺栓定位孔2的位置线和样冲眼8并进行钻孔,在施工安装过程中,选择与连接角钢5上螺栓孔配套使用的螺栓6将圆弧定位架1两两连接固定,根据图纸的指定位置将圆弧定位架1上的编号对准安装,同时利用圆弧定位架1上的样冲眼8轴线对准圆形基础的轴线安装定位,将圆弧定位架1焊接在圆形基础的支撑架上,并将弦向支撑柱3连接在圆形基础的脚手架上以便对地脚螺栓定位架进行加固,最后使用旋转扣件将连接支撑柱7连接固定在地脚螺栓定位架的弦向支撑柱3中部,进而稳定整个地脚螺栓定位架。Release the actual sample on the steel platform in a ratio of 1:1 according to the size of the drawing, make a circular steel plate according to the lofted size, and weld and fix the chord support column 3 and the connecting rod 4 on the circular steel plate to form a whole, and then The ring steel plate is divided into three equal arc positioning frames 1, and the connecting angle steel 5 with bolt holes is fixedly welded to the end of the arc positioning frame 1, and the three pieces of arc positioning frames 1 are drawn according to the installation requirements. The position line of the bolt positioning hole 2 and the sample punching hole 8 are drilled. During the construction and installation process, the bolt 6 used in conjunction with the bolt hole on the connecting angle steel 5 is selected to connect and fix the arc positioning frame 1 in pairs. According to the drawing Align the number on the arc positioning frame 1 with the specified position, and at the same time use the axis of the sample punching hole 8 on the arc positioning frame 1 to align with the axis of the circular foundation for installation and positioning, and weld the arc positioning frame 1 on the circular on the support frame of the foundation, and connect the chord support column 3 to the scaffold of the circular foundation in order to reinforce the anchor bolt positioning frame, and finally use the rotating fastener to connect and fix the connecting support column 7 on the anchor bolt positioning frame The chord is in the middle of the support column 3, thereby stabilizing the entire anchor bolt positioning frame.
以上示意性的对本实用新型及其实施方式进行了描述,该描述没有限制性,附图中所示的也只是本实用新型的实施方式之一,实际的结构并不局限于此。所以,如果本领域的普通技术人员受其启示,在不脱离本实用新型创造宗旨的情况下,不经创造性的设计出与该技术方案相似的结构方式及实施例,均应属于本实用新型的保护范围。The above schematically describes the utility model and its implementation, which is not restrictive, and what is shown in the accompanying drawings is only one implementation of the utility model, and the actual structure is not limited thereto. Therefore, if a person of ordinary skill in the art is inspired by it, and without departing from the purpose of the invention of the utility model, without creatively designing a structural mode and an embodiment similar to the technical solution, it shall belong to the utility model. protected range.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520313252.XU CN204608825U (en) | 2015-05-14 | 2015-05-14 | A kind of three-chip type stone bolt locating rack |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520313252.XU CN204608825U (en) | 2015-05-14 | 2015-05-14 | A kind of three-chip type stone bolt locating rack |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204608825U true CN204608825U (en) | 2015-09-02 |
Family
ID=53961386
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520313252.XU Expired - Lifetime CN204608825U (en) | 2015-05-14 | 2015-05-14 | A kind of three-chip type stone bolt locating rack |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204608825U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106284399A (en) * | 2016-08-31 | 2017-01-04 | 中国冶集团有限公司 | The building pre-buried locating template of pedestal anchor bolt and construction method |
| CN107653899A (en) * | 2017-11-13 | 2018-02-02 | 中冶建工集团有限公司 | A kind of method for rapidly positioning of ring-type foundation bolt |
| CN109235483A (en) * | 2018-10-08 | 2019-01-18 | 中石化石油工程技术服务有限公司 | A kind of large equipment base foundation bolt positioning device and its application method |
| CN111005744A (en) * | 2019-12-30 | 2020-04-14 | 湖南尚上公路桥梁建设有限公司 | Support beam structure of municipal shield tunnel |
-
2015
- 2015-05-14 CN CN201520313252.XU patent/CN204608825U/en not_active Expired - Lifetime
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106284399A (en) * | 2016-08-31 | 2017-01-04 | 中国冶集团有限公司 | The building pre-buried locating template of pedestal anchor bolt and construction method |
| CN106284399B (en) * | 2016-08-31 | 2018-10-23 | 中国一冶集团有限公司 | Build the pre-buried locating template of pedestal anchor bolt and construction method |
| CN107653899A (en) * | 2017-11-13 | 2018-02-02 | 中冶建工集团有限公司 | A kind of method for rapidly positioning of ring-type foundation bolt |
| CN109235483A (en) * | 2018-10-08 | 2019-01-18 | 中石化石油工程技术服务有限公司 | A kind of large equipment base foundation bolt positioning device and its application method |
| CN111005744A (en) * | 2019-12-30 | 2020-04-14 | 湖南尚上公路桥梁建设有限公司 | Support beam structure of municipal shield tunnel |
| CN111005744B (en) * | 2019-12-30 | 2021-10-19 | 湖南尚上市政建设开发有限公司 | Support beam structure of municipal shield tunnel |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203594213U (en) | Flexible assembling and disassembling bearing truss | |
| CN104912191B (en) | Prefabricated concrete prefabricated column splicing device and using method | |
| CN106884505A (en) | A kind of adjustable frame post reinforcing bar spacer ferrule and its installation and method for dismounting | |
| CN104196152B (en) | Connecting structure for steel coupling beam and concrete wall | |
| CN205531410U (en) | A simply can dismantle construction canopy for steel construction job site | |
| CN204060148U (en) | A kind of fence that can improve application life | |
| CN206752855U (en) | A kind of adjustable frame post reinforcing bar spacer ferrule | |
| CN205701894U (en) | A kind of large-diameter pipeline supports | |
| CN206554500U (en) | Steel structure concrete, which is poured, uses adjustable transverse support bar | |
| CN104018655B (en) | A kind of assembly type monomer bracing frame | |
| CN204753839U (en) | Support between steel column and use connecting device | |
| CN205822414U (en) | A kind of scalable fixes the device of L-type drain pipe | |
| CN206600005U (en) | The positioning component and positioner of reserved joint bar in shear wall | |
| CN204343154U (en) | Assembled continuous rigid frame bridge steel tie beam | |
| CN210713741U (en) | Overhanging type scaffold structure | |
| CN114775463A (en) | Rapid reinforcing device and method for bridge pier after transverse damage | |
| CN209620242U (en) | Strenthening member for basement structure | |
| CN207582685U (en) | A kind of wall beam tie rod connection structure | |
| CN204290167U (en) | Put stringing crossing frame | |
| CN219011995U (en) | Prefabricated part limiting template | |
| CN205382561U (en) | Assembled steel frame cast steel joint | |
| CN206273915U (en) | A kind of attachment structure of new quadrate steel pipe column and steel I-beam | |
| CN204435810U (en) | A kind of braced structures for building | |
| CN204418236U (en) | A kind of detachable anti-float anchor rod pull-out test reaction support | |
| CN206594939U (en) | Detachable Simple steel canopy training model |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20150902 |