CN204455148U - A kind of blast furnace slag quenching water waste heat recovery washing slag water switched system - Google Patents

A kind of blast furnace slag quenching water waste heat recovery washing slag water switched system Download PDF

Info

Publication number
CN204455148U
CN204455148U CN201420864724.6U CN201420864724U CN204455148U CN 204455148 U CN204455148 U CN 204455148U CN 201420864724 U CN201420864724 U CN 201420864724U CN 204455148 U CN204455148 U CN 204455148U
Authority
CN
China
Prior art keywords
washing
slag water
slag
washing slag
valve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420864724.6U
Other languages
Chinese (zh)
Inventor
宋秉棠
赵殿金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN HUASAIER HEAT TRANSFER EQUIPMENT CO Ltd
Original Assignee
TIANJIN HUASAIER HEAT TRANSFER EQUIPMENT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN HUASAIER HEAT TRANSFER EQUIPMENT CO Ltd filed Critical TIANJIN HUASAIER HEAT TRANSFER EQUIPMENT CO Ltd
Priority to CN201420864724.6U priority Critical patent/CN204455148U/en
Application granted granted Critical
Publication of CN204455148U publication Critical patent/CN204455148U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

The utility model proposes a kind of blast furnace slag quenching water waste heat recovery washing slag water switched system, only adopt a set of washing slag water heat-obtaining system, the waste heat recovery achieving washing slag water system and washing slag water system for subsequent use is switched by pipeline, can also by controlling water pump, valve controls washing slag water current through line flexibly, ensure flushing cinder system and heat-obtaining system quick, switch timely, comprise: blast furnace and a set of washing slag water system, washing slag water system comprises at least 2 slag-washing-out pumps, 2 cover washing slag water pipelines, washing slag water switched system and washing slag water heat-obtaining system, 2 cover washing slag water pipelines are all connected with washing slag water heat-obtaining system.

Description

A kind of blast furnace slag quenching water waste heat recovery washing slag water switched system
Technical field
The utility model relates to blast furnace slag quenching water heat recovery technology field, particularly a kind of blast furnace slag quenching water waste heat recovery washing slag water switched system.
Background technology
Large-scale iron-smelting blast furnace slag flushing process adopts mostly because of bar, Ming Te or good permanent method, and often overlap flushing cinder system configuration 2 or multiple stage slag-washing-out pump, two cover flushing cinder pipelines in this type of technique, do not relate to large-scale flushing cinder pond, floor space is little, compact construction, saving space.1 or multiple stage water pump operation during normal work, remain 1 or multiple stage water pump is reserve pump; Washing slag water pipeline has two, and a conveying washing slag water, another is spare duct.When the slag-washing-out pump run or washing slag water pipeline occur abnormal, washing slag water system for subsequent use can be switched to fast.Using exhaust heat of slag flushing water recovery technology is day by day ripe, can realize the waste heat recycling in flushing cinder system.But, for the UTILIZATION OF VESIDUAL HEAT IN of flushing cinder system for subsequent use, there is no good solution at present.
Utility model content
The utility model is intended to propose that a kind of structure is simple, easy switching, can realize the blast furnace slag quenching water waste heat recovery washing slag water switched system that washing slag water and washing slag water system waste heat for subsequent use reclaim.
The technical solution of the utility model is achieved in that
A kind of blast furnace slag quenching water waste heat recovery washing slag water switched system, comprise: blast furnace and a set of washing slag water system, washing slag water system comprises at least 2 slag-washing-out pumps, 2 cover washing slag water pipelines, washing slag water switched system and washing slag water heat-obtaining system, and 2 cover washing slag water pipelines are all connected with washing slag water heat-obtaining system;
Washing slag water pipeline comprises the first washing slag water pipeline and the second washing slag water pipeline, the entrance of the first washing slag water pipeline and the second washing slag water pipeline is respectively arranged with the first slag-washing-out pump and the second slag-washing-out pump, and the first slag-washing-out pump and the second slag-washing-out pump are respectively arranged with the first slag-washing-out pump valve and the second slag-washing-out pump valve;
First washing slag water pipeline enters washing slag water heat-obtaining system by the first washing slag water pipeline heat-obtaining system entry valve, and leaves washing slag water heat-obtaining system by the first washing slag water pipeline heat-obtaining system outlet valve;
Second washing slag water pipeline enters washing slag water heat-obtaining system by the second washing slag water pipeline heat-obtaining system entry valve, and leaves washing slag water heat-obtaining system by the second washing slag water pipeline heat-obtaining system outlet valve;
First washing slag water pipeline and the second washing slag water pipeline are respectively arranged with the first washing slag water pipe valve and the second washing slag water pipe valve, between the first washing slag water pipeline and the second washing slag water pipeline, are provided with pipeline switching valve door.
Preferably, also comprise 1 the 3rd slag-washing-out pump, the 3rd slag-washing-out pump is arranged the 3rd slag-washing-out pump valve, the 3rd slag-washing-out pump valve is connected with the first washing slag water pipeline by the 4th valve, is connected with the second washing slag water pipeline by the 5th valve.
Preferably, pipeline switching valve door is the one in manually-operated gate, electrically operated valve or operated pneumatic valve.
Compared with prior art, the blast furnace slag quenching water waste heat recovery washing slag water switched system that the utility model proposes, adopt a set of washing slag water heat-obtaining system, the waste heat recovery achieving washing slag water system and washing slag water system for subsequent use is switched by pipeline, washing slag water current through line can also be controlled flexibly by control water pump, valve, ensure that flushing cinder system and heat-obtaining system switch fast, timely.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is only embodiments more of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of a kind of blast furnace slag quenching water waste heat recovery of the utility model washing slag water switched system;
Fig. 2 is another embodiment of Fig. 1.
In figure: 1, the first slag-washing-out pump; 2, the second slag-washing-out pump; 3, the first slag-washing-out pump valve; 4, the second slag-washing-out pump valve; 5, the first washing slag water pipe valve; 6, the second washing slag water pipe valve; 7, the first washing slag water pipeline; 8, the second washing slag water pipeline; 9, the first washing slag water pipeline heat-obtaining system entry valve; 10, the second washing slag water pipeline heat-obtaining system entry valve; 11, the second washing slag water pipeline heat-obtaining system outlet valve; 12, the first washing slag water pipeline heat-obtaining system outlet valve; 13, pipeline switching valve door; 14, the 3rd slag-washing-out pump; 15, the 3rd slag-washing-out pump valve; 16, the 5th valve; 17, the 4th valve.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, be clearly and completely described the technical scheme in the utility model embodiment, obviously, described embodiment is only the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all belong to the scope of the utility model protection.
As shown in Figure 1: a kind of blast furnace slag quenching water waste heat recovery washing slag water switched system, comprise: blast furnace and a set of washing slag water system, washing slag water system comprises at least 2 slag-washing-out pumps, 2 cover washing slag water pipelines, washing slag water switched system and washing slag water heat-obtaining system, and 2 cover washing slag water pipelines are all connected with washing slag water heat-obtaining system;
Washing slag water pipeline comprises the first washing slag water pipeline 7 and the second washing slag water pipeline 8, the entrance of the first washing slag water pipeline 7 and the second washing slag water pipeline 8 is respectively arranged with on the first slag-washing-out pump 1 and the second slag-washing-out pump 2, first slag-washing-out pump 1 and the second slag-washing-out pump 2 and is respectively arranged with the first slag-washing-out pump valve 3 and the second slag-washing-out pump valve 4;
First washing slag water pipeline 7 enters washing slag water heat-obtaining system by the first washing slag water pipeline heat-obtaining system entry valve 9, and leaves washing slag water heat-obtaining system by the first washing slag water pipeline heat-obtaining system outlet valve 12;
Second washing slag water pipeline 8 enters washing slag water heat-obtaining system by the second washing slag water pipeline heat-obtaining system entry valve 10, and leaves washing slag water heat-obtaining system by the second washing slag water pipeline heat-obtaining system outlet valve 11;
First washing slag water pipeline 7 and the second washing slag water pipeline 8 are respectively arranged with the first washing slag water pipe valve 5 and are provided with pipeline switching valve door 13 between the second washing slag water pipe valve 6, first washing slag water pipeline 7 and the second washing slag water pipeline 8.
Workflow:
Washing slag water heat-obtaining can utilize the first washing slag water pipeline 7: open the first slag-washing-out pump valve 3, close the first washing slag water pipe valve 5, pipeline switching valve door 13, open the first washing slag water pipeline heat-obtaining system entry valve 9, close the second washing slag water pipeline heat-obtaining system entry valve 10, close the first washing slag water pipeline heat-obtaining system outlet valve 12, open the second washing slag water pipeline heat-obtaining system outlet valve 11; First slag-washing-out pump 1 is opened, then washing slag water enters washing slag water heat-obtaining system by valve, the first washing slag water pipeline 7, washing slag water cooled in this heat-obtaining system gets back to the first washing slag water pipeline 7 through the first washing slag water pipeline heat-obtaining system outlet valve 12, then proceeds flushing cinder;
This flow process also can adopt the second slag-washing-out pump 2 to realize, open the second slag-washing-out pump valve 4, second washing slag water pipeline heat-obtaining system entry valve 10, second washing slag water pipeline heat-obtaining system outlet valve 11, all the other valve closess, after then washing slag water can be extracted by the second slag-washing-out pump 2, through valve, pipeline, washing slag water heat-obtaining system, enter the first washing slag water pipeline 7, then carry out flushing cinder;
Washing slag water heat-obtaining flow process utilizes the second washing slag water pipeline 8: similar to utilizing the first washing slag water pipeline 7, the unlatching valve corresponding with the second slag-washing-out pump 2 and on the way valve, also can open the first slag-washing-out pump 1 after valve transfer, be transported to the second washing slag water pipeline 8, then carry out flushing cinder.
Compared with prior art, the blast furnace slag quenching water waste heat recovery washing slag water switched system that the utility model proposes, adopt a set of washing slag water heat-obtaining system, the waste heat recovery achieving washing slag water system and washing slag water system for subsequent use is switched by pipeline, washing slag water current through line can also be controlled flexibly by control water pump, valve, ensure that flushing cinder system and heat-obtaining system switch fast, timely.
As shown in Figure 2: as one preferred embodiment, an embodiment more of the present utility model, also comprise 1 the 3rd slag-washing-out pump 14,3rd slag-washing-out pump 14 is arranged the 3rd slag-washing-out pump valve 15,3rd slag-washing-out pump valve 15 is connected with the first washing slag water pipeline 7 by the 4th valve 17, is connected with the second washing slag water pipeline 8 by the 5th valve 16.
When slag-washing-out pump has 3 cover, then flushing cinder system running state is 2 open 1 standby, and any 2 water pumps all can cooperation, and it is for subsequent use for remaining a water pump.
When startup first slag-washing-out pump 1 and the second slag-washing-out pump 2, open the second slag-washing-out pump valve 4, first slag-washing-out pump valve 3, pipeline switching valve door 13, unlatching second washing slag water pipe valve 6 or the first washing slag water pipe valve 5 can be selected according to pipeline, all the other valve closess, then 2 water pumps gather after current the first washing slag water pipeline 7 or the second washing slag water pipeline 8 can be selected to carry out waste heat recovery and flushing cinder.When unlatching first slag-washing-out pump the 1, the 3rd slag-washing-out pump 14 or open the second slag-washing-out pump 2, the 3rd slag-washing-out pump time 14, similar to unlatching first slag-washing-out pump 1, second slag-washing-out pump 2.
In above-described embodiment, pipeline switching valve door 13 is the one in manually-operated gate, electrically operated valve or operated pneumatic valve.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (3)

1. a blast furnace slag quenching water waste heat recovery washing slag water switched system, it is characterized in that: comprising: blast furnace and a set of washing slag water system, described washing slag water system comprises at least 2 slag-washing-out pumps, 2 cover washing slag water pipelines, washing slag water switched system and washing slag water heat-obtaining system, and the described washing slag water pipeline of 2 cover is all connected with described washing slag water heat-obtaining system;
Described washing slag water pipeline comprises the first washing slag water pipeline (7) and the second washing slag water pipeline (8), described first washing slag water pipeline (7) is respectively arranged with the first slag-washing-out pump (1) and the second slag-washing-out pump (2) with the entrance of described second washing slag water pipeline (8), and described first slag-washing-out pump (1) and described second slag-washing-out pump (2) are respectively arranged with the first slag-washing-out pump valve (3) and the second slag-washing-out pump valve (4);
Described first washing slag water pipeline (7) enters described washing slag water heat-obtaining system by the first washing slag water pipeline heat-obtaining system entry valve (9), and leaves described washing slag water heat-obtaining system by the first washing slag water pipeline heat-obtaining system outlet valve (12);
Described second washing slag water pipeline (8) enters described washing slag water heat-obtaining system by the second washing slag water pipeline heat-obtaining system entry valve (10), and leaves described washing slag water heat-obtaining system by the second washing slag water pipeline heat-obtaining system outlet valve (11);
Described first washing slag water pipeline (7) and described second washing slag water pipeline (8) are respectively arranged with the first washing slag water pipe valve (5) and the second washing slag water pipe valve (6), between described first washing slag water pipeline (7) and described second washing slag water pipeline (8), are provided with pipeline switching valve door (13).
2. blast furnace slag quenching water waste heat recovery washing slag water switched system according to claim 1, it is characterized in that: also comprise 1 the 3rd slag-washing-out pump (14), described 3rd slag-washing-out pump (14) arranges the 3rd slag-washing-out pump valve (15), described 3rd slag-washing-out pump valve (15) is connected with the first washing slag water pipeline (7) by the 4th valve (17), is connected with the second washing slag water pipeline (8) by the 5th valve (16).
3. blast furnace slag quenching water waste heat recovery washing slag water switched system according to claim 1 and 2, is characterized in that: described pipeline switching valve door (13) is manually-operated gate, one in electrically operated valve or operated pneumatic valve.
CN201420864724.6U 2014-12-31 2014-12-31 A kind of blast furnace slag quenching water waste heat recovery washing slag water switched system Active CN204455148U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420864724.6U CN204455148U (en) 2014-12-31 2014-12-31 A kind of blast furnace slag quenching water waste heat recovery washing slag water switched system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420864724.6U CN204455148U (en) 2014-12-31 2014-12-31 A kind of blast furnace slag quenching water waste heat recovery washing slag water switched system

Publications (1)

Publication Number Publication Date
CN204455148U true CN204455148U (en) 2015-07-08

Family

ID=53662061

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420864724.6U Active CN204455148U (en) 2014-12-31 2014-12-31 A kind of blast furnace slag quenching water waste heat recovery washing slag water switched system

Country Status (1)

Country Link
CN (1) CN204455148U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105803137A (en) * 2014-12-31 2016-07-27 天津华赛尔传热设备有限公司 Blast furnace slag washing water waste heat recovery and slag washing water switching process system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105803137A (en) * 2014-12-31 2016-07-27 天津华赛尔传热设备有限公司 Blast furnace slag washing water waste heat recovery and slag washing water switching process system

Similar Documents

Publication Publication Date Title
CN103742397B (en) A kind of noiseless switched system of feeding pump and switching method thereof
CN104266343A (en) Method for recycling bathing wastewater
CN204455148U (en) A kind of blast furnace slag quenching water waste heat recovery washing slag water switched system
CN202692719U (en) Waste heat recovery system for annealing furnace smoke
CN204342839U (en) A kind of vacuum heat treatment furnace cooling water recirculation system
CN104948913B (en) Zero-leakage safe alkali discharging device and method thereof
CN109879567A (en) A kind of system and processing method of reply sludge supercritical water oxidation apparatus burst power outage
CN205346989U (en) Simple and easy water purification system
CN102777351A (en) Waste heat recycling device and recycling method of oil-free compressor
CN203736974U (en) Economic sandstone geothermal tail water recharging system
CN207996540U (en) A kind of adsorption tower backwashing system
CN203501801U (en) Cooling water system of medium-frequency induction furnace
CN103628913A (en) Automatic cleaning system and method of dual-redundancy paste filling pipes
CN103758350A (en) Air and electricity linkage device of full-automatic high-speed concrete spraying machine
CN203742689U (en) Boiler sewage water waste heat utilization device
CN105803137A (en) Blast furnace slag washing water waste heat recovery and slag washing water switching process system
CN204986419U (en) Alkali device is unloaded to zero leakage safety
CN207507064U (en) A kind of thickener underflow system
CN204455149U (en) A kind of waste heat recovery system of blast furnace slag quenching water
CN203670178U (en) Interference-free changing-over system for feeding pumps
CN103410199B (en) H-shaped fluid delivery pipeline system and fluid delivery method
CN102537469A (en) Remote monitoring device of electric valve of iron ore concentrate pipeline and monitoring method of remote monitoring device
CN202757524U (en) Cooling system capable of washing heat exchanger in on-line mode
CN105755189A (en) Waste heat recovery device for blast furnace slag flushing water
CN203595338U (en) Cooling water circulation system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant