CN204454844U - A kind of sludge gasification quality coal in cement kiln systems - Google Patents

A kind of sludge gasification quality coal in cement kiln systems Download PDF

Info

Publication number
CN204454844U
CN204454844U CN201420808485.2U CN201420808485U CN204454844U CN 204454844 U CN204454844 U CN 204454844U CN 201420808485 U CN201420808485 U CN 201420808485U CN 204454844 U CN204454844 U CN 204454844U
Authority
CN
China
Prior art keywords
dewatered sludge
vapourizing furnace
furnace
mud
cement kiln
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420808485.2U
Other languages
Chinese (zh)
Inventor
顾军
刘海兵
李威
陈晓东
韩力
蔡文涛
郝利炜
王肇嘉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING TAIHANG QIANJING CEMENT Co Ltd
Beijing Jinyu Limited-Liability Co
Beijing Building Materials Academy of Sciences Research
Original Assignee
BEIJING TAIHANG QIANJING CEMENT Co Ltd
Beijing Jinyu Limited-Liability Co
Beijing Building Materials Academy of Sciences Research
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING TAIHANG QIANJING CEMENT Co Ltd, Beijing Jinyu Limited-Liability Co, Beijing Building Materials Academy of Sciences Research filed Critical BEIJING TAIHANG QIANJING CEMENT Co Ltd
Priority to CN201420808485.2U priority Critical patent/CN204454844U/en
Application granted granted Critical
Publication of CN204454844U publication Critical patent/CN204454844U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P40/00Technologies relating to the processing of minerals
    • Y02P40/10Production of cement, e.g. improving or optimising the production methods; Cement grinding
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P40/00Technologies relating to the processing of minerals
    • Y02P40/10Production of cement, e.g. improving or optimising the production methods; Cement grinding
    • Y02P40/121Energy efficiency measures, e.g. improving or optimising the production methods

Abstract

The utility model discloses a kind of sludge gasification quality coal in cement kiln systems, described sludge gasification quality coal in cement kiln systems, comprise cement kiln Sum decomposition stove, the import of described cement kiln and the outlet of described decomposing furnace, the inlet mouth of described decomposing furnace is communicated with by gas pipeline with the air outlet of vapourizing furnace, the opening for feed of described vapourizing furnace is communicated with material storehouse by delivery system, and the slag notch of described vapourizing furnace is communicated with Raw Material System by dreg removing system.The utility model can improve the disposal scale of mud greatly; Decrease solid sludges and directly enter difference between its form of kiln and coal dust, cement raw material fineness, add mass-and heat-transfer effect.

Description

A kind of sludge gasification quality coal in cement kiln systems
Technical field
The utility model relates to a kind of system of disposing sludge, particularly relates to a kind of sludge gasification quality coal in cement kiln systems.
Background technology
Cement industry is one of China industrial circle energy consumption rich and influential family, accounts for 6.5% of national total energy consumption.Cement industry fuel consumption accounts for 75% of cement industry total energy consumption, and coal accounts for nearly 100% of total fuel consumption.Seek to use alternative fuel to meet the strategy of China's energy structure optimizing and the displacement of Cement industry production capacity.
Along with the construction of urban wastewater treatment facility, sewage plant sludge and sewage sludge become a new Urban Environmental Problem.Moisture percentage in sewage sludge about 80% after Sewage Plant mechanical dehydration.The conventional method of disposal such as landfill, burning, compost is difficult to the environmental emission standard and the resource utilization needs that adapt to increasingly stringent.Because the main chemical compositions of mud comprises SiO 2, Fe 20 3, and A1 2o 3, more similar with the siliceous raw material in cement raw material, can be used for Some substitute siliceous raw material in theory prepares burden, and its calorific value can be used as fuel and uses.Therefore utilizing cement kiln synergic processing town sewage plant mud, is a kind of economy, feasible recycling mode.But concerning cement kiln synergic processing mud utilizes, moisture, calorific value and physical dimension are the important factors affecting cement kiln mass-producing and stability disposing sludge.Wet sludge calorific value is low, directly enters kiln and can form floc sedimentation shape structure, causes cement kiln temperature to decline and worsens combustion conditions.Affect the yield and quality of grog.Moisture content is high in addition, will increase the load of exhaust gas volumn and exhaust-gas treatment facilities, easily produce foul gas.
Domestic and international cement kiln disposing sludge is all that after utilizing mummification, single-point enters kiln technology, does not have sludge gasification to enter the case of cement kiln at present in the world.In prior art, be first mud is transported to cement mill from Sewage Plant with the main common ground of cement kiln disposing sludge, recycling cement kiln waste heat carries out ovens dry deodorizing to mud and directly enters decomposing furnace and burn, due to mud conglomeration and skewness, dispose small, and energy consumption is higher.Zaozhuang, Shandong Province Zhong Lian cement limited liability company builds up dewatered sludge (water ratio about 75%) the demonstration line that 60 ton per days dispose Zaozhuang Sewage Plant.
Utility model content
A technical problem to be solved in the utility model is to provide a kind of method of cement kiln disposing sludge, and the method can improve the disposal scale of mud greatly.
Another technical problem to be solved in the utility model is to provide a kind of sludge gasification quality coal in cement kiln systems, and this system can improve the disposal scale of mud greatly.
With regard to method, in order to solve an above-mentioned technical problem, the method of the utility model cement kiln disposing sludge first wet mud is made dewatered sludge particle, again dewatered sludge particle is gasified, then, decomposing furnace is sent in the combustion gas obtained after gasification, the lime-ash obtained after gasification is sent into Raw Material System.
Described dewatered sludge particle of being made by wet mud is first by adding mineral substance and/or biomass in the wet mud of Sewage Plant or water drain, moisture in wet mud is reduced to 40-50%, again the mud after reduction moisture is made wet mud granule, then, mud granule ventilation mummification of wetting forms dewatered sludge particle.
Describedly moisture in wet mud is reduced to 40-50% carries out in mud mixing machine, described wet mud is squeezed in described mud mixing machine by sludge pump, described mineral substance is flyash and/or unslaked lime, described mineral substance adds in described mud mixing machine by mineral substance measuring apparatus, describedly make wet mud granule realized reducing the mud after moisture by sludge granulator, describedly send into described sludge granulator by reducing the mud after moisture by rotary conveyor, described wet mud granule ventilation mummification to be realized by mud granule drying device, described wet mud granule sends into described mud granule drying device by forklift, the moisture content of described dewatered sludge particle is 20-30%, described dewatered sludge particle is transported in the dewatered sludge particulate material storehouse in cement mill by dewatered sludge particulate transportation car.
Described biomass are garbage waste materials, and described biomass are added in described mud mixing machine by biomass measuring apparatus.
Described gasification by dewatered sludge particle carries out in dewatered sludge particle vapourizing furnace, described dewatered sludge particle sends into dewatered sludge particle vapourizing furnace by dewatered sludge particle transport system, described combustion gas sends into decomposing furnace by pipeline, and described lime-ash sends into Raw Material System by dreg removing system.
Described combustion gas sends into decomposing furnace when temperature is more than or equal to 900 DEG C, and the temperature in cement kiln is more than or equal to 1450 DEG C.
The method of the utility model cement kiln disposing sludge compared with prior art has following beneficial effect.
1, wet mud is first made dewatered sludge particle owing to have employed by the technical program, then is gasified by dewatered sludge particle, then, decomposing furnace is sent in the combustion gas obtained after gasification, the lime-ash obtained after gasification is sent into the technique means of Raw Material System, so, greatly can improve the disposal scale of mud; Decrease solid sludges and directly enter difference between its form of kiln and coal dust, cement raw material fineness, add mass-and heat-transfer effect; Tangentially enter cement kiln decomposition furnace system by combustion gas, solid sludges can be avoided directly to enter kiln burning insufficient and cause the problem of sinter leaching quality; Because lime-ash burn-off rate is high, be rich in the elements such as silico-calcium, send into cement kiln Raw Material System, can be used as cement kiln raw meal proportioning, solve lime-ash problem of outlet.
2, the technical program is first by adding mineral substance in the wet mud of Sewage Plant or water drain owing to have employed described dewatered sludge particle of being made by wet mud, moisture in wet mud is reduced to 40-50%, again the mud after reduction moisture is made wet mud granule, then, wet mud granule ventilation mummification is formed the technique means of dewatered sludge particle, so, the moisture in mud can be reduced, be conducive to the transport to mud, improve the calorific value of mud, for the disposal amount improving mud creates favourable condition, enhance the adaptability of cement kiln to sludge disposal; By sewage plant sludge is mixed preliminary precipitation and drying particles precipitation with additive, reach low cost precipitation, the cement kiln achieving dewatered sludge is disposed; Because mud with the addition of the additive such as mineral substance, biomass, both reduce moisture and also inhibits foul smell, decrease deodoration system investment.
3, moisture in wet mud is describedly reduced to 40-50% owing to have employed and carries out in mud mixing machine by the technical program, described wet mud is squeezed in described mud mixing machine by sludge pump, described mineral substance is flyash and/or unslaked lime, described mineral substance adds in described mud mixing machine by mineral substance measuring apparatus, describedly make wet mud granule realized reducing the mud after moisture by sludge granulator, describedly send into described sludge granulator by reducing the mud after moisture by rotary conveyor, described wet mud granule ventilation mummification to be realized by mud granule drying device, described wet mud granule sends into described mud granule drying device by forklift, the moisture content of described dewatered sludge particle is 20-30%, described dewatered sludge particle is transported to the technique means in the dewatered sludge particulate material storehouse in cement mill by dewatered sludge particulate transportation car, so, substantially reduce the investment of equipment, be conducive to applying by cement kiln disposing sludge method.
4, the technical program is garbage waste materials owing to have employed described biomass, described biomass are the technique means of being added to by biomass measuring apparatus in described mud mixing machine, so, the cost of sludge pretreatment can be greatly reduced, increase the calorific value of mud further.
5, the technical program due to have employed described by dewatered sludge particle gasification carry out in dewatered sludge particle vapourizing furnace, described dewatered sludge particle sends into dewatered sludge particle vapourizing furnace by dewatered sludge particle transport system, described combustion gas sends into decomposing furnace by pipeline, described lime-ash sends into the technique means of Raw Material System by dreg removing system, so, not only make the whole resource utilization of mud, and, flow process is simple, and disposal amount is large.
6, the technical program sends into decomposing furnace owing to have employed described combustion gas when temperature is more than or equal to 900 DEG C, temperature in cement kiln is more than or equal to the technique means of 1450 DEG C, so, complete harmlessness disposing can be realized, can thoroughly eliminate the objectionable impurities such as Dioxins, furans, and these objectionable impuritiess there will not be the hidden danger of regeneration; Significantly can reduce the acid gas emissions such as cement kiln oxynitride oxysulfide; Realize waste zero release, cement kiln does not produce flying dust and slag, does not have the problem of secondary pollution.
With regard to system, in order to solve another above-mentioned technical problem, sludge gasification quality coal in cement kiln systems of the present utility model, comprise cement kiln Sum decomposition stove, the import of described cement kiln and the outlet of described decomposing furnace, the inlet mouth of described decomposing furnace is communicated with by gas pipeline with the air outlet of dewatered sludge particle vapourizing furnace, the opening for feed of described dewatered sludge particle vapourizing furnace is communicated with dewatered sludge particulate material storehouse by dewatered sludge particle transport system, and the slag notch of described dewatered sludge particle vapourizing furnace is communicated with Raw Material System by dreg removing system.
Described dewatered sludge particle vapourizing furnace is vertical fixing vapourizing furnace, the air outlet of described mud granule vapourizing furnace is arranged on the top in face, described vertical fixing gasification furnace side, the opening for feed of described dewatered sludge particle vapourizing furnace is arranged on the central authorities of described vertical fixing gasification furnace top surface, the ash output hole of described dewatered sludge particle vapourizing furnace is arranged on the central authorities in described vertical fixing gasification furnace bottom face, described gas pipeline is configured with baffle door, described dewatered sludge particle transport system comprises grab mechanisms, stepped start-stop system feeding machine and the double roll feeding machine with frequency transformer, the discharge port of described double roll feeding machine is positioned at the top of the opening for feed of described dewatered sludge particle vapourizing furnace down, the opening for feed of described double roll feeding machine upward, the discharge port of described stepped start-stop system feeding machine is positioned at the top of described double roll feeding machine inlet capable down, the opening for feed of described stepped start-stop system feeding machine is positioned at described dewatered sludge particulate material storehouse upward, described grab mechanisms is arranged in described dewatered sludge particulate material storehouse, the blanking position of described grab mechanisms is positioned at the top of described stepped start-stop system feeding machine opening for feed, described dreg removing system comprises Residue extraction pipeline, slag notch near described dewatered sludge particle vapourizing furnace on described Residue extraction pipeline is provided with mucking machine.
Described sludge gasification quality coal in cement kiln systems also comprises the mud mixing machine, sludge granulator and the mud granule drying device that are arranged on Sewage Plant; described mud mixing machine is configured with sludge pump and mineral substance measuring apparatus; rotary conveyor is configured with between described mud mixing machine and described sludge granulator; be configured with forklift between described sludge granulator and described mud granule drying device, between described Sewage Plant and cement mill, be configured with dewatered sludge particulate transportation car.
Described mud granule drying device comprises the barrier of rectangle, is provided with multiple stage blower fan below the barrier of described rectangle.
Sludge gasification quality coal in cement kiln systems of the present utility model compared with prior art has following beneficial effect.
1, the technical program is communicated with by gas pipeline with the air outlet of dewatered sludge particle vapourizing furnace due to the inlet mouth that have employed described decomposing furnace, the opening for feed of described dewatered sludge particle vapourizing furnace is communicated with dewatered sludge particulate material storehouse by dewatered sludge particle transport system, the technique means that the slag notch of described dewatered sludge particle vapourizing furnace is communicated with Raw Material System by dreg removing system, so, greatly can improve the disposal scale of mud; Decrease solid sludges and directly enter difference between its form of kiln and coal dust, cement raw material fineness, add mass-and heat-transfer effect; Tangentially enter cement kiln decomposition furnace system by combustion gas, solid sludges can be avoided directly to enter kiln burning insufficient and cause the problem of sinter leaching quality; Because lime-ash burn-off rate is high, be rich in the elements such as silico-calcium, send into cement kiln Raw Material System, can be used as cement kiln raw meal proportioning, solve lime-ash problem of outlet.
2, the technical program is vertical fixing vapourizing furnace owing to have employed described dewatered sludge particle vapourizing furnace, the air outlet of described mud granule vapourizing furnace is arranged on the top in face, described vertical fixing gasification furnace side, the opening for feed of described dewatered sludge particle vapourizing furnace is arranged on the central authorities of described vertical fixing gasification furnace top surface, the ash output hole of described dewatered sludge particle vapourizing furnace is arranged on the central authorities in described vertical fixing gasification furnace bottom face, described gas pipeline is configured with baffle door, described dewatered sludge particle transport system comprises grab mechanisms, stepped start-stop system feeding machine and the double roll feeding machine with frequency transformer, the discharge port of described double roll feeding machine is positioned at the top of the opening for feed of described dewatered sludge particle vapourizing furnace down, the opening for feed of described double roll feeding machine upward, the discharge port of described stepped start-stop system feeding machine is positioned at the top of described double roll feeding machine inlet capable down, the opening for feed of described stepped start-stop system feeding machine is positioned at described dewatered sludge particulate material storehouse upward, described grab mechanisms is arranged in described dewatered sludge particulate material storehouse, the blanking position of described grab mechanisms is positioned at the top of described stepped start-stop system feeding machine opening for feed, described dreg removing system comprises Residue extraction pipeline, described Residue extraction pipeline is provided with the technique means of mucking machine near the slag notch of described dewatered sludge particle vapourizing furnace, so, equipment is simple, the low cost of manufacture of equipment, feeding is even, ensure the burning quality of mud.
3, the technical program also comprises owing to have employed described sludge gasification quality coal in cement kiln systems the mud mixing machine being arranged on Sewage Plant, sludge granulator and mud granule drying device, described mud mixing machine is configured with sludge pump and mineral substance measuring apparatus, rotary conveyor is configured with between described mud mixing machine and described sludge granulator, forklift is configured with between described sludge granulator and described mud granule drying device, the technique means of dewatered sludge particulate transportation car is configured with between described Sewage Plant and cement mill, so, not only can reduce the manufacturing cost of equipment widely, and, greatly reduce the transportation cost of mud.
4, the technical program comprises the barrier of rectangle owing to have employed described mud granule drying device, the technique means of multiple stage blower fan is provided with below the barrier of described rectangle, so, the structure of mud granule drying device is simple, reduce further the manufacturing cost of mud granule drying device, improve the mummification efficiency of mud granule.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the method for the utility model cement kiln disposing sludge and sludge gasification quality coal in cement kiln systems are described in further detail.
Fig. 1 is the method schematic diagram of the utility model cement kiln disposing sludge.
Fig. 2 is sludge gasification quality coal in cement kiln systems schematic diagram of the present utility model.
Embodiment
As depicted in figs. 1 and 2, the method of present embodiment cement kiln disposing sludge first wet mud is made dewatered sludge particle, then gasified by dewatered sludge particle, then, decomposing furnace 2 is sent in the combustion gas obtained after gasification, the lime-ash obtained after gasification is sent into Raw Material System 11.Preferred as one, described dewatered sludge particle gasification is degassing of heat another part dewatered sludge particle by being produced by a part of dewatered sludge particle burning thus generation combustion gas.Greatly can save the consumption of the energy like this.
Wet mud is first made dewatered sludge particle owing to have employed by present embodiment, then is gasified by dewatered sludge particle, then, decomposing furnace is sent in the combustion gas obtained after gasification, the lime-ash obtained after gasification is sent into the technique means of Raw Material System, so, greatly can improve the disposal scale of mud; Decrease solid sludges and directly enter difference between its form of kiln and coal dust, cement raw material fineness, add mass-and heat-transfer effect; Tangentially enter cement kiln decomposition furnace system by combustion gas, solid sludges can be avoided directly to enter kiln burning insufficient and cause the problem of sinter leaching quality; Because lime-ash burn-off rate is high, be rich in the elements such as silico-calcium, send into cement kiln Raw Material System, can be used as cement kiln raw meal proportioning, solve lime-ash problem of outlet.
One as present embodiment is improved, as depicted in figs. 1 and 2, described dewatered sludge particle of being made by wet mud is first by adding mineral substance and/or biomass in the wet mud of Sewage Plant A or water drain, moisture in wet mud is reduced to 40-50%, again the mud after reduction moisture is made wet mud granule, then, mud granule ventilation mummification of wetting forms dewatered sludge particle.
Present embodiment is first by adding mineral substance in the wet mud of Sewage Plant or water drain owing to have employed described dewatered sludge particle of being made by wet mud, moisture in wet mud is reduced to 40-50%, again the mud after reduction moisture is made wet mud granule, then, wet mud granule ventilation mummification is formed the technique means of dewatered sludge particle, so, the moisture in mud can be reduced, be conducive to the transport to mud, improve the calorific value of mud, for the disposal amount improving mud creates favourable condition, enhance the adaptability of cement kiln to sludge disposal; By sewage plant sludge is mixed preliminary precipitation and drying particles precipitation with additive, reach low cost precipitation, the cement kiln achieving dewatered sludge is disposed; Because mud with the addition of the additive such as mineral substance, biomass, both reduce moisture and also inhibits foul smell, decrease deodoration system investment.
Further improve as present embodiment, as depicted in figs. 1 and 2, describedly moisture in wet mud is reduced to 40-50% carries out in mud mixing machine 12, described wet mud is squeezed in described mud mixing machine 12 by sludge pump 13, described mineral substance is flyash and/or unslaked lime, described mineral substance adds in described mud mixing machine 12 by mineral substance measuring apparatus 14, describedly make wet mud granule realized reducing the mud after moisture by sludge granulator 17, describedly send into described sludge granulator 17 by reducing the mud after moisture by rotary conveyor 16, described wet mud granule ventilation mummification to be realized by mud granule drying device 19, described wet mud granule sends into described mud granule drying device 19 by forklift 18, the moisture content of described dewatered sludge particle is 20-30%, described dewatered sludge particle is transported in the dewatered sludge particulate material storehouse 21 of cement mill B by dewatered sludge particulate transportation car 20.
Moisture in wet mud is describedly reduced to 40-50% owing to have employed and carries out in mud mixing machine by present embodiment, described wet mud is squeezed in described mud mixing machine by sludge pump, described mineral substance is flyash and/or unslaked lime, described mineral substance adds in described mud mixing machine by mineral substance measuring apparatus, describedly make wet mud granule realized reducing the mud after moisture by sludge granulator, describedly send into described sludge granulator by reducing the mud after moisture by rotary conveyor, described wet mud granule ventilation mummification to be realized by mud granule drying device, described wet mud granule sends into described mud granule drying device by forklift, the moisture content of described dewatered sludge particle is 20-30%, described dewatered sludge particle is transported to the technique means in the dewatered sludge particulate material storehouse in cement mill by dewatered sludge particulate transportation car, so, substantially reduce the investment of equipment, be conducive to applying by cement kiln disposing sludge method.
Further improve as present embodiment, as depicted in figs. 1 and 2, described biomass are garbage waste materials, and described biomass are added in described mud mixing machine 12 by biomass measuring apparatus 15.
Present embodiment is garbage waste materials owing to have employed described biomass, described biomass are the technique means of being added to by biomass measuring apparatus in described mud mixing machine, so, the cost of sludge pretreatment can be greatly reduced, increase the calorific value of mud further.
Further improve as present embodiment, as depicted in figs. 1 and 2, described gasification by dewatered sludge particle carries out in dewatered sludge particle vapourizing furnace 3, described dewatered sludge particle sends into dewatered sludge particle vapourizing furnace 3 by dewatered sludge particle transport system 4,5,6, described combustion gas sends into decomposing furnace 2 by pipeline 7, and described lime-ash sends into Raw Material System 11 by dreg removing system 9,10.
Present embodiment due to have employed described by dewatered sludge particle gasification carry out in dewatered sludge particle vapourizing furnace, described dewatered sludge particle sends into dewatered sludge particle vapourizing furnace by dewatered sludge particle transport system, described combustion gas sends into decomposing furnace by pipeline, described lime-ash sends into the technique means of Raw Material System by dreg removing system, so, not only make the whole resource utilization of mud, and, flow process is simple, and disposal amount is large.
Further improve as present embodiment, as depicted in figs. 1 and 2, described combustion gas sends into decomposing furnace when temperature is more than or equal to 900 DEG C, and the temperature in cement kiln is more than or equal to 1450 DEG C.
Present embodiment sends into decomposing furnace owing to have employed described combustion gas when temperature is more than or equal to 900 DEG C, temperature in cement kiln is more than or equal to the technique means of 1450 DEG C, so, complete harmlessness disposing can be realized, can thoroughly eliminate the objectionable impurities such as Dioxins, furans, and these objectionable impuritiess there will not be the hidden danger of regeneration; Significantly can reduce the acid gas emissions such as cement kiln oxynitride oxysulfide; Realize waste zero release, cement kiln does not produce flying dust and slag, does not have the problem of secondary pollution.
As shown in Figure 2, sludge gasification quality coal in cement kiln systems of the present utility model, comprise cement kiln 1 Sum decomposition stove 2, the import of described cement kiln 1 and the outlet of described decomposing furnace 2, the inlet mouth of described decomposing furnace 2 is communicated with by gas pipeline 7 with the air outlet of dewatered sludge particle vapourizing furnace 3, the opening for feed of described dewatered sludge particle vapourizing furnace 3 is communicated with dewatered sludge particulate material storehouse 21 by dewatered sludge particle transport system 4,5,6, and the slag notch of described dewatered sludge particle vapourizing furnace 3 is communicated with Raw Material System 11 by dreg removing system 9,10.
Present embodiment is communicated with by gas pipeline with the air outlet of dewatered sludge particle vapourizing furnace due to the inlet mouth that have employed described decomposing furnace, the opening for feed of described dewatered sludge particle vapourizing furnace is communicated with dewatered sludge particulate material storehouse by dewatered sludge particle transport system, the technique means that the slag notch of described dewatered sludge particle vapourizing furnace is communicated with Raw Material System by dreg removing system, so, greatly can improve the disposal scale of mud; Decrease solid sludges and directly enter difference between its form of kiln and coal dust, cement raw material fineness, add mass-and heat-transfer effect; Tangentially enter cement kiln decomposition furnace system by combustion gas, solid sludges can be avoided directly to enter kiln burning insufficient and cause the problem of sinter leaching quality; Because lime-ash burn-off rate is high, be rich in the elements such as silico-calcium, send into cement kiln Raw Material System, can be used as cement kiln raw meal proportioning, solve lime-ash problem of outlet.
One as present embodiment is improved, as shown in Figure 2, described dewatered sludge particle vapourizing furnace 3 is vertical fixing vapourizing furnaces, the air outlet of described mud granule vapourizing furnace 3 is arranged on the top in face, described vertical fixing gasification furnace side, the opening for feed of described dewatered sludge particle vapourizing furnace 3 is arranged on the central authorities of described vertical fixing gasification furnace top surface, the ash output hole of described dewatered sludge particle vapourizing furnace 3 is arranged on the central authorities in described vertical fixing gasification furnace bottom face, described gas pipeline 7 is configured with baffle door 8, described dewatered sludge particle transport system 4, 5, 6 comprise grab mechanisms 4, stepped start-stop system feeding machine 5 and the double roll feeding machine 6 with frequency transformer, the discharge port of described double roll feeding machine 6 is positioned at the top of the opening for feed of described dewatered sludge particle vapourizing furnace 3 down, the opening for feed of described double roll feeding machine 6 upward, the discharge port of described stepped start-stop system feeding machine 5 is positioned at the top of described double roll feeding machine 6 opening for feed down, the opening for feed of described stepped start-stop system feeding machine 5 is positioned at described dewatered sludge particulate material storehouse 21 upward, described grab mechanisms 4 is arranged in described dewatered sludge particulate material storehouse 21, the blanking position of described grab mechanisms 4 is positioned at the top of described stepped start-stop system feeding machine 5 opening for feed, described dreg removing system 9, 10 comprise Residue extraction pipeline 9, slag notch near described dewatered sludge particle vapourizing furnace 3 on described Residue extraction pipeline 9 is provided with mucking machine 10.Preferred as one, bottom in described dewatered sludge particle vapourizing furnace 3 is provided with comb formula supporting disk, the central authorities of described comb formula supporting disk 3-1 are fixed with supporter 3-2, the central authorities of described supporter 3-2 are provided with axis hole, rotation axis 3-3 is provided with in described axis hole, the top of described rotation axis is fixed with tower ash-pan 3-4, described tower ash-pan 3-4 is made up of the circular fire grate of the different size of multilayer, fire grate described in multilayer is fixed on the top of described rotation axis according to order from big to small from top to bottom, with vertical shape cast iron 3-10 above every layer of described fire grate, bevel gear wheel dish 3-5 is circumferentially provided with below nethermost large fire grate, described bevel gear wheel dish 3-5 is furnished with bevel pinion 3-6, described bevel pinion 3-6 is fixed with transmission shaft 3-7, described transmission shaft 3-7 passes the sidewall of described dewatered sludge particle vapourizing furnace 3 and is fixedly connected with the rotation axis of electric motor 3-8, described electric motor 3-8 is fixed on the support 3-9 of described dewatered sludge particle vapourizing furnace 3.Lime-ash can be made like this to fall to the slag notch of described dewatered sludge particle vapourizing furnace 3 along the edge of tower ash-pan 3-4.Described slag notch is provided with vaporized chemical input unit 23, and described vaporized chemical is air, and described vaporized chemical input unit 23 is blower fans.Gasification efficiency can be improved like this.
Present embodiment is vertical fixing vapourizing furnace owing to have employed described dewatered sludge particle vapourizing furnace, the air outlet of described mud granule vapourizing furnace is arranged on the top in face, described vertical fixing gasification furnace side, the opening for feed of described dewatered sludge particle vapourizing furnace is arranged on the central authorities of described vertical fixing gasification furnace top surface, the ash output hole of described dewatered sludge particle vapourizing furnace is arranged on the central authorities in described vertical fixing gasification furnace bottom face, described gas pipeline is configured with baffle door, described dewatered sludge particle transport system comprises grab mechanisms, stepped start-stop system feeding machine and the double roll feeding machine with frequency transformer, the discharge port of described double roll feeding machine is positioned at the top of the opening for feed of described dewatered sludge particle vapourizing furnace down, the opening for feed of described double roll feeding machine upward, the discharge port of described stepped start-stop system feeding machine is positioned at the top of described double roll feeding machine inlet capable down, the opening for feed of described stepped start-stop system feeding machine is positioned at described dewatered sludge particulate material storehouse upward, described grab mechanisms is arranged in described dewatered sludge particulate material storehouse, the blanking position of described grab mechanisms is positioned at the top of described stepped start-stop system feeding machine opening for feed, described dreg removing system comprises Residue extraction pipeline, described Residue extraction pipeline is provided with the technique means of mucking machine near the slag notch of described dewatered sludge particle vapourizing furnace, so, equipment is simple, the low cost of manufacture of equipment, feeding is even, ensure the burning quality of mud.
Further improve as present embodiment; as shown in Figure 2; described sludge gasification quality coal in cement kiln systems also comprises the sludge sump 22 being arranged on Sewage Plant A; mud mixing machine 12, sludge granulator 17 and mud granule drying device 19; described mud mixing machine 12 is configured with sludge pump 13 and mineral substance measuring apparatus 14, and described mineral substance measuring apparatus 14 also can be used for biomass measuring apparatus.Certainly, also can be that described mud mixing machine 12 is separately configured with biomass measuring apparatus 15.Rotary conveyor 16 is configured with between described mud mixing machine 12 and described sludge granulator 17; be configured with forklift 18 between described sludge granulator 17 and described mud granule drying device 19, between described Sewage Plant A and cement mill B, be configured with dewatered sludge particulate transportation car 20.
Present embodiment also comprises owing to have employed described sludge gasification quality coal in cement kiln systems the mud mixing machine being arranged on Sewage Plant, sludge granulator and mud granule drying device, described mud mixing machine is configured with sludge pump and mineral substance measuring apparatus, rotary conveyor is configured with between described mud mixing machine and described sludge granulator, forklift is configured with between described sludge granulator and described mud granule drying device, the technique means of dewatered sludge particulate transportation car is configured with between described Sewage Plant and cement mill, so, not only can reduce the manufacturing cost of equipment widely, and, greatly reduce the transportation cost of mud.
Further improve as present embodiment, as shown in Figure 2, described mud granule drying device 19 comprises the barrier 19-1 of rectangle, is provided with multiple stage blower fan 19-2 below the barrier 19-1 of described rectangle.
Present embodiment comprises the barrier of rectangle owing to have employed described mud granule drying device, the technique means of multiple stage blower fan is provided with below the barrier of described rectangle, so, the structure of mud granule drying device is simple, reduce further the manufacturing cost of mud granule drying device, improve the mummification efficiency of mud granule.

Claims (2)

1. a sludge gasification quality coal in cement kiln systems, comprise cement kiln Sum decomposition stove, the import of described cement kiln and the outlet of described decomposing furnace, it is characterized in that: the inlet mouth of described decomposing furnace is communicated with by gas pipeline with the air outlet of dewatered sludge particle vapourizing furnace, the opening for feed of described dewatered sludge particle vapourizing furnace is communicated with dewatered sludge particulate material storehouse by dewatered sludge particle transport system, and the slag notch of described dewatered sludge particle vapourizing furnace is communicated with Raw Material System by dreg removing system.
2. sludge gasification quality coal in cement kiln systems according to claim 1, it is characterized in that: described dewatered sludge particle vapourizing furnace is vertical fixing vapourizing furnace, the air outlet of described mud granule vapourizing furnace is arranged on the top in face, described vertical fixing gasification furnace side, the opening for feed of described dewatered sludge particle vapourizing furnace is arranged on the central authorities of described vertical fixing gasification furnace top surface, the ash output hole of described dewatered sludge particle vapourizing furnace is arranged on the central authorities in described vertical fixing gasification furnace bottom face, described gas pipeline is configured with baffle door, described dewatered sludge particle transport system comprises grab mechanisms, stepped start-stop system feeding machine and the double roll feeding machine with frequency transformer, the discharge port of described double roll feeding machine is positioned at the top of the opening for feed of described dewatered sludge particle vapourizing furnace down, the opening for feed of described double roll feeding machine upward, the discharge port of described stepped start-stop system feeding machine is positioned at the top of described double roll feeding machine inlet capable down, the opening for feed of described stepped start-stop system feeding machine is positioned at described dewatered sludge particulate material storehouse upward, described grab mechanisms is arranged in described dewatered sludge particulate material storehouse, the blanking position of described grab mechanisms is positioned at the top of described stepped start-stop system feeding machine opening for feed, described dreg removing system comprises Residue extraction pipeline, slag notch near described dewatered sludge particle vapourizing furnace on described Residue extraction pipeline is provided with mucking machine.
CN201420808485.2U 2014-12-19 2014-12-19 A kind of sludge gasification quality coal in cement kiln systems Active CN204454844U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420808485.2U CN204454844U (en) 2014-12-19 2014-12-19 A kind of sludge gasification quality coal in cement kiln systems

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420808485.2U CN204454844U (en) 2014-12-19 2014-12-19 A kind of sludge gasification quality coal in cement kiln systems

Publications (1)

Publication Number Publication Date
CN204454844U true CN204454844U (en) 2015-07-08

Family

ID=53661757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420808485.2U Active CN204454844U (en) 2014-12-19 2014-12-19 A kind of sludge gasification quality coal in cement kiln systems

Country Status (1)

Country Link
CN (1) CN204454844U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104496135A (en) * 2014-12-19 2015-04-08 北京金隅股份有限公司 Method for treating sludge by using cement kiln, and sludge gasifying cement kiln system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104496135A (en) * 2014-12-19 2015-04-08 北京金隅股份有限公司 Method for treating sludge by using cement kiln, and sludge gasifying cement kiln system

Similar Documents

Publication Publication Date Title
CN102070308B (en) Device technology configuration method for treating house refuses by using rotary cement kiln
CN103896505B (en) A kind of method of feeding mode regulation and control of cement kiln synergic processing lime mummification municipal sludge
CN103934254B (en) A kind of system and method for cement kiln associated treatment domestic waste
CN102875003B (en) Integrated technology of thermal decomposing, dry distilling and gasifying sludge and preparing of ceramsite
CN101962590B (en) Regenerative coal produced by multiple kinds of oily sludge in oil refinery and preparation method thereof
CN101993181B (en) Method for dehydration and recycling of continuous dyeing sludge
CN201990601U (en) System capable of cooperatively treating domestic garbage with cement clinker production line
CN203530270U (en) Refuse derived fuel production system based on bio-drying
CN107339702B (en) Method for cooperatively treating urban and rural domestic garbage by using cement kiln
CN101723570B (en) Sludge treatment method for drying sludge by using coal grinding machine and using sludge for electricity generation
CN203513455U (en) Sludge drying and incineration system
CN105757677A (en) Intelligent garbage treatment system with multiple gas circulation function
CN101618954A (en) Process system for processing municipal domestic waste by cement rotary kiln
CN105733734A (en) Method and device for preparing fuel by means of mixing coke powder with sludge from sewage plants
CN113182313A (en) Multi-source organic solid waste disposal system and method for recycling pollutants
CN109181807A (en) A kind of preparation method of sewage sludge biomass environment-friendly fuel
CN107639100A (en) A kind of rubbish and red mud coprocessing system and method
CN204454844U (en) A kind of sludge gasification quality coal in cement kiln systems
CN204356237U (en) With the quality coal in cement kiln systems of grate-cooler disposing sludge
CN210035511U (en) System for generating power by drying and granulating sludge and incinerating garbage in cooperation in grate furnace
CN217677230U (en) Cement kiln cooperative disposal system for crushing, coupling, distributing and feeding large-volume dried sludge into furnace
CN204356208U (en) A kind of quality coal in cement kiln systems of disposing sludge
CN203582743U (en) Three-way kiln inlet treatment device for cement kiln household garbage
CN104496135A (en) Method for treating sludge by using cement kiln, and sludge gasifying cement kiln system
CN102140003A (en) Sludge drying method, incineration method, sludge incineration device, thermal power plant and system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant