CN204435438U - The steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top - Google Patents

The steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top Download PDF

Info

Publication number
CN204435438U
CN204435438U CN201520003350.3U CN201520003350U CN204435438U CN 204435438 U CN204435438 U CN 204435438U CN 201520003350 U CN201520003350 U CN 201520003350U CN 204435438 U CN204435438 U CN 204435438U
Authority
CN
China
Prior art keywords
steel
jacket box
cushion cap
loading test
secondary load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520003350.3U
Other languages
Chinese (zh)
Inventor
黄明
邓涛
关振长
许少平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Fuzhou Survey & Design Institute Co Ltd
Fuzhou University
Third Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd
Original Assignee
Fuzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou University filed Critical Fuzhou University
Priority to CN201520003350.3U priority Critical patent/CN204435438U/en
Application granted granted Critical
Publication of CN204435438U publication Critical patent/CN204435438U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)

Abstract

The utility model relates to the steel jacket box of secondary load in the vertical accumulated loading test in a kind of cushion cap top, it is characterized in that: the mutual bolt of prefabricated standard steel plate that four side panels of described steel jacket box are vertically arranged by polylith forms, described prefabricated standard steel plate comprises steel frame and is welded on the steel plate of its lateral surface.This steel jacket box well can reduce the height of preloading, ensures the safety of preloading process; Simultaneously its working procedure and material requested less, splicing is convenient, greatly provides cost savings, the vertical preloading of cushion cap can be carried out smoothly under more convenient, economic, safe condition.

Description

The steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top
Technical field
The utility model relates to the steel jacket box of secondary load in the vertical accumulated loading test in a kind of cushion cap top.
Background technology
In the vertical accumulated loading test in cushion cap top, when constantly loading, traditional way directly the load such as sandstone, fragment of brick, stone is directly placed on cushion cap, in order to avoid sandstone, fragment of brick, stone etc. drop from cushion cap, during loading, general by those load concentration at cushion cap center, preloading aspect ratio is higher, and on-the-spot danger is higher; Even at the surrounding welding ordinary steel casing of cushion cap, the intensity of those steel jacket boxes is lower, easy spreading, and recombination fraction is high, and operating efficiency is low, and safety is low.
Utility model content
The utility model makes improvement for above-mentioned prior art Problems existing, provides that a kind of structure is simple, the steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top that ensures preloading process safety.
In order to solve the problems of the technologies described above, the technical solution of the utility model is:
The steel jacket box of secondary load in the vertical accumulated loading test in the utility model cushion cap top, it is characterized in that: the mutual bolt of prefabricated standard steel plate that four side panels of described steel jacket box are vertically arranged by polylith forms, described prefabricated standard steel plate comprises steel frame and is welded on the steel plate of its lateral surface.
Further, the high 3.5m of above-mentioned prefabricated standard steel plate, wide 1.5m, the thick 8mm of steel plate.
Further, above-mentioned steel frame is welded into " day " font by angle steel.
Further, the long limit, both sides of above-mentioned steel frame offers several bolts hole respectively, and two adjacent bolt hole spacing are 0.5m, and topmost bolt hole and steel frame top end face, foot bolt hole and steel frame bottom face are all at a distance of 0.25m.
Further, longitudinal Screw arbor with nut at both-ends is being arranged near the bottom of described steel jacket box and horizontal, the vertical horizontal Screw arbor with nut at both-ends of a row and that is fixedly connected with of center.
Further, often arrange Screw arbor with nut at both-ends and comprise three Screw arbor with nut at both-ends, often arrange Screw arbor with nut at both-ends and be positioned at same plane.
Further, all horizontal support channel-section steel had for preventing Screw arbor with nut at both-ends from steel plate drawn distortion along steel jacket box outer circumferential side and in the end of same row's screw rod.
Compared with prior art, the utility model has following beneficial effect: this steel jacket box well can reduce the height of preloading, ensures the safety of preloading process; Simultaneously its working procedure and material requested less, splicing is convenient, greatly provides cost savings, the vertical preloading of cushion cap can be carried out smoothly under more convenient, economic, safe condition.
Below in conjunction with the drawings and specific embodiments, the utility model is described in more detail.
Accompanying drawing explanation
Fig. 1 is the organigram of the utility model embodiment;
Fig. 2 is the prefabricated standard steel plate schematic top plan view of the utility model embodiment;
Fig. 3 is the prefabricated standard steel plate schematic side view of the utility model embodiment;
Fig. 4 is the schematic top plan view of the utility model embodiment;
Fig. 5 is the schematic side view of the utility model embodiment.
In figure: the prefabricated standard steel plate of 1-, 11-steel frame, 111-bolt hole, 12-steel plate, 21-Screw arbor with nut at both-ends, the horizontal Screw arbor with nut at both-ends of 211-, the longitudinal Screw arbor with nut at both-ends of 212-, 3-supports channel-section steel, 4-cushion cap, 5-base plate.
Detailed description of the invention
As shown in Fig. 1 ~ 5, the utility model is used for the steel jacket box of secondary load in the vertical accumulated loading test in cushion cap 4 top, comprise 24 blocks of prefabricated standard steel plates 1, each side panel of described steel jacket box forms by the mutual bolt of six blocks of prefabricated standard steel plates 1, described steel jacket box is rectangular, and described prefabricated standard steel plate 1 comprises the steel frame 11 in " day " font and is welded on the steel plate 12 of steel frame 11 lateral surface, and described steel plate 12 is long is 3.5m, wide is 1.5m, and thick is 8mm; Described steel frame 11 adopts 80 angle steel to be welded, and the described steel frame 11 in " day " font considerably increases the intensity of steel jacket box; The length of described steel jacket box entirety is 3.5m, and wide is 1.5m.
In the present embodiment, the long limit, steel frame 11 both sides of described prefabricated standard steel plate 1 is respectively equipped with seven bolts hole 111, two adjacent bolt hole 111 spacing are 0.5m, and topmost bolt hole 111 and steel frame 11 top end face, foot bolt hole 111 and steel frame 11 bottom face are all at a distance of 0.25m.
In the present embodiment, near the bottom of described steel jacket box with center is horizontal, vertical is fixedly connected with the horizontal Screw arbor with nut at both-ends 211 of a row and the longitudinal Screw arbor with nut at both-ends 212 of a row, described Screw arbor with nut at both-ends 21 adopts diameter to be the reinforcing bar of 20mm.
Screw arbor with nut at both-ends can either destroy for preventing it from spreading occurring in loading procedure, can not affect again hanging of sandstone and send.
In the present embodiment, because Screw arbor with nut at both-ends 21 runs through steel jacket box and steel plate 12 is thinner, the all horizontal reinforcement channel-section steel 3 had for preventing Screw arbor with nut at both-ends 21 from steel plate 12 drawn distortion along steel jacket box outer circumferential side and in the end of Screw arbor with nut at both-ends 21, also arrive, long No. 18 channel-section steels for 9m are added as support to prevent Screw arbor with nut at both-ends 21 from steel plate 12 is drawn distortion in the end of often arranging Screw arbor with nut at both-ends 21, described reinforcement channel-section steel 3 is arranged along steel jacket box side outer Thursday, bottom and middle part four roads respectively, totally eight roads, that is, channel-section steel 3 is strengthened by steel bushing case band jail in eight roads, certainly, the quantity strengthening channel-section steel 3 suitably can be increased according to operating mode.
Use procedure of the present utility model is as follows: after processing pre-buried steel component, bury pre-buried steel component and cushion cap 4 underground to construct and synchronously carry out, then welding supports channel-section steel and base plate 5, and then some blocks of prefabricated standard steel plates 1 are assembled into steel jacket box, two contiguous prefabricated standard steel plates 1 are mutually permanently connected through bolt, weld with base plate 5 bottom described steel jacket box, that is, lower surface bottom the steel frame 11 of 24 blocks of prefabricated standard steel plates 1 to be welded with base plate 5 or through bolted-on, then horizontal Screw arbor with nut at both-ends 211 and longitudinal Screw arbor with nut at both-ends 212 is set up respectively in the bottom of steel jacket box and center, and strengthen channel-section steel 3 at the exposed welding edges at steel jacket box outer circumferential side of Screw arbor with nut at both-ends, finally carry out the hierarchical loading of process of the test.
The foregoing is only preferred embodiment of the present utility model, all equalizations done according to the utility model claim change and modify, and all should belong to covering scope of the present utility model.

Claims (7)

1. the steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top, it is characterized in that: the mutual bolt of prefabricated standard steel plate that four side panels of described steel jacket box are vertically arranged by polylith forms, described prefabricated standard steel plate comprises steel frame and is welded on the steel plate of its lateral surface.
2. the steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top according to claim 1, is characterized in that: the high 3.5m of described prefabricated standard steel plate, wide 1.5m, the thick 8mm of steel plate.
3. the steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top according to claim 1, is characterized in that: described steel frame is welded into " day " font by angle steel.
4. the steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top according to claim 1 or 2, it is characterized in that: the long limit, both sides of described steel frame offers several bolts hole respectively, two adjacent bolt hole spacing are 0.5m, and topmost bolt hole and steel frame top end face, foot bolt hole and steel frame bottom face are all at a distance of 0.25m.
5. the steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top according to claim 1, is characterized in that: near the bottom of described steel jacket box with center is horizontal, vertical is fixedly connected with the horizontal Screw arbor with nut at both-ends of a row and the longitudinal Screw arbor with nut at both-ends of a row.
6. the steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top according to claim 5, is characterized in that: often arrange Screw arbor with nut at both-ends and comprise three Screw arbor with nut at both-ends, often arranges Screw arbor with nut at both-ends and be positioned at same plane.
7. the steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top according to claim 5, is characterized in that: all horizontal support channel-section steel had for preventing Screw arbor with nut at both-ends from steel plate drawn distortion along steel jacket box outer circumferential side and in the end of same row's screw rod.
CN201520003350.3U 2015-01-05 2015-01-05 The steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top Active CN204435438U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520003350.3U CN204435438U (en) 2015-01-05 2015-01-05 The steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520003350.3U CN204435438U (en) 2015-01-05 2015-01-05 The steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top

Publications (1)

Publication Number Publication Date
CN204435438U true CN204435438U (en) 2015-07-01

Family

ID=53603325

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520003350.3U Active CN204435438U (en) 2015-01-05 2015-01-05 The steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top

Country Status (1)

Country Link
CN (1) CN204435438U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108414686A (en) * 2018-02-06 2018-08-17 太原理工大学 A kind of experimental rig of vertical-lateral non-linear support stiffness of analog basis

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108414686A (en) * 2018-02-06 2018-08-17 太原理工大学 A kind of experimental rig of vertical-lateral non-linear support stiffness of analog basis
CN108414686B (en) * 2018-02-06 2020-06-09 太原理工大学 Test device for simulating longitudinal-transverse nonlinear supporting rigidity of foundation

Similar Documents

Publication Publication Date Title
CN103114681B (en) High-altitude long-span reinforced concrete beam treat pouring structure
CN204212070U (en) Can the inspection platform of way moving under uninterrupted traffic condition
CN207582665U (en) Assembled square steel tube concrete column
CN204387075U (en) Can assembled protective cap Sheet Steel Form
CN204435816U (en) Telescopic steel post operation platform
CN106948232A (en) Have enough to meet the need movable light-duty road surface
CN204435438U (en) The steel jacket box of secondary load in the vertical accumulated loading test in cushion cap top
CN204644878U (en) A kind of transom pier steel truss girder lifting construction device
CN202560079U (en) Instrumentalizing work site gate
CN204590599U (en) A kind of corner internal corner formwork for aluminum alloy mould plate system
CN203403681U (en) Temporary supporting frame of string beam
CN203247703U (en) Steel structural plant frame
CN203063982U (en) Conveying vehicle
CN202431000U (en) Horizontal supporting structure of building formwork
CN202807268U (en) Steel structure box body
CN205088575U (en) Top of tower constructional device is crossed to suspension bridge continuous type catwalk track cable
CN202483083U (en) Concrete split heads
CN102444283A (en) Lateral bracing structure of building formwork
CN202954574U (en) Non-side upright steel bar processing shed
CN204850247U (en) Stirrup connection structure of cross steel sheet
CN203462403U (en) Reinforced cast-in-situ box girder template
CN203924851U (en) The small-sized steel column of installing for overhead contact line
CN204728478U (en) A kind of for the angle steel anchor combination embedded part in reinforced concrete frame
CN203740268U (en) Novel split-scale plate end box structure
CN202577980U (en) Laminated tool type material stack frame unit and stack frames

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180404

Address after: Minhou County of Fuzhou City, Fujian province 350108 Street Town Road No. 2 University City School District of Fuzhou University

Co-patentee after: The No.3 Engineering., Ltd. of China Railway 22th Bureau Group

Patentee after: Fuzhou University

Co-patentee after: China Fuzhou Survey & Design Institute Co Ltd

Address before: Minhou County of Fuzhou City, Fujian province 350108 Street Town Road No. 2 University City School District of Fuzhou University

Patentee before: Fuzhou University

TR01 Transfer of patent right