CN204389074U - A kind of steel construction stress prior-warning device - Google Patents
A kind of steel construction stress prior-warning device Download PDFInfo
- Publication number
- CN204389074U CN204389074U CN201520112287.7U CN201520112287U CN204389074U CN 204389074 U CN204389074 U CN 204389074U CN 201520112287 U CN201520112287 U CN 201520112287U CN 204389074 U CN204389074 U CN 204389074U
- Authority
- CN
- China
- Prior art keywords
- base plate
- pressure
- lever
- pressure base
- contact piece
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
The utility model discloses a kind of steel construction stress prior-warning device, it is characterized in that the triangle place of three corner steadies is evenly placed in bottom bearing plate, connecting hole is placed in above bearing plate, three corner steady tops are connected with pressure survey bar one end by connecting bushing, the other end of pressure survey bar is vertically placed in pressure base plate center, described pressure survey bar bending can be out of shape or break after stressed, preferably bending distortion, double layer sleeve barrel is placed on pressure base plate, lever Amplification device is by limited support groove, conduction lever, metal contact piece, support conducting rod and Compress Spring composition, supporting conducting rod one end is vertically placed on pressure base plate, limited support groove is placed in and supports the conducting rod other end, conduction lever one end and connecting bushing are socketed, the other end is connected with metal contact piece through limited support groove, Compress Spring one end is placed on pressure base plate, the other end connects between conduction lever and metal contact piece.
Description
Technical field
A kind of steel construction stress of the utility model prior-warning device, relates to and a kind ofly to the prior-warning device of the stress stressing conditions at steel structure node place, can belong to security appliance field.Be arranged on steel structure node place in particular to one, utilize lever principle that suffered Amplification is carried out the device of early warning.
Background technology
At present, due to the high-ductility of steel and toughness and its excellent wind resistance anti-seismic performance.Steel construction is just widely used in the fields such as industrial premises, executive information systems, residential houses, large public building, railroad bridge, offshore platform as a kind of novel energy-conserving and environment-protective building system.But due to the anti-corrosion property the subject of knowledge and the object of knowledge limit of steel own, therefore among its Long-Time Service, especially can produce certain distortion for large for formed steel construction framework, then can cause caving in of steel structure body when deforming more than corresponding limit, causing casualties and property loss.Therefore, the deformation monitoring for early stage steel structure body seems particularly important.At present, the main flow plant quarantine that steel construction adopts is single, is generally to utilize surveying and mapping technology carry out corresponding geometric distortion monitoring or utilize information network to form the digitized monitoring system of a set of complexity.In the process come into operation the former due to its general field work amount large, be subject to operation side interference, and can not meet and dynamically wait technical requirement continuously and can not extensively be promoted.Accordingly, for the digitized monitoring system of complete set, because steel construction shortterm deflection is less, therefore, it comes into operation costly on a large scale for a long time, and economic benefit is lower, and its installation monitoring facilities is comparatively complicated, needs to be equipped with the personnel with corresponding professional knowledge and carry out monitoring management.Monitoring cost is higher.
Summary of the invention
In order to improve above-mentioned situation, a kind of steel construction stress of the utility model prior-warning device provides one and is arranged on steel structure node place, utilize lever principle by steel structure node place carry out the device of early warning by Amplification.Structure is simple, easy to use.Greatly reduce the cost of steel construction deformation monitoring.
A kind of steel construction stress of the utility model prior-warning device is achieved in that a kind of steel construction stress of the utility model prior-warning device is made up of subject support means, circuit triggers part and lever Amplification device.Subject support means is made up of pressure base plate, connecting hole, pressure survey bar, connecting bushing, double layer sleeve barrel, bearing plate and three corner steadies.The triangle place of three corner steadies is evenly placed in bottom bearing plate, and connecting hole is placed in above bearing plate.Three corner steady tops are connected with pressure survey bar one end by connecting bushing, and the other end of pressure survey bar is vertically placed in pressure base plate center, and described pressure survey bar bending can be out of shape or break after stressed, preferably bending distortion.Double layer sleeve barrel is placed on pressure base plate.Lever Amplification device is made up of limited support groove, conduction lever, metal contact piece, support conducting rod and Compress Spring.Supporting conducting rod one end is vertically placed on pressure base plate, limited support groove is placed in and supports the conducting rod other end, conduction lever one end and connecting bushing are socketed, the other end is connected with metal contact piece through limited support groove, distance between described limited support groove and connecting bushing, is less than the distance between metal contact piece.Described limited support groove conduction.Compress Spring one end is placed on pressure base plate, and the other end connects between conduction lever and metal contact piece, and circuit triggers part is made up of early-warning lamp, wire, L shape contact and accumulator.Accumulator is placed on pressure base plate, and be connected with support conducting rod by wire, L shape contact one end is vertically placed on pressure base plate, the other end is positioned at directly over the metal contact piece of conduction lever one end, early-warning lamp is placed between double layer sleeve barrel, early-warning lamp is connected with accumulator by wire, and is connected with L shape contact by wire.Preferably transparent acrylic material outside described double layer sleeve barrel.
During use, be placed in the easily deformable place in steel structure node place, particularly steel construction by device level.Then fixed by the connecting hole above bearing plate, steel structure frame produces distortion, apply pressure to bearing plate, produce toward downforce bearing plate, STRESS VARIATION is passed to pressure survey bar by three corner steadies by bearing plate, after pressure survey bar is stressed, bending distortion or stressedly to fracture, now three corner steady tops are pressed down by connecting bushing band moving conductive lever one end, utilize lever principle, the conduction lever other end is up moved, and metal contact piece produces displacement upwards.When displacement is greater than certain limit, metal contact piece and L shape contact pad, now accumulator, by the limited support groove of conductive supporting bar, conduction and metal contact piece and L shape contact, form circuit pathways, early-warning lamp lights between double layer sleeve barrel.Utilize lever principle by steel structure node place carry out the object of early warning by Amplification.
Beneficial effect
One, structure is simple, convenient and practical.
Two, with low cost, be easy to promote.
Accompanying drawing explanation
Accompanying drawing 1 is the three-dimensional structure diagram of a kind of steel construction stress of the utility model prior-warning device
In accompanying drawing
Wherein part is: bearing plate (1), connecting hole (2), three corner steadies (3), conduction lever (4), L shape contact (5), double layer sleeve barrel (6), metal contact piece (7), Compress Spring (8), support conducting rod (9), pressure base plate (10), early-warning lamp (11), accumulator (12), wire (13), pressure survey bar (14), connecting bushing (15), limited support groove (16)
Embodiment:
A kind of steel construction stress of the utility model prior-warning device is achieved in that and is made up of subject support means, circuit triggers part and lever Amplification device.Subject support means is made up of pressure base plate (10), connecting hole (2), pressure survey bar (14), connecting bushing (15), double layer sleeve barrel (6), bearing plate (1) and three corner steadies (3).The triangle place of three corner steadies (3) is evenly placed in bearing plate (1) bottom, and connecting hole (2) is placed in bearing plate (1) top.Three corner steadies (3) top is connected with pressure survey bar (14) one end by connecting bushing (15), the other end of pressure survey bar (14) is vertically placed in pressure base plate (10) center, described pressure survey bar (14) bending can be out of shape or break after stressed, preferably bending distortion.Double layer sleeve barrel (6) is placed on pressure base plate (10).Lever Amplification device is made up of limited support groove (16), conduction lever (4), metal contact piece (7), support conducting rod (9) and Compress Spring (8).Supporting conducting rod (9) one end is vertically placed on pressure base plate (10), limited support groove (16) is placed in and supports conducting rod (9) other end, conduction lever (4) one end and connecting bushing (15) are socketed, the other end is connected with metal contact piece (7) through limited support groove (16), distance between described limited support groove (16) and connecting bushing (15), is less than the distance between metal contact piece (7).Described limited support groove (16) conduction.Compress Spring (8) one end is placed on pressure base plate (10), the other end connects between conduction lever (4) and metal contact piece (7), and circuit triggers part is made up of early-warning lamp (11), wire (13), L shape contact (5) and accumulator (12).Accumulator (12) is placed on pressure base plate (10), and be connected with support conducting rod (9) by wire (13), L shape contact (5) one end is vertically placed on pressure base plate (10), the other end is positioned at directly over the metal contact piece (7) of conduction lever (4) one end, early-warning lamp (11) is placed between double layer sleeve barrel (6), early-warning lamp (11) is connected with accumulator (12) by wire (13), and is connected with L shape contact (5) by wire (13).Described double layer sleeve barrel (6) outside preferably transparent acrylic material, during use, is placed in the easily deformable place in steel structure node place, particularly steel construction by device level.Then fixed by the connecting hole (2) of bearing plate (1) top, steel structure frame produces distortion, pressure is applied to bearing plate (1), produce toward downforce to bearing plate (1), STRESS VARIATION is passed to pressure survey bar (14) by three corner steadies (3) by bearing plate (1), after pressure survey bar (14) is stressed, bending distortion or stressedly to fracture, now three corner steadies (3) top is pressed down by connecting bushing (15) band moving conductive lever (4) one end, utilize lever principle, the conduction lever other end is up moved, metal contact piece (7) produces displacement upwards.When displacement is greater than certain limit, metal contact piece (7) contacts with L shape contact (5), now accumulator (12), by supporting conducting rod (9), the limited support groove (16) conducted electricity and metal contact piece (7) and L shape contact (5), form circuit pathways, early-warning lamp (11) lights between double layer sleeve barrel (6).Reach utilize lever principle by steel structure node place carry out the object of early warning by Amplification.
Claims (1)
1. a steel construction stress prior-warning device, it is characterized in that: by subject support means, circuit triggers part and lever Amplification device composition, subject support means is by pressure base plate, connecting hole, pressure survey bar, connecting bushing, double layer sleeve barrel, bearing plate and three corner steadies composition, the triangle place of three corner steadies is evenly placed in bottom bearing plate, connecting hole is placed in above bearing plate, three corner steady tops are connected with pressure survey bar one end by connecting bushing, the other end of pressure survey bar is vertically placed in pressure base plate center, double layer sleeve barrel is placed on pressure base plate, lever Amplification device is by limited support groove, conduction lever, metal contact piece, support conducting rod and Compress Spring composition, supporting conducting rod one end is vertically placed on pressure base plate, limited support groove is placed in and supports the conducting rod other end, conduction lever one end and connecting bushing are socketed, the other end is connected with metal contact piece through limited support groove, described limited support groove conduction, Compress Spring one end is placed on pressure base plate, the other end connects between conduction lever and metal contact piece, circuit triggers part is by early-warning lamp, wire, L shape contact and accumulator composition, accumulator is placed on pressure base plate, and be connected with support conducting rod by wire, L shape contact one end is vertically placed on pressure base plate, the other end is positioned at directly over the metal contact piece of conduction lever one end, early-warning lamp is placed between double layer sleeve barrel, early-warning lamp is connected with accumulator by wire, and be connected with L shape contact by wire.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520112287.7U CN204389074U (en) | 2015-02-11 | 2015-02-11 | A kind of steel construction stress prior-warning device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520112287.7U CN204389074U (en) | 2015-02-11 | 2015-02-11 | A kind of steel construction stress prior-warning device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204389074U true CN204389074U (en) | 2015-06-10 |
Family
ID=53361784
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520112287.7U Expired - Fee Related CN204389074U (en) | 2015-02-11 | 2015-02-11 | A kind of steel construction stress prior-warning device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204389074U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107702030A (en) * | 2017-09-28 | 2018-02-16 | 谢志坚 | A kind of constructing tunnel lighting device |
CN114235258A (en) * | 2021-10-27 | 2022-03-25 | 福建省永正工程质量检测有限公司 | Steel structure stress early warning device |
-
2015
- 2015-02-11 CN CN201520112287.7U patent/CN204389074U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107702030A (en) * | 2017-09-28 | 2018-02-16 | 谢志坚 | A kind of constructing tunnel lighting device |
CN114235258A (en) * | 2021-10-27 | 2022-03-25 | 福建省永正工程质量检测有限公司 | Steel structure stress early warning device |
CN114235258B (en) * | 2021-10-27 | 2024-05-17 | 福建省永正工程质量检测有限公司 | Steel structure stress early warning device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204389074U (en) | A kind of steel construction stress prior-warning device | |
CN204163474U (en) | Environment protection fence moulded by wood | |
CN204183445U (en) | The localization tool of automatic film applicator | |
CN203616206U (en) | Concrete compression creep test system | |
CN203565590U (en) | Copper bar bending-based hydraulic equipment | |
CN102610336A (en) | Compound cross arm insulator | |
CN204901066U (en) | Section bar hoist and mount support frame | |
CN204897325U (en) | A sister block mechanism for high -pressure rubber pipe | |
CN204711963U (en) | A kind of novel mechanical automation cannula system | |
CN203203739U (en) | Novel bearing beam load tester | |
CN207479236U (en) | A kind of hydraulic moving straightener | |
CN111215480A (en) | Steel pipe shaping device | |
CN204470509U (en) | A kind of fixture of forging press travelling table oil cylinder | |
CN204103205U (en) | A kind of conductor compression jointing pipe straightener | |
CN204899175U (en) | Building strutting arrangement | |
CN205833905U (en) | A kind of forming elbow mould for tubing manufacturer | |
CN104723245A (en) | Novel assembling and clamping device of automobile pipeline support | |
CN205217701U (en) | Multistation stamping device with bearing structure | |
CN203341821U (en) | Medical tower crane anchor installation system | |
CN204675744U (en) | Large part furniture appliance lifting apparatus | |
CN204899174U (en) | Building support frame | |
CN204265387U (en) | Novel extruded sheet metering bont | |
CN204657374U (en) | Fluid pressure type quick die change device | |
CN204199438U (en) | A kind of bilateral purlin holder | |
CN208559511U (en) | A kind of Rear frame mechanism arrangement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150610 Termination date: 20170211 |