CN204372915U - Fluidized-bed combustion boiler open type gas spiral coal supply system - Google Patents

Fluidized-bed combustion boiler open type gas spiral coal supply system Download PDF

Info

Publication number
CN204372915U
CN204372915U CN201420858075.9U CN201420858075U CN204372915U CN 204372915 U CN204372915 U CN 204372915U CN 201420858075 U CN201420858075 U CN 201420858075U CN 204372915 U CN204372915 U CN 204372915U
Authority
CN
China
Prior art keywords
coal
fluidized
bed combustion
combustion boiler
flow guiding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420858075.9U
Other languages
Chinese (zh)
Inventor
陈巨辉
邹英永
胡长胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Guo Ling Development In Science And Technology Co Ltd
Original Assignee
Harbin Guo Ling Development In Science And Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Guo Ling Development In Science And Technology Co Ltd filed Critical Harbin Guo Ling Development In Science And Technology Co Ltd
Priority to CN201420858075.9U priority Critical patent/CN204372915U/en
Application granted granted Critical
Publication of CN204372915U publication Critical patent/CN204372915U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Fluidized-Bed Combustion And Resonant Combustion (AREA)

Abstract

Fluidized-bed combustion boiler open type gas spiral coal supply system.At present, the feeder of fluidized-bed combustion boiler mainly contains screw-type coal distributor, Scraper and closed belt feeder.Even if the sealing property of new installed equipment is better, through use after a while, because of reasons such as wearing and tearing, maintenance dismounting, sealing property can decrease, and Coal powder spray phenomenon more or less all can exist.A kind of fluidized-bed combustion boiler open type gas spiral coal supply system, its composition comprises: coal bunker (1), described coal bunker is connected with Gravimetric Coal Feeders (2), described Gravimetric Coal Feeders is connected with coal chute (3), described coal chute is connected with coal sliding tube (11), described coal sliding tube is connected with burner hearth (13) with coal spread wind case (12) by pipeline, and described coal chute has pipe (7), coal breakage bucket (5), defeated coal bellows (4) in flow guiding casing tube outer tube (6), flow guiding casing tube.The utility model is applied to fluidized-bed combustion boiler.

Description

Fluidized-bed combustion boiler open type gas spiral coal supply system
technical field:
the utility model relates to a kind of title, coal is delivered into burner hearth by the gas spiral that open type gas spiral coal supply technology utilizes air force to be formed, mechanical coal feeder technology general at present can be replaced, device structure is simple, small investment, gas spiral coal supply technology can form negative pressure at coal dropping port place, coal dust is sucked burner hearth, eliminates mechanical coal feeder technology insurmountable production scene airborne dust problem.
background technology:
fluidized-bed combustion boiler is generally malleation in burner hearth in design, and neutral point is generally at furnace outlet.In order to extend coal dust and the time of staying of fugitive constituent in burner hearth, improve efficiency of combustion, the coal supply point of boiler coal feeding equipment on burner hearth is generally at the emulsion zone of lower furnace portion, therefore require that coal supply equipment will have good sealing property, otherwise at poorly sealed place's ejection coal dust, flue gas even flame, on-the-spot pollution will be caused.At present, the feeder of fluidized-bed combustion boiler mainly contains screw-type coal distributor, Scraper and closed belt feeder.These equipment mainly stop the ejection of malleation flue gas and coal dust in stove by the material envelope of material formation during work or the sealing of device housings, even if the sealing property of new installed equipment is better, through use after a while, because of reasons such as wearing and tearing, maintenance dismounting, sealing property can decrease, and Coal powder spray phenomenon more or less all can exist.Meanwhile, because the throughput direction of coal is contrary with flue gas emission direction, be easy to cause equipment chute blockage.In addition, the shell of these equipment is airtight, and inspection and maintenance inconvenience, equipment failure rate is high.
utility model content:
the purpose of this utility model is to provide a kind of fluidized-bed combustion boiler open type gas spiral coal supply system.
above-mentioned object is realized by following technical scheme:
a kind of fluidized-bed combustion boiler open type gas spiral coal supply system, its composition comprises: coal bunker, described coal bunker is connected with Gravimetric Coal Feeders, described Gravimetric Coal Feeders is connected with coal chute, described coal chute is connected with coal sliding tube, described coal sliding tube is connected with burner hearth with coal spread wind case by pipeline, and described coal chute has pipe, coal breakage bucket, defeated coal bellows in flow guiding casing tube outer tube, flow guiding casing tube.
described fluidized-bed combustion boiler open type gas spiral coal supply system, in described defeated coal bellows, coal breakage bucket is installed, described coal breakage bucket is connected with pipe in described flow guiding casing tube, described defeated coal bellows outer wall is connected with described flow guiding casing tube outer tube, in described flow guiding casing tube, pipe forms chuck with described flow guiding casing tube outer tube is defeated coal wind duct, has the distributing fin counterclockwise arranged in described defeated coal wind duct.
described fluidized-bed combustion boiler open type gas spiral coal supply system, described defeated coal bellows are connected with air distribution line, described air distribution line is connected with air distribution house steward, described air distribution house steward is connected with tubule, described tubule inserts along described coal breakage bucket center, described defeated coal bellows are the cylinder of hollow, and described coal breakage bucket is cone.
the beneficial effects of the utility model:
1. the coal in the utility model coal bunker falls into after coal chute from belt and forms Dual-Phrase Distribution of Gas olid, can be rotated counterclockwise by nature when Dual-Phrase Distribution of Gas olid not only in coal chute is fallen, defeated coal wind in flow guiding casing tube equally also can be rotated counterclockwise, and can accelerate the rotation of defeated coal wind in sleeve pipe by the fin counterclockwise arranged.Lower rotational gas flow is evenly distributed in pipe, and the active force moved downward is strong, not only can resist the malleation in stove, the vortex sucked can also be formed in coal spout porch, the coal dust kicked up by belt conveyer head of weighing sucks, and scene will there will be no coal dust to fly upward, and greatly improve production environment.
the defeated coal wind of the utility model forms wind cover, and under the effect of vortex, the large coal stream of concentration is at coal chute center, little to coal chute wearing and tearing, extends the service life of coal chute, avoids coal dust simultaneously and bonds on coal chute tube wall and cause chute blockage.
after the utility model transformation, coal chute extends, vertical tube segment length reaches about 5m, coal natural whereabouts hourly velocity in pipe greatly improves the coal fallen at a high speed and not only produces impact to ascending air, simultaneously owing to forming the piston effect moved downward when coal falls continuously, air is produced and downward pulls effect, weaken the strength of ascending air.4. the utility model structure is simple, small investment, operating cost are low, safeguard simple coal supply technology, not only can be used for the front coal feeding system of newly-built fluidized-bed combustion boiler, also can be used for the transformation of old device, can be applicable to the industry that cement, metallurgy etc. relate to solid particle material, powder carry simultaneously.
accompanying drawing illustrates:
accompanying drawing 1 is system architecture schematic diagram of the present utility model.
accompanying drawing 2 is defeated coal bellows air intake schematic diagrames.
Detailed description of the invention
embodiment 1:
a kind of fluidized-bed combustion boiler open type gas spiral coal supply system, its composition comprises: coal bunker 1, described coal bunker is connected with Gravimetric Coal Feeders 2, described Gravimetric Coal Feeders is connected with coal chute 3, described coal chute is connected with coal sliding tube 11, described coal sliding tube is connected with burner hearth 13 with coal spread wind case 12 by pipeline, and described coal chute has pipe 7 in flow guiding casing tube outer tube 6, flow guiding casing tube, coal breakage bucket 5, defeated coal bellows 4.
embodiment 2:
fluidized-bed combustion boiler open type gas spiral coal supply system according to embodiment 1, in described defeated coal bellows, described coal breakage bucket is installed, described coal breakage bucket is connected with pipe in described flow guiding casing tube, described defeated coal bellows outer wall is connected with described flow guiding casing tube outer tube, in described flow guiding casing tube, pipe forms chuck with described flow guiding casing tube outer tube is defeated coal wind duct, has the distributing fin counterclockwise arranged in described defeated coal wind duct.
embodiment 3:
fluidized-bed combustion boiler open type gas spiral coal supply system according to embodiment 1 or 2, described defeated coal bellows are connected with air distribution line 8, described air distribution line is connected with air distribution house steward 9, described air distribution house steward is connected with tubule 10, described tubule inserts along described coal breakage bucket center, described defeated coal bellows are the cylinder of hollow, and described coal breakage bucket is cone.

Claims (3)

1. a fluidized-bed combustion boiler open type gas spiral coal supply system, its composition comprises: coal bunker, it is characterized in that: described coal bunker is connected with Gravimetric Coal Feeders, described Gravimetric Coal Feeders is connected with coal chute, described coal chute is connected with coal sliding tube, described coal sliding tube is connected with burner hearth with coal spread wind case by pipeline, and described coal chute has pipe, coal breakage bucket, defeated coal bellows in flow guiding casing tube outer tube, flow guiding casing tube.
2. fluidized-bed combustion boiler open type gas spiral coal supply system according to claim 1, it is characterized in that: in described defeated coal bellows, coal breakage bucket is installed, described coal breakage bucket is connected with pipe in described flow guiding casing tube, described defeated coal bellows outer wall is connected with described flow guiding casing tube outer tube, in described flow guiding casing tube, pipe forms chuck with described flow guiding casing tube outer tube is defeated coal wind duct, has the distributing fin counterclockwise arranged in described defeated coal wind duct.
3. fluidized-bed combustion boiler open type gas spiral coal supply system according to claim 1 and 2, it is characterized in that: described defeated coal bellows are connected with air distribution line, described air distribution line is connected with air distribution house steward, described air distribution house steward is connected with tubule, described tubule inserts along described coal breakage bucket center, described defeated coal bellows are the cylinder of hollow, and described coal breakage bucket is cone.
CN201420858075.9U 2014-12-30 2014-12-30 Fluidized-bed combustion boiler open type gas spiral coal supply system Expired - Fee Related CN204372915U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420858075.9U CN204372915U (en) 2014-12-30 2014-12-30 Fluidized-bed combustion boiler open type gas spiral coal supply system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420858075.9U CN204372915U (en) 2014-12-30 2014-12-30 Fluidized-bed combustion boiler open type gas spiral coal supply system

Publications (1)

Publication Number Publication Date
CN204372915U true CN204372915U (en) 2015-06-03

Family

ID=53329133

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420858075.9U Expired - Fee Related CN204372915U (en) 2014-12-30 2014-12-30 Fluidized-bed combustion boiler open type gas spiral coal supply system

Country Status (1)

Country Link
CN (1) CN204372915U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107091473A (en) * 2016-12-27 2017-08-25 四川川锅锅炉有限责任公司 A kind of CFBB high-speed rotational coal spread wind air inlet structure
CN107246624A (en) * 2017-07-27 2017-10-13 韩明龙 One kind fire prevention defeated coal device of Wind-Pressure Resistance

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107091473A (en) * 2016-12-27 2017-08-25 四川川锅锅炉有限责任公司 A kind of CFBB high-speed rotational coal spread wind air inlet structure
CN107246624A (en) * 2017-07-27 2017-10-13 韩明龙 One kind fire prevention defeated coal device of Wind-Pressure Resistance

Similar Documents

Publication Publication Date Title
CN203857473U (en) Ash discharge delivery system of coal economizer
CN104399607A (en) Cyclone separating device and cyclone separation system based on cyclone separating device
CN204372915U (en) Fluidized-bed combustion boiler open type gas spiral coal supply system
CN103557697B (en) Novel rotary kiln
CN205288084U (en) Sweetener in circulating fluidized bed boiler stove
CN207471522U (en) A kind of industrial coal powder boiler that adherent wind nozzle is set
CN205860053U (en) Flying dust Automatic continuous discharger bottom a kind of boiler SCR denitration device
CN202132962U (en) Industry boiler with an ash-retention grilling device
CN203237785U (en) Pneumatic conveying throat pipe
CN206018661U (en) A kind of automatic continuous discharger of boiler back end ductwork ash bucket dust stratification
CN208802378U (en) A kind of blanking device suitable for coal water slurry boiler dust collector ash hopper
CN205187360U (en) Material sealing pump
CN107062208A (en) It is a kind of suitable for fluid bed Wu Du Sai Give device for coal
CN209042433U (en) A kind of pneumatic conveying boiler coal-ash combustion system
CN208868677U (en) A kind of anti-blocking powder dust feeder
CN203068983U (en) Air-swept distributing box
CN206739281U (en) It is a kind of suitable for fluid bed without blocking coal feeder
CN208186405U (en) A kind of coal base distribution boiler transmission & distribution pulverized coal system
CN206290279U (en) A kind of drawing chute deduster
CN205965319U (en) Stifled air inlet system is prevented to dust remover
CN205746811U (en) A kind of boiler quickly adds bed system
CN105351957A (en) Novel biomass particle combustion boiler system
CN205973068U (en) Buggy feedway
CN204051947U (en) A kind of novel powder cyclone collector
CN205119814U (en) Eliminate device of big flue laying dust of sintering

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150603

Termination date: 20151230

EXPY Termination of patent right or utility model