CN204326022U - Dou Shan Canyon Area mud-rock flow safeguard structure - Google Patents

Dou Shan Canyon Area mud-rock flow safeguard structure Download PDF

Info

Publication number
CN204326022U
CN204326022U CN201420708415.XU CN201420708415U CN204326022U CN 204326022 U CN204326022 U CN 204326022U CN 201420708415 U CN201420708415 U CN 201420708415U CN 204326022 U CN204326022 U CN 204326022U
Authority
CN
China
Prior art keywords
safeguard structure
mud
rock flow
net
protecting wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420708415.XU
Other languages
Chinese (zh)
Inventor
姚裕春
袁碧玉
李安洪
魏永幸
刘洋
徐骏
庞应刚
张敏静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201420708415.XU priority Critical patent/CN204326022U/en
Application granted granted Critical
Publication of CN204326022U publication Critical patent/CN204326022U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

Dou Shan Canyon Area mud-rock flow safeguard structure, effectively to strengthen the protection effect of safeguard structure and to facilitate preventive works to construct.This safeguard structure comprises: anchor cable net, arranges along debris flow valley Upstream section interval; Middle tight defense protecting wire net, is arranged along debris flow valley middle reaches spacer segment; Tight defense protecting wire net, is arranged along debris flow valley tract interval.

Description

Dou Shan Canyon Area mud-rock flow safeguard structure
Technical field
The utility model relates to mountain area mud-rock flow protection, particularly Dou Shan Canyon Area mud-rock flow protection.
Background technology
Southwestern China mountain area mud-rock flow is extremely grown; the harmfulness of mud-stone flow disaster to society is very big; usually great personnel or property loss can be caused; particularly huge at Dou Shan Canyon Area mud-rock flow energy; destructive strong; the simultaneously control of mud-rock flow and protection very difficult, one is the traditional blocking dam safeguard procedures constructional difficulties in Dou Shan Canyon Area, and two are that protection effect is poor and preventive works investment is large.For this reason, urgent a kind of Dou Shan Canyon Area mud-rock flow safeguard structure that needs solves problems.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of Dou Shan Canyon Area mud-rock flow safeguard structure, effectively to strengthen the protection effect of safeguard structure and to facilitate preventive works to construct.
It is as follows that the utility model solves the technical scheme that its technical problem adopts:
Dou Shan Canyon Area of the present utility model mud-rock flow safeguard structure, is characterized in that it comprises: anchor cable net, arranges along debris flow valley Upstream section interval; Middle tight defense protecting wire net, is arranged along debris flow valley middle reaches spacer segment; Tight defense protecting wire net, is arranged along debris flow valley tract interval.
The beneficial effects of the utility model are, adopt light flexible structure convenient construction, repair fast, take the segmentation of segmentation safeguard procedures energy effectively to consume mud-rock flow energy, avoid energy constantly to accumulate the large disaster of formation, adopt classified filtering mud-rock flow particle diameter can give full play to protection effect at different levels and save construction investment, this safeguard structure has that easy construction, protection effect are good, economic dispatch feature, has wide popularizing application prospect.
Accompanying drawing explanation
This manual comprises following four width accompanying drawings:
Fig. 1 is the floor map of the utility model Dou Shan Canyon Area mud-rock flow safeguard structure;
Fig. 2 is the structural representation of the utility model Dou Shan Canyon Area mud-rock flow safeguard structure stream line net;
Fig. 3 is the structural representation of middle tight defense protecting wire net in the mud-rock flow safeguard structure of the utility model Dou Shan Canyon Area;
Fig. 4 is the structural representation of tight defense protecting wire net in the mud-rock flow safeguard structure of the utility model Dou Shan Canyon Area.
Component name shown in figure and corresponding mark: anchor cable net 1, anchor cable cross bracing wire 11, anchor cable indulge bracing wire 12, anchorage cable anchoring section 13, middle tight defense protecting wire net 2, passive protection net 21, anchor cable cross bracing wire 22, anchorage cable anchoring section 23, tight defense protecting wire net 3, passive protection net 31, anchor cable cross bracing wire 32, anchorage cable anchoring section 33, debris flow valley upstream A, debris flow valley middle reaches B, debris flow valley downstream C.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is further illustrated.
Comprise with reference to Fig. 1, Dou Shan Canyon Area mud-rock flow safeguard structure: anchor cable net 1, is arranged along debris flow valley Upstream section A interval; Middle tight defense protecting wire net 2, is arranged along section B interval, debris flow valley middle reaches; Tight defense protecting wire net 3, is arranged along debris flow valley tract C interval.
The utility model adopts light flexible structure convenient construction, repairs fast, solve the problem that Dou Shan Canyon Area adopts traditional its materials handling of blocking dam protection form and constructional difficulties, take the segmentation of segmentation safeguard procedures energy effectively to consume mud-rock flow energy, avoid energy accumulation to form large disaster, adopt classified filtering mud-rock flow particle diameter can give full play to protection effect at different levels and save construction investment.Anchor cable net 1 is utilized to tackle large-size material in mud-rock flow, in utilization, tight defense protecting wire net 2 tackles mud-rock flow median diameter material, tight defense protecting wire net 3 is utilized to tackle in mud-rock flow comparatively small particle diameter material, protective screening classification, subsection setup can form multistage interception, classified energy-dissipation, classified filtering, effectively tackles the coarse granule forming mud-rock flow, allow fine grained and muddy water flow out, thus avoid formation mud-stone flow disaster.This safeguard structure has that easy construction, protection effect are good, economic dispatch feature, has wide popularizing application prospect.
With reference to Fig. 1, anchor cable net 1, middle tight defense protecting wire net 2, tight defense protecting wire net 3 arrange number of channels and determine according to materials of debris flow source quantity delivered.
With reference to Fig. 2, anchor cable net 1 indulges bracing wire 12 by anchor cable cross bracing wire 11, anchor cable, anchorage cable anchoring section 13 forms, bracing wire 12 indulged by anchor cable cross bracing wire 11, anchor cable, anchorage cable anchoring section 13 can be made up of the Φ 152mm high strength steel strand of 4 ~ 8 bundles, it should carry out anti-corrosion measure, anchorage cable anchoring section 13 adopts bored grouting to be anchored in cheuch ground, and its length is not less than 10m.The size of mesh opening of anchor cable net 1 is determined according to materials of debris flow particle size, generally can be 40 ~ 50cm.
With reference to Fig. 3, middle tight defense protecting wire net 2 is made up of passive protection net 21, anchor cable cross bracing wire 22, anchorage cable anchoring section 23, anchor cable cross bracing wire 22, anchorage cable anchoring section 23 can be made up of the Φ 152mm high strength steel strand of 4 ~ 6 bundles, it should carry out anti-corrosion measure, anchorage cable anchoring section 23 adopts bored grouting to be anchored in cheuch ground, and its length is not less than 8m.The size of mesh opening of middle tight defense protecting wire net 2 is generally 20 ~ 30cm.
With reference to Fig. 4, tight defense protecting wire net 3 is made up of passive protection net 31, anchor cable cross bracing wire 32, anchorage cable anchoring section 33, anchor cable cross bracing wire 32, anchorage cable anchoring section 33 can be made up of the Φ 152mm high strength steel strand of 4 ~ 6 bundles, it should carry out anti-corrosion measure, anchorage cable anchoring section 33 adopts bored grouting to be anchored in cheuch ground, and its length is not less than 5m.The size of mesh opening of tight defense protecting wire net 3 is generally 5 ~ 10cm.
Some principles of the above the utility model Dou Shan Canyon Area mud-rock flow safeguard structure that just explains through diagrams, be not the utility model to be confined to shown in and in described concrete structure and the scope of application, therefore every corresponding modify of being likely utilized and equivalent, all belong to the scope of the claims that the utility model is applied for.

Claims (4)

1. Dou Shan Canyon Area mud-rock flow safeguard structure, is characterized in that it comprises: anchor cable net (1), arranges along debris flow valley Upstream section (A) interval; Middle tight defense protecting wire net (2), is arranged along debris flow valley middle reaches section (B) interval; Tight defense protecting wire net (3), is arranged along debris flow valley tract (C) interval.
2. Dou Shan Canyon Area as claimed in claim 1 mud-rock flow safeguard structure, is characterized in that: the size of mesh opening of described anchor cable net (1) is 40 ~ 50cm.
3. Dou Shan Canyon Area as claimed in claim 1 mud-rock flow safeguard structure, is characterized in that: the size of mesh opening of described middle tight defense protecting wire net (2) is 20 ~ 30cm.
4. Dou Shan Canyon Area as claimed in claim 1 mud-rock flow safeguard structure, is characterized in that: the size of mesh opening of described tight defense protecting wire net (3) is 5 ~ 10cm.
CN201420708415.XU 2014-11-23 2014-11-23 Dou Shan Canyon Area mud-rock flow safeguard structure Expired - Fee Related CN204326022U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420708415.XU CN204326022U (en) 2014-11-23 2014-11-23 Dou Shan Canyon Area mud-rock flow safeguard structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420708415.XU CN204326022U (en) 2014-11-23 2014-11-23 Dou Shan Canyon Area mud-rock flow safeguard structure

Publications (1)

Publication Number Publication Date
CN204326022U true CN204326022U (en) 2015-05-13

Family

ID=53162398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420708415.XU Expired - Fee Related CN204326022U (en) 2014-11-23 2014-11-23 Dou Shan Canyon Area mud-rock flow safeguard structure

Country Status (1)

Country Link
CN (1) CN204326022U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350444A (en) * 2015-10-30 2016-02-24 中国电建集团成都勘测设计研究院有限公司 Pipe bridge protective structure for debris flow high-incidence area
CN106480851A (en) * 2016-11-15 2017-03-08 吉林大学 A kind of mud-rock flow filtration system step by step
CN107938613A (en) * 2017-12-25 2018-04-20 浙江大学 A kind of novel belt spring supporting mud-rock flow porotective wall and its construction method
RU2731057C1 (en) * 2019-03-11 2020-08-28 федеральное государственное бюджетное образовательное учреждение высшего образования "Южно-Российский государственный политехнический университет (НПИ) имени М.И. Платова" Protective system of urban development and recreation objects from natural and industrial processes and method of erection thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350444A (en) * 2015-10-30 2016-02-24 中国电建集团成都勘测设计研究院有限公司 Pipe bridge protective structure for debris flow high-incidence area
CN106480851A (en) * 2016-11-15 2017-03-08 吉林大学 A kind of mud-rock flow filtration system step by step
CN107938613A (en) * 2017-12-25 2018-04-20 浙江大学 A kind of novel belt spring supporting mud-rock flow porotective wall and its construction method
RU2731057C1 (en) * 2019-03-11 2020-08-28 федеральное государственное бюджетное образовательное учреждение высшего образования "Южно-Российский государственный политехнический университет (НПИ) имени М.И. Платова" Protective system of urban development and recreation objects from natural and industrial processes and method of erection thereof

Similar Documents

Publication Publication Date Title
CN204326022U (en) Dou Shan Canyon Area mud-rock flow safeguard structure
CN205604096U (en) Husky system of roadlock says in husky district
CN103334419A (en) Novel geogrid with ground anchors attached
CN203129121U (en) Windproof sand resistance sand barrier
CN202787190U (en) Frame used in riprap closure method for high flow rate closure gap
CN202482782U (en) Doublet sand resistance structure for road protection in sandstorm area
CN205088656U (en) A interception structures for river course
CN201856290U (en) Bridge pier body concrete curing device
EA200901342A1 (en) OPEN TYPE DAMBA FOR PROTECTION AGAINST A GREEN FLOW
CN205217532U (en) Circular pipeline sediment removal device
CN205399343U (en) Reinforcement type waterproof and anti -seepage bank protection
CN203866719U (en) Debris flow protection net
CN203716104U (en) Reservoir branch course desilting equipment
CN204850520U (en) Loam wall body reinforced structure
CN204282850U (en) Steel work-concrete combined floor reserved opening protective net frame
CN204125929U (en) The plastics lattice-valued automata of checking winds and fixing drifting sand
CN102852063B (en) concrete block and construction method for road construction
CN104213550A (en) Plastic grid-shaped sand barrier for wind prevention and sand fixation
CN201485844U (en) Splayed net cage sand barrier and construction structure thereof
CN205475270U (en) Ecological bank protection of two sides of a road scour prevention
CN207469270U (en) High slope combined bearing structure
CN201848126U (en) Net cord comb-flow sedimentation tank
CN103741644A (en) Separation desilting device for reservoir
CN206581219U (en) A kind of flood fighting triangle round steel structure
CN205062750U (en) Water blocking device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150513